Substation · 11 kV · primary

Smithy Green

Northern Powergrid · United Kingdom

Latest published values

83 served · 0 withheld

Each row is what the operator’s latest published dataset reports for one combination of direction, technology, measure, firmness and horizon. Hosting-capacity figures are indicative and reflect what operators publish. They are not a connection offer; only the operator can confirm capacity for a specific request.

Latest published capacity values, one row per series
DirectionTechnologyMeasureValueFirmnessHorizonSource date
InjectionGeneration (any)Available1.14 MWFirmNow (snapshot)27 Jul 2026
InjectionGeneration (any)Available0 MWUnknown2026 (2026)scenario: DFES 2026 - Holistic Transition24 Apr 2026
InjectionGeneration (any)Available0 MWUnknown2026 (2026)scenario: DFES 2026 - Hydrogen Evolution24 Apr 2026
InjectionGeneration (any)Available0 MWUnknown2026 (2026)scenario: DFES 2026 - Electric Engagement24 Apr 2026
InjectionGeneration (any)Available0 MWUnknown2027 (2027)scenario: DFES 2026 - Holistic Transition24 Apr 2026
InjectionGeneration (any)Available0 MWUnknown2027 (2027)scenario: DFES 2026 - Hydrogen Evolution24 Apr 2026
InjectionGeneration (any)Available0 MWUnknown2027 (2027)scenario: DFES 2026 - Electric Engagement24 Apr 2026
InjectionGeneration (any)Available0 MWUnknown2028 (2028)scenario: DFES 2026 - Holistic Transition24 Apr 2026
InjectionGeneration (any)Available0 MWUnknown2028 (2028)scenario: DFES 2026 - Hydrogen Evolution24 Apr 2026
InjectionGeneration (any)Available0 MWUnknown2028 (2028)scenario: DFES 2026 - Electric Engagement24 Apr 2026
InjectionGeneration (any)Available0 MWUnknown2029 (2029)scenario: DFES 2026 - Holistic Transition24 Apr 2026
InjectionGeneration (any)Available0 MWUnknown2029 (2029)scenario: DFES 2026 - Hydrogen Evolution24 Apr 2026
InjectionGeneration (any)Available0 MWUnknown2029 (2029)scenario: DFES 2026 - Electric Engagement24 Apr 2026
InjectionGeneration (any)Available0 MWUnknown2030 (2030)scenario: DFES 2026 - Holistic Transition24 Apr 2026
InjectionGeneration (any)Available0 MWUnknown2030 (2030)scenario: DFES 2026 - Hydrogen Evolution24 Apr 2026
InjectionGeneration (any)Available0 MWUnknown2030 (2030)scenario: DFES 2026 - Electric Engagement24 Apr 2026
InjectionGeneration (any)Available0 MWUnknown2031 (2031)scenario: DFES 2026 - Holistic Transition24 Apr 2026
InjectionGeneration (any)Available0 MWUnknown2031 (2031)scenario: DFES 2026 - Hydrogen Evolution24 Apr 2026
InjectionGeneration (any)Available0 MWUnknown2031 (2031)scenario: DFES 2026 - Electric Engagement24 Apr 2026
InjectionGeneration (any)Available0 MWUnknown2032 (2032)scenario: DFES 2026 - Holistic Transition24 Apr 2026
InjectionGeneration (any)Available0 MWUnknown2032 (2032)scenario: DFES 2026 - Hydrogen Evolution24 Apr 2026
InjectionGeneration (any)Available0 MWUnknown2032 (2032)scenario: DFES 2026 - Electric Engagement24 Apr 2026
InjectionGeneration (any)Available0 MWUnknown2033 (2033)scenario: DFES 2026 - Holistic Transition24 Apr 2026
InjectionGeneration (any)Available0 MWUnknown2033 (2033)scenario: DFES 2026 - Hydrogen Evolution24 Apr 2026
InjectionGeneration (any)Available0 MWUnknown2033 (2033)scenario: DFES 2026 - Electric Engagement24 Apr 2026
InjectionGeneration (any)Available0 MWUnknown2034 (2034)scenario: DFES 2026 - Holistic Transition24 Apr 2026
InjectionGeneration (any)Available0 MWUnknown2034 (2034)scenario: DFES 2026 - Hydrogen Evolution24 Apr 2026
InjectionGeneration (any)Available0 MWUnknown2034 (2034)scenario: DFES 2026 - Electric Engagement24 Apr 2026
InjectionGeneration (any)Available0 MWUnknown2035 (2035)scenario: DFES 2026 - Holistic Transition24 Apr 2026
InjectionGeneration (any)Available0 MWUnknown2035 (2035)scenario: DFES 2026 - Hydrogen Evolution24 Apr 2026
InjectionGeneration (any)Available0 MWUnknown2035 (2035)scenario: DFES 2026 - Electric Engagement24 Apr 2026
InjectionGeneration (any)Available0 MWUnknown2040 (2040)scenario: DFES 2026 - Holistic Transition24 Apr 2026
InjectionGeneration (any)Available0 MWUnknown2040 (2040)scenario: DFES 2026 - Hydrogen Evolution24 Apr 2026
InjectionGeneration (any)Available0 MWUnknown2040 (2040)scenario: DFES 2026 - Electric Engagement24 Apr 2026
InjectionGeneration (any)Available0 MWUnknown2045 (2045)scenario: DFES 2026 - Holistic Transition24 Apr 2026
InjectionGeneration (any)Available0 MWUnknown2045 (2045)scenario: DFES 2026 - Hydrogen Evolution24 Apr 2026
InjectionGeneration (any)Available0 MWUnknown2045 (2045)scenario: DFES 2026 - Electric Engagement24 Apr 2026
InjectionGeneration (any)Available0 MWUnknown2050 (2050)scenario: DFES 2026 - Holistic Transition24 Apr 2026
InjectionGeneration (any)Available0 MWUnknown2050 (2050)scenario: DFES 2026 - Hydrogen Evolution24 Apr 2026
InjectionGeneration (any)Available0 MWUnknown2050 (2050)scenario: DFES 2026 - Electric Engagement24 Apr 2026
InjectionGeneration (any)Contracted0 MWUnknownNow (snapshot)27 Jul 2026
OfftakeLoad (any)Available3.24 MVAFirmNow (snapshot)27 Jul 2026
OfftakeLoad (any)Available2.64 MWUnknown2026 (2026)scenario: DFES 2026 - Holistic Transition24 Apr 2026
OfftakeLoad (any)Available2.64 MWUnknown2026 (2026)scenario: DFES 2026 - Electric Engagement24 Apr 2026
OfftakeLoad (any)Available2.64 MWUnknown2026 (2026)scenario: DFES 2026 - Hydrogen Evolution24 Apr 2026
OfftakeLoad (any)Available2.44 MWUnknown2027 (2027)scenario: DFES 2026 - Holistic Transition24 Apr 2026
OfftakeLoad (any)Available2.44 MWUnknown2027 (2027)scenario: DFES 2026 - Electric Engagement24 Apr 2026
OfftakeLoad (any)Available2.44 MWUnknown2027 (2027)scenario: DFES 2026 - Hydrogen Evolution24 Apr 2026
OfftakeLoad (any)Available2.19 MWUnknown2028 (2028)scenario: DFES 2026 - Holistic Transition24 Apr 2026
OfftakeLoad (any)Available2.19 MWUnknown2028 (2028)scenario: DFES 2026 - Electric Engagement24 Apr 2026
OfftakeLoad (any)Available2.19 MWUnknown2028 (2028)scenario: DFES 2026 - Hydrogen Evolution24 Apr 2026
OfftakeLoad (any)Available1.9 MWUnknown2029 (2029)scenario: DFES 2026 - Holistic Transition24 Apr 2026
OfftakeLoad (any)Available1.9 MWUnknown2029 (2029)scenario: DFES 2026 - Electric Engagement24 Apr 2026
OfftakeLoad (any)Available1.9 MWUnknown2029 (2029)scenario: DFES 2026 - Hydrogen Evolution24 Apr 2026
OfftakeLoad (any)Available1.52 MWUnknown2030 (2030)scenario: DFES 2026 - Holistic Transition24 Apr 2026
OfftakeLoad (any)Available1.52 MWUnknown2030 (2030)scenario: DFES 2026 - Electric Engagement24 Apr 2026
OfftakeLoad (any)Available1.52 MWUnknown2030 (2030)scenario: DFES 2026 - Hydrogen Evolution24 Apr 2026
OfftakeLoad (any)Available1.07 MWUnknown2031 (2031)scenario: DFES 2026 - Holistic Transition24 Apr 2026
OfftakeLoad (any)Available1.07 MWUnknown2031 (2031)scenario: DFES 2026 - Electric Engagement24 Apr 2026
OfftakeLoad (any)Available1.07 MWUnknown2031 (2031)scenario: DFES 2026 - Hydrogen Evolution24 Apr 2026
OfftakeLoad (any)Available0.64 MWUnknown2032 (2032)scenario: DFES 2026 - Holistic Transition24 Apr 2026
OfftakeLoad (any)Available0.64 MWUnknown2032 (2032)scenario: DFES 2026 - Electric Engagement24 Apr 2026
OfftakeLoad (any)Available0.64 MWUnknown2032 (2032)scenario: DFES 2026 - Hydrogen Evolution24 Apr 2026
OfftakeLoad (any)Available0.15 MWUnknown2033 (2033)scenario: DFES 2026 - Holistic Transition24 Apr 2026
OfftakeLoad (any)Available0.15 MWUnknown2033 (2033)scenario: DFES 2026 - Electric Engagement24 Apr 2026
OfftakeLoad (any)Available0.15 MWUnknown2033 (2033)scenario: DFES 2026 - Hydrogen Evolution24 Apr 2026
OfftakeLoad (any)Available0 MWUnknown2034 (2034)scenario: DFES 2026 - Holistic Transition24 Apr 2026
OfftakeLoad (any)Available0 MWUnknown2034 (2034)scenario: DFES 2026 - Electric Engagement24 Apr 2026
OfftakeLoad (any)Available0 MWUnknown2034 (2034)scenario: DFES 2026 - Hydrogen Evolution24 Apr 2026
OfftakeLoad (any)Available0 MWUnknown2035 (2035)scenario: DFES 2026 - Holistic Transition24 Apr 2026
OfftakeLoad (any)Available0 MWUnknown2035 (2035)scenario: DFES 2026 - Electric Engagement24 Apr 2026
OfftakeLoad (any)Available0 MWUnknown2035 (2035)scenario: DFES 2026 - Hydrogen Evolution24 Apr 2026
OfftakeLoad (any)Available0 MWUnknown2040 (2040)scenario: DFES 2026 - Holistic Transition24 Apr 2026
OfftakeLoad (any)Available0 MWUnknown2040 (2040)scenario: DFES 2026 - Electric Engagement24 Apr 2026
OfftakeLoad (any)Available0 MWUnknown2040 (2040)scenario: DFES 2026 - Hydrogen Evolution24 Apr 2026
OfftakeLoad (any)Available0 MWUnknown2045 (2045)scenario: DFES 2026 - Holistic Transition24 Apr 2026
OfftakeLoad (any)Available0 MWUnknown2045 (2045)scenario: DFES 2026 - Electric Engagement24 Apr 2026
OfftakeLoad (any)Available0 MWUnknown2045 (2045)scenario: DFES 2026 - Hydrogen Evolution24 Apr 2026
OfftakeLoad (any)Available0 MWUnknown2050 (2050)scenario: DFES 2026 - Holistic Transition24 Apr 2026
OfftakeLoad (any)Available0 MWUnknown2050 (2050)scenario: DFES 2026 - Electric Engagement24 Apr 2026
OfftakeLoad (any)Available0 MWUnknown2050 (2050)scenario: DFES 2026 - Hydrogen Evolution24 Apr 2026
OfftakeLoad (any)Contracted0 MVAUnknownNow (snapshot)27 Jul 2026
OfftakeLoad (any)Total8 MVAFirmNow (snapshot)27 Jul 2026

Supported by Northern Powergrid Open Data (last updated 2026-04-24)Supported by Northern Powergrid Open Data (last updated 2026-07-27)

What each value means

Methodology, both clocks, provenance and rights

Injection · Generation (any) · Available

1.14 MW

Granted

The operator's latest published dataset reports 1.139999986 MW under methodology gb_npg_heatmap_2026.

Firmness
Firm
Horizon
Now (snapshot)
Methodology
gb_npg_heatmap_2026Northern Powergrid heat-map data: thermal headroombasis operator calculated · network state unknown · comparability class gb_npg_heatmapNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
27 Jul 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_heatmaprecord Smithy Green · payload sha256 9426743f6a19…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-07-27)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: gen voltage constraint
No Voltage Constraint
Operator note: genconstraint
Red - Fault Level
Operator note: gsp hm constraint manual
R
Operator note: rag colour
red
Operator note: source field
genhr
Operator note: upgenconst
GSP Constraint
Operator note: worst case constraint gen colour
Red

Injection · Generation (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2026 (2026) · scenario: DFES 2026 - Holistic Transition
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Smithy Green|DFES 2026 - Holistic Transition · payload sha256 990d6ed91ff2…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2026

Injection · Generation (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2026 (2026) · scenario: DFES 2026 - Hydrogen Evolution
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Smithy Green|DFES 2026 - Hydrogen Evolution · payload sha256 72fa01fcc36c…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2026

Injection · Generation (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2026 (2026) · scenario: DFES 2026 - Electric Engagement
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Smithy Green|DFES 2026 - Electric Engagement · payload sha256 127b5812b8eb…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2026

Injection · Generation (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2027 (2027) · scenario: DFES 2026 - Holistic Transition
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Smithy Green|DFES 2026 - Holistic Transition · payload sha256 990d6ed91ff2…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2027

Injection · Generation (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2027 (2027) · scenario: DFES 2026 - Hydrogen Evolution
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Smithy Green|DFES 2026 - Hydrogen Evolution · payload sha256 72fa01fcc36c…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2027

Injection · Generation (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2027 (2027) · scenario: DFES 2026 - Electric Engagement
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Smithy Green|DFES 2026 - Electric Engagement · payload sha256 127b5812b8eb…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2027

Injection · Generation (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2028 (2028) · scenario: DFES 2026 - Holistic Transition
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Smithy Green|DFES 2026 - Holistic Transition · payload sha256 990d6ed91ff2…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2028

Injection · Generation (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2028 (2028) · scenario: DFES 2026 - Hydrogen Evolution
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Smithy Green|DFES 2026 - Hydrogen Evolution · payload sha256 72fa01fcc36c…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2028

Injection · Generation (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2028 (2028) · scenario: DFES 2026 - Electric Engagement
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Smithy Green|DFES 2026 - Electric Engagement · payload sha256 127b5812b8eb…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2028

Injection · Generation (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2029 (2029) · scenario: DFES 2026 - Holistic Transition
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Smithy Green|DFES 2026 - Holistic Transition · payload sha256 990d6ed91ff2…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2029

Injection · Generation (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2029 (2029) · scenario: DFES 2026 - Hydrogen Evolution
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Smithy Green|DFES 2026 - Hydrogen Evolution · payload sha256 72fa01fcc36c…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2029

Injection · Generation (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2029 (2029) · scenario: DFES 2026 - Electric Engagement
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Smithy Green|DFES 2026 - Electric Engagement · payload sha256 127b5812b8eb…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2029

Injection · Generation (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2030 (2030) · scenario: DFES 2026 - Holistic Transition
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Smithy Green|DFES 2026 - Holistic Transition · payload sha256 990d6ed91ff2…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2030

Injection · Generation (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2030 (2030) · scenario: DFES 2026 - Hydrogen Evolution
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Smithy Green|DFES 2026 - Hydrogen Evolution · payload sha256 72fa01fcc36c…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2030

Injection · Generation (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2030 (2030) · scenario: DFES 2026 - Electric Engagement
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Smithy Green|DFES 2026 - Electric Engagement · payload sha256 127b5812b8eb…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2030

Injection · Generation (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2031 (2031) · scenario: DFES 2026 - Holistic Transition
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Smithy Green|DFES 2026 - Holistic Transition · payload sha256 990d6ed91ff2…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2031

Injection · Generation (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2031 (2031) · scenario: DFES 2026 - Hydrogen Evolution
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Smithy Green|DFES 2026 - Hydrogen Evolution · payload sha256 72fa01fcc36c…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2031

Injection · Generation (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2031 (2031) · scenario: DFES 2026 - Electric Engagement
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Smithy Green|DFES 2026 - Electric Engagement · payload sha256 127b5812b8eb…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2031

Injection · Generation (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2032 (2032) · scenario: DFES 2026 - Holistic Transition
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Smithy Green|DFES 2026 - Holistic Transition · payload sha256 990d6ed91ff2…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2032

Injection · Generation (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2032 (2032) · scenario: DFES 2026 - Hydrogen Evolution
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Smithy Green|DFES 2026 - Hydrogen Evolution · payload sha256 72fa01fcc36c…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2032

Injection · Generation (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2032 (2032) · scenario: DFES 2026 - Electric Engagement
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Smithy Green|DFES 2026 - Electric Engagement · payload sha256 127b5812b8eb…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2032

Injection · Generation (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2033 (2033) · scenario: DFES 2026 - Holistic Transition
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Smithy Green|DFES 2026 - Holistic Transition · payload sha256 990d6ed91ff2…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2033

Injection · Generation (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2033 (2033) · scenario: DFES 2026 - Hydrogen Evolution
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Smithy Green|DFES 2026 - Hydrogen Evolution · payload sha256 72fa01fcc36c…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2033

Injection · Generation (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2033 (2033) · scenario: DFES 2026 - Electric Engagement
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Smithy Green|DFES 2026 - Electric Engagement · payload sha256 127b5812b8eb…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2033

Injection · Generation (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2034 (2034) · scenario: DFES 2026 - Holistic Transition
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Smithy Green|DFES 2026 - Holistic Transition · payload sha256 990d6ed91ff2…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2034

Injection · Generation (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2034 (2034) · scenario: DFES 2026 - Hydrogen Evolution
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Smithy Green|DFES 2026 - Hydrogen Evolution · payload sha256 72fa01fcc36c…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2034

Injection · Generation (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2034 (2034) · scenario: DFES 2026 - Electric Engagement
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Smithy Green|DFES 2026 - Electric Engagement · payload sha256 127b5812b8eb…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2034

Injection · Generation (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2035 (2035) · scenario: DFES 2026 - Holistic Transition
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Smithy Green|DFES 2026 - Holistic Transition · payload sha256 990d6ed91ff2…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2035

Injection · Generation (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2035 (2035) · scenario: DFES 2026 - Hydrogen Evolution
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Smithy Green|DFES 2026 - Hydrogen Evolution · payload sha256 72fa01fcc36c…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2035

Injection · Generation (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2035 (2035) · scenario: DFES 2026 - Electric Engagement
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Smithy Green|DFES 2026 - Electric Engagement · payload sha256 127b5812b8eb…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2035

Injection · Generation (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2040 (2040) · scenario: DFES 2026 - Holistic Transition
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Smithy Green|DFES 2026 - Holistic Transition · payload sha256 990d6ed91ff2…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2040

Injection · Generation (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2040 (2040) · scenario: DFES 2026 - Hydrogen Evolution
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Smithy Green|DFES 2026 - Hydrogen Evolution · payload sha256 72fa01fcc36c…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2040

Injection · Generation (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2040 (2040) · scenario: DFES 2026 - Electric Engagement
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Smithy Green|DFES 2026 - Electric Engagement · payload sha256 127b5812b8eb…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2040

Injection · Generation (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2045 (2045) · scenario: DFES 2026 - Holistic Transition
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Smithy Green|DFES 2026 - Holistic Transition · payload sha256 990d6ed91ff2…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2045

Injection · Generation (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2045 (2045) · scenario: DFES 2026 - Hydrogen Evolution
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Smithy Green|DFES 2026 - Hydrogen Evolution · payload sha256 72fa01fcc36c…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2045

Injection · Generation (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2045 (2045) · scenario: DFES 2026 - Electric Engagement
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Smithy Green|DFES 2026 - Electric Engagement · payload sha256 127b5812b8eb…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2045

Injection · Generation (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2050 (2050) · scenario: DFES 2026 - Holistic Transition
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Smithy Green|DFES 2026 - Holistic Transition · payload sha256 990d6ed91ff2…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2050

Injection · Generation (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2050 (2050) · scenario: DFES 2026 - Hydrogen Evolution
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Smithy Green|DFES 2026 - Hydrogen Evolution · payload sha256 72fa01fcc36c…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2050

Injection · Generation (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2050 (2050) · scenario: DFES 2026 - Electric Engagement
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Smithy Green|DFES 2026 - Electric Engagement · payload sha256 127b5812b8eb…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2050

Injection · Generation (any) · Contracted

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology gb_npg_heatmap_2026.

Firmness
Unknown
Horizon
Now (snapshot)
Methodology
gb_npg_heatmap_2026Northern Powergrid heat-map data: thermal headroombasis operator calculated · network state unknown · comparability class gb_npg_heatmapNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
27 Jul 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_heatmaprecord Smithy Green · payload sha256 9426743f6a19…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-07-27)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
gentot

Offtake · Load (any) · Available

3.24 MVA

Published in MVA; no MW figure is derived from it.

Granted

The operator's latest published dataset reports 3.239999771 MVA under methodology gb_npg_heatmap_2026.

Firmness
Firm
Horizon
Now (snapshot)
Methodology
gb_npg_heatmap_2026Northern Powergrid heat-map data: thermal headroombasis operator calculated · network state unknown · comparability class gb_npg_heatmapNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
27 Jul 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_heatmaprecord Smithy Green · payload sha256 9426743f6a19…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-07-27)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: dem voltage constraint
No Voltage Constraint
Operator note: demconstraint
Red - Fault Level
Operator note: gsp hm constraint manual
R
Operator note: rag colour
red
Operator note: source field
demhr
Operator note: updemconst
No
Operator note: worst case constraint dem colour
Red

Offtake · Load (any) · Available

2.64 MW

Granted

The operator's latest published dataset reports 2.64 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2026 (2026) · scenario: DFES 2026 - Holistic Transition
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Smithy Green|DFES 2026 - Holistic Transition · payload sha256 a14be9f4925c…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2026

Offtake · Load (any) · Available

2.64 MW

Granted

The operator's latest published dataset reports 2.64 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2026 (2026) · scenario: DFES 2026 - Electric Engagement
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Smithy Green|DFES 2026 - Electric Engagement · payload sha256 c766c9390123…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2026

Offtake · Load (any) · Available

2.64 MW

Granted

The operator's latest published dataset reports 2.64 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2026 (2026) · scenario: DFES 2026 - Hydrogen Evolution
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Smithy Green|DFES 2026 - Hydrogen Evolution · payload sha256 748ce048c80d…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2026

Offtake · Load (any) · Available

2.44 MW

Granted

The operator's latest published dataset reports 2.44 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2027 (2027) · scenario: DFES 2026 - Holistic Transition
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Smithy Green|DFES 2026 - Holistic Transition · payload sha256 a14be9f4925c…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2027

Offtake · Load (any) · Available

2.44 MW

Granted

The operator's latest published dataset reports 2.44 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2027 (2027) · scenario: DFES 2026 - Electric Engagement
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Smithy Green|DFES 2026 - Electric Engagement · payload sha256 c766c9390123…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2027

Offtake · Load (any) · Available

2.44 MW

Granted

The operator's latest published dataset reports 2.44 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2027 (2027) · scenario: DFES 2026 - Hydrogen Evolution
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Smithy Green|DFES 2026 - Hydrogen Evolution · payload sha256 748ce048c80d…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2027

Offtake · Load (any) · Available

2.19 MW

Granted

The operator's latest published dataset reports 2.19 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2028 (2028) · scenario: DFES 2026 - Holistic Transition
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Smithy Green|DFES 2026 - Holistic Transition · payload sha256 a14be9f4925c…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2028

Offtake · Load (any) · Available

2.19 MW

Granted

The operator's latest published dataset reports 2.19 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2028 (2028) · scenario: DFES 2026 - Electric Engagement
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Smithy Green|DFES 2026 - Electric Engagement · payload sha256 c766c9390123…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2028

Offtake · Load (any) · Available

2.19 MW

Granted

The operator's latest published dataset reports 2.19 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2028 (2028) · scenario: DFES 2026 - Hydrogen Evolution
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Smithy Green|DFES 2026 - Hydrogen Evolution · payload sha256 748ce048c80d…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2028

Offtake · Load (any) · Available

1.9 MW

Granted

The operator's latest published dataset reports 1.9 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2029 (2029) · scenario: DFES 2026 - Holistic Transition
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Smithy Green|DFES 2026 - Holistic Transition · payload sha256 a14be9f4925c…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2029

Offtake · Load (any) · Available

1.9 MW

Granted

The operator's latest published dataset reports 1.9 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2029 (2029) · scenario: DFES 2026 - Electric Engagement
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Smithy Green|DFES 2026 - Electric Engagement · payload sha256 c766c9390123…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2029

Offtake · Load (any) · Available

1.9 MW

Granted

The operator's latest published dataset reports 1.9 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2029 (2029) · scenario: DFES 2026 - Hydrogen Evolution
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Smithy Green|DFES 2026 - Hydrogen Evolution · payload sha256 748ce048c80d…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2029

Offtake · Load (any) · Available

1.52 MW

Granted

The operator's latest published dataset reports 1.52 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2030 (2030) · scenario: DFES 2026 - Holistic Transition
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Smithy Green|DFES 2026 - Holistic Transition · payload sha256 a14be9f4925c…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2030

Offtake · Load (any) · Available

1.52 MW

Granted

The operator's latest published dataset reports 1.52 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2030 (2030) · scenario: DFES 2026 - Electric Engagement
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Smithy Green|DFES 2026 - Electric Engagement · payload sha256 c766c9390123…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2030

Offtake · Load (any) · Available

1.52 MW

Granted

The operator's latest published dataset reports 1.52 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2030 (2030) · scenario: DFES 2026 - Hydrogen Evolution
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Smithy Green|DFES 2026 - Hydrogen Evolution · payload sha256 748ce048c80d…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2030

Offtake · Load (any) · Available

1.07 MW

Granted

The operator's latest published dataset reports 1.07 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2031 (2031) · scenario: DFES 2026 - Holistic Transition
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Smithy Green|DFES 2026 - Holistic Transition · payload sha256 a14be9f4925c…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2031

Offtake · Load (any) · Available

1.07 MW

Granted

The operator's latest published dataset reports 1.07 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2031 (2031) · scenario: DFES 2026 - Electric Engagement
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Smithy Green|DFES 2026 - Electric Engagement · payload sha256 c766c9390123…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2031

Offtake · Load (any) · Available

1.07 MW

Granted

The operator's latest published dataset reports 1.07 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2031 (2031) · scenario: DFES 2026 - Hydrogen Evolution
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Smithy Green|DFES 2026 - Hydrogen Evolution · payload sha256 748ce048c80d…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2031

Offtake · Load (any) · Available

0.64 MW

Granted

The operator's latest published dataset reports 0.64 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2032 (2032) · scenario: DFES 2026 - Holistic Transition
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Smithy Green|DFES 2026 - Holistic Transition · payload sha256 a14be9f4925c…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2032

Offtake · Load (any) · Available

0.64 MW

Granted

The operator's latest published dataset reports 0.64 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2032 (2032) · scenario: DFES 2026 - Electric Engagement
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Smithy Green|DFES 2026 - Electric Engagement · payload sha256 c766c9390123…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2032

Offtake · Load (any) · Available

0.64 MW

Granted

The operator's latest published dataset reports 0.64 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2032 (2032) · scenario: DFES 2026 - Hydrogen Evolution
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Smithy Green|DFES 2026 - Hydrogen Evolution · payload sha256 748ce048c80d…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2032

Offtake · Load (any) · Available

0.15 MW

Granted

The operator's latest published dataset reports 0.15 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2033 (2033) · scenario: DFES 2026 - Holistic Transition
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Smithy Green|DFES 2026 - Holistic Transition · payload sha256 a14be9f4925c…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2033

Offtake · Load (any) · Available

0.15 MW

Granted

The operator's latest published dataset reports 0.15 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2033 (2033) · scenario: DFES 2026 - Electric Engagement
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Smithy Green|DFES 2026 - Electric Engagement · payload sha256 c766c9390123…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2033

Offtake · Load (any) · Available

0.15 MW

Granted

The operator's latest published dataset reports 0.15 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2033 (2033) · scenario: DFES 2026 - Hydrogen Evolution
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Smithy Green|DFES 2026 - Hydrogen Evolution · payload sha256 748ce048c80d…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2033

Offtake · Load (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2034 (2034) · scenario: DFES 2026 - Holistic Transition
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Smithy Green|DFES 2026 - Holistic Transition · payload sha256 a14be9f4925c…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2034

Offtake · Load (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2034 (2034) · scenario: DFES 2026 - Electric Engagement
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Smithy Green|DFES 2026 - Electric Engagement · payload sha256 c766c9390123…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2034

Offtake · Load (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2034 (2034) · scenario: DFES 2026 - Hydrogen Evolution
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Smithy Green|DFES 2026 - Hydrogen Evolution · payload sha256 748ce048c80d…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2034

Offtake · Load (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2035 (2035) · scenario: DFES 2026 - Holistic Transition
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Smithy Green|DFES 2026 - Holistic Transition · payload sha256 a14be9f4925c…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2035

Offtake · Load (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2035 (2035) · scenario: DFES 2026 - Electric Engagement
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Smithy Green|DFES 2026 - Electric Engagement · payload sha256 c766c9390123…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2035

Offtake · Load (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2035 (2035) · scenario: DFES 2026 - Hydrogen Evolution
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Smithy Green|DFES 2026 - Hydrogen Evolution · payload sha256 748ce048c80d…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2035

Offtake · Load (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2040 (2040) · scenario: DFES 2026 - Holistic Transition
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Smithy Green|DFES 2026 - Holistic Transition · payload sha256 a14be9f4925c…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2040

Offtake · Load (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2040 (2040) · scenario: DFES 2026 - Electric Engagement
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Smithy Green|DFES 2026 - Electric Engagement · payload sha256 c766c9390123…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2040

Offtake · Load (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2040 (2040) · scenario: DFES 2026 - Hydrogen Evolution
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Smithy Green|DFES 2026 - Hydrogen Evolution · payload sha256 748ce048c80d…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2040

Offtake · Load (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2045 (2045) · scenario: DFES 2026 - Holistic Transition
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Smithy Green|DFES 2026 - Holistic Transition · payload sha256 a14be9f4925c…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2045

Offtake · Load (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2045 (2045) · scenario: DFES 2026 - Electric Engagement
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Smithy Green|DFES 2026 - Electric Engagement · payload sha256 c766c9390123…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2045

Offtake · Load (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2045 (2045) · scenario: DFES 2026 - Hydrogen Evolution
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Smithy Green|DFES 2026 - Hydrogen Evolution · payload sha256 748ce048c80d…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2045

Offtake · Load (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2050 (2050) · scenario: DFES 2026 - Holistic Transition
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Smithy Green|DFES 2026 - Holistic Transition · payload sha256 a14be9f4925c…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2050

Offtake · Load (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2050 (2050) · scenario: DFES 2026 - Electric Engagement
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Smithy Green|DFES 2026 - Electric Engagement · payload sha256 c766c9390123…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2050

Offtake · Load (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2050 (2050) · scenario: DFES 2026 - Hydrogen Evolution
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Smithy Green|DFES 2026 - Hydrogen Evolution · payload sha256 748ce048c80d…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2050

Offtake · Load (any) · Contracted

0 MVA

Published in MVA; no MW figure is derived from it.

Granted

The operator's latest published dataset reports 0 MVA under methodology gb_npg_heatmap_2026.

Firmness
Unknown
Horizon
Now (snapshot)
Methodology
gb_npg_heatmap_2026Northern Powergrid heat-map data: thermal headroombasis operator calculated · network state unknown · comparability class gb_npg_heatmapNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
27 Jul 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_heatmaprecord Smithy Green · payload sha256 9426743f6a19…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-07-27)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demtot

Offtake · Load (any) · Total

8 MVA

Published in MVA; no MW figure is derived from it.

Granted

The operator's latest published dataset reports 8 MVA under methodology gb_npg_heatmap_2026.

Firmness
Firm
Horizon
Now (snapshot)
Methodology
gb_npg_heatmap_2026Northern Powergrid heat-map data: thermal headroombasis operator calculated · network state unknown · comparability class gb_npg_heatmapNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
27 Jul 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_heatmaprecord Smithy Green · payload sha256 9426743f6a19…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-07-27)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
firm_cap

History

Served series only

Injection · Generation (any) · Available

current 1.14 MW

26 Sep 2026: 1.14 MW
26 Sep 2026range 1.14–1.14 MW26 Sep 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current1.14 MW

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Load (any) · Available

current 3.24 MVA

26 Sep 2026: 3.24 MVA
26 Sep 2026range 3.24–3.24 MVA26 Sep 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current3.24 MVA

Time axis: when we observed each value, not the operator’s effective date.

Injection · Generation (any) · Contracted

current 0 MW

26 Sep 2026: 0 MW
26 Sep 2026range 0–0 MW26 Sep 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current0 MW

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Load (any) · Contracted

current 0 MVA

26 Sep 2026: 0 MVA
26 Sep 2026range 0–0 MVA26 Sep 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current0 MVA

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Load (any) · Total

current 8 MVA

26 Sep 2026: 8 MVA
26 Sep 2026range 8–8 MVA26 Sep 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current8 MVA

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Load (any) · Available · 2026

current 2.64 MW

26 Sep 2026: 2.64 MW
26 Sep 2026range 2.64–2.64 MW26 Sep 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current2.64 MW

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Load (any) · Available · 2027

current 2.44 MW

26 Sep 2026: 2.44 MW
26 Sep 2026range 2.44–2.44 MW26 Sep 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current2.44 MW

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Load (any) · Available · 2028

current 2.19 MW

26 Sep 2026: 2.19 MW
26 Sep 2026range 2.19–2.19 MW26 Sep 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current2.19 MW

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Load (any) · Available · 2029

current 1.9 MW

26 Sep 2026: 1.9 MW
26 Sep 2026range 1.9–1.9 MW26 Sep 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current1.9 MW

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Load (any) · Available · 2030

current 1.52 MW

26 Sep 2026: 1.52 MW
26 Sep 2026range 1.52–1.52 MW26 Sep 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current1.52 MW

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Load (any) · Available · 2031

current 1.07 MW

26 Sep 2026: 1.07 MW
26 Sep 2026range 1.07–1.07 MW26 Sep 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current1.07 MW

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Load (any) · Available · 2032

current 0.64 MW

26 Sep 2026: 0.64 MW
26 Sep 2026range 0.64–0.64 MW26 Sep 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current0.64 MW

Time axis: when we observed each value, not the operator’s effective date.

The first 12 of 83 served series with a history. The history route returns every one of them.

Through the API

curl "https://api.gridcapacityapi.com/v1/substations/sub_06gdq6mqndsghdcm1rs9k818w0/capacity" \  -H "Authorization: Bearer gc_live_..."
Smithy Green 11 kV substation: grid capacity (Northern Powergrid) · GridCapacity API