GridCapacityAPI.com

Congestion zone · mv

OS OVERVEEN 10-1i

Liander · Noord-Holland, Netherlands

Latest published values

6 served · 0 withheld

Each row is what the operator’s latest published dataset reports for one combination of direction, technology, measure, firmness and horizon. Hosting-capacity figures are indicative and reflect what operators publish. They are not a connection offer; only the operator can confirm capacity for a specific request.

Latest published capacity values, one row per series
DirectionTechnologyMeasureValueFirmnessHorizonSource date
InjectionGeneration (any)Contracted5 MWFirmNow (snapshot)7 Sep 2026
InjectionGeneration (any)Total41 MWFirmNow (snapshot)7 Sep 2026
OfftakeLoad (any)Contracted31 MWFirmNow (snapshot)7 Sep 2026
OfftakeLoad (any)Total41 MWFirmNow (snapshot)7 Sep 2026
OfftakeLoad (any)Waitlisted1.34074 MWFirmNow (snapshot)7 Sep 2026
OfftakeLoad (any)Waitlisted14FirmNow (snapshot)variant: requests7 Sep 2026

gezamenlijke netbeheerders 2026 — de gezamenlijke regionale netbeheerders behouden hun intellectuele eigendomsrechten (zoals het databankenrecht) (last updated 2026-09-07)

What each value means

Methodology, both clocks, provenance and rights

Injection · Generation (any) · Contracted

5 MW

Granted

The operator's latest published dataset reports 5 MW under methodology nl_nbnl_voedingsgebieden_v2.

Firmness
Firm
Horizon
Now (snapshot)
Methodology
nl_nbnl_voedingsgebieden_v2Capaciteitskaart: DSO transport capacity, contracted peak need and queue per supply areabasis operator published · network state unknown · comparability class nl_capaciteitskaart_rnb_mvNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: no
Operator’s date
7 Sep 2026
Retrieved / confirmed
2026-09-26 02:49 UTClast confirmed unchanged 2026-09-26 08:57 UTC
Source health
Healthy
Provenance
nl_nbnl_voedingsgebiedenrecord OS OVERVEEN 10-1i · payload sha256 f5992e714ddb…Operator’s publication (opens the operator’s site)
Licence
Energie Dataportaal — Algemene gebruiksvoorwaarden (Open omgeving)Attribution: gezamenlijke netbeheerders 2026 — de gezamenlijke regionale netbeheerders behouden hun intellectuele eigendomsrechten (zoals het databankenrecht) (last updated 2026-09-07)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: jaar
2026

Injection · Generation (any) · Total

41 MW

Granted

The operator's latest published dataset reports 41 MW under methodology nl_nbnl_voedingsgebieden_v2.

Firmness
Firm
Horizon
Now (snapshot)
Methodology
nl_nbnl_voedingsgebieden_v2Capaciteitskaart: DSO transport capacity, contracted peak need and queue per supply areabasis operator published · network state unknown · comparability class nl_capaciteitskaart_rnb_mvNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: no
Operator’s date
7 Sep 2026
Retrieved / confirmed
2026-09-26 02:49 UTClast confirmed unchanged 2026-09-26 08:57 UTC
Source health
Healthy
Provenance
nl_nbnl_voedingsgebiedenrecord OS OVERVEEN 10-1i · payload sha256 f5992e714ddb…Operator’s publication (opens the operator’s site)
Licence
Energie Dataportaal — Algemene gebruiksvoorwaarden (Open omgeving)Attribution: gezamenlijke netbeheerders 2026 — de gezamenlijke regionale netbeheerders behouden hun intellectuele eigendomsrechten (zoals het databankenrecht) (last updated 2026-09-07)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: jaar
2026

Offtake · Load (any) · Contracted

31 MW

Granted

The operator's latest published dataset reports 31 MW under methodology nl_nbnl_voedingsgebieden_v2.

Firmness
Firm
Horizon
Now (snapshot)
Methodology
nl_nbnl_voedingsgebieden_v2Capaciteitskaart: DSO transport capacity, contracted peak need and queue per supply areabasis operator published · network state unknown · comparability class nl_capaciteitskaart_rnb_mvNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: no
Operator’s date
7 Sep 2026
Retrieved / confirmed
2026-09-26 02:49 UTClast confirmed unchanged 2026-09-26 08:57 UTC
Source health
Healthy
Provenance
nl_nbnl_voedingsgebiedenrecord OS OVERVEEN 10-1i · payload sha256 f5992e714ddb…Operator’s publication (opens the operator’s site)
Licence
Energie Dataportaal — Algemene gebruiksvoorwaarden (Open omgeving)Attribution: gezamenlijke netbeheerders 2026 — de gezamenlijke regionale netbeheerders behouden hun intellectuele eigendomsrechten (zoals het databankenrecht) (last updated 2026-09-07)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: jaar
2026

Offtake · Load (any) · Total

41 MW

Granted

The operator's latest published dataset reports 41 MW under methodology nl_nbnl_voedingsgebieden_v2.

Firmness
Firm
Horizon
Now (snapshot)
Methodology
nl_nbnl_voedingsgebieden_v2Capaciteitskaart: DSO transport capacity, contracted peak need and queue per supply areabasis operator published · network state unknown · comparability class nl_capaciteitskaart_rnb_mvNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: no
Operator’s date
7 Sep 2026
Retrieved / confirmed
2026-09-26 02:49 UTClast confirmed unchanged 2026-09-26 08:57 UTC
Source health
Healthy
Provenance
nl_nbnl_voedingsgebiedenrecord OS OVERVEEN 10-1i · payload sha256 f5992e714ddb…Operator’s publication (opens the operator’s site)
Licence
Energie Dataportaal — Algemene gebruiksvoorwaarden (Open omgeving)Attribution: gezamenlijke netbeheerders 2026 — de gezamenlijke regionale netbeheerders behouden hun intellectuele eigendomsrechten (zoals het databankenrecht) (last updated 2026-09-07)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: jaar
2026

Offtake · Load (any) · Waitlisted

1.34074 MW

Granted

The operator's latest published dataset reports 1.34074 MW under methodology nl_nbnl_voedingsgebieden_v2.

Firmness
Firm
Horizon
Now (snapshot)
Methodology
nl_nbnl_voedingsgebieden_v2Capaciteitskaart: DSO transport capacity, contracted peak need and queue per supply areabasis operator published · network state unknown · comparability class nl_capaciteitskaart_rnb_mvNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: no
Operator’s date
7 Sep 2026
Retrieved / confirmed
2026-09-26 02:49 UTClast confirmed unchanged 2026-09-26 08:57 UTC
Source health
Healthy
Provenance
nl_nbnl_voedingsgebiedenrecord OS OVERVEEN 10-1i · payload sha256 f5992e714ddb…Operator’s publication (opens the operator’s site)
Licence
Energie Dataportaal — Algemene gebruiksvoorwaarden (Open omgeving)Attribution: gezamenlijke netbeheerders 2026 — de gezamenlijke regionale netbeheerders behouden hun intellectuele eigendomsrechten (zoals het databankenrecht) (last updated 2026-09-07)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: jaar
2026

Offtake · Load (any) · Waitlisted

14

Published in count; no MW figure is derived from it.

Granted

The operator's latest published dataset reports 14 count under methodology nl_nbnl_voedingsgebieden_v2.

Firmness
Firm
Horizon
Now (snapshot) · variant: requests
Methodology
nl_nbnl_voedingsgebieden_v2Capaciteitskaart: DSO transport capacity, contracted peak need and queue per supply areabasis operator published · network state unknown · comparability class nl_capaciteitskaart_rnb_mvNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: no
Operator’s date
7 Sep 2026
Retrieved / confirmed
2026-09-26 02:49 UTClast confirmed unchanged 2026-09-26 08:57 UTC
Source health
Healthy
Provenance
nl_nbnl_voedingsgebiedenrecord OS OVERVEEN 10-1i · payload sha256 f5992e714ddb…Operator’s publication (opens the operator’s site)
Licence
Energie Dataportaal — Algemene gebruiksvoorwaarden (Open omgeving)Attribution: gezamenlijke netbeheerders 2026 — de gezamenlijke regionale netbeheerders behouden hun intellectuele eigendomsrechten (zoals het databankenrecht) (last updated 2026-09-07)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: jaar
2026
Operator note: variant
requests

History

Served series only

Offtake · Load (any) · Total

current 41 MW

26 Sep 2026: 41 MW
26 Sep 2026range 41–41 MW26 Sep 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current41 MW

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Load (any) · Contracted

current 31 MW

26 Sep 2026: 31 MW
26 Sep 2026range 31–31 MW26 Sep 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current31 MW

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Load (any) · Waitlisted

current 1.34074 MW

26 Sep 2026: 1.34074 MW
26 Sep 2026range 1.34074–1.34074 MW26 Sep 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current1.34074 MW

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Load (any) · Waitlisted

current 14

26 Sep 2026: 14
26 Sep 2026range 14–1426 Sep 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current14

Time axis: when we observed each value, not the operator’s effective date.

Injection · Generation (any) · Total

current 41 MW

26 Sep 2026: 41 MW
26 Sep 2026range 41–41 MW26 Sep 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current41 MW

Time axis: when we observed each value, not the operator’s effective date.

Injection · Generation (any) · Contracted

current 5 MW

26 Sep 2026: 5 MW
26 Sep 2026range 5–5 MW26 Sep 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current5 MW

Time axis: when we observed each value, not the operator’s effective date.

Through the API

curl "https://api.gridcapacityapi.com/v1/grid-assets/zone_06gdq77485rq7ez6hkq3j5nt88/capacity" \  -H "Authorization: Bearer gc_live_..."
OS OVERVEEN 10-1i congestion zone: grid capacity (Liander) · GridCapacity API