GridCapacityAPI.com

Substation · 33 kV · bsp

Featherstone

Northern Powergrid · United Kingdom

Latest published values

83 served · 0 withheld

Each row is what the operator’s latest published dataset reports for one combination of direction, technology, measure, firmness and horizon. Hosting-capacity figures are indicative and reflect what operators publish. They are not a connection offer; only the operator can confirm capacity for a specific request.

Latest published capacity values, one row per series
DirectionTechnologyMeasureValueFirmnessHorizonSource date
InjectionGeneration (any)Available62.8595 MWFirmNow (snapshot)27 Jul 2026
InjectionGeneration (any)Available63.72 MWUnknown2026 (2026)scenario: DFES 2026 - Electric Engagement24 Apr 2026
InjectionGeneration (any)Available63.72 MWUnknown2026 (2026)scenario: DFES 2026 - Holistic Transition24 Apr 2026
InjectionGeneration (any)Available63.72 MWUnknown2026 (2026)scenario: DFES 2026 - Hydrogen Evolution24 Apr 2026
InjectionGeneration (any)Available61.68 MWUnknown2027 (2027)scenario: DFES 2026 - Electric Engagement24 Apr 2026
InjectionGeneration (any)Available61.68 MWUnknown2027 (2027)scenario: DFES 2026 - Holistic Transition24 Apr 2026
InjectionGeneration (any)Available61.68 MWUnknown2027 (2027)scenario: DFES 2026 - Hydrogen Evolution24 Apr 2026
InjectionGeneration (any)Available55.74 MWUnknown2028 (2028)scenario: DFES 2026 - Electric Engagement24 Apr 2026
InjectionGeneration (any)Available55.74 MWUnknown2028 (2028)scenario: DFES 2026 - Holistic Transition24 Apr 2026
InjectionGeneration (any)Available55.74 MWUnknown2028 (2028)scenario: DFES 2026 - Hydrogen Evolution24 Apr 2026
InjectionGeneration (any)Available50.42 MWUnknown2029 (2029)scenario: DFES 2026 - Electric Engagement24 Apr 2026
InjectionGeneration (any)Available50.42 MWUnknown2029 (2029)scenario: DFES 2026 - Holistic Transition24 Apr 2026
InjectionGeneration (any)Available50.42 MWUnknown2029 (2029)scenario: DFES 2026 - Hydrogen Evolution24 Apr 2026
InjectionGeneration (any)Available50.98 MWUnknown2030 (2030)scenario: DFES 2026 - Electric Engagement24 Apr 2026
InjectionGeneration (any)Available50.98 MWUnknown2030 (2030)scenario: DFES 2026 - Holistic Transition24 Apr 2026
InjectionGeneration (any)Available50.98 MWUnknown2030 (2030)scenario: DFES 2026 - Hydrogen Evolution24 Apr 2026
InjectionGeneration (any)Available47.11 MWUnknown2031 (2031)scenario: DFES 2026 - Electric Engagement24 Apr 2026
InjectionGeneration (any)Available47.11 MWUnknown2031 (2031)scenario: DFES 2026 - Holistic Transition24 Apr 2026
InjectionGeneration (any)Available47.11 MWUnknown2031 (2031)scenario: DFES 2026 - Hydrogen Evolution24 Apr 2026
InjectionGeneration (any)Available45.83 MWUnknown2032 (2032)scenario: DFES 2026 - Electric Engagement24 Apr 2026
InjectionGeneration (any)Available45.83 MWUnknown2032 (2032)scenario: DFES 2026 - Holistic Transition24 Apr 2026
InjectionGeneration (any)Available45.83 MWUnknown2032 (2032)scenario: DFES 2026 - Hydrogen Evolution24 Apr 2026
InjectionGeneration (any)Available50.58 MWUnknown2033 (2033)scenario: DFES 2026 - Electric Engagement24 Apr 2026
InjectionGeneration (any)Available50.58 MWUnknown2033 (2033)scenario: DFES 2026 - Holistic Transition24 Apr 2026
InjectionGeneration (any)Available50.58 MWUnknown2033 (2033)scenario: DFES 2026 - Hydrogen Evolution24 Apr 2026
InjectionGeneration (any)Available67.52 MWUnknown2034 (2034)scenario: DFES 2026 - Electric Engagement24 Apr 2026
InjectionGeneration (any)Available67.52 MWUnknown2034 (2034)scenario: DFES 2026 - Holistic Transition24 Apr 2026
InjectionGeneration (any)Available67.52 MWUnknown2034 (2034)scenario: DFES 2026 - Hydrogen Evolution24 Apr 2026
InjectionGeneration (any)Available86.51 MWUnknown2035 (2035)scenario: DFES 2026 - Holistic Transition24 Apr 2026
InjectionGeneration (any)Available70.58 MWUnknown2035 (2035)scenario: DFES 2026 - Hydrogen Evolution24 Apr 2026
InjectionGeneration (any)Available65.53 MWUnknown2035 (2035)scenario: DFES 2026 - Electric Engagement24 Apr 2026
InjectionGeneration (any)Available98.09 MWUnknown2040 (2040)scenario: DFES 2026 - Holistic Transition24 Apr 2026
InjectionGeneration (any)Available95.55 MWUnknown2040 (2040)scenario: DFES 2026 - Hydrogen Evolution24 Apr 2026
InjectionGeneration (any)Available89.57 MWUnknown2040 (2040)scenario: DFES 2026 - Electric Engagement24 Apr 2026
InjectionGeneration (any)Available106.55 MWUnknown2045 (2045)scenario: DFES 2026 - Hydrogen Evolution24 Apr 2026
InjectionGeneration (any)Available100.18 MWUnknown2045 (2045)scenario: DFES 2026 - Holistic Transition24 Apr 2026
InjectionGeneration (any)Available98.03 MWUnknown2045 (2045)scenario: DFES 2026 - Electric Engagement24 Apr 2026
InjectionGeneration (any)Available110.81 MWUnknown2050 (2050)scenario: DFES 2026 - Hydrogen Evolution24 Apr 2026
InjectionGeneration (any)Available99.9 MWUnknown2050 (2050)scenario: DFES 2026 - Holistic Transition24 Apr 2026
InjectionGeneration (any)Available98.81 MWUnknown2050 (2050)scenario: DFES 2026 - Electric Engagement24 Apr 2026
InjectionGeneration (any)Contracted2.018 MWUnknownNow (snapshot)27 Jul 2026
OfftakeLoad (any)Available27.723201 MVAFirmNow (snapshot)27 Jul 2026
OfftakeLoad (any)Available24.13 MWUnknown2026 (2026)scenario: DFES 2026 - Holistic Transition24 Apr 2026
OfftakeLoad (any)Available24.13 MWUnknown2026 (2026)scenario: DFES 2026 - Electric Engagement24 Apr 2026
OfftakeLoad (any)Available24.13 MWUnknown2026 (2026)scenario: DFES 2026 - Hydrogen Evolution24 Apr 2026
OfftakeLoad (any)Available22.41 MWUnknown2027 (2027)scenario: DFES 2026 - Holistic Transition24 Apr 2026
OfftakeLoad (any)Available22.41 MWUnknown2027 (2027)scenario: DFES 2026 - Electric Engagement24 Apr 2026
OfftakeLoad (any)Available22.41 MWUnknown2027 (2027)scenario: DFES 2026 - Hydrogen Evolution24 Apr 2026
OfftakeLoad (any)Available20.1 MWUnknown2028 (2028)scenario: DFES 2026 - Holistic Transition24 Apr 2026
OfftakeLoad (any)Available20.1 MWUnknown2028 (2028)scenario: DFES 2026 - Electric Engagement24 Apr 2026
OfftakeLoad (any)Available20.1 MWUnknown2028 (2028)scenario: DFES 2026 - Hydrogen Evolution24 Apr 2026
OfftakeLoad (any)Available17.52 MWUnknown2029 (2029)scenario: DFES 2026 - Holistic Transition24 Apr 2026
OfftakeLoad (any)Available17.52 MWUnknown2029 (2029)scenario: DFES 2026 - Electric Engagement24 Apr 2026
OfftakeLoad (any)Available17.52 MWUnknown2029 (2029)scenario: DFES 2026 - Hydrogen Evolution24 Apr 2026
OfftakeLoad (any)Available13.79 MWUnknown2030 (2030)scenario: DFES 2026 - Holistic Transition24 Apr 2026
OfftakeLoad (any)Available13.79 MWUnknown2030 (2030)scenario: DFES 2026 - Electric Engagement24 Apr 2026
OfftakeLoad (any)Available13.79 MWUnknown2030 (2030)scenario: DFES 2026 - Hydrogen Evolution24 Apr 2026
OfftakeLoad (any)Available9.95 MWUnknown2031 (2031)scenario: DFES 2026 - Holistic Transition24 Apr 2026
OfftakeLoad (any)Available9.95 MWUnknown2031 (2031)scenario: DFES 2026 - Electric Engagement24 Apr 2026
OfftakeLoad (any)Available9.95 MWUnknown2031 (2031)scenario: DFES 2026 - Hydrogen Evolution24 Apr 2026
OfftakeLoad (any)Available6.76 MWUnknown2032 (2032)scenario: DFES 2026 - Holistic Transition24 Apr 2026
OfftakeLoad (any)Available6.76 MWUnknown2032 (2032)scenario: DFES 2026 - Electric Engagement24 Apr 2026
OfftakeLoad (any)Available6.76 MWUnknown2032 (2032)scenario: DFES 2026 - Hydrogen Evolution24 Apr 2026
OfftakeLoad (any)Available2.98 MWUnknown2033 (2033)scenario: DFES 2026 - Holistic Transition24 Apr 2026
OfftakeLoad (any)Available2.98 MWUnknown2033 (2033)scenario: DFES 2026 - Electric Engagement24 Apr 2026
OfftakeLoad (any)Available2.98 MWUnknown2033 (2033)scenario: DFES 2026 - Hydrogen Evolution24 Apr 2026
OfftakeLoad (any)Available0 MWUnknown2034 (2034)scenario: DFES 2026 - Holistic Transition24 Apr 2026
OfftakeLoad (any)Available0 MWUnknown2034 (2034)scenario: DFES 2026 - Electric Engagement24 Apr 2026
OfftakeLoad (any)Available0 MWUnknown2034 (2034)scenario: DFES 2026 - Hydrogen Evolution24 Apr 2026
OfftakeLoad (any)Available0 MWUnknown2035 (2035)scenario: DFES 2026 - Holistic Transition24 Apr 2026
OfftakeLoad (any)Available0 MWUnknown2035 (2035)scenario: DFES 2026 - Electric Engagement24 Apr 2026
OfftakeLoad (any)Available0 MWUnknown2035 (2035)scenario: DFES 2026 - Hydrogen Evolution24 Apr 2026
OfftakeLoad (any)Available0 MWUnknown2040 (2040)scenario: DFES 2026 - Holistic Transition24 Apr 2026
OfftakeLoad (any)Available0 MWUnknown2040 (2040)scenario: DFES 2026 - Electric Engagement24 Apr 2026
OfftakeLoad (any)Available0 MWUnknown2040 (2040)scenario: DFES 2026 - Hydrogen Evolution24 Apr 2026
OfftakeLoad (any)Available0 MWUnknown2045 (2045)scenario: DFES 2026 - Holistic Transition24 Apr 2026
OfftakeLoad (any)Available0 MWUnknown2045 (2045)scenario: DFES 2026 - Electric Engagement24 Apr 2026
OfftakeLoad (any)Available0 MWUnknown2045 (2045)scenario: DFES 2026 - Hydrogen Evolution24 Apr 2026
OfftakeLoad (any)Available0 MWUnknown2050 (2050)scenario: DFES 2026 - Holistic Transition24 Apr 2026
OfftakeLoad (any)Available0 MWUnknown2050 (2050)scenario: DFES 2026 - Electric Engagement24 Apr 2026
OfftakeLoad (any)Available0 MWUnknown2050 (2050)scenario: DFES 2026 - Hydrogen Evolution24 Apr 2026
OfftakeLoad (any)Contracted16.4368 MVAUnknownNow (snapshot)27 Jul 2026
OfftakeLoad (any)Total114.3 MVAFirmNow (snapshot)27 Jul 2026

Supported by Northern Powergrid Open Data (last updated 2026-04-24)Supported by Northern Powergrid Open Data (last updated 2026-07-27)

What each value means

Methodology, both clocks, provenance and rights

Injection · Generation (any) · Available

62.8595 MW

Granted

The operator's latest published dataset reports 62.8595 MW under methodology gb_npg_heatmap_2026.

Firmness
Firm
Horizon
Now (snapshot)
Methodology
gb_npg_heatmap_2026Northern Powergrid heat-map data: thermal headroombasis operator calculated · network state unknown · comparability class gb_npg_heatmapNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
27 Jul 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_heatmaprecord Featherstone · payload sha256 8697521d37aa…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-07-27)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: gen voltage constraint
Data Not Available
Operator note: genconstraint
Amber - Fault Level
Operator note: gsp hm constraint manual
R
Operator note: rag colour
amber
Operator note: source field
genhr
Operator note: upgenconst
NO
Operator note: worst case constraint gen colour
Amber

Injection · Generation (any) · Available

63.72 MW

Granted

The operator's latest published dataset reports 63.72 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2026 (2026) · scenario: DFES 2026 - Electric Engagement
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Featherstone|DFES 2026 - Electric Engagement · payload sha256 7a535e71aca2…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2026

Injection · Generation (any) · Available

63.72 MW

Granted

The operator's latest published dataset reports 63.72 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2026 (2026) · scenario: DFES 2026 - Holistic Transition
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Featherstone|DFES 2026 - Holistic Transition · payload sha256 4a4aa1670cc7…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2026

Injection · Generation (any) · Available

63.72 MW

Granted

The operator's latest published dataset reports 63.72 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2026 (2026) · scenario: DFES 2026 - Hydrogen Evolution
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Featherstone|DFES 2026 - Hydrogen Evolution · payload sha256 bfb078822117…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2026

Injection · Generation (any) · Available

61.68 MW

Granted

The operator's latest published dataset reports 61.68 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2027 (2027) · scenario: DFES 2026 - Electric Engagement
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Featherstone|DFES 2026 - Electric Engagement · payload sha256 7a535e71aca2…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2027

Injection · Generation (any) · Available

61.68 MW

Granted

The operator's latest published dataset reports 61.68 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2027 (2027) · scenario: DFES 2026 - Holistic Transition
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Featherstone|DFES 2026 - Holistic Transition · payload sha256 4a4aa1670cc7…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2027

Injection · Generation (any) · Available

61.68 MW

Granted

The operator's latest published dataset reports 61.68 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2027 (2027) · scenario: DFES 2026 - Hydrogen Evolution
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Featherstone|DFES 2026 - Hydrogen Evolution · payload sha256 bfb078822117…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2027

Injection · Generation (any) · Available

55.74 MW

Granted

The operator's latest published dataset reports 55.74 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2028 (2028) · scenario: DFES 2026 - Electric Engagement
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Featherstone|DFES 2026 - Electric Engagement · payload sha256 7a535e71aca2…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2028

Injection · Generation (any) · Available

55.74 MW

Granted

The operator's latest published dataset reports 55.74 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2028 (2028) · scenario: DFES 2026 - Holistic Transition
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Featherstone|DFES 2026 - Holistic Transition · payload sha256 4a4aa1670cc7…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2028

Injection · Generation (any) · Available

55.74 MW

Granted

The operator's latest published dataset reports 55.74 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2028 (2028) · scenario: DFES 2026 - Hydrogen Evolution
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Featherstone|DFES 2026 - Hydrogen Evolution · payload sha256 bfb078822117…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2028

Injection · Generation (any) · Available

50.42 MW

Granted

The operator's latest published dataset reports 50.42 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2029 (2029) · scenario: DFES 2026 - Electric Engagement
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Featherstone|DFES 2026 - Electric Engagement · payload sha256 7a535e71aca2…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2029

Injection · Generation (any) · Available

50.42 MW

Granted

The operator's latest published dataset reports 50.42 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2029 (2029) · scenario: DFES 2026 - Holistic Transition
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Featherstone|DFES 2026 - Holistic Transition · payload sha256 4a4aa1670cc7…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2029

Injection · Generation (any) · Available

50.42 MW

Granted

The operator's latest published dataset reports 50.42 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2029 (2029) · scenario: DFES 2026 - Hydrogen Evolution
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Featherstone|DFES 2026 - Hydrogen Evolution · payload sha256 bfb078822117…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2029

Injection · Generation (any) · Available

50.98 MW

Granted

The operator's latest published dataset reports 50.98 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2030 (2030) · scenario: DFES 2026 - Electric Engagement
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Featherstone|DFES 2026 - Electric Engagement · payload sha256 7a535e71aca2…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2030

Injection · Generation (any) · Available

50.98 MW

Granted

The operator's latest published dataset reports 50.98 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2030 (2030) · scenario: DFES 2026 - Holistic Transition
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Featherstone|DFES 2026 - Holistic Transition · payload sha256 4a4aa1670cc7…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2030

Injection · Generation (any) · Available

50.98 MW

Granted

The operator's latest published dataset reports 50.98 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2030 (2030) · scenario: DFES 2026 - Hydrogen Evolution
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Featherstone|DFES 2026 - Hydrogen Evolution · payload sha256 bfb078822117…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2030

Injection · Generation (any) · Available

47.11 MW

Granted

The operator's latest published dataset reports 47.11 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2031 (2031) · scenario: DFES 2026 - Electric Engagement
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Featherstone|DFES 2026 - Electric Engagement · payload sha256 7a535e71aca2…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2031

Injection · Generation (any) · Available

47.11 MW

Granted

The operator's latest published dataset reports 47.11 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2031 (2031) · scenario: DFES 2026 - Holistic Transition
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Featherstone|DFES 2026 - Holistic Transition · payload sha256 4a4aa1670cc7…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2031

Injection · Generation (any) · Available

47.11 MW

Granted

The operator's latest published dataset reports 47.11 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2031 (2031) · scenario: DFES 2026 - Hydrogen Evolution
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Featherstone|DFES 2026 - Hydrogen Evolution · payload sha256 bfb078822117…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2031

Injection · Generation (any) · Available

45.83 MW

Granted

The operator's latest published dataset reports 45.83 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2032 (2032) · scenario: DFES 2026 - Electric Engagement
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Featherstone|DFES 2026 - Electric Engagement · payload sha256 7a535e71aca2…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2032

Injection · Generation (any) · Available

45.83 MW

Granted

The operator's latest published dataset reports 45.83 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2032 (2032) · scenario: DFES 2026 - Holistic Transition
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Featherstone|DFES 2026 - Holistic Transition · payload sha256 4a4aa1670cc7…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2032

Injection · Generation (any) · Available

45.83 MW

Granted

The operator's latest published dataset reports 45.83 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2032 (2032) · scenario: DFES 2026 - Hydrogen Evolution
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Featherstone|DFES 2026 - Hydrogen Evolution · payload sha256 bfb078822117…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2032

Injection · Generation (any) · Available

50.58 MW

Granted

The operator's latest published dataset reports 50.58 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2033 (2033) · scenario: DFES 2026 - Electric Engagement
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Featherstone|DFES 2026 - Electric Engagement · payload sha256 7a535e71aca2…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2033

Injection · Generation (any) · Available

50.58 MW

Granted

The operator's latest published dataset reports 50.58 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2033 (2033) · scenario: DFES 2026 - Holistic Transition
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Featherstone|DFES 2026 - Holistic Transition · payload sha256 4a4aa1670cc7…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2033

Injection · Generation (any) · Available

50.58 MW

Granted

The operator's latest published dataset reports 50.58 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2033 (2033) · scenario: DFES 2026 - Hydrogen Evolution
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Featherstone|DFES 2026 - Hydrogen Evolution · payload sha256 bfb078822117…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2033

Injection · Generation (any) · Available

67.52 MW

Granted

The operator's latest published dataset reports 67.52 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2034 (2034) · scenario: DFES 2026 - Electric Engagement
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Featherstone|DFES 2026 - Electric Engagement · payload sha256 7a535e71aca2…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2034

Injection · Generation (any) · Available

67.52 MW

Granted

The operator's latest published dataset reports 67.52 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2034 (2034) · scenario: DFES 2026 - Holistic Transition
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Featherstone|DFES 2026 - Holistic Transition · payload sha256 4a4aa1670cc7…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2034

Injection · Generation (any) · Available

67.52 MW

Granted

The operator's latest published dataset reports 67.52 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2034 (2034) · scenario: DFES 2026 - Hydrogen Evolution
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Featherstone|DFES 2026 - Hydrogen Evolution · payload sha256 bfb078822117…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2034

Injection · Generation (any) · Available

86.51 MW

Granted

The operator's latest published dataset reports 86.51 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2035 (2035) · scenario: DFES 2026 - Holistic Transition
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Featherstone|DFES 2026 - Holistic Transition · payload sha256 4a4aa1670cc7…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2035

Injection · Generation (any) · Available

70.58 MW

Granted

The operator's latest published dataset reports 70.58 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2035 (2035) · scenario: DFES 2026 - Hydrogen Evolution
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Featherstone|DFES 2026 - Hydrogen Evolution · payload sha256 bfb078822117…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2035

Injection · Generation (any) · Available

65.53 MW

Granted

The operator's latest published dataset reports 65.53 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2035 (2035) · scenario: DFES 2026 - Electric Engagement
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Featherstone|DFES 2026 - Electric Engagement · payload sha256 7a535e71aca2…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2035

Injection · Generation (any) · Available

98.09 MW

Granted

The operator's latest published dataset reports 98.09 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2040 (2040) · scenario: DFES 2026 - Holistic Transition
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Featherstone|DFES 2026 - Holistic Transition · payload sha256 4a4aa1670cc7…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2040

Injection · Generation (any) · Available

95.55 MW

Granted

The operator's latest published dataset reports 95.55 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2040 (2040) · scenario: DFES 2026 - Hydrogen Evolution
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Featherstone|DFES 2026 - Hydrogen Evolution · payload sha256 bfb078822117…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2040

Injection · Generation (any) · Available

89.57 MW

Granted

The operator's latest published dataset reports 89.57 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2040 (2040) · scenario: DFES 2026 - Electric Engagement
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Featherstone|DFES 2026 - Electric Engagement · payload sha256 7a535e71aca2…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2040

Injection · Generation (any) · Available

106.55 MW

Granted

The operator's latest published dataset reports 106.55 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2045 (2045) · scenario: DFES 2026 - Hydrogen Evolution
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Featherstone|DFES 2026 - Hydrogen Evolution · payload sha256 bfb078822117…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2045

Injection · Generation (any) · Available

100.18 MW

Granted

The operator's latest published dataset reports 100.18 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2045 (2045) · scenario: DFES 2026 - Holistic Transition
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Featherstone|DFES 2026 - Holistic Transition · payload sha256 4a4aa1670cc7…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2045

Injection · Generation (any) · Available

98.03 MW

Granted

The operator's latest published dataset reports 98.03 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2045 (2045) · scenario: DFES 2026 - Electric Engagement
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Featherstone|DFES 2026 - Electric Engagement · payload sha256 7a535e71aca2…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2045

Injection · Generation (any) · Available

110.81 MW

Granted

The operator's latest published dataset reports 110.81 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2050 (2050) · scenario: DFES 2026 - Hydrogen Evolution
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Featherstone|DFES 2026 - Hydrogen Evolution · payload sha256 bfb078822117…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2050

Injection · Generation (any) · Available

99.9 MW

Granted

The operator's latest published dataset reports 99.9 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2050 (2050) · scenario: DFES 2026 - Holistic Transition
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Featherstone|DFES 2026 - Holistic Transition · payload sha256 4a4aa1670cc7…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2050

Injection · Generation (any) · Available

98.81 MW

Granted

The operator's latest published dataset reports 98.81 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2050 (2050) · scenario: DFES 2026 - Electric Engagement
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Featherstone|DFES 2026 - Electric Engagement · payload sha256 7a535e71aca2…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2050

Injection · Generation (any) · Contracted

2.018 MW

Granted

The operator's latest published dataset reports 2.018 MW under methodology gb_npg_heatmap_2026.

Firmness
Unknown
Horizon
Now (snapshot)
Methodology
gb_npg_heatmap_2026Northern Powergrid heat-map data: thermal headroombasis operator calculated · network state unknown · comparability class gb_npg_heatmapNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
27 Jul 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_heatmaprecord Featherstone · payload sha256 8697521d37aa…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-07-27)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
gentot

Offtake · Load (any) · Available

27.723201 MVA

Published in MVA; no MW figure is derived from it.

Granted

The operator's latest published dataset reports 27.72320061 MVA under methodology gb_npg_heatmap_2026.

Firmness
Firm
Horizon
Now (snapshot)
Methodology
gb_npg_heatmap_2026Northern Powergrid heat-map data: thermal headroombasis operator calculated · network state unknown · comparability class gb_npg_heatmapNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
27 Jul 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_heatmaprecord Featherstone · payload sha256 8697521d37aa…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-07-27)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: dem voltage constraint
Data Not Available
Operator note: demconstraint
Amber - Fault Level
Operator note: gsp hm constraint manual
R
Operator note: rag colour
amber
Operator note: source field
demhr
Operator note: updemconst
NO
Operator note: worst case constraint dem colour
Amber

Offtake · Load (any) · Available

24.13 MW

Granted

The operator's latest published dataset reports 24.13 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2026 (2026) · scenario: DFES 2026 - Holistic Transition
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Featherstone|DFES 2026 - Holistic Transition · payload sha256 680ce0a4c5f8…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2026

Offtake · Load (any) · Available

24.13 MW

Granted

The operator's latest published dataset reports 24.13 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2026 (2026) · scenario: DFES 2026 - Electric Engagement
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Featherstone|DFES 2026 - Electric Engagement · payload sha256 9b5abf5da2cb…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2026

Offtake · Load (any) · Available

24.13 MW

Granted

The operator's latest published dataset reports 24.13 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2026 (2026) · scenario: DFES 2026 - Hydrogen Evolution
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Featherstone|DFES 2026 - Hydrogen Evolution · payload sha256 76301826ea61…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2026

Offtake · Load (any) · Available

22.41 MW

Granted

The operator's latest published dataset reports 22.41 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2027 (2027) · scenario: DFES 2026 - Holistic Transition
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Featherstone|DFES 2026 - Holistic Transition · payload sha256 680ce0a4c5f8…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2027

Offtake · Load (any) · Available

22.41 MW

Granted

The operator's latest published dataset reports 22.41 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2027 (2027) · scenario: DFES 2026 - Electric Engagement
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Featherstone|DFES 2026 - Electric Engagement · payload sha256 9b5abf5da2cb…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2027

Offtake · Load (any) · Available

22.41 MW

Granted

The operator's latest published dataset reports 22.41 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2027 (2027) · scenario: DFES 2026 - Hydrogen Evolution
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Featherstone|DFES 2026 - Hydrogen Evolution · payload sha256 76301826ea61…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2027

Offtake · Load (any) · Available

20.1 MW

Granted

The operator's latest published dataset reports 20.1 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2028 (2028) · scenario: DFES 2026 - Holistic Transition
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Featherstone|DFES 2026 - Holistic Transition · payload sha256 680ce0a4c5f8…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2028

Offtake · Load (any) · Available

20.1 MW

Granted

The operator's latest published dataset reports 20.1 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2028 (2028) · scenario: DFES 2026 - Electric Engagement
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Featherstone|DFES 2026 - Electric Engagement · payload sha256 9b5abf5da2cb…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2028

Offtake · Load (any) · Available

20.1 MW

Granted

The operator's latest published dataset reports 20.1 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2028 (2028) · scenario: DFES 2026 - Hydrogen Evolution
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Featherstone|DFES 2026 - Hydrogen Evolution · payload sha256 76301826ea61…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2028

Offtake · Load (any) · Available

17.52 MW

Granted

The operator's latest published dataset reports 17.52 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2029 (2029) · scenario: DFES 2026 - Holistic Transition
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Featherstone|DFES 2026 - Holistic Transition · payload sha256 680ce0a4c5f8…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2029

Offtake · Load (any) · Available

17.52 MW

Granted

The operator's latest published dataset reports 17.52 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2029 (2029) · scenario: DFES 2026 - Electric Engagement
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Featherstone|DFES 2026 - Electric Engagement · payload sha256 9b5abf5da2cb…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2029

Offtake · Load (any) · Available

17.52 MW

Granted

The operator's latest published dataset reports 17.52 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2029 (2029) · scenario: DFES 2026 - Hydrogen Evolution
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Featherstone|DFES 2026 - Hydrogen Evolution · payload sha256 76301826ea61…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2029

Offtake · Load (any) · Available

13.79 MW

Granted

The operator's latest published dataset reports 13.79 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2030 (2030) · scenario: DFES 2026 - Holistic Transition
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Featherstone|DFES 2026 - Holistic Transition · payload sha256 680ce0a4c5f8…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2030

Offtake · Load (any) · Available

13.79 MW

Granted

The operator's latest published dataset reports 13.79 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2030 (2030) · scenario: DFES 2026 - Electric Engagement
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Featherstone|DFES 2026 - Electric Engagement · payload sha256 9b5abf5da2cb…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2030

Offtake · Load (any) · Available

13.79 MW

Granted

The operator's latest published dataset reports 13.79 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2030 (2030) · scenario: DFES 2026 - Hydrogen Evolution
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Featherstone|DFES 2026 - Hydrogen Evolution · payload sha256 76301826ea61…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2030

Offtake · Load (any) · Available

9.95 MW

Granted

The operator's latest published dataset reports 9.95 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2031 (2031) · scenario: DFES 2026 - Holistic Transition
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Featherstone|DFES 2026 - Holistic Transition · payload sha256 680ce0a4c5f8…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2031

Offtake · Load (any) · Available

9.95 MW

Granted

The operator's latest published dataset reports 9.95 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2031 (2031) · scenario: DFES 2026 - Electric Engagement
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Featherstone|DFES 2026 - Electric Engagement · payload sha256 9b5abf5da2cb…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2031

Offtake · Load (any) · Available

9.95 MW

Granted

The operator's latest published dataset reports 9.95 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2031 (2031) · scenario: DFES 2026 - Hydrogen Evolution
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Featherstone|DFES 2026 - Hydrogen Evolution · payload sha256 76301826ea61…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2031

Offtake · Load (any) · Available

6.76 MW

Granted

The operator's latest published dataset reports 6.76 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2032 (2032) · scenario: DFES 2026 - Holistic Transition
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Featherstone|DFES 2026 - Holistic Transition · payload sha256 680ce0a4c5f8…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2032

Offtake · Load (any) · Available

6.76 MW

Granted

The operator's latest published dataset reports 6.76 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2032 (2032) · scenario: DFES 2026 - Electric Engagement
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Featherstone|DFES 2026 - Electric Engagement · payload sha256 9b5abf5da2cb…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2032

Offtake · Load (any) · Available

6.76 MW

Granted

The operator's latest published dataset reports 6.76 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2032 (2032) · scenario: DFES 2026 - Hydrogen Evolution
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Featherstone|DFES 2026 - Hydrogen Evolution · payload sha256 76301826ea61…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2032

Offtake · Load (any) · Available

2.98 MW

Granted

The operator's latest published dataset reports 2.98 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2033 (2033) · scenario: DFES 2026 - Holistic Transition
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Featherstone|DFES 2026 - Holistic Transition · payload sha256 680ce0a4c5f8…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2033

Offtake · Load (any) · Available

2.98 MW

Granted

The operator's latest published dataset reports 2.98 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2033 (2033) · scenario: DFES 2026 - Electric Engagement
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Featherstone|DFES 2026 - Electric Engagement · payload sha256 9b5abf5da2cb…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2033

Offtake · Load (any) · Available

2.98 MW

Granted

The operator's latest published dataset reports 2.98 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2033 (2033) · scenario: DFES 2026 - Hydrogen Evolution
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Featherstone|DFES 2026 - Hydrogen Evolution · payload sha256 76301826ea61…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2033

Offtake · Load (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2034 (2034) · scenario: DFES 2026 - Holistic Transition
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Featherstone|DFES 2026 - Holistic Transition · payload sha256 680ce0a4c5f8…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2034

Offtake · Load (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2034 (2034) · scenario: DFES 2026 - Electric Engagement
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Featherstone|DFES 2026 - Electric Engagement · payload sha256 9b5abf5da2cb…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2034

Offtake · Load (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2034 (2034) · scenario: DFES 2026 - Hydrogen Evolution
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Featherstone|DFES 2026 - Hydrogen Evolution · payload sha256 76301826ea61…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2034

Offtake · Load (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2035 (2035) · scenario: DFES 2026 - Holistic Transition
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Featherstone|DFES 2026 - Holistic Transition · payload sha256 680ce0a4c5f8…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2035

Offtake · Load (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2035 (2035) · scenario: DFES 2026 - Electric Engagement
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Featherstone|DFES 2026 - Electric Engagement · payload sha256 9b5abf5da2cb…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2035

Offtake · Load (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2035 (2035) · scenario: DFES 2026 - Hydrogen Evolution
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Featherstone|DFES 2026 - Hydrogen Evolution · payload sha256 76301826ea61…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2035

Offtake · Load (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2040 (2040) · scenario: DFES 2026 - Holistic Transition
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Featherstone|DFES 2026 - Holistic Transition · payload sha256 680ce0a4c5f8…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2040

Offtake · Load (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2040 (2040) · scenario: DFES 2026 - Electric Engagement
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Featherstone|DFES 2026 - Electric Engagement · payload sha256 9b5abf5da2cb…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2040

Offtake · Load (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2040 (2040) · scenario: DFES 2026 - Hydrogen Evolution
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Featherstone|DFES 2026 - Hydrogen Evolution · payload sha256 76301826ea61…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2040

Offtake · Load (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2045 (2045) · scenario: DFES 2026 - Holistic Transition
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Featherstone|DFES 2026 - Holistic Transition · payload sha256 680ce0a4c5f8…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2045

Offtake · Load (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2045 (2045) · scenario: DFES 2026 - Electric Engagement
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Featherstone|DFES 2026 - Electric Engagement · payload sha256 9b5abf5da2cb…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2045

Offtake · Load (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2045 (2045) · scenario: DFES 2026 - Hydrogen Evolution
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Featherstone|DFES 2026 - Hydrogen Evolution · payload sha256 76301826ea61…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2045

Offtake · Load (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2050 (2050) · scenario: DFES 2026 - Holistic Transition
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Featherstone|DFES 2026 - Holistic Transition · payload sha256 680ce0a4c5f8…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2050

Offtake · Load (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2050 (2050) · scenario: DFES 2026 - Electric Engagement
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Featherstone|DFES 2026 - Electric Engagement · payload sha256 9b5abf5da2cb…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2050

Offtake · Load (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2050 (2050) · scenario: DFES 2026 - Hydrogen Evolution
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Featherstone|DFES 2026 - Hydrogen Evolution · payload sha256 76301826ea61…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2050

Offtake · Load (any) · Contracted

16.4368 MVA

Published in MVA; no MW figure is derived from it.

Granted

The operator's latest published dataset reports 16.4368 MVA under methodology gb_npg_heatmap_2026.

Firmness
Unknown
Horizon
Now (snapshot)
Methodology
gb_npg_heatmap_2026Northern Powergrid heat-map data: thermal headroombasis operator calculated · network state unknown · comparability class gb_npg_heatmapNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
27 Jul 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_heatmaprecord Featherstone · payload sha256 8697521d37aa…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-07-27)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demtot

Offtake · Load (any) · Total

114.3 MVA

Published in MVA; no MW figure is derived from it.

Granted

The operator's latest published dataset reports 114.3 MVA under methodology gb_npg_heatmap_2026.

Firmness
Firm
Horizon
Now (snapshot)
Methodology
gb_npg_heatmap_2026Northern Powergrid heat-map data: thermal headroombasis operator calculated · network state unknown · comparability class gb_npg_heatmapNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
27 Jul 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_heatmaprecord Featherstone · payload sha256 8697521d37aa…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-07-27)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
firm_cap

History

Served series only

Injection · Generation (any) · Available

current 62.8595 MW

26 Sep 2026: 62.8595 MW
26 Sep 2026range 62.8595–62.8595 MW26 Sep 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current62.8595 MW

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Load (any) · Available

current 27.723201 MVA

26 Sep 2026: 27.723201 MVA
26 Sep 2026range 27.723201–27.723201 MVA26 Sep 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current27.723201 MVA

Time axis: when we observed each value, not the operator’s effective date.

Injection · Generation (any) · Contracted

current 2.018 MW

26 Sep 2026: 2.018 MW
26 Sep 2026range 2.018–2.018 MW26 Sep 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current2.018 MW

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Load (any) · Contracted

current 16.4368 MVA

26 Sep 2026: 16.4368 MVA
26 Sep 2026range 16.4368–16.4368 MVA26 Sep 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current16.4368 MVA

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Load (any) · Total

current 114.3 MVA

26 Sep 2026: 114.3 MVA
26 Sep 2026range 114.3–114.3 MVA26 Sep 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current114.3 MVA

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Load (any) · Available · 2026

current 24.13 MW

26 Sep 2026: 24.13 MW
26 Sep 2026range 24.13–24.13 MW26 Sep 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current24.13 MW

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Load (any) · Available · 2027

current 22.41 MW

26 Sep 2026: 22.41 MW
26 Sep 2026range 22.41–22.41 MW26 Sep 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current22.41 MW

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Load (any) · Available · 2028

current 20.1 MW

26 Sep 2026: 20.1 MW
26 Sep 2026range 20.1–20.1 MW26 Sep 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current20.1 MW

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Load (any) · Available · 2029

current 17.52 MW

26 Sep 2026: 17.52 MW
26 Sep 2026range 17.52–17.52 MW26 Sep 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current17.52 MW

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Load (any) · Available · 2030

current 13.79 MW

26 Sep 2026: 13.79 MW
26 Sep 2026range 13.79–13.79 MW26 Sep 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current13.79 MW

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Load (any) · Available · 2031

current 9.95 MW

26 Sep 2026: 9.95 MW
26 Sep 2026range 9.95–9.95 MW26 Sep 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current9.95 MW

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Load (any) · Available · 2032

current 6.76 MW

26 Sep 2026: 6.76 MW
26 Sep 2026range 6.76–6.76 MW26 Sep 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current6.76 MW

Time axis: when we observed each value, not the operator’s effective date.

The first 12 of 83 served series with a history. The history route returns every one of them.

Through the API

curl "https://api.gridcapacityapi.com/v1/substations/sub_06gdq6mrsxswdacsjb78taaja8/capacity" \  -H "Authorization: Bearer gc_live_..."
Featherstone 33 kV substation: grid capacity (Northern Powergrid) · GridCapacity API