Substation · 11 kV · primary

Amberton Road

Northern Powergrid · United Kingdom

Latest published values

83 served · 0 withheld

Each row is what the operator’s latest published dataset reports for one combination of direction, technology, measure, firmness and horizon. Hosting-capacity figures are indicative and reflect what operators publish. They are not a connection offer; only the operator can confirm capacity for a specific request.

Latest published capacity values, one row per series
DirectionTechnologyMeasureValueFirmnessHorizonSource date
InjectionGeneration (any)Available0 MWFirmNow (snapshot)27 Jul 2026
InjectionGeneration (any)Available42.23 MWUnknown2026 (2026)scenario: DFES 2026 - Holistic Transition24 Apr 2026
InjectionGeneration (any)Available42.23 MWUnknown2026 (2026)scenario: DFES 2026 - Hydrogen Evolution24 Apr 2026
InjectionGeneration (any)Available42.23 MWUnknown2026 (2026)scenario: DFES 2026 - Electric Engagement24 Apr 2026
InjectionGeneration (any)Available40.95 MWUnknown2027 (2027)scenario: DFES 2026 - Holistic Transition24 Apr 2026
InjectionGeneration (any)Available40.95 MWUnknown2027 (2027)scenario: DFES 2026 - Hydrogen Evolution24 Apr 2026
InjectionGeneration (any)Available40.95 MWUnknown2027 (2027)scenario: DFES 2026 - Electric Engagement24 Apr 2026
InjectionGeneration (any)Available40.26 MWUnknown2028 (2028)scenario: DFES 2026 - Holistic Transition24 Apr 2026
InjectionGeneration (any)Available40.26 MWUnknown2028 (2028)scenario: DFES 2026 - Hydrogen Evolution24 Apr 2026
InjectionGeneration (any)Available40.26 MWUnknown2028 (2028)scenario: DFES 2026 - Electric Engagement24 Apr 2026
InjectionGeneration (any)Available38.99 MWUnknown2029 (2029)scenario: DFES 2026 - Holistic Transition24 Apr 2026
InjectionGeneration (any)Available38.99 MWUnknown2029 (2029)scenario: DFES 2026 - Hydrogen Evolution24 Apr 2026
InjectionGeneration (any)Available38.99 MWUnknown2029 (2029)scenario: DFES 2026 - Electric Engagement24 Apr 2026
InjectionGeneration (any)Available38.63 MWUnknown2030 (2030)scenario: DFES 2026 - Holistic Transition24 Apr 2026
InjectionGeneration (any)Available38.63 MWUnknown2030 (2030)scenario: DFES 2026 - Hydrogen Evolution24 Apr 2026
InjectionGeneration (any)Available38.63 MWUnknown2030 (2030)scenario: DFES 2026 - Electric Engagement24 Apr 2026
InjectionGeneration (any)Available37.15 MWUnknown2031 (2031)scenario: DFES 2026 - Holistic Transition24 Apr 2026
InjectionGeneration (any)Available37.15 MWUnknown2031 (2031)scenario: DFES 2026 - Hydrogen Evolution24 Apr 2026
InjectionGeneration (any)Available37.15 MWUnknown2031 (2031)scenario: DFES 2026 - Electric Engagement24 Apr 2026
InjectionGeneration (any)Available35.74 MWUnknown2032 (2032)scenario: DFES 2026 - Holistic Transition24 Apr 2026
InjectionGeneration (any)Available35.74 MWUnknown2032 (2032)scenario: DFES 2026 - Hydrogen Evolution24 Apr 2026
InjectionGeneration (any)Available35.74 MWUnknown2032 (2032)scenario: DFES 2026 - Electric Engagement24 Apr 2026
InjectionGeneration (any)Available34.68 MWUnknown2033 (2033)scenario: DFES 2026 - Holistic Transition24 Apr 2026
InjectionGeneration (any)Available34.68 MWUnknown2033 (2033)scenario: DFES 2026 - Hydrogen Evolution24 Apr 2026
InjectionGeneration (any)Available34.68 MWUnknown2033 (2033)scenario: DFES 2026 - Electric Engagement24 Apr 2026
InjectionGeneration (any)Available34.31 MWUnknown2034 (2034)scenario: DFES 2026 - Holistic Transition24 Apr 2026
InjectionGeneration (any)Available34.31 MWUnknown2034 (2034)scenario: DFES 2026 - Hydrogen Evolution24 Apr 2026
InjectionGeneration (any)Available34.31 MWUnknown2034 (2034)scenario: DFES 2026 - Electric Engagement24 Apr 2026
InjectionGeneration (any)Available33.6 MWUnknown2035 (2035)scenario: DFES 2026 - Holistic Transition24 Apr 2026
InjectionGeneration (any)Available32.91 MWUnknown2035 (2035)scenario: DFES 2026 - Hydrogen Evolution24 Apr 2026
InjectionGeneration (any)Available32.38 MWUnknown2035 (2035)scenario: DFES 2026 - Electric Engagement24 Apr 2026
InjectionGeneration (any)Available32.83 MWUnknown2040 (2040)scenario: DFES 2026 - Hydrogen Evolution24 Apr 2026
InjectionGeneration (any)Available30.98 MWUnknown2040 (2040)scenario: DFES 2026 - Holistic Transition24 Apr 2026
InjectionGeneration (any)Available30.56 MWUnknown2040 (2040)scenario: DFES 2026 - Electric Engagement24 Apr 2026
InjectionGeneration (any)Available34.02 MWUnknown2045 (2045)scenario: DFES 2026 - Hydrogen Evolution24 Apr 2026
InjectionGeneration (any)Available29.49 MWUnknown2045 (2045)scenario: DFES 2026 - Electric Engagement24 Apr 2026
InjectionGeneration (any)Available29.31 MWUnknown2045 (2045)scenario: DFES 2026 - Holistic Transition24 Apr 2026
InjectionGeneration (any)Available33.39 MWUnknown2050 (2050)scenario: DFES 2026 - Hydrogen Evolution24 Apr 2026
InjectionGeneration (any)Available27.15 MWUnknown2050 (2050)scenario: DFES 2026 - Electric Engagement24 Apr 2026
InjectionGeneration (any)Available26.75 MWUnknown2050 (2050)scenario: DFES 2026 - Holistic Transition24 Apr 2026
InjectionGeneration (any)Contracted0 MWUnknownNow (snapshot)27 Jul 2026
OfftakeLoad (any)Available11.268 MVAFirmNow (snapshot)27 Jul 2026
OfftakeLoad (any)Available12.5 MWUnknown2026 (2026)scenario: DFES 2026 - Holistic Transition24 Apr 2026
OfftakeLoad (any)Available12.5 MWUnknown2026 (2026)scenario: DFES 2026 - Hydrogen Evolution24 Apr 2026
OfftakeLoad (any)Available12.5 MWUnknown2026 (2026)scenario: DFES 2026 - Electric Engagement24 Apr 2026
OfftakeLoad (any)Available12.38 MWUnknown2027 (2027)scenario: DFES 2026 - Holistic Transition24 Apr 2026
OfftakeLoad (any)Available12.38 MWUnknown2027 (2027)scenario: DFES 2026 - Hydrogen Evolution24 Apr 2026
OfftakeLoad (any)Available12.38 MWUnknown2027 (2027)scenario: DFES 2026 - Electric Engagement24 Apr 2026
OfftakeLoad (any)Available12.13 MWUnknown2028 (2028)scenario: DFES 2026 - Holistic Transition24 Apr 2026
OfftakeLoad (any)Available12.13 MWUnknown2028 (2028)scenario: DFES 2026 - Hydrogen Evolution24 Apr 2026
OfftakeLoad (any)Available12.13 MWUnknown2028 (2028)scenario: DFES 2026 - Electric Engagement24 Apr 2026
OfftakeLoad (any)Available11.79 MWUnknown2029 (2029)scenario: DFES 2026 - Holistic Transition24 Apr 2026
OfftakeLoad (any)Available11.79 MWUnknown2029 (2029)scenario: DFES 2026 - Hydrogen Evolution24 Apr 2026
OfftakeLoad (any)Available11.79 MWUnknown2029 (2029)scenario: DFES 2026 - Electric Engagement24 Apr 2026
OfftakeLoad (any)Available11.27 MWUnknown2030 (2030)scenario: DFES 2026 - Holistic Transition24 Apr 2026
OfftakeLoad (any)Available11.27 MWUnknown2030 (2030)scenario: DFES 2026 - Hydrogen Evolution24 Apr 2026
OfftakeLoad (any)Available11.27 MWUnknown2030 (2030)scenario: DFES 2026 - Electric Engagement24 Apr 2026
OfftakeLoad (any)Available10.89 MWUnknown2031 (2031)scenario: DFES 2026 - Holistic Transition24 Apr 2026
OfftakeLoad (any)Available10.89 MWUnknown2031 (2031)scenario: DFES 2026 - Hydrogen Evolution24 Apr 2026
OfftakeLoad (any)Available10.89 MWUnknown2031 (2031)scenario: DFES 2026 - Electric Engagement24 Apr 2026
OfftakeLoad (any)Available10.63 MWUnknown2032 (2032)scenario: DFES 2026 - Holistic Transition24 Apr 2026
OfftakeLoad (any)Available10.63 MWUnknown2032 (2032)scenario: DFES 2026 - Hydrogen Evolution24 Apr 2026
OfftakeLoad (any)Available10.63 MWUnknown2032 (2032)scenario: DFES 2026 - Electric Engagement24 Apr 2026
OfftakeLoad (any)Available10.2 MWUnknown2033 (2033)scenario: DFES 2026 - Holistic Transition24 Apr 2026
OfftakeLoad (any)Available10.2 MWUnknown2033 (2033)scenario: DFES 2026 - Hydrogen Evolution24 Apr 2026
OfftakeLoad (any)Available10.2 MWUnknown2033 (2033)scenario: DFES 2026 - Electric Engagement24 Apr 2026
OfftakeLoad (any)Available9.7 MWUnknown2034 (2034)scenario: DFES 2026 - Holistic Transition24 Apr 2026
OfftakeLoad (any)Available9.7 MWUnknown2034 (2034)scenario: DFES 2026 - Hydrogen Evolution24 Apr 2026
OfftakeLoad (any)Available9.7 MWUnknown2034 (2034)scenario: DFES 2026 - Electric Engagement24 Apr 2026
OfftakeLoad (any)Available9.22 MWUnknown2035 (2035)scenario: DFES 2026 - Electric Engagement24 Apr 2026
OfftakeLoad (any)Available9.11 MWUnknown2035 (2035)scenario: DFES 2026 - Holistic Transition24 Apr 2026
OfftakeLoad (any)Available8.23 MWUnknown2035 (2035)scenario: DFES 2026 - Hydrogen Evolution24 Apr 2026
OfftakeLoad (any)Available6.1 MWUnknown2040 (2040)scenario: DFES 2026 - Electric Engagement24 Apr 2026
OfftakeLoad (any)Available5.83 MWUnknown2040 (2040)scenario: DFES 2026 - Holistic Transition24 Apr 2026
OfftakeLoad (any)Available5.65 MWUnknown2040 (2040)scenario: DFES 2026 - Hydrogen Evolution24 Apr 2026
OfftakeLoad (any)Available4.52 MWUnknown2045 (2045)scenario: DFES 2026 - Electric Engagement24 Apr 2026
OfftakeLoad (any)Available4.48 MWUnknown2045 (2045)scenario: DFES 2026 - Holistic Transition24 Apr 2026
OfftakeLoad (any)Available3.85 MWUnknown2045 (2045)scenario: DFES 2026 - Hydrogen Evolution24 Apr 2026
OfftakeLoad (any)Available4.01 MWUnknown2050 (2050)scenario: DFES 2026 - Holistic Transition24 Apr 2026
OfftakeLoad (any)Available3.67 MWUnknown2050 (2050)scenario: DFES 2026 - Electric Engagement24 Apr 2026
OfftakeLoad (any)Available3.09 MWUnknown2050 (2050)scenario: DFES 2026 - Hydrogen Evolution24 Apr 2026
OfftakeLoad (any)Contracted3.912 MVAUnknownNow (snapshot)27 Jul 2026
OfftakeLoad (any)Total40 MVAFirmNow (snapshot)27 Jul 2026

Supported by Northern Powergrid Open Data (last updated 2026-04-24)Supported by Northern Powergrid Open Data (last updated 2026-07-27)

What each value means

Methodology, both clocks, provenance and rights

Injection · Generation (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology gb_npg_heatmap_2026.

Firmness
Firm
Horizon
Now (snapshot)
Methodology
gb_npg_heatmap_2026Northern Powergrid heat-map data: thermal headroombasis operator calculated · network state unknown · comparability class gb_npg_heatmapNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
27 Jul 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_heatmaprecord Amberton Road · payload sha256 1db53e13e254…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-07-27)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: gen voltage constraint
Some Voltage Constraint
Operator note: genconstraint
Amber - Voltage
Operator note: gsp hm constraint manual
R
Operator note: rag colour
amber
Operator note: source field
genhr
Operator note: upgenconst
Upstream Constraint
Operator note: worst case constraint gen colour
Amber

Injection · Generation (any) · Available

42.23 MW

Granted

The operator's latest published dataset reports 42.23 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2026 (2026) · scenario: DFES 2026 - Holistic Transition
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Amberton Road|DFES 2026 - Holistic Transition · payload sha256 50af03bac76a…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2026

Injection · Generation (any) · Available

42.23 MW

Granted

The operator's latest published dataset reports 42.23 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2026 (2026) · scenario: DFES 2026 - Hydrogen Evolution
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Amberton Road|DFES 2026 - Hydrogen Evolution · payload sha256 0b27ba631591…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2026

Injection · Generation (any) · Available

42.23 MW

Granted

The operator's latest published dataset reports 42.23 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2026 (2026) · scenario: DFES 2026 - Electric Engagement
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Amberton Road|DFES 2026 - Electric Engagement · payload sha256 6c6dded4f018…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2026

Injection · Generation (any) · Available

40.95 MW

Granted

The operator's latest published dataset reports 40.95 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2027 (2027) · scenario: DFES 2026 - Holistic Transition
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Amberton Road|DFES 2026 - Holistic Transition · payload sha256 50af03bac76a…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2027

Injection · Generation (any) · Available

40.95 MW

Granted

The operator's latest published dataset reports 40.95 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2027 (2027) · scenario: DFES 2026 - Hydrogen Evolution
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Amberton Road|DFES 2026 - Hydrogen Evolution · payload sha256 0b27ba631591…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2027

Injection · Generation (any) · Available

40.95 MW

Granted

The operator's latest published dataset reports 40.95 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2027 (2027) · scenario: DFES 2026 - Electric Engagement
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Amberton Road|DFES 2026 - Electric Engagement · payload sha256 6c6dded4f018…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2027

Injection · Generation (any) · Available

40.26 MW

Granted

The operator's latest published dataset reports 40.26 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2028 (2028) · scenario: DFES 2026 - Holistic Transition
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Amberton Road|DFES 2026 - Holistic Transition · payload sha256 50af03bac76a…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2028

Injection · Generation (any) · Available

40.26 MW

Granted

The operator's latest published dataset reports 40.26 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2028 (2028) · scenario: DFES 2026 - Hydrogen Evolution
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Amberton Road|DFES 2026 - Hydrogen Evolution · payload sha256 0b27ba631591…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2028

Injection · Generation (any) · Available

40.26 MW

Granted

The operator's latest published dataset reports 40.26 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2028 (2028) · scenario: DFES 2026 - Electric Engagement
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Amberton Road|DFES 2026 - Electric Engagement · payload sha256 6c6dded4f018…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2028

Injection · Generation (any) · Available

38.99 MW

Granted

The operator's latest published dataset reports 38.99 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2029 (2029) · scenario: DFES 2026 - Holistic Transition
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Amberton Road|DFES 2026 - Holistic Transition · payload sha256 50af03bac76a…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2029

Injection · Generation (any) · Available

38.99 MW

Granted

The operator's latest published dataset reports 38.99 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2029 (2029) · scenario: DFES 2026 - Hydrogen Evolution
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Amberton Road|DFES 2026 - Hydrogen Evolution · payload sha256 0b27ba631591…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2029

Injection · Generation (any) · Available

38.99 MW

Granted

The operator's latest published dataset reports 38.99 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2029 (2029) · scenario: DFES 2026 - Electric Engagement
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Amberton Road|DFES 2026 - Electric Engagement · payload sha256 6c6dded4f018…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2029

Injection · Generation (any) · Available

38.63 MW

Granted

The operator's latest published dataset reports 38.63 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2030 (2030) · scenario: DFES 2026 - Holistic Transition
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Amberton Road|DFES 2026 - Holistic Transition · payload sha256 50af03bac76a…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2030

Injection · Generation (any) · Available

38.63 MW

Granted

The operator's latest published dataset reports 38.63 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2030 (2030) · scenario: DFES 2026 - Hydrogen Evolution
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Amberton Road|DFES 2026 - Hydrogen Evolution · payload sha256 0b27ba631591…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2030

Injection · Generation (any) · Available

38.63 MW

Granted

The operator's latest published dataset reports 38.63 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2030 (2030) · scenario: DFES 2026 - Electric Engagement
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Amberton Road|DFES 2026 - Electric Engagement · payload sha256 6c6dded4f018…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2030

Injection · Generation (any) · Available

37.15 MW

Granted

The operator's latest published dataset reports 37.15 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2031 (2031) · scenario: DFES 2026 - Holistic Transition
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Amberton Road|DFES 2026 - Holistic Transition · payload sha256 50af03bac76a…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2031

Injection · Generation (any) · Available

37.15 MW

Granted

The operator's latest published dataset reports 37.15 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2031 (2031) · scenario: DFES 2026 - Hydrogen Evolution
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Amberton Road|DFES 2026 - Hydrogen Evolution · payload sha256 0b27ba631591…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2031

Injection · Generation (any) · Available

37.15 MW

Granted

The operator's latest published dataset reports 37.15 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2031 (2031) · scenario: DFES 2026 - Electric Engagement
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Amberton Road|DFES 2026 - Electric Engagement · payload sha256 6c6dded4f018…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2031

Injection · Generation (any) · Available

35.74 MW

Granted

The operator's latest published dataset reports 35.74 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2032 (2032) · scenario: DFES 2026 - Holistic Transition
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Amberton Road|DFES 2026 - Holistic Transition · payload sha256 50af03bac76a…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2032

Injection · Generation (any) · Available

35.74 MW

Granted

The operator's latest published dataset reports 35.74 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2032 (2032) · scenario: DFES 2026 - Hydrogen Evolution
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Amberton Road|DFES 2026 - Hydrogen Evolution · payload sha256 0b27ba631591…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2032

Injection · Generation (any) · Available

35.74 MW

Granted

The operator's latest published dataset reports 35.74 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2032 (2032) · scenario: DFES 2026 - Electric Engagement
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Amberton Road|DFES 2026 - Electric Engagement · payload sha256 6c6dded4f018…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2032

Injection · Generation (any) · Available

34.68 MW

Granted

The operator's latest published dataset reports 34.68 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2033 (2033) · scenario: DFES 2026 - Holistic Transition
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Amberton Road|DFES 2026 - Holistic Transition · payload sha256 50af03bac76a…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2033

Injection · Generation (any) · Available

34.68 MW

Granted

The operator's latest published dataset reports 34.68 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2033 (2033) · scenario: DFES 2026 - Hydrogen Evolution
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Amberton Road|DFES 2026 - Hydrogen Evolution · payload sha256 0b27ba631591…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2033

Injection · Generation (any) · Available

34.68 MW

Granted

The operator's latest published dataset reports 34.68 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2033 (2033) · scenario: DFES 2026 - Electric Engagement
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Amberton Road|DFES 2026 - Electric Engagement · payload sha256 6c6dded4f018…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2033

Injection · Generation (any) · Available

34.31 MW

Granted

The operator's latest published dataset reports 34.31 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2034 (2034) · scenario: DFES 2026 - Holistic Transition
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Amberton Road|DFES 2026 - Holistic Transition · payload sha256 50af03bac76a…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2034

Injection · Generation (any) · Available

34.31 MW

Granted

The operator's latest published dataset reports 34.31 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2034 (2034) · scenario: DFES 2026 - Hydrogen Evolution
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Amberton Road|DFES 2026 - Hydrogen Evolution · payload sha256 0b27ba631591…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2034

Injection · Generation (any) · Available

34.31 MW

Granted

The operator's latest published dataset reports 34.31 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2034 (2034) · scenario: DFES 2026 - Electric Engagement
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Amberton Road|DFES 2026 - Electric Engagement · payload sha256 6c6dded4f018…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2034

Injection · Generation (any) · Available

33.6 MW

Granted

The operator's latest published dataset reports 33.6 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2035 (2035) · scenario: DFES 2026 - Holistic Transition
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Amberton Road|DFES 2026 - Holistic Transition · payload sha256 50af03bac76a…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2035

Injection · Generation (any) · Available

32.91 MW

Granted

The operator's latest published dataset reports 32.91 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2035 (2035) · scenario: DFES 2026 - Hydrogen Evolution
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Amberton Road|DFES 2026 - Hydrogen Evolution · payload sha256 0b27ba631591…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2035

Injection · Generation (any) · Available

32.38 MW

Granted

The operator's latest published dataset reports 32.38 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2035 (2035) · scenario: DFES 2026 - Electric Engagement
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Amberton Road|DFES 2026 - Electric Engagement · payload sha256 6c6dded4f018…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2035

Injection · Generation (any) · Available

32.83 MW

Granted

The operator's latest published dataset reports 32.83 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2040 (2040) · scenario: DFES 2026 - Hydrogen Evolution
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Amberton Road|DFES 2026 - Hydrogen Evolution · payload sha256 0b27ba631591…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2040

Injection · Generation (any) · Available

30.98 MW

Granted

The operator's latest published dataset reports 30.98 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2040 (2040) · scenario: DFES 2026 - Holistic Transition
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Amberton Road|DFES 2026 - Holistic Transition · payload sha256 50af03bac76a…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2040

Injection · Generation (any) · Available

30.56 MW

Granted

The operator's latest published dataset reports 30.56 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2040 (2040) · scenario: DFES 2026 - Electric Engagement
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Amberton Road|DFES 2026 - Electric Engagement · payload sha256 6c6dded4f018…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2040

Injection · Generation (any) · Available

34.02 MW

Granted

The operator's latest published dataset reports 34.02 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2045 (2045) · scenario: DFES 2026 - Hydrogen Evolution
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Amberton Road|DFES 2026 - Hydrogen Evolution · payload sha256 0b27ba631591…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2045

Injection · Generation (any) · Available

29.49 MW

Granted

The operator's latest published dataset reports 29.49 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2045 (2045) · scenario: DFES 2026 - Electric Engagement
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Amberton Road|DFES 2026 - Electric Engagement · payload sha256 6c6dded4f018…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2045

Injection · Generation (any) · Available

29.31 MW

Granted

The operator's latest published dataset reports 29.31 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2045 (2045) · scenario: DFES 2026 - Holistic Transition
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Amberton Road|DFES 2026 - Holistic Transition · payload sha256 50af03bac76a…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2045

Injection · Generation (any) · Available

33.39 MW

Granted

The operator's latest published dataset reports 33.39 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2050 (2050) · scenario: DFES 2026 - Hydrogen Evolution
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Amberton Road|DFES 2026 - Hydrogen Evolution · payload sha256 0b27ba631591…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2050

Injection · Generation (any) · Available

27.15 MW

Granted

The operator's latest published dataset reports 27.15 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2050 (2050) · scenario: DFES 2026 - Electric Engagement
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Amberton Road|DFES 2026 - Electric Engagement · payload sha256 6c6dded4f018…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2050

Injection · Generation (any) · Available

26.75 MW

Granted

The operator's latest published dataset reports 26.75 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2050 (2050) · scenario: DFES 2026 - Holistic Transition
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord generation|Amberton Road|DFES 2026 - Holistic Transition · payload sha256 50af03bac76a…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generation_headroom_capacity_mw_2050

Injection · Generation (any) · Contracted

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology gb_npg_heatmap_2026.

Firmness
Unknown
Horizon
Now (snapshot)
Methodology
gb_npg_heatmap_2026Northern Powergrid heat-map data: thermal headroombasis operator calculated · network state unknown · comparability class gb_npg_heatmapNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
27 Jul 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_heatmaprecord Amberton Road · payload sha256 1db53e13e254…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-07-27)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
gentot

Offtake · Load (any) · Available

11.268 MVA

Published in MVA; no MW figure is derived from it.

Granted

The operator's latest published dataset reports 11.268000305 MVA under methodology gb_npg_heatmap_2026.

Firmness
Firm
Horizon
Now (snapshot)
Methodology
gb_npg_heatmap_2026Northern Powergrid heat-map data: thermal headroombasis operator calculated · network state unknown · comparability class gb_npg_heatmapNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
27 Jul 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_heatmaprecord Amberton Road · payload sha256 1db53e13e254…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-07-27)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: dem voltage constraint
No Voltage Constraint
Operator note: demconstraint
Green
Operator note: gsp hm constraint manual
R
Operator note: rag colour
green
Operator note: source field
demhr
Operator note: updemconst
No
Operator note: worst case constraint dem colour
Green

Offtake · Load (any) · Available

12.5 MW

Granted

The operator's latest published dataset reports 12.5 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2026 (2026) · scenario: DFES 2026 - Holistic Transition
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Amberton Road|DFES 2026 - Holistic Transition · payload sha256 3b91b3af3c35…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2026

Offtake · Load (any) · Available

12.5 MW

Granted

The operator's latest published dataset reports 12.5 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2026 (2026) · scenario: DFES 2026 - Hydrogen Evolution
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Amberton Road|DFES 2026 - Hydrogen Evolution · payload sha256 ec4c777b8811…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2026

Offtake · Load (any) · Available

12.5 MW

Granted

The operator's latest published dataset reports 12.5 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2026 (2026) · scenario: DFES 2026 - Electric Engagement
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Amberton Road|DFES 2026 - Electric Engagement · payload sha256 bc3d2c933c71…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2026

Offtake · Load (any) · Available

12.38 MW

Granted

The operator's latest published dataset reports 12.38 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2027 (2027) · scenario: DFES 2026 - Holistic Transition
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Amberton Road|DFES 2026 - Holistic Transition · payload sha256 3b91b3af3c35…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2027

Offtake · Load (any) · Available

12.38 MW

Granted

The operator's latest published dataset reports 12.38 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2027 (2027) · scenario: DFES 2026 - Hydrogen Evolution
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Amberton Road|DFES 2026 - Hydrogen Evolution · payload sha256 ec4c777b8811…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2027

Offtake · Load (any) · Available

12.38 MW

Granted

The operator's latest published dataset reports 12.38 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2027 (2027) · scenario: DFES 2026 - Electric Engagement
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Amberton Road|DFES 2026 - Electric Engagement · payload sha256 bc3d2c933c71…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2027

Offtake · Load (any) · Available

12.13 MW

Granted

The operator's latest published dataset reports 12.13 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2028 (2028) · scenario: DFES 2026 - Holistic Transition
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Amberton Road|DFES 2026 - Holistic Transition · payload sha256 3b91b3af3c35…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2028

Offtake · Load (any) · Available

12.13 MW

Granted

The operator's latest published dataset reports 12.13 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2028 (2028) · scenario: DFES 2026 - Hydrogen Evolution
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Amberton Road|DFES 2026 - Hydrogen Evolution · payload sha256 ec4c777b8811…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2028

Offtake · Load (any) · Available

12.13 MW

Granted

The operator's latest published dataset reports 12.13 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2028 (2028) · scenario: DFES 2026 - Electric Engagement
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Amberton Road|DFES 2026 - Electric Engagement · payload sha256 bc3d2c933c71…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2028

Offtake · Load (any) · Available

11.79 MW

Granted

The operator's latest published dataset reports 11.79 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2029 (2029) · scenario: DFES 2026 - Holistic Transition
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Amberton Road|DFES 2026 - Holistic Transition · payload sha256 3b91b3af3c35…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2029

Offtake · Load (any) · Available

11.79 MW

Granted

The operator's latest published dataset reports 11.79 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2029 (2029) · scenario: DFES 2026 - Hydrogen Evolution
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Amberton Road|DFES 2026 - Hydrogen Evolution · payload sha256 ec4c777b8811…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2029

Offtake · Load (any) · Available

11.79 MW

Granted

The operator's latest published dataset reports 11.79 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2029 (2029) · scenario: DFES 2026 - Electric Engagement
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Amberton Road|DFES 2026 - Electric Engagement · payload sha256 bc3d2c933c71…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2029

Offtake · Load (any) · Available

11.27 MW

Granted

The operator's latest published dataset reports 11.27 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2030 (2030) · scenario: DFES 2026 - Holistic Transition
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Amberton Road|DFES 2026 - Holistic Transition · payload sha256 3b91b3af3c35…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2030

Offtake · Load (any) · Available

11.27 MW

Granted

The operator's latest published dataset reports 11.27 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2030 (2030) · scenario: DFES 2026 - Hydrogen Evolution
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Amberton Road|DFES 2026 - Hydrogen Evolution · payload sha256 ec4c777b8811…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2030

Offtake · Load (any) · Available

11.27 MW

Granted

The operator's latest published dataset reports 11.27 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2030 (2030) · scenario: DFES 2026 - Electric Engagement
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Amberton Road|DFES 2026 - Electric Engagement · payload sha256 bc3d2c933c71…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2030

Offtake · Load (any) · Available

10.89 MW

Granted

The operator's latest published dataset reports 10.89 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2031 (2031) · scenario: DFES 2026 - Holistic Transition
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Amberton Road|DFES 2026 - Holistic Transition · payload sha256 3b91b3af3c35…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2031

Offtake · Load (any) · Available

10.89 MW

Granted

The operator's latest published dataset reports 10.89 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2031 (2031) · scenario: DFES 2026 - Hydrogen Evolution
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Amberton Road|DFES 2026 - Hydrogen Evolution · payload sha256 ec4c777b8811…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2031

Offtake · Load (any) · Available

10.89 MW

Granted

The operator's latest published dataset reports 10.89 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2031 (2031) · scenario: DFES 2026 - Electric Engagement
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Amberton Road|DFES 2026 - Electric Engagement · payload sha256 bc3d2c933c71…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2031

Offtake · Load (any) · Available

10.63 MW

Granted

The operator's latest published dataset reports 10.63 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2032 (2032) · scenario: DFES 2026 - Holistic Transition
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Amberton Road|DFES 2026 - Holistic Transition · payload sha256 3b91b3af3c35…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2032

Offtake · Load (any) · Available

10.63 MW

Granted

The operator's latest published dataset reports 10.63 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2032 (2032) · scenario: DFES 2026 - Hydrogen Evolution
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Amberton Road|DFES 2026 - Hydrogen Evolution · payload sha256 ec4c777b8811…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2032

Offtake · Load (any) · Available

10.63 MW

Granted

The operator's latest published dataset reports 10.63 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2032 (2032) · scenario: DFES 2026 - Electric Engagement
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Amberton Road|DFES 2026 - Electric Engagement · payload sha256 bc3d2c933c71…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2032

Offtake · Load (any) · Available

10.2 MW

Granted

The operator's latest published dataset reports 10.2 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2033 (2033) · scenario: DFES 2026 - Holistic Transition
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Amberton Road|DFES 2026 - Holistic Transition · payload sha256 3b91b3af3c35…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2033

Offtake · Load (any) · Available

10.2 MW

Granted

The operator's latest published dataset reports 10.2 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2033 (2033) · scenario: DFES 2026 - Hydrogen Evolution
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Amberton Road|DFES 2026 - Hydrogen Evolution · payload sha256 ec4c777b8811…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2033

Offtake · Load (any) · Available

10.2 MW

Granted

The operator's latest published dataset reports 10.2 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2033 (2033) · scenario: DFES 2026 - Electric Engagement
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Amberton Road|DFES 2026 - Electric Engagement · payload sha256 bc3d2c933c71…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2033

Offtake · Load (any) · Available

9.7 MW

Granted

The operator's latest published dataset reports 9.7 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2034 (2034) · scenario: DFES 2026 - Holistic Transition
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Amberton Road|DFES 2026 - Holistic Transition · payload sha256 3b91b3af3c35…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2034

Offtake · Load (any) · Available

9.7 MW

Granted

The operator's latest published dataset reports 9.7 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2034 (2034) · scenario: DFES 2026 - Hydrogen Evolution
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Amberton Road|DFES 2026 - Hydrogen Evolution · payload sha256 ec4c777b8811…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2034

Offtake · Load (any) · Available

9.7 MW

Granted

The operator's latest published dataset reports 9.7 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2034 (2034) · scenario: DFES 2026 - Electric Engagement
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Amberton Road|DFES 2026 - Electric Engagement · payload sha256 bc3d2c933c71…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2034

Offtake · Load (any) · Available

9.22 MW

Granted

The operator's latest published dataset reports 9.22 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2035 (2035) · scenario: DFES 2026 - Electric Engagement
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Amberton Road|DFES 2026 - Electric Engagement · payload sha256 bc3d2c933c71…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2035

Offtake · Load (any) · Available

9.11 MW

Granted

The operator's latest published dataset reports 9.11 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2035 (2035) · scenario: DFES 2026 - Holistic Transition
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Amberton Road|DFES 2026 - Holistic Transition · payload sha256 3b91b3af3c35…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2035

Offtake · Load (any) · Available

8.23 MW

Granted

The operator's latest published dataset reports 8.23 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2035 (2035) · scenario: DFES 2026 - Hydrogen Evolution
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Amberton Road|DFES 2026 - Hydrogen Evolution · payload sha256 ec4c777b8811…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2035

Offtake · Load (any) · Available

6.1 MW

Granted

The operator's latest published dataset reports 6.1 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2040 (2040) · scenario: DFES 2026 - Electric Engagement
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Amberton Road|DFES 2026 - Electric Engagement · payload sha256 bc3d2c933c71…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2040

Offtake · Load (any) · Available

5.83 MW

Granted

The operator's latest published dataset reports 5.83 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2040 (2040) · scenario: DFES 2026 - Holistic Transition
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Amberton Road|DFES 2026 - Holistic Transition · payload sha256 3b91b3af3c35…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2040

Offtake · Load (any) · Available

5.65 MW

Granted

The operator's latest published dataset reports 5.65 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2040 (2040) · scenario: DFES 2026 - Hydrogen Evolution
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Amberton Road|DFES 2026 - Hydrogen Evolution · payload sha256 ec4c777b8811…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2040

Offtake · Load (any) · Available

4.52 MW

Granted

The operator's latest published dataset reports 4.52 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2045 (2045) · scenario: DFES 2026 - Electric Engagement
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Amberton Road|DFES 2026 - Electric Engagement · payload sha256 bc3d2c933c71…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2045

Offtake · Load (any) · Available

4.48 MW

Granted

The operator's latest published dataset reports 4.48 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2045 (2045) · scenario: DFES 2026 - Holistic Transition
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Amberton Road|DFES 2026 - Holistic Transition · payload sha256 3b91b3af3c35…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2045

Offtake · Load (any) · Available

3.85 MW

Granted

The operator's latest published dataset reports 3.85 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2045 (2045) · scenario: DFES 2026 - Hydrogen Evolution
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Amberton Road|DFES 2026 - Hydrogen Evolution · payload sha256 ec4c777b8811…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2045

Offtake · Load (any) · Available

4.01 MW

Granted

The operator's latest published dataset reports 4.01 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2050 (2050) · scenario: DFES 2026 - Holistic Transition
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Amberton Road|DFES 2026 - Holistic Transition · payload sha256 3b91b3af3c35…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2050

Offtake · Load (any) · Available

3.67 MW

Granted

The operator's latest published dataset reports 3.67 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2050 (2050) · scenario: DFES 2026 - Electric Engagement
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Amberton Road|DFES 2026 - Electric Engagement · payload sha256 bc3d2c933c71…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2050

Offtake · Load (any) · Available

3.09 MW

Granted

The operator's latest published dataset reports 3.09 MW under methodology gb_npg_nhr_2026.

Firmness
Unknown
Horizon
2050 (2050) · scenario: DFES 2026 - Hydrogen Evolution
Methodology
gb_npg_nhr_2026NPg Network Development Plan — Network Headroom Report (DFES 2026)basis operator calculated · network state unknown · comparability class gb_npg_nhrNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
24 Apr 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_ndp_headroomrecord demand|Amberton Road|DFES 2026 - Hydrogen Evolution · payload sha256 ec4c777b8811…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-04-24)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demand_headroom_capacity_mw_2050

Offtake · Load (any) · Contracted

3.912 MVA

Published in MVA; no MW figure is derived from it.

Granted

The operator's latest published dataset reports 3.912 MVA under methodology gb_npg_heatmap_2026.

Firmness
Unknown
Horizon
Now (snapshot)
Methodology
gb_npg_heatmap_2026Northern Powergrid heat-map data: thermal headroombasis operator calculated · network state unknown · comparability class gb_npg_heatmapNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
27 Jul 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_heatmaprecord Amberton Road · payload sha256 1db53e13e254…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-07-27)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demtot

Offtake · Load (any) · Total

40 MVA

Published in MVA; no MW figure is derived from it.

Granted

The operator's latest published dataset reports 40 MVA under methodology gb_npg_heatmap_2026.

Firmness
Firm
Horizon
Now (snapshot)
Methodology
gb_npg_heatmap_2026Northern Powergrid heat-map data: thermal headroombasis operator calculated · network state unknown · comparability class gb_npg_heatmapNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
27 Jul 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-09-26 02:45 UTC
Source health
Healthy
Provenance
gb_npg_heatmaprecord Amberton Road · payload sha256 1db53e13e254…Operator’s publication (opens the operator’s site)
Licence
Northern Powergrid Open Data Licence v1.0Attribution: Supported by Northern Powergrid Open Data (last updated 2026-07-27)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
firm_cap

History

Served series only

Injection · Generation (any) · Available

current 0 MW

26 Sep 2026: 0 MW
26 Sep 2026range 0–0 MW26 Sep 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current0 MW

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Load (any) · Available

current 11.268 MVA

26 Sep 2026: 11.268 MVA
26 Sep 2026range 11.268–11.268 MVA26 Sep 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current11.268 MVA

Time axis: when we observed each value, not the operator’s effective date.

Injection · Generation (any) · Contracted

current 0 MW

26 Sep 2026: 0 MW
26 Sep 2026range 0–0 MW26 Sep 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current0 MW

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Load (any) · Contracted

current 3.912 MVA

26 Sep 2026: 3.912 MVA
26 Sep 2026range 3.912–3.912 MVA26 Sep 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current3.912 MVA

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Load (any) · Total

current 40 MVA

26 Sep 2026: 40 MVA
26 Sep 2026range 40–40 MVA26 Sep 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current40 MVA

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Load (any) · Available · 2026

current 12.5 MW

26 Sep 2026: 12.5 MW
26 Sep 2026range 12.5–12.5 MW26 Sep 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current12.5 MW

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Load (any) · Available · 2027

current 12.38 MW

26 Sep 2026: 12.38 MW
26 Sep 2026range 12.38–12.38 MW26 Sep 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current12.38 MW

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Load (any) · Available · 2028

current 12.13 MW

26 Sep 2026: 12.13 MW
26 Sep 2026range 12.13–12.13 MW26 Sep 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current12.13 MW

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Load (any) · Available · 2029

current 11.79 MW

26 Sep 2026: 11.79 MW
26 Sep 2026range 11.79–11.79 MW26 Sep 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current11.79 MW

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Load (any) · Available · 2030

current 11.27 MW

26 Sep 2026: 11.27 MW
26 Sep 2026range 11.27–11.27 MW26 Sep 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current11.27 MW

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Load (any) · Available · 2031

current 10.89 MW

26 Sep 2026: 10.89 MW
26 Sep 2026range 10.89–10.89 MW26 Sep 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current10.89 MW

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Load (any) · Available · 2032

current 10.63 MW

26 Sep 2026: 10.63 MW
26 Sep 2026range 10.63–10.63 MW26 Sep 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current10.63 MW

Time axis: when we observed each value, not the operator’s effective date.

The first 12 of 83 served series with a history. The history route returns every one of them.

Through the API

curl "https://api.gridcapacityapi.com/v1/substations/sub_06gdq6mq11vmvfekfqw5zd5xgg/capacity" \  -H "Authorization: Bearer gc_live_..."