Substation · 33 kV · bsp

Scunthorpe South

Northern Powergrid · United Kingdom

Latest published values

83 served · 0 withheld

Each row is what the operator’s latest published dataset reports for one combination of direction, technology, measure, firmness and horizon. Hosting-capacity figures are indicative and reflect what operators publish. They are not a connection offer; only the operator can confirm capacity for a specific request.

Latest published capacity values, one row per series
DirectionTechnologyMeasureValueFirmnessHorizonSource date
InjectionGeneration (any)Available0 MWFirmNow (snapshot)27 Jul 2026
InjectionGeneration (any)Available0 MWUnknown2026 (2026)scenario: DFES 2026 - Electric Engagement24 Apr 2026
InjectionGeneration (any)Available0 MWUnknown2026 (2026)scenario: DFES 2026 - Holistic Transition24 Apr 2026
InjectionGeneration (any)Available0 MWUnknown2026 (2026)scenario: DFES 2026 - Hydrogen Evolution24 Apr 2026
InjectionGeneration (any)Available0 MWUnknown2027 (2027)scenario: DFES 2026 - Electric Engagement24 Apr 2026
InjectionGeneration (any)Available0 MWUnknown2027 (2027)scenario: DFES 2026 - Holistic Transition24 Apr 2026
InjectionGeneration (any)Available0 MWUnknown2027 (2027)scenario: DFES 2026 - Hydrogen Evolution24 Apr 2026
InjectionGeneration (any)Available0 MWUnknown2028 (2028)scenario: DFES 2026 - Electric Engagement24 Apr 2026
InjectionGeneration (any)Available0 MWUnknown2028 (2028)scenario: DFES 2026 - Holistic Transition24 Apr 2026
InjectionGeneration (any)Available0 MWUnknown2028 (2028)scenario: DFES 2026 - Hydrogen Evolution24 Apr 2026
InjectionGeneration (any)Available0 MWUnknown2029 (2029)scenario: DFES 2026 - Electric Engagement24 Apr 2026
InjectionGeneration (any)Available0 MWUnknown2029 (2029)scenario: DFES 2026 - Holistic Transition24 Apr 2026
InjectionGeneration (any)Available0 MWUnknown2029 (2029)scenario: DFES 2026 - Hydrogen Evolution24 Apr 2026
InjectionGeneration (any)Available0 MWUnknown2030 (2030)scenario: DFES 2026 - Electric Engagement24 Apr 2026
InjectionGeneration (any)Available0 MWUnknown2030 (2030)scenario: DFES 2026 - Holistic Transition24 Apr 2026
InjectionGeneration (any)Available0 MWUnknown2030 (2030)scenario: DFES 2026 - Hydrogen Evolution24 Apr 2026
InjectionGeneration (any)Available0 MWUnknown2031 (2031)scenario: DFES 2026 - Electric Engagement24 Apr 2026
InjectionGeneration (any)Available0 MWUnknown2031 (2031)scenario: DFES 2026 - Holistic Transition24 Apr 2026
InjectionGeneration (any)Available0 MWUnknown2031 (2031)scenario: DFES 2026 - Hydrogen Evolution24 Apr 2026
InjectionGeneration (any)Available0 MWUnknown2032 (2032)scenario: DFES 2026 - Electric Engagement24 Apr 2026
InjectionGeneration (any)Available0 MWUnknown2032 (2032)scenario: DFES 2026 - Holistic Transition24 Apr 2026
InjectionGeneration (any)Available0 MWUnknown2032 (2032)scenario: DFES 2026 - Hydrogen Evolution24 Apr 2026
InjectionGeneration (any)Available0 MWUnknown2033 (2033)scenario: DFES 2026 - Electric Engagement24 Apr 2026
InjectionGeneration (any)Available0 MWUnknown2033 (2033)scenario: DFES 2026 - Holistic Transition24 Apr 2026
InjectionGeneration (any)Available0 MWUnknown2033 (2033)scenario: DFES 2026 - Hydrogen Evolution24 Apr 2026
InjectionGeneration (any)Available0 MWUnknown2034 (2034)scenario: DFES 2026 - Electric Engagement24 Apr 2026
InjectionGeneration (any)Available0 MWUnknown2034 (2034)scenario: DFES 2026 - Holistic Transition24 Apr 2026
InjectionGeneration (any)Available0 MWUnknown2034 (2034)scenario: DFES 2026 - Hydrogen Evolution24 Apr 2026
InjectionGeneration (any)Available0 MWUnknown2035 (2035)scenario: DFES 2026 - Electric Engagement24 Apr 2026
InjectionGeneration (any)Available0 MWUnknown2035 (2035)scenario: DFES 2026 - Holistic Transition24 Apr 2026
InjectionGeneration (any)Available0 MWUnknown2035 (2035)scenario: DFES 2026 - Hydrogen Evolution24 Apr 2026
InjectionGeneration (any)Available0 MWUnknown2040 (2040)scenario: DFES 2026 - Electric Engagement24 Apr 2026
InjectionGeneration (any)Available0 MWUnknown2040 (2040)scenario: DFES 2026 - Holistic Transition24 Apr 2026
InjectionGeneration (any)Available0 MWUnknown2040 (2040)scenario: DFES 2026 - Hydrogen Evolution24 Apr 2026
InjectionGeneration (any)Available0 MWUnknown2045 (2045)scenario: DFES 2026 - Electric Engagement24 Apr 2026
InjectionGeneration (any)Available0 MWUnknown2045 (2045)scenario: DFES 2026 - Holistic Transition24 Apr 2026
InjectionGeneration (any)Available0 MWUnknown2045 (2045)scenario: DFES 2026 - Hydrogen Evolution24 Apr 2026
InjectionGeneration (any)Available0 MWUnknown2050 (2050)scenario: DFES 2026 - Electric Engagement24 Apr 2026
InjectionGeneration (any)Available0 MWUnknown2050 (2050)scenario: DFES 2026 - Holistic Transition24 Apr 2026
InjectionGeneration (any)Available0 MWUnknown2050 (2050)scenario: DFES 2026 - Hydrogen Evolution24 Apr 2026
InjectionGeneration (any)Contracted20.384 MWUnknownNow (snapshot)27 Jul 2026
OfftakeLoad (any)Available0 MVAFirmNow (snapshot)27 Jul 2026
OfftakeLoad (any)Available77.77 MWUnknown2026 (2026)scenario: DFES 2026 - Electric Engagement24 Apr 2026
OfftakeLoad (any)Available77.77 MWUnknown2026 (2026)scenario: DFES 2026 - Holistic Transition24 Apr 2026
OfftakeLoad (any)Available77.77 MWUnknown2026 (2026)scenario: DFES 2026 - Hydrogen Evolution24 Apr 2026
OfftakeLoad (any)Available76.92 MWUnknown2027 (2027)scenario: DFES 2026 - Electric Engagement24 Apr 2026
OfftakeLoad (any)Available76.92 MWUnknown2027 (2027)scenario: DFES 2026 - Holistic Transition24 Apr 2026
OfftakeLoad (any)Available76.92 MWUnknown2027 (2027)scenario: DFES 2026 - Hydrogen Evolution24 Apr 2026
OfftakeLoad (any)Available75.86 MWUnknown2028 (2028)scenario: DFES 2026 - Electric Engagement24 Apr 2026
OfftakeLoad (any)Available75.86 MWUnknown2028 (2028)scenario: DFES 2026 - Holistic Transition24 Apr 2026
OfftakeLoad (any)Available75.86 MWUnknown2028 (2028)scenario: DFES 2026 - Hydrogen Evolution24 Apr 2026
OfftakeLoad (any)Available74.72 MWUnknown2029 (2029)scenario: DFES 2026 - Electric Engagement24 Apr 2026
OfftakeLoad (any)Available74.72 MWUnknown2029 (2029)scenario: DFES 2026 - Holistic Transition24 Apr 2026
OfftakeLoad (any)Available74.72 MWUnknown2029 (2029)scenario: DFES 2026 - Hydrogen Evolution24 Apr 2026
OfftakeLoad (any)Available73.16 MWUnknown2030 (2030)scenario: DFES 2026 - Electric Engagement24 Apr 2026
OfftakeLoad (any)Available73.16 MWUnknown2030 (2030)scenario: DFES 2026 - Holistic Transition24 Apr 2026
OfftakeLoad (any)Available73.16 MWUnknown2030 (2030)scenario: DFES 2026 - Hydrogen Evolution24 Apr 2026
OfftakeLoad (any)Available71.24 MWUnknown2031 (2031)scenario: DFES 2026 - Electric Engagement24 Apr 2026
OfftakeLoad (any)Available71.24 MWUnknown2031 (2031)scenario: DFES 2026 - Holistic Transition24 Apr 2026
OfftakeLoad (any)Available71.24 MWUnknown2031 (2031)scenario: DFES 2026 - Hydrogen Evolution24 Apr 2026
OfftakeLoad (any)Available69.4 MWUnknown2032 (2032)scenario: DFES 2026 - Electric Engagement24 Apr 2026
OfftakeLoad (any)Available69.4 MWUnknown2032 (2032)scenario: DFES 2026 - Holistic Transition24 Apr 2026
OfftakeLoad (any)Available69.4 MWUnknown2032 (2032)scenario: DFES 2026 - Hydrogen Evolution24 Apr 2026
OfftakeLoad (any)Available67.31 MWUnknown2033 (2033)scenario: DFES 2026 - Electric Engagement24 Apr 2026
OfftakeLoad (any)Available67.31 MWUnknown2033 (2033)scenario: DFES 2026 - Holistic Transition24 Apr 2026
OfftakeLoad (any)Available67.31 MWUnknown2033 (2033)scenario: DFES 2026 - Hydrogen Evolution24 Apr 2026
OfftakeLoad (any)Available65.14 MWUnknown2034 (2034)scenario: DFES 2026 - Electric Engagement24 Apr 2026
OfftakeLoad (any)Available65.14 MWUnknown2034 (2034)scenario: DFES 2026 - Holistic Transition24 Apr 2026
OfftakeLoad (any)Available65.14 MWUnknown2034 (2034)scenario: DFES 2026 - Hydrogen Evolution24 Apr 2026
OfftakeLoad (any)Available63.01 MWUnknown2035 (2035)scenario: DFES 2026 - Electric Engagement24 Apr 2026
OfftakeLoad (any)Available62.85 MWUnknown2035 (2035)scenario: DFES 2026 - Holistic Transition24 Apr 2026
OfftakeLoad (any)Available61.61 MWUnknown2035 (2035)scenario: DFES 2026 - Hydrogen Evolution24 Apr 2026
OfftakeLoad (any)Available50.65 MWUnknown2040 (2040)scenario: DFES 2026 - Hydrogen Evolution24 Apr 2026
OfftakeLoad (any)Available49.23 MWUnknown2040 (2040)scenario: DFES 2026 - Electric Engagement24 Apr 2026
OfftakeLoad (any)Available47.82 MWUnknown2040 (2040)scenario: DFES 2026 - Holistic Transition24 Apr 2026
OfftakeLoad (any)Available43.34 MWUnknown2045 (2045)scenario: DFES 2026 - Hydrogen Evolution24 Apr 2026
OfftakeLoad (any)Available40.94 MWUnknown2045 (2045)scenario: DFES 2026 - Electric Engagement24 Apr 2026
OfftakeLoad (any)Available39.99 MWUnknown2045 (2045)scenario: DFES 2026 - Holistic Transition24 Apr 2026
OfftakeLoad (any)Available38.69 MWUnknown2050 (2050)scenario: DFES 2026 - Hydrogen Evolution24 Apr 2026
OfftakeLoad (any)Available35.67 MWUnknown2050 (2050)scenario: DFES 2026 - Electric Engagement24 Apr 2026
OfftakeLoad (any)Available35.64 MWUnknown2050 (2050)scenario: DFES 2026 - Holistic Transition24 Apr 2026
OfftakeLoad (any)Contracted3.8127 MVAUnknownNow (snapshot)27 Jul 2026
OfftakeLoad (any)Total112 MVAFirmNow (snapshot)27 Jul 2026

Supported by Northern Powergrid Open Data (last updated 2026-04-24)Supported by Northern Powergrid Open Data (last updated 2026-07-27)

What each value means

Methodology, both clocks, provenance and rights

Injection · Generation (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology gb_npg_heatmap_2026.

Firmness
Firm
Horizon
Now (snapshot)
Methodology
gb_npg_heatmap_2026Northern Powergrid heat-map data: thermal headroombasis operator calculated · network state unknown · comparability class gb_npg_heatmapNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
27 Jul 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_heatmaprecord Scunthorpe South · payload sha256 bb9acca41c75…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-07-27)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: gen voltage constraint
Data Not Available
Operator note: genconstraint
Red - Fault Level
Operator note: gsp hm constraint manual
R
Operator note: rag colour
red
Operator note: source field
genhr
Operator note: upgenconst
NO
Operator note: worst case constraint gen colour
Red

Injection · Generation (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2026 (2026) · scenario: DFES 2026 - Electric Engagement
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Scunthorpe South|DFES 2026 - Electric Engagement · payload sha256 0a46f05357c0…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2026

Injection · Generation (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2026 (2026) · scenario: DFES 2026 - Holistic Transition
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Scunthorpe South|DFES 2026 - Holistic Transition · payload sha256 24de074fbe25…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2026

Injection · Generation (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2026 (2026) · scenario: DFES 2026 - Hydrogen Evolution
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Scunthorpe South|DFES 2026 - Hydrogen Evolution · payload sha256 aa1445c1bebf…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2026

Injection · Generation (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2027 (2027) · scenario: DFES 2026 - Electric Engagement
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Scunthorpe South|DFES 2026 - Electric Engagement · payload sha256 0a46f05357c0…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2027

Injection · Generation (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2027 (2027) · scenario: DFES 2026 - Holistic Transition
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Scunthorpe South|DFES 2026 - Holistic Transition · payload sha256 24de074fbe25…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2027

Injection · Generation (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2027 (2027) · scenario: DFES 2026 - Hydrogen Evolution
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Scunthorpe South|DFES 2026 - Hydrogen Evolution · payload sha256 aa1445c1bebf…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2027

Injection · Generation (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2028 (2028) · scenario: DFES 2026 - Electric Engagement
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Scunthorpe South|DFES 2026 - Electric Engagement · payload sha256 0a46f05357c0…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2028

Injection · Generation (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2028 (2028) · scenario: DFES 2026 - Holistic Transition
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Scunthorpe South|DFES 2026 - Holistic Transition · payload sha256 24de074fbe25…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2028

Injection · Generation (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2028 (2028) · scenario: DFES 2026 - Hydrogen Evolution
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Scunthorpe South|DFES 2026 - Hydrogen Evolution · payload sha256 aa1445c1bebf…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2028

Injection · Generation (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2029 (2029) · scenario: DFES 2026 - Electric Engagement
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Scunthorpe South|DFES 2026 - Electric Engagement · payload sha256 0a46f05357c0…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2029

Injection · Generation (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2029 (2029) · scenario: DFES 2026 - Holistic Transition
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Scunthorpe South|DFES 2026 - Holistic Transition · payload sha256 24de074fbe25…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2029

Injection · Generation (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2029 (2029) · scenario: DFES 2026 - Hydrogen Evolution
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Scunthorpe South|DFES 2026 - Hydrogen Evolution · payload sha256 aa1445c1bebf…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2029

Injection · Generation (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2030 (2030) · scenario: DFES 2026 - Electric Engagement
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Scunthorpe South|DFES 2026 - Electric Engagement · payload sha256 0a46f05357c0…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2030

Injection · Generation (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2030 (2030) · scenario: DFES 2026 - Holistic Transition
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Scunthorpe South|DFES 2026 - Holistic Transition · payload sha256 24de074fbe25…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2030

Injection · Generation (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2030 (2030) · scenario: DFES 2026 - Hydrogen Evolution
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Scunthorpe South|DFES 2026 - Hydrogen Evolution · payload sha256 aa1445c1bebf…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2030

Injection · Generation (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2031 (2031) · scenario: DFES 2026 - Electric Engagement
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Scunthorpe South|DFES 2026 - Electric Engagement · payload sha256 0a46f05357c0…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2031

Injection · Generation (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2031 (2031) · scenario: DFES 2026 - Holistic Transition
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Scunthorpe South|DFES 2026 - Holistic Transition · payload sha256 24de074fbe25…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2031

Injection · Generation (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2031 (2031) · scenario: DFES 2026 - Hydrogen Evolution
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Scunthorpe South|DFES 2026 - Hydrogen Evolution · payload sha256 aa1445c1bebf…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2031

Injection · Generation (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2032 (2032) · scenario: DFES 2026 - Electric Engagement
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Scunthorpe South|DFES 2026 - Electric Engagement · payload sha256 0a46f05357c0…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2032

Injection · Generation (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2032 (2032) · scenario: DFES 2026 - Holistic Transition
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Scunthorpe South|DFES 2026 - Holistic Transition · payload sha256 24de074fbe25…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2032

Injection · Generation (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2032 (2032) · scenario: DFES 2026 - Hydrogen Evolution
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Scunthorpe South|DFES 2026 - Hydrogen Evolution · payload sha256 aa1445c1bebf…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2032

Injection · Generation (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2033 (2033) · scenario: DFES 2026 - Electric Engagement
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Scunthorpe South|DFES 2026 - Electric Engagement · payload sha256 0a46f05357c0…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2033

Injection · Generation (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2033 (2033) · scenario: DFES 2026 - Holistic Transition
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Scunthorpe South|DFES 2026 - Holistic Transition · payload sha256 24de074fbe25…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2033

Injection · Generation (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2033 (2033) · scenario: DFES 2026 - Hydrogen Evolution
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Scunthorpe South|DFES 2026 - Hydrogen Evolution · payload sha256 aa1445c1bebf…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2033

Injection · Generation (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2034 (2034) · scenario: DFES 2026 - Electric Engagement
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Scunthorpe South|DFES 2026 - Electric Engagement · payload sha256 0a46f05357c0…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2034

Injection · Generation (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2034 (2034) · scenario: DFES 2026 - Holistic Transition
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Scunthorpe South|DFES 2026 - Holistic Transition · payload sha256 24de074fbe25…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2034

Injection · Generation (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2034 (2034) · scenario: DFES 2026 - Hydrogen Evolution
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Scunthorpe South|DFES 2026 - Hydrogen Evolution · payload sha256 aa1445c1bebf…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2034

Injection · Generation (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2035 (2035) · scenario: DFES 2026 - Electric Engagement
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Scunthorpe South|DFES 2026 - Electric Engagement · payload sha256 0a46f05357c0…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2035

Injection · Generation (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2035 (2035) · scenario: DFES 2026 - Holistic Transition
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Scunthorpe South|DFES 2026 - Holistic Transition · payload sha256 24de074fbe25…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2035

Injection · Generation (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2035 (2035) · scenario: DFES 2026 - Hydrogen Evolution
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Scunthorpe South|DFES 2026 - Hydrogen Evolution · payload sha256 aa1445c1bebf…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2035

Injection · Generation (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2040 (2040) · scenario: DFES 2026 - Electric Engagement
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Scunthorpe South|DFES 2026 - Electric Engagement · payload sha256 0a46f05357c0…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2040

Injection · Generation (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2040 (2040) · scenario: DFES 2026 - Holistic Transition
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Scunthorpe South|DFES 2026 - Holistic Transition · payload sha256 24de074fbe25…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2040

Injection · Generation (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2040 (2040) · scenario: DFES 2026 - Hydrogen Evolution
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Scunthorpe South|DFES 2026 - Hydrogen Evolution · payload sha256 aa1445c1bebf…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2040

Injection · Generation (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2045 (2045) · scenario: DFES 2026 - Electric Engagement
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Scunthorpe South|DFES 2026 - Electric Engagement · payload sha256 0a46f05357c0…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2045

Injection · Generation (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2045 (2045) · scenario: DFES 2026 - Holistic Transition
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Scunthorpe South|DFES 2026 - Holistic Transition · payload sha256 24de074fbe25…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2045

Injection · Generation (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2045 (2045) · scenario: DFES 2026 - Hydrogen Evolution
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Scunthorpe South|DFES 2026 - Hydrogen Evolution · payload sha256 aa1445c1bebf…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2045

Injection · Generation (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2050 (2050) · scenario: DFES 2026 - Electric Engagement
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Scunthorpe South|DFES 2026 - Electric Engagement · payload sha256 0a46f05357c0…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2050

Injection · Generation (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2050 (2050) · scenario: DFES 2026 - Holistic Transition
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Scunthorpe South|DFES 2026 - Holistic Transition · payload sha256 24de074fbe25…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2050

Injection · Generation (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2050 (2050) · scenario: DFES 2026 - Hydrogen Evolution
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Scunthorpe South|DFES 2026 - Hydrogen Evolution · payload sha256 aa1445c1bebf…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2050

Injection · Generation (any) · Contracted

20.384 MW

Granted

The operator's latest published dataset reports 20.384 MW under methodology gb_npg_heatmap_2026.

Firmness
Unknown
Horizon
Now (snapshot)
Methodology
gb_npg_heatmap_2026Northern Powergrid heat-map data: thermal headroombasis operator calculated · network state unknown · comparability class gb_npg_heatmapNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
27 Jul 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_heatmaprecord Scunthorpe South · payload sha256 bb9acca41c75…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-07-27)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
gentot

Offtake · Load (any) · Available

0 MVA

Published in MVA; no MW figure is derived from it.

Granted

The operator's latest published dataset reports 0 MVA under methodology gb_npg_heatmap_2026.

Firmness
Firm
Horizon
Now (snapshot)
Methodology
gb_npg_heatmap_2026Northern Powergrid heat-map data: thermal headroombasis operator calculated · network state unknown · comparability class gb_npg_heatmapNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
27 Jul 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_heatmaprecord Scunthorpe South · payload sha256 bb9acca41c75…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-07-27)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: dem voltage constraint
Data Not Available
Operator note: demconstraint
Red - Fault Level
Operator note: gsp hm constraint manual
R
Operator note: rag colour
red
Operator note: source field
demhr
Operator note: updemconst
Upstream Constraint
Operator note: worst case constraint dem colour
Red

Offtake · Load (any) · Available

77.77 MW

Granted

The operator's latest published dataset reports 77.77 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2026 (2026) · scenario: DFES 2026 - Electric Engagement
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Scunthorpe South|DFES 2026 - Electric Engagement · payload sha256 8e7a414bd2d9…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2026

Offtake · Load (any) · Available

77.77 MW

Granted

The operator's latest published dataset reports 77.77 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2026 (2026) · scenario: DFES 2026 - Holistic Transition
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Scunthorpe South|DFES 2026 - Holistic Transition · payload sha256 ff6ec7534edd…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2026

Offtake · Load (any) · Available

77.77 MW

Granted

The operator's latest published dataset reports 77.77 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2026 (2026) · scenario: DFES 2026 - Hydrogen Evolution
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Scunthorpe South|DFES 2026 - Hydrogen Evolution · payload sha256 3bee4d7f222e…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2026

Offtake · Load (any) · Available

76.92 MW

Granted

The operator's latest published dataset reports 76.92 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2027 (2027) · scenario: DFES 2026 - Electric Engagement
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Scunthorpe South|DFES 2026 - Electric Engagement · payload sha256 8e7a414bd2d9…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2027

Offtake · Load (any) · Available

76.92 MW

Granted

The operator's latest published dataset reports 76.92 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2027 (2027) · scenario: DFES 2026 - Holistic Transition
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Scunthorpe South|DFES 2026 - Holistic Transition · payload sha256 ff6ec7534edd…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2027

Offtake · Load (any) · Available

76.92 MW

Granted

The operator's latest published dataset reports 76.92 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2027 (2027) · scenario: DFES 2026 - Hydrogen Evolution
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Scunthorpe South|DFES 2026 - Hydrogen Evolution · payload sha256 3bee4d7f222e…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2027

Offtake · Load (any) · Available

75.86 MW

Granted

The operator's latest published dataset reports 75.86 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2028 (2028) · scenario: DFES 2026 - Electric Engagement
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Scunthorpe South|DFES 2026 - Electric Engagement · payload sha256 8e7a414bd2d9…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2028

Offtake · Load (any) · Available

75.86 MW

Granted

The operator's latest published dataset reports 75.86 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2028 (2028) · scenario: DFES 2026 - Holistic Transition
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Scunthorpe South|DFES 2026 - Holistic Transition · payload sha256 ff6ec7534edd…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2028

Offtake · Load (any) · Available

75.86 MW

Granted

The operator's latest published dataset reports 75.86 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2028 (2028) · scenario: DFES 2026 - Hydrogen Evolution
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Scunthorpe South|DFES 2026 - Hydrogen Evolution · payload sha256 3bee4d7f222e…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2028

Offtake · Load (any) · Available

74.72 MW

Granted

The operator's latest published dataset reports 74.72 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2029 (2029) · scenario: DFES 2026 - Electric Engagement
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Scunthorpe South|DFES 2026 - Electric Engagement · payload sha256 8e7a414bd2d9…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2029

Offtake · Load (any) · Available

74.72 MW

Granted

The operator's latest published dataset reports 74.72 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2029 (2029) · scenario: DFES 2026 - Holistic Transition
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Scunthorpe South|DFES 2026 - Holistic Transition · payload sha256 ff6ec7534edd…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2029

Offtake · Load (any) · Available

74.72 MW

Granted

The operator's latest published dataset reports 74.72 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2029 (2029) · scenario: DFES 2026 - Hydrogen Evolution
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Scunthorpe South|DFES 2026 - Hydrogen Evolution · payload sha256 3bee4d7f222e…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2029

Offtake · Load (any) · Available

73.16 MW

Granted

The operator's latest published dataset reports 73.16 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2030 (2030) · scenario: DFES 2026 - Electric Engagement
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Scunthorpe South|DFES 2026 - Electric Engagement · payload sha256 8e7a414bd2d9…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2030

Offtake · Load (any) · Available

73.16 MW

Granted

The operator's latest published dataset reports 73.16 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2030 (2030) · scenario: DFES 2026 - Holistic Transition
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Scunthorpe South|DFES 2026 - Holistic Transition · payload sha256 ff6ec7534edd…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2030

Offtake · Load (any) · Available

73.16 MW

Granted

The operator's latest published dataset reports 73.16 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2030 (2030) · scenario: DFES 2026 - Hydrogen Evolution
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Scunthorpe South|DFES 2026 - Hydrogen Evolution · payload sha256 3bee4d7f222e…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2030

Offtake · Load (any) · Available

71.24 MW

Granted

The operator's latest published dataset reports 71.24 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2031 (2031) · scenario: DFES 2026 - Electric Engagement
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Scunthorpe South|DFES 2026 - Electric Engagement · payload sha256 8e7a414bd2d9…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2031

Offtake · Load (any) · Available

71.24 MW

Granted

The operator's latest published dataset reports 71.24 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2031 (2031) · scenario: DFES 2026 - Holistic Transition
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Scunthorpe South|DFES 2026 - Holistic Transition · payload sha256 ff6ec7534edd…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2031

Offtake · Load (any) · Available

71.24 MW

Granted

The operator's latest published dataset reports 71.24 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2031 (2031) · scenario: DFES 2026 - Hydrogen Evolution
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Scunthorpe South|DFES 2026 - Hydrogen Evolution · payload sha256 3bee4d7f222e…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2031

Offtake · Load (any) · Available

69.4 MW

Granted

The operator's latest published dataset reports 69.4 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2032 (2032) · scenario: DFES 2026 - Electric Engagement
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Scunthorpe South|DFES 2026 - Electric Engagement · payload sha256 8e7a414bd2d9…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2032

Offtake · Load (any) · Available

69.4 MW

Granted

The operator's latest published dataset reports 69.4 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2032 (2032) · scenario: DFES 2026 - Holistic Transition
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Scunthorpe South|DFES 2026 - Holistic Transition · payload sha256 ff6ec7534edd…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2032

Offtake · Load (any) · Available

69.4 MW

Granted

The operator's latest published dataset reports 69.4 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2032 (2032) · scenario: DFES 2026 - Hydrogen Evolution
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Scunthorpe South|DFES 2026 - Hydrogen Evolution · payload sha256 3bee4d7f222e…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2032

Offtake · Load (any) · Available

67.31 MW

Granted

The operator's latest published dataset reports 67.31 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2033 (2033) · scenario: DFES 2026 - Electric Engagement
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Scunthorpe South|DFES 2026 - Electric Engagement · payload sha256 8e7a414bd2d9…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2033

Offtake · Load (any) · Available

67.31 MW

Granted

The operator's latest published dataset reports 67.31 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2033 (2033) · scenario: DFES 2026 - Holistic Transition
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Scunthorpe South|DFES 2026 - Holistic Transition · payload sha256 ff6ec7534edd…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2033

Offtake · Load (any) · Available

67.31 MW

Granted

The operator's latest published dataset reports 67.31 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2033 (2033) · scenario: DFES 2026 - Hydrogen Evolution
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Scunthorpe South|DFES 2026 - Hydrogen Evolution · payload sha256 3bee4d7f222e…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2033

Offtake · Load (any) · Available

65.14 MW

Granted

The operator's latest published dataset reports 65.14 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2034 (2034) · scenario: DFES 2026 - Electric Engagement
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Scunthorpe South|DFES 2026 - Electric Engagement · payload sha256 8e7a414bd2d9…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2034

Offtake · Load (any) · Available

65.14 MW

Granted

The operator's latest published dataset reports 65.14 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2034 (2034) · scenario: DFES 2026 - Holistic Transition
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Scunthorpe South|DFES 2026 - Holistic Transition · payload sha256 ff6ec7534edd…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2034

Offtake · Load (any) · Available

65.14 MW

Granted

The operator's latest published dataset reports 65.14 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2034 (2034) · scenario: DFES 2026 - Hydrogen Evolution
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Scunthorpe South|DFES 2026 - Hydrogen Evolution · payload sha256 3bee4d7f222e…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2034

Offtake · Load (any) · Available

63.01 MW

Granted

The operator's latest published dataset reports 63.01 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2035 (2035) · scenario: DFES 2026 - Electric Engagement
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Scunthorpe South|DFES 2026 - Electric Engagement · payload sha256 8e7a414bd2d9…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2035

Offtake · Load (any) · Available

62.85 MW

Granted

The operator's latest published dataset reports 62.85 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2035 (2035) · scenario: DFES 2026 - Holistic Transition
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Scunthorpe South|DFES 2026 - Holistic Transition · payload sha256 ff6ec7534edd…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2035

Offtake · Load (any) · Available

61.61 MW

Granted

The operator's latest published dataset reports 61.61 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2035 (2035) · scenario: DFES 2026 - Hydrogen Evolution
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Scunthorpe South|DFES 2026 - Hydrogen Evolution · payload sha256 3bee4d7f222e…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2035

Offtake · Load (any) · Available

50.65 MW

Granted

The operator's latest published dataset reports 50.65 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2040 (2040) · scenario: DFES 2026 - Hydrogen Evolution
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Scunthorpe South|DFES 2026 - Hydrogen Evolution · payload sha256 3bee4d7f222e…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2040

Offtake · Load (any) · Available

49.23 MW

Granted

The operator's latest published dataset reports 49.23 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2040 (2040) · scenario: DFES 2026 - Electric Engagement
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Scunthorpe South|DFES 2026 - Electric Engagement · payload sha256 8e7a414bd2d9…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2040

Offtake · Load (any) · Available

47.82 MW

Granted

The operator's latest published dataset reports 47.82 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2040 (2040) · scenario: DFES 2026 - Holistic Transition
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Scunthorpe South|DFES 2026 - Holistic Transition · payload sha256 ff6ec7534edd…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2040

Offtake · Load (any) · Available

43.34 MW

Granted

The operator's latest published dataset reports 43.34 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2045 (2045) · scenario: DFES 2026 - Hydrogen Evolution
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Scunthorpe South|DFES 2026 - Hydrogen Evolution · payload sha256 3bee4d7f222e…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2045

Offtake · Load (any) · Available

40.94 MW

Granted

The operator's latest published dataset reports 40.94 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2045 (2045) · scenario: DFES 2026 - Electric Engagement
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Scunthorpe South|DFES 2026 - Electric Engagement · payload sha256 8e7a414bd2d9…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2045

Offtake · Load (any) · Available

39.99 MW

Granted

The operator's latest published dataset reports 39.99 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2045 (2045) · scenario: DFES 2026 - Holistic Transition
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Scunthorpe South|DFES 2026 - Holistic Transition · payload sha256 ff6ec7534edd…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2045

Offtake · Load (any) · Available

38.69 MW

Granted

The operator's latest published dataset reports 38.69 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2050 (2050) · scenario: DFES 2026 - Hydrogen Evolution
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Scunthorpe South|DFES 2026 - Hydrogen Evolution · payload sha256 3bee4d7f222e…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2050

Offtake · Load (any) · Available

35.67 MW

Granted

The operator's latest published dataset reports 35.67 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2050 (2050) · scenario: DFES 2026 - Electric Engagement
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Scunthorpe South|DFES 2026 - Electric Engagement · payload sha256 8e7a414bd2d9…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2050

Offtake · Load (any) · Available

35.64 MW

Granted

The operator's latest published dataset reports 35.64 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2050 (2050) · scenario: DFES 2026 - Holistic Transition
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Scunthorpe South|DFES 2026 - Holistic Transition · payload sha256 ff6ec7534edd…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2050

Offtake · Load (any) · Contracted

3.8127 MVA

Published in MVA; no MW figure is derived from it.

Granted

The operator's latest published dataset reports 3.8127 MVA under methodology gb_npg_heatmap_2026.

Firmness
Unknown
Horizon
Now (snapshot)
Methodology
gb_npg_heatmap_2026Northern Powergrid heat-map data: thermal headroombasis operator calculated · network state unknown · comparability class gb_npg_heatmapNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
27 Jul 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_heatmaprecord Scunthorpe South · payload sha256 bb9acca41c75…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-07-27)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demtot

Offtake · Load (any) · Total

112 MVA

Published in MVA; no MW figure is derived from it.

Granted

The operator's latest published dataset reports 112 MVA under methodology gb_npg_heatmap_2026.

Firmness
Firm
Horizon
Now (snapshot)
Methodology
gb_npg_heatmap_2026Northern Powergrid heat-map data: thermal headroombasis operator calculated · network state unknown · comparability class gb_npg_heatmapNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
27 Jul 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_heatmaprecord Scunthorpe South · payload sha256 bb9acca41c75…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-07-27)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
firm_cap

History

Served series only

Injection · Generation (any) · Available

current 0 MW

26 Sep 2026: 0 MW
26 Sep 2026range 0–0 MW26 Sep 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current0 MW

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Load (any) · Available

current 0 MVA

26 Sep 2026: 0 MVA
26 Sep 2026range 0–0 MVA26 Sep 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current0 MVA

Time axis: when we observed each value, not the operator’s effective date.

Injection · Generation (any) · Contracted

current 20.384 MW

26 Sep 2026: 20.384 MW
26 Sep 2026range 20.384–20.384 MW26 Sep 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current20.384 MW

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Load (any) · Contracted

current 3.8127 MVA

26 Sep 2026: 3.8127 MVA
26 Sep 2026range 3.8127–3.8127 MVA26 Sep 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current3.8127 MVA

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Load (any) · Total

current 112 MVA

26 Sep 2026: 112 MVA
26 Sep 2026range 112–112 MVA26 Sep 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current112 MVA

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Load (any) · Available · 2026

current 77.77 MW

26 Sep 2026: 77.77 MW
26 Sep 2026range 77.77–77.77 MW26 Sep 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current77.77 MW

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Load (any) · Available · 2027

current 76.92 MW

26 Sep 2026: 76.92 MW
26 Sep 2026range 76.92–76.92 MW26 Sep 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current76.92 MW

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Load (any) · Available · 2028

current 75.86 MW

26 Sep 2026: 75.86 MW
26 Sep 2026range 75.86–75.86 MW26 Sep 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current75.86 MW

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Load (any) · Available · 2029

current 74.72 MW

26 Sep 2026: 74.72 MW
26 Sep 2026range 74.72–74.72 MW26 Sep 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current74.72 MW

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Load (any) · Available · 2030

current 73.16 MW

26 Sep 2026: 73.16 MW
26 Sep 2026range 73.16–73.16 MW26 Sep 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current73.16 MW

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Load (any) · Available · 2031

current 71.24 MW

26 Sep 2026: 71.24 MW
26 Sep 2026range 71.24–71.24 MW26 Sep 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current71.24 MW

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Load (any) · Available · 2032

current 69.4 MW

26 Sep 2026: 69.4 MW
26 Sep 2026range 69.4–69.4 MW26 Sep 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current69.4 MW

Time axis: when we observed each value, not the operator’s effective date.

The first 12 of 83 served series with a history. The history route returns every one of them.

Through the API

curl "https://api.gridcapacityapi.com/v1/substations/sub_06gdq6mqknr5k66kpv70ta6wkm/capacity" \  -H "Authorization: Bearer gc_live_..."