Substation · 11 kV · primary

Darlington Central 33/11kV

Northern Powergrid · United Kingdom

Latest published values

83 served · 0 withheld

Each row is what the operator’s latest published dataset reports for one combination of direction, technology, measure, firmness and horizon. Hosting-capacity figures are indicative and reflect what operators publish. They are not a connection offer; only the operator can confirm capacity for a specific request.

Latest published capacity values, one row per series
DirectionTechnologyMeasureValueFirmnessHorizonSource date
InjectionGeneration (any)Available0 MWFirmNow (snapshot)27 Jul 2026
InjectionGeneration (any)Available33.59 MWUnknown2026 (2026)scenario: DFES 2026 - Electric Engagement24 Apr 2026
InjectionGeneration (any)Available33.59 MWUnknown2026 (2026)scenario: DFES 2026 - Holistic Transition24 Apr 2026
InjectionGeneration (any)Available33.59 MWUnknown2026 (2026)scenario: DFES 2026 - Hydrogen Evolution24 Apr 2026
InjectionGeneration (any)Available33.38 MWUnknown2027 (2027)scenario: DFES 2026 - Electric Engagement24 Apr 2026
InjectionGeneration (any)Available33.38 MWUnknown2027 (2027)scenario: DFES 2026 - Holistic Transition24 Apr 2026
InjectionGeneration (any)Available33.38 MWUnknown2027 (2027)scenario: DFES 2026 - Hydrogen Evolution24 Apr 2026
InjectionGeneration (any)Available33.28 MWUnknown2028 (2028)scenario: DFES 2026 - Electric Engagement24 Apr 2026
InjectionGeneration (any)Available33.28 MWUnknown2028 (2028)scenario: DFES 2026 - Holistic Transition24 Apr 2026
InjectionGeneration (any)Available33.28 MWUnknown2028 (2028)scenario: DFES 2026 - Hydrogen Evolution24 Apr 2026
InjectionGeneration (any)Available33.05 MWUnknown2029 (2029)scenario: DFES 2026 - Electric Engagement24 Apr 2026
InjectionGeneration (any)Available33.05 MWUnknown2029 (2029)scenario: DFES 2026 - Holistic Transition24 Apr 2026
InjectionGeneration (any)Available33.05 MWUnknown2029 (2029)scenario: DFES 2026 - Hydrogen Evolution24 Apr 2026
InjectionGeneration (any)Available32.99 MWUnknown2030 (2030)scenario: DFES 2026 - Electric Engagement24 Apr 2026
InjectionGeneration (any)Available32.99 MWUnknown2030 (2030)scenario: DFES 2026 - Holistic Transition24 Apr 2026
InjectionGeneration (any)Available32.99 MWUnknown2030 (2030)scenario: DFES 2026 - Hydrogen Evolution24 Apr 2026
InjectionGeneration (any)Available32.7 MWUnknown2031 (2031)scenario: DFES 2026 - Electric Engagement24 Apr 2026
InjectionGeneration (any)Available32.7 MWUnknown2031 (2031)scenario: DFES 2026 - Holistic Transition24 Apr 2026
InjectionGeneration (any)Available32.7 MWUnknown2031 (2031)scenario: DFES 2026 - Hydrogen Evolution24 Apr 2026
InjectionGeneration (any)Available32.41 MWUnknown2032 (2032)scenario: DFES 2026 - Electric Engagement24 Apr 2026
InjectionGeneration (any)Available32.41 MWUnknown2032 (2032)scenario: DFES 2026 - Holistic Transition24 Apr 2026
InjectionGeneration (any)Available32.41 MWUnknown2032 (2032)scenario: DFES 2026 - Hydrogen Evolution24 Apr 2026
InjectionGeneration (any)Available32.15 MWUnknown2033 (2033)scenario: DFES 2026 - Electric Engagement24 Apr 2026
InjectionGeneration (any)Available32.15 MWUnknown2033 (2033)scenario: DFES 2026 - Holistic Transition24 Apr 2026
InjectionGeneration (any)Available32.15 MWUnknown2033 (2033)scenario: DFES 2026 - Hydrogen Evolution24 Apr 2026
InjectionGeneration (any)Available31.89 MWUnknown2034 (2034)scenario: DFES 2026 - Electric Engagement24 Apr 2026
InjectionGeneration (any)Available31.89 MWUnknown2034 (2034)scenario: DFES 2026 - Holistic Transition24 Apr 2026
InjectionGeneration (any)Available31.89 MWUnknown2034 (2034)scenario: DFES 2026 - Hydrogen Evolution24 Apr 2026
InjectionGeneration (any)Available31.68 MWUnknown2035 (2035)scenario: DFES 2026 - Hydrogen Evolution24 Apr 2026
InjectionGeneration (any)Available31.67 MWUnknown2035 (2035)scenario: DFES 2026 - Holistic Transition24 Apr 2026
InjectionGeneration (any)Available31.56 MWUnknown2035 (2035)scenario: DFES 2026 - Electric Engagement24 Apr 2026
InjectionGeneration (any)Available31.69 MWUnknown2040 (2040)scenario: DFES 2026 - Hydrogen Evolution24 Apr 2026
InjectionGeneration (any)Available31.41 MWUnknown2040 (2040)scenario: DFES 2026 - Holistic Transition24 Apr 2026
InjectionGeneration (any)Available31.31 MWUnknown2040 (2040)scenario: DFES 2026 - Electric Engagement24 Apr 2026
InjectionGeneration (any)Available31.95 MWUnknown2045 (2045)scenario: DFES 2026 - Hydrogen Evolution24 Apr 2026
InjectionGeneration (any)Available31.24 MWUnknown2045 (2045)scenario: DFES 2026 - Holistic Transition24 Apr 2026
InjectionGeneration (any)Available31.16 MWUnknown2045 (2045)scenario: DFES 2026 - Electric Engagement24 Apr 2026
InjectionGeneration (any)Available31.81 MWUnknown2050 (2050)scenario: DFES 2026 - Hydrogen Evolution24 Apr 2026
InjectionGeneration (any)Available30.76 MWUnknown2050 (2050)scenario: DFES 2026 - Holistic Transition24 Apr 2026
InjectionGeneration (any)Available30.74 MWUnknown2050 (2050)scenario: DFES 2026 - Electric Engagement24 Apr 2026
InjectionGeneration (any)Contracted0 MWUnknownNow (snapshot)27 Jul 2026
OfftakeLoad (any)Available0 MVAFirmNow (snapshot)27 Jul 2026
OfftakeLoad (any)Available21.25 MWUnknown2026 (2026)scenario: DFES 2026 - Electric Engagement24 Apr 2026
OfftakeLoad (any)Available21.25 MWUnknown2026 (2026)scenario: DFES 2026 - Holistic Transition24 Apr 2026
OfftakeLoad (any)Available21.25 MWUnknown2026 (2026)scenario: DFES 2026 - Hydrogen Evolution24 Apr 2026
OfftakeLoad (any)Available21.28 MWUnknown2027 (2027)scenario: DFES 2026 - Electric Engagement24 Apr 2026
OfftakeLoad (any)Available21.28 MWUnknown2027 (2027)scenario: DFES 2026 - Holistic Transition24 Apr 2026
OfftakeLoad (any)Available21.28 MWUnknown2027 (2027)scenario: DFES 2026 - Hydrogen Evolution24 Apr 2026
OfftakeLoad (any)Available21.25 MWUnknown2028 (2028)scenario: DFES 2026 - Electric Engagement24 Apr 2026
OfftakeLoad (any)Available21.25 MWUnknown2028 (2028)scenario: DFES 2026 - Holistic Transition24 Apr 2026
OfftakeLoad (any)Available21.25 MWUnknown2028 (2028)scenario: DFES 2026 - Hydrogen Evolution24 Apr 2026
OfftakeLoad (any)Available21.2 MWUnknown2029 (2029)scenario: DFES 2026 - Electric Engagement24 Apr 2026
OfftakeLoad (any)Available21.2 MWUnknown2029 (2029)scenario: DFES 2026 - Holistic Transition24 Apr 2026
OfftakeLoad (any)Available21.2 MWUnknown2029 (2029)scenario: DFES 2026 - Hydrogen Evolution24 Apr 2026
OfftakeLoad (any)Available21.12 MWUnknown2030 (2030)scenario: DFES 2026 - Electric Engagement24 Apr 2026
OfftakeLoad (any)Available21.12 MWUnknown2030 (2030)scenario: DFES 2026 - Holistic Transition24 Apr 2026
OfftakeLoad (any)Available21.12 MWUnknown2030 (2030)scenario: DFES 2026 - Hydrogen Evolution24 Apr 2026
OfftakeLoad (any)Available21.08 MWUnknown2031 (2031)scenario: DFES 2026 - Electric Engagement24 Apr 2026
OfftakeLoad (any)Available21.08 MWUnknown2031 (2031)scenario: DFES 2026 - Holistic Transition24 Apr 2026
OfftakeLoad (any)Available21.08 MWUnknown2031 (2031)scenario: DFES 2026 - Hydrogen Evolution24 Apr 2026
OfftakeLoad (any)Available21.08 MWUnknown2032 (2032)scenario: DFES 2026 - Electric Engagement24 Apr 2026
OfftakeLoad (any)Available21.08 MWUnknown2032 (2032)scenario: DFES 2026 - Holistic Transition24 Apr 2026
OfftakeLoad (any)Available21.08 MWUnknown2032 (2032)scenario: DFES 2026 - Hydrogen Evolution24 Apr 2026
OfftakeLoad (any)Available21.03 MWUnknown2033 (2033)scenario: DFES 2026 - Electric Engagement24 Apr 2026
OfftakeLoad (any)Available21.03 MWUnknown2033 (2033)scenario: DFES 2026 - Holistic Transition24 Apr 2026
OfftakeLoad (any)Available21.03 MWUnknown2033 (2033)scenario: DFES 2026 - Hydrogen Evolution24 Apr 2026
OfftakeLoad (any)Available20.97 MWUnknown2034 (2034)scenario: DFES 2026 - Electric Engagement24 Apr 2026
OfftakeLoad (any)Available20.97 MWUnknown2034 (2034)scenario: DFES 2026 - Holistic Transition24 Apr 2026
OfftakeLoad (any)Available20.97 MWUnknown2034 (2034)scenario: DFES 2026 - Hydrogen Evolution24 Apr 2026
OfftakeLoad (any)Available20.89 MWUnknown2035 (2035)scenario: DFES 2026 - Electric Engagement24 Apr 2026
OfftakeLoad (any)Available20.88 MWUnknown2035 (2035)scenario: DFES 2026 - Holistic Transition24 Apr 2026
OfftakeLoad (any)Available20.51 MWUnknown2035 (2035)scenario: DFES 2026 - Hydrogen Evolution24 Apr 2026
OfftakeLoad (any)Available20.34 MWUnknown2040 (2040)scenario: DFES 2026 - Electric Engagement24 Apr 2026
OfftakeLoad (any)Available20.29 MWUnknown2040 (2040)scenario: DFES 2026 - Holistic Transition24 Apr 2026
OfftakeLoad (any)Available20.03 MWUnknown2040 (2040)scenario: DFES 2026 - Hydrogen Evolution24 Apr 2026
OfftakeLoad (any)Available20.1 MWUnknown2045 (2045)scenario: DFES 2026 - Electric Engagement24 Apr 2026
OfftakeLoad (any)Available20.1 MWUnknown2045 (2045)scenario: DFES 2026 - Holistic Transition24 Apr 2026
OfftakeLoad (any)Available19.71 MWUnknown2045 (2045)scenario: DFES 2026 - Hydrogen Evolution24 Apr 2026
OfftakeLoad (any)Available20.14 MWUnknown2050 (2050)scenario: DFES 2026 - Holistic Transition24 Apr 2026
OfftakeLoad (any)Available20.06 MWUnknown2050 (2050)scenario: DFES 2026 - Electric Engagement24 Apr 2026
OfftakeLoad (any)Available19.62 MWUnknown2050 (2050)scenario: DFES 2026 - Hydrogen Evolution24 Apr 2026
OfftakeLoad (any)Contracted0 MVAUnknownNow (snapshot)27 Jul 2026
OfftakeLoad (any)Total32 MVAFirmNow (snapshot)27 Jul 2026

Supported by Northern Powergrid Open Data (last updated 2026-04-24)Supported by Northern Powergrid Open Data (last updated 2026-07-27)

What each value means

Methodology, both clocks, provenance and rights

Injection · Generation (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology gb_npg_heatmap_2026.

Firmness
Firm
Horizon
Now (snapshot)
Methodology
gb_npg_heatmap_2026Northern Powergrid heat-map data: thermal headroombasis operator calculated · network state unknown · comparability class gb_npg_heatmapNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
27 Jul 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_heatmaprecord Darlington Central 33/11kV · payload sha256 177d24f3df7c…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-07-27)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: gen voltage constraint
Some Voltage Constraint
Operator note: genconstraint
Amber - Voltage
Operator note: gsp hm constraint manual
R
Operator note: rag colour
amber
Operator note: source field
genhr
Operator note: upgenconst
Upstream Constraint
Operator note: worst case constraint gen colour
Amber

Injection · Generation (any) · Available

33.59 MW

Granted

The operator's latest published dataset reports 33.59 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2026 (2026) · scenario: DFES 2026 - Electric Engagement
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Darlington Central 33/11kV|DFES 2026 - Electric Engagement · payload sha256 3d988d1d5993…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2026

Injection · Generation (any) · Available

33.59 MW

Granted

The operator's latest published dataset reports 33.59 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2026 (2026) · scenario: DFES 2026 - Holistic Transition
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Darlington Central 33/11kV|DFES 2026 - Holistic Transition · payload sha256 e7ef502223df…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2026

Injection · Generation (any) · Available

33.59 MW

Granted

The operator's latest published dataset reports 33.59 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2026 (2026) · scenario: DFES 2026 - Hydrogen Evolution
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Darlington Central 33/11kV|DFES 2026 - Hydrogen Evolution · payload sha256 e56be3700932…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2026

Injection · Generation (any) · Available

33.38 MW

Granted

The operator's latest published dataset reports 33.38 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2027 (2027) · scenario: DFES 2026 - Electric Engagement
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Darlington Central 33/11kV|DFES 2026 - Electric Engagement · payload sha256 3d988d1d5993…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2027

Injection · Generation (any) · Available

33.38 MW

Granted

The operator's latest published dataset reports 33.38 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2027 (2027) · scenario: DFES 2026 - Holistic Transition
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Darlington Central 33/11kV|DFES 2026 - Holistic Transition · payload sha256 e7ef502223df…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2027

Injection · Generation (any) · Available

33.38 MW

Granted

The operator's latest published dataset reports 33.38 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2027 (2027) · scenario: DFES 2026 - Hydrogen Evolution
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Darlington Central 33/11kV|DFES 2026 - Hydrogen Evolution · payload sha256 e56be3700932…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2027

Injection · Generation (any) · Available

33.28 MW

Granted

The operator's latest published dataset reports 33.28 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2028 (2028) · scenario: DFES 2026 - Electric Engagement
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Darlington Central 33/11kV|DFES 2026 - Electric Engagement · payload sha256 3d988d1d5993…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2028

Injection · Generation (any) · Available

33.28 MW

Granted

The operator's latest published dataset reports 33.28 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2028 (2028) · scenario: DFES 2026 - Holistic Transition
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Darlington Central 33/11kV|DFES 2026 - Holistic Transition · payload sha256 e7ef502223df…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2028

Injection · Generation (any) · Available

33.28 MW

Granted

The operator's latest published dataset reports 33.28 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2028 (2028) · scenario: DFES 2026 - Hydrogen Evolution
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Darlington Central 33/11kV|DFES 2026 - Hydrogen Evolution · payload sha256 e56be3700932…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2028

Injection · Generation (any) · Available

33.05 MW

Granted

The operator's latest published dataset reports 33.05 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2029 (2029) · scenario: DFES 2026 - Electric Engagement
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Darlington Central 33/11kV|DFES 2026 - Electric Engagement · payload sha256 3d988d1d5993…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2029

Injection · Generation (any) · Available

33.05 MW

Granted

The operator's latest published dataset reports 33.05 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2029 (2029) · scenario: DFES 2026 - Holistic Transition
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Darlington Central 33/11kV|DFES 2026 - Holistic Transition · payload sha256 e7ef502223df…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2029

Injection · Generation (any) · Available

33.05 MW

Granted

The operator's latest published dataset reports 33.05 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2029 (2029) · scenario: DFES 2026 - Hydrogen Evolution
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Darlington Central 33/11kV|DFES 2026 - Hydrogen Evolution · payload sha256 e56be3700932…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2029

Injection · Generation (any) · Available

32.99 MW

Granted

The operator's latest published dataset reports 32.99 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2030 (2030) · scenario: DFES 2026 - Electric Engagement
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Darlington Central 33/11kV|DFES 2026 - Electric Engagement · payload sha256 3d988d1d5993…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2030

Injection · Generation (any) · Available

32.99 MW

Granted

The operator's latest published dataset reports 32.99 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2030 (2030) · scenario: DFES 2026 - Holistic Transition
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Darlington Central 33/11kV|DFES 2026 - Holistic Transition · payload sha256 e7ef502223df…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2030

Injection · Generation (any) · Available

32.99 MW

Granted

The operator's latest published dataset reports 32.99 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2030 (2030) · scenario: DFES 2026 - Hydrogen Evolution
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Darlington Central 33/11kV|DFES 2026 - Hydrogen Evolution · payload sha256 e56be3700932…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2030

Injection · Generation (any) · Available

32.7 MW

Granted

The operator's latest published dataset reports 32.7 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2031 (2031) · scenario: DFES 2026 - Electric Engagement
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Darlington Central 33/11kV|DFES 2026 - Electric Engagement · payload sha256 3d988d1d5993…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2031

Injection · Generation (any) · Available

32.7 MW

Granted

The operator's latest published dataset reports 32.7 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2031 (2031) · scenario: DFES 2026 - Holistic Transition
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Darlington Central 33/11kV|DFES 2026 - Holistic Transition · payload sha256 e7ef502223df…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2031

Injection · Generation (any) · Available

32.7 MW

Granted

The operator's latest published dataset reports 32.7 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2031 (2031) · scenario: DFES 2026 - Hydrogen Evolution
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Darlington Central 33/11kV|DFES 2026 - Hydrogen Evolution · payload sha256 e56be3700932…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2031

Injection · Generation (any) · Available

32.41 MW

Granted

The operator's latest published dataset reports 32.41 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2032 (2032) · scenario: DFES 2026 - Electric Engagement
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Darlington Central 33/11kV|DFES 2026 - Electric Engagement · payload sha256 3d988d1d5993…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2032

Injection · Generation (any) · Available

32.41 MW

Granted

The operator's latest published dataset reports 32.41 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2032 (2032) · scenario: DFES 2026 - Holistic Transition
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Darlington Central 33/11kV|DFES 2026 - Holistic Transition · payload sha256 e7ef502223df…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2032

Injection · Generation (any) · Available

32.41 MW

Granted

The operator's latest published dataset reports 32.41 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2032 (2032) · scenario: DFES 2026 - Hydrogen Evolution
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Darlington Central 33/11kV|DFES 2026 - Hydrogen Evolution · payload sha256 e56be3700932…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2032

Injection · Generation (any) · Available

32.15 MW

Granted

The operator's latest published dataset reports 32.15 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2033 (2033) · scenario: DFES 2026 - Electric Engagement
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Darlington Central 33/11kV|DFES 2026 - Electric Engagement · payload sha256 3d988d1d5993…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2033

Injection · Generation (any) · Available

32.15 MW

Granted

The operator's latest published dataset reports 32.15 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2033 (2033) · scenario: DFES 2026 - Holistic Transition
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Darlington Central 33/11kV|DFES 2026 - Holistic Transition · payload sha256 e7ef502223df…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2033

Injection · Generation (any) · Available

32.15 MW

Granted

The operator's latest published dataset reports 32.15 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2033 (2033) · scenario: DFES 2026 - Hydrogen Evolution
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Darlington Central 33/11kV|DFES 2026 - Hydrogen Evolution · payload sha256 e56be3700932…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2033

Injection · Generation (any) · Available

31.89 MW

Granted

The operator's latest published dataset reports 31.89 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2034 (2034) · scenario: DFES 2026 - Electric Engagement
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Darlington Central 33/11kV|DFES 2026 - Electric Engagement · payload sha256 3d988d1d5993…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2034

Injection · Generation (any) · Available

31.89 MW

Granted

The operator's latest published dataset reports 31.89 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2034 (2034) · scenario: DFES 2026 - Holistic Transition
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Darlington Central 33/11kV|DFES 2026 - Holistic Transition · payload sha256 e7ef502223df…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2034

Injection · Generation (any) · Available

31.89 MW

Granted

The operator's latest published dataset reports 31.89 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2034 (2034) · scenario: DFES 2026 - Hydrogen Evolution
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Darlington Central 33/11kV|DFES 2026 - Hydrogen Evolution · payload sha256 e56be3700932…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2034

Injection · Generation (any) · Available

31.68 MW

Granted

The operator's latest published dataset reports 31.68 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2035 (2035) · scenario: DFES 2026 - Hydrogen Evolution
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Darlington Central 33/11kV|DFES 2026 - Hydrogen Evolution · payload sha256 e56be3700932…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2035

Injection · Generation (any) · Available

31.67 MW

Granted

The operator's latest published dataset reports 31.67 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2035 (2035) · scenario: DFES 2026 - Holistic Transition
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Darlington Central 33/11kV|DFES 2026 - Holistic Transition · payload sha256 e7ef502223df…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2035

Injection · Generation (any) · Available

31.56 MW

Granted

The operator's latest published dataset reports 31.56 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2035 (2035) · scenario: DFES 2026 - Electric Engagement
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Darlington Central 33/11kV|DFES 2026 - Electric Engagement · payload sha256 3d988d1d5993…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2035

Injection · Generation (any) · Available

31.69 MW

Granted

The operator's latest published dataset reports 31.69 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2040 (2040) · scenario: DFES 2026 - Hydrogen Evolution
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Darlington Central 33/11kV|DFES 2026 - Hydrogen Evolution · payload sha256 e56be3700932…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2040

Injection · Generation (any) · Available

31.41 MW

Granted

The operator's latest published dataset reports 31.41 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2040 (2040) · scenario: DFES 2026 - Holistic Transition
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Darlington Central 33/11kV|DFES 2026 - Holistic Transition · payload sha256 e7ef502223df…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2040

Injection · Generation (any) · Available

31.31 MW

Granted

The operator's latest published dataset reports 31.31 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2040 (2040) · scenario: DFES 2026 - Electric Engagement
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Darlington Central 33/11kV|DFES 2026 - Electric Engagement · payload sha256 3d988d1d5993…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2040

Injection · Generation (any) · Available

31.95 MW

Granted

The operator's latest published dataset reports 31.95 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2045 (2045) · scenario: DFES 2026 - Hydrogen Evolution
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Darlington Central 33/11kV|DFES 2026 - Hydrogen Evolution · payload sha256 e56be3700932…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2045

Injection · Generation (any) · Available

31.24 MW

Granted

The operator's latest published dataset reports 31.24 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2045 (2045) · scenario: DFES 2026 - Holistic Transition
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Darlington Central 33/11kV|DFES 2026 - Holistic Transition · payload sha256 e7ef502223df…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2045

Injection · Generation (any) · Available

31.16 MW

Granted

The operator's latest published dataset reports 31.16 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2045 (2045) · scenario: DFES 2026 - Electric Engagement
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Darlington Central 33/11kV|DFES 2026 - Electric Engagement · payload sha256 3d988d1d5993…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2045

Injection · Generation (any) · Available

31.81 MW

Granted

The operator's latest published dataset reports 31.81 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2050 (2050) · scenario: DFES 2026 - Hydrogen Evolution
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Darlington Central 33/11kV|DFES 2026 - Hydrogen Evolution · payload sha256 e56be3700932…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2050

Injection · Generation (any) · Available

30.76 MW

Granted

The operator's latest published dataset reports 30.76 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2050 (2050) · scenario: DFES 2026 - Holistic Transition
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Darlington Central 33/11kV|DFES 2026 - Holistic Transition · payload sha256 e7ef502223df…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2050

Injection · Generation (any) · Available

30.74 MW

Granted

The operator's latest published dataset reports 30.74 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2050 (2050) · scenario: DFES 2026 - Electric Engagement
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Darlington Central 33/11kV|DFES 2026 - Electric Engagement · payload sha256 3d988d1d5993…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2050

Injection · Generation (any) · Contracted

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology gb_npg_heatmap_2026.

Firmness
Unknown
Horizon
Now (snapshot)
Methodology
gb_npg_heatmap_2026Northern Powergrid heat-map data: thermal headroombasis operator calculated · network state unknown · comparability class gb_npg_heatmapNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
27 Jul 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_heatmaprecord Darlington Central 33/11kV · payload sha256 177d24f3df7c…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-07-27)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
gentot

Offtake · Load (any) · Available

0 MVA

Published in MVA; no MW figure is derived from it.

Granted

The operator's latest published dataset reports 0 MVA under methodology gb_npg_heatmap_2026.

Firmness
Firm
Horizon
Now (snapshot)
Methodology
gb_npg_heatmap_2026Northern Powergrid heat-map data: thermal headroombasis operator calculated · network state unknown · comparability class gb_npg_heatmapNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
27 Jul 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_heatmaprecord Darlington Central 33/11kV · payload sha256 177d24f3df7c…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-07-27)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: dem voltage constraint
No Voltage Constraint
Operator note: demconstraint
Green
Operator note: gsp hm constraint manual
R
Operator note: rag colour
green
Operator note: source field
demhr
Operator note: updemconst
GSP Constraint
Operator note: worst case constraint dem colour
Green

Offtake · Load (any) · Available

21.25 MW

Granted

The operator's latest published dataset reports 21.25 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2026 (2026) · scenario: DFES 2026 - Electric Engagement
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Darlington Central 33/11kV|DFES 2026 - Electric Engagement · payload sha256 99a46f3cbfda…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2026

Offtake · Load (any) · Available

21.25 MW

Granted

The operator's latest published dataset reports 21.25 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2026 (2026) · scenario: DFES 2026 - Holistic Transition
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Darlington Central 33/11kV|DFES 2026 - Holistic Transition · payload sha256 bb545c21c8a5…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2026

Offtake · Load (any) · Available

21.25 MW

Granted

The operator's latest published dataset reports 21.25 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2026 (2026) · scenario: DFES 2026 - Hydrogen Evolution
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Darlington Central 33/11kV|DFES 2026 - Hydrogen Evolution · payload sha256 7fb7767eebc2…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2026

Offtake · Load (any) · Available

21.28 MW

Granted

The operator's latest published dataset reports 21.28 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2027 (2027) · scenario: DFES 2026 - Electric Engagement
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Darlington Central 33/11kV|DFES 2026 - Electric Engagement · payload sha256 99a46f3cbfda…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2027

Offtake · Load (any) · Available

21.28 MW

Granted

The operator's latest published dataset reports 21.28 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2027 (2027) · scenario: DFES 2026 - Holistic Transition
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Darlington Central 33/11kV|DFES 2026 - Holistic Transition · payload sha256 bb545c21c8a5…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2027

Offtake · Load (any) · Available

21.28 MW

Granted

The operator's latest published dataset reports 21.28 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2027 (2027) · scenario: DFES 2026 - Hydrogen Evolution
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Darlington Central 33/11kV|DFES 2026 - Hydrogen Evolution · payload sha256 7fb7767eebc2…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2027

Offtake · Load (any) · Available

21.25 MW

Granted

The operator's latest published dataset reports 21.25 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2028 (2028) · scenario: DFES 2026 - Electric Engagement
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Darlington Central 33/11kV|DFES 2026 - Electric Engagement · payload sha256 99a46f3cbfda…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2028

Offtake · Load (any) · Available

21.25 MW

Granted

The operator's latest published dataset reports 21.25 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2028 (2028) · scenario: DFES 2026 - Holistic Transition
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Darlington Central 33/11kV|DFES 2026 - Holistic Transition · payload sha256 bb545c21c8a5…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2028

Offtake · Load (any) · Available

21.25 MW

Granted

The operator's latest published dataset reports 21.25 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2028 (2028) · scenario: DFES 2026 - Hydrogen Evolution
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Darlington Central 33/11kV|DFES 2026 - Hydrogen Evolution · payload sha256 7fb7767eebc2…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2028

Offtake · Load (any) · Available

21.2 MW

Granted

The operator's latest published dataset reports 21.2 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2029 (2029) · scenario: DFES 2026 - Electric Engagement
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Darlington Central 33/11kV|DFES 2026 - Electric Engagement · payload sha256 99a46f3cbfda…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2029

Offtake · Load (any) · Available

21.2 MW

Granted

The operator's latest published dataset reports 21.2 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2029 (2029) · scenario: DFES 2026 - Holistic Transition
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Darlington Central 33/11kV|DFES 2026 - Holistic Transition · payload sha256 bb545c21c8a5…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2029

Offtake · Load (any) · Available

21.2 MW

Granted

The operator's latest published dataset reports 21.2 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2029 (2029) · scenario: DFES 2026 - Hydrogen Evolution
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Darlington Central 33/11kV|DFES 2026 - Hydrogen Evolution · payload sha256 7fb7767eebc2…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2029

Offtake · Load (any) · Available

21.12 MW

Granted

The operator's latest published dataset reports 21.12 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2030 (2030) · scenario: DFES 2026 - Electric Engagement
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Darlington Central 33/11kV|DFES 2026 - Electric Engagement · payload sha256 99a46f3cbfda…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2030

Offtake · Load (any) · Available

21.12 MW

Granted

The operator's latest published dataset reports 21.12 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2030 (2030) · scenario: DFES 2026 - Holistic Transition
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Darlington Central 33/11kV|DFES 2026 - Holistic Transition · payload sha256 bb545c21c8a5…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2030

Offtake · Load (any) · Available

21.12 MW

Granted

The operator's latest published dataset reports 21.12 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2030 (2030) · scenario: DFES 2026 - Hydrogen Evolution
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Darlington Central 33/11kV|DFES 2026 - Hydrogen Evolution · payload sha256 7fb7767eebc2…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2030

Offtake · Load (any) · Available

21.08 MW

Granted

The operator's latest published dataset reports 21.08 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2031 (2031) · scenario: DFES 2026 - Electric Engagement
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Darlington Central 33/11kV|DFES 2026 - Electric Engagement · payload sha256 99a46f3cbfda…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2031

Offtake · Load (any) · Available

21.08 MW

Granted

The operator's latest published dataset reports 21.08 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2031 (2031) · scenario: DFES 2026 - Holistic Transition
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Darlington Central 33/11kV|DFES 2026 - Holistic Transition · payload sha256 bb545c21c8a5…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2031

Offtake · Load (any) · Available

21.08 MW

Granted

The operator's latest published dataset reports 21.08 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2031 (2031) · scenario: DFES 2026 - Hydrogen Evolution
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Darlington Central 33/11kV|DFES 2026 - Hydrogen Evolution · payload sha256 7fb7767eebc2…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2031

Offtake · Load (any) · Available

21.08 MW

Granted

The operator's latest published dataset reports 21.08 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2032 (2032) · scenario: DFES 2026 - Electric Engagement
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Darlington Central 33/11kV|DFES 2026 - Electric Engagement · payload sha256 99a46f3cbfda…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2032

Offtake · Load (any) · Available

21.08 MW

Granted

The operator's latest published dataset reports 21.08 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2032 (2032) · scenario: DFES 2026 - Holistic Transition
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Darlington Central 33/11kV|DFES 2026 - Holistic Transition · payload sha256 bb545c21c8a5…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2032

Offtake · Load (any) · Available

21.08 MW

Granted

The operator's latest published dataset reports 21.08 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2032 (2032) · scenario: DFES 2026 - Hydrogen Evolution
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Darlington Central 33/11kV|DFES 2026 - Hydrogen Evolution · payload sha256 7fb7767eebc2…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2032

Offtake · Load (any) · Available

21.03 MW

Granted

The operator's latest published dataset reports 21.03 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2033 (2033) · scenario: DFES 2026 - Electric Engagement
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Darlington Central 33/11kV|DFES 2026 - Electric Engagement · payload sha256 99a46f3cbfda…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2033

Offtake · Load (any) · Available

21.03 MW

Granted

The operator's latest published dataset reports 21.03 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2033 (2033) · scenario: DFES 2026 - Holistic Transition
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Darlington Central 33/11kV|DFES 2026 - Holistic Transition · payload sha256 bb545c21c8a5…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2033

Offtake · Load (any) · Available

21.03 MW

Granted

The operator's latest published dataset reports 21.03 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2033 (2033) · scenario: DFES 2026 - Hydrogen Evolution
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Darlington Central 33/11kV|DFES 2026 - Hydrogen Evolution · payload sha256 7fb7767eebc2…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2033

Offtake · Load (any) · Available

20.97 MW

Granted

The operator's latest published dataset reports 20.97 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2034 (2034) · scenario: DFES 2026 - Electric Engagement
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Darlington Central 33/11kV|DFES 2026 - Electric Engagement · payload sha256 99a46f3cbfda…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2034

Offtake · Load (any) · Available

20.97 MW

Granted

The operator's latest published dataset reports 20.97 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2034 (2034) · scenario: DFES 2026 - Holistic Transition
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Darlington Central 33/11kV|DFES 2026 - Holistic Transition · payload sha256 bb545c21c8a5…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2034

Offtake · Load (any) · Available

20.97 MW

Granted

The operator's latest published dataset reports 20.97 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2034 (2034) · scenario: DFES 2026 - Hydrogen Evolution
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Darlington Central 33/11kV|DFES 2026 - Hydrogen Evolution · payload sha256 7fb7767eebc2…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2034

Offtake · Load (any) · Available

20.89 MW

Granted

The operator's latest published dataset reports 20.89 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2035 (2035) · scenario: DFES 2026 - Electric Engagement
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Darlington Central 33/11kV|DFES 2026 - Electric Engagement · payload sha256 99a46f3cbfda…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2035

Offtake · Load (any) · Available

20.88 MW

Granted

The operator's latest published dataset reports 20.88 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2035 (2035) · scenario: DFES 2026 - Holistic Transition
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Darlington Central 33/11kV|DFES 2026 - Holistic Transition · payload sha256 bb545c21c8a5…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2035

Offtake · Load (any) · Available

20.51 MW

Granted

The operator's latest published dataset reports 20.51 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2035 (2035) · scenario: DFES 2026 - Hydrogen Evolution
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Darlington Central 33/11kV|DFES 2026 - Hydrogen Evolution · payload sha256 7fb7767eebc2…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2035

Offtake · Load (any) · Available

20.34 MW

Granted

The operator's latest published dataset reports 20.34 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2040 (2040) · scenario: DFES 2026 - Electric Engagement
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Darlington Central 33/11kV|DFES 2026 - Electric Engagement · payload sha256 99a46f3cbfda…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2040

Offtake · Load (any) · Available

20.29 MW

Granted

The operator's latest published dataset reports 20.29 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2040 (2040) · scenario: DFES 2026 - Holistic Transition
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Darlington Central 33/11kV|DFES 2026 - Holistic Transition · payload sha256 bb545c21c8a5…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2040

Offtake · Load (any) · Available

20.03 MW

Granted

The operator's latest published dataset reports 20.03 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2040 (2040) · scenario: DFES 2026 - Hydrogen Evolution
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Darlington Central 33/11kV|DFES 2026 - Hydrogen Evolution · payload sha256 7fb7767eebc2…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2040

Offtake · Load (any) · Available

20.1 MW

Granted

The operator's latest published dataset reports 20.1 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2045 (2045) · scenario: DFES 2026 - Electric Engagement
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Darlington Central 33/11kV|DFES 2026 - Electric Engagement · payload sha256 99a46f3cbfda…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2045

Offtake · Load (any) · Available

20.1 MW

Granted

The operator's latest published dataset reports 20.1 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2045 (2045) · scenario: DFES 2026 - Holistic Transition
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Darlington Central 33/11kV|DFES 2026 - Holistic Transition · payload sha256 bb545c21c8a5…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2045

Offtake · Load (any) · Available

19.71 MW

Granted

The operator's latest published dataset reports 19.71 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2045 (2045) · scenario: DFES 2026 - Hydrogen Evolution
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Darlington Central 33/11kV|DFES 2026 - Hydrogen Evolution · payload sha256 7fb7767eebc2…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2045

Offtake · Load (any) · Available

20.14 MW

Granted

The operator's latest published dataset reports 20.14 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2050 (2050) · scenario: DFES 2026 - Holistic Transition
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Darlington Central 33/11kV|DFES 2026 - Holistic Transition · payload sha256 bb545c21c8a5…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2050

Offtake · Load (any) · Available

20.06 MW

Granted

The operator's latest published dataset reports 20.06 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2050 (2050) · scenario: DFES 2026 - Electric Engagement
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Darlington Central 33/11kV|DFES 2026 - Electric Engagement · payload sha256 99a46f3cbfda…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2050

Offtake · Load (any) · Available

19.62 MW

Granted

The operator's latest published dataset reports 19.62 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2050 (2050) · scenario: DFES 2026 - Hydrogen Evolution
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Darlington Central 33/11kV|DFES 2026 - Hydrogen Evolution · payload sha256 7fb7767eebc2…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2050

Offtake · Load (any) · Contracted

0 MVA

Published in MVA; no MW figure is derived from it.

Granted

The operator's latest published dataset reports 0 MVA under methodology gb_npg_heatmap_2026.

Firmness
Unknown
Horizon
Now (snapshot)
Methodology
gb_npg_heatmap_2026Northern Powergrid heat-map data: thermal headroombasis operator calculated · network state unknown · comparability class gb_npg_heatmapNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
27 Jul 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_heatmaprecord Darlington Central 33/11kV · payload sha256 177d24f3df7c…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-07-27)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demtot

Offtake · Load (any) · Total

32 MVA

Published in MVA; no MW figure is derived from it.

Granted

The operator's latest published dataset reports 32 MVA under methodology gb_npg_heatmap_2026.

Firmness
Firm
Horizon
Now (snapshot)
Methodology
gb_npg_heatmap_2026Northern Powergrid heat-map data: thermal headroombasis operator calculated · network state unknown · comparability class gb_npg_heatmapNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
27 Jul 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_heatmaprecord Darlington Central 33/11kV · payload sha256 177d24f3df7c…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-07-27)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
firm_cap

History

Served series only

Injection · Generation (any) · Available

current 0 MW

26 Sep 2026: 0 MW
26 Sep 2026range 0–0 MW26 Sep 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current0 MW

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Load (any) · Available

current 0 MVA

26 Sep 2026: 0 MVA
26 Sep 2026range 0–0 MVA26 Sep 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current0 MVA

Time axis: when we observed each value, not the operator’s effective date.

Injection · Generation (any) · Contracted

current 0 MW

26 Sep 2026: 0 MW
26 Sep 2026range 0–0 MW26 Sep 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current0 MW

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Load (any) · Contracted

current 0 MVA

26 Sep 2026: 0 MVA
26 Sep 2026range 0–0 MVA26 Sep 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current0 MVA

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Load (any) · Total

current 32 MVA

26 Sep 2026: 32 MVA
26 Sep 2026range 32–32 MVA26 Sep 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current32 MVA

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Load (any) · Available · 2026

current 21.25 MW

26 Sep 2026: 21.25 MW
26 Sep 2026range 21.25–21.25 MW26 Sep 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current21.25 MW

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Load (any) · Available · 2027

current 21.28 MW

26 Sep 2026: 21.28 MW
26 Sep 2026range 21.28–21.28 MW26 Sep 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current21.28 MW

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Load (any) · Available · 2028

current 21.25 MW

26 Sep 2026: 21.25 MW
26 Sep 2026range 21.25–21.25 MW26 Sep 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current21.25 MW

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Load (any) · Available · 2029

current 21.2 MW

26 Sep 2026: 21.2 MW
26 Sep 2026range 21.2–21.2 MW26 Sep 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current21.2 MW

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Load (any) · Available · 2030

current 21.12 MW

26 Sep 2026: 21.12 MW
26 Sep 2026range 21.12–21.12 MW26 Sep 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current21.12 MW

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Load (any) · Available · 2031

current 21.08 MW

26 Sep 2026: 21.08 MW
26 Sep 2026range 21.08–21.08 MW26 Sep 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current21.08 MW

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Load (any) · Available · 2032

current 21.08 MW

26 Sep 2026: 21.08 MW
26 Sep 2026range 21.08–21.08 MW26 Sep 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current21.08 MW

Time axis: when we observed each value, not the operator’s effective date.

The first 12 of 83 served series with a history. The history route returns every one of them.

Through the API

curl "https://api.gridcapacityapi.com/v1/substations/sub_06gdq6mq65tf544vbzpxb2z3y4/capacity" \  -H "Authorization: Bearer gc_live_..."
Darlington Central 33/11kV substation: grid capacity (Northern Powergrid) · GridCapacity API