Congestion zone · mv

OS HARDERWIJK 10-2i

Liander · Gelderland, Netherlands

Latest published values

8 served · 0 withheld

Each row is what the operator’s latest published dataset reports for one combination of direction, technology, measure, firmness and horizon. Hosting-capacity figures are indicative and reflect what operators publish. They are not a connection offer; only the operator can confirm capacity for a specific request.

Latest published capacity values, one row per series
DirectionTechnologyMeasureValueFirmnessHorizonSource date
InjectionGeneration (any)Contracted37 MWFirmNow (snapshot)7 Sep 2026
InjectionGeneration (any)Total97 MWFirmNow (snapshot)7 Sep 2026
InjectionGeneration (any)Waitlisted8.328 MWFirmNow (snapshot)7 Sep 2026
InjectionGeneration (any)Waitlisted38FirmNow (snapshot)variant: requests7 Sep 2026
OfftakeLoad (any)Contracted67 MWFirmNow (snapshot)7 Sep 2026
OfftakeLoad (any)Total73 MWFirmNow (snapshot)7 Sep 2026
OfftakeLoad (any)Waitlisted9.79177 MWFirmNow (snapshot)7 Sep 2026
OfftakeLoad (any)Waitlisted56FirmNow (snapshot)variant: requests7 Sep 2026

gezamenlijke netbeheerders 2026 — de gezamenlijke regionale netbeheerders behouden hun intellectuele eigendomsrechten (zoals het databankenrecht) (last updated 2026-09-07)

What each value means

Methodology, both clocks, provenance and rights

Injection · Generation (any) · Contracted

37 MW

Granted

The operator's latest published dataset reports 37 MW under methodology nl_nbnl_voedingsgebieden_v2.

Firmness
Firm
Horizon
Now (snapshot)
Methodology
nl_nbnl_voedingsgebieden_v2Capaciteitskaart: DSO transport capacity, contracted peak need and queue per supply areabasis operator published · network state unknown · comparability class nl_capaciteitskaart_rnb_mvNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: no
Operator’s date
7 Sep 2026
Retrieved / confirmed
2026-09-26 02:49 UTClast confirmed unchanged 2026-09-26 08:57 UTC
Source health
Healthy
Provenance
nl_nbnl_voedingsgebiedenrecord OS HARDERWIJK 10-2i · payload sha256 e9d16ce9be92…Operator’s publication (opens the operator’s site)
Licence
Energie Dataportaal — Algemene gebruiksvoorwaarden (Open omgeving)Attribution: gezamenlijke netbeheerders 2026 — de gezamenlijke regionale netbeheerders behouden hun intellectuele eigendomsrechten (zoals het databankenrecht) (last updated 2026-09-07)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: jaar
2026

Injection · Generation (any) · Total

97 MW

Granted

The operator's latest published dataset reports 97 MW under methodology nl_nbnl_voedingsgebieden_v2.

Firmness
Firm
Horizon
Now (snapshot)
Methodology
nl_nbnl_voedingsgebieden_v2Capaciteitskaart: DSO transport capacity, contracted peak need and queue per supply areabasis operator published · network state unknown · comparability class nl_capaciteitskaart_rnb_mvNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: no
Operator’s date
7 Sep 2026
Retrieved / confirmed
2026-09-26 02:49 UTClast confirmed unchanged 2026-09-26 08:57 UTC
Source health
Healthy
Provenance
nl_nbnl_voedingsgebiedenrecord OS HARDERWIJK 10-2i · payload sha256 e9d16ce9be92…Operator’s publication (opens the operator’s site)
Licence
Energie Dataportaal — Algemene gebruiksvoorwaarden (Open omgeving)Attribution: gezamenlijke netbeheerders 2026 — de gezamenlijke regionale netbeheerders behouden hun intellectuele eigendomsrechten (zoals het databankenrecht) (last updated 2026-09-07)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: jaar
2026

Injection · Generation (any) · Waitlisted

8.328 MW

Granted

The operator's latest published dataset reports 8.328 MW under methodology nl_nbnl_voedingsgebieden_v2.

Firmness
Firm
Horizon
Now (snapshot)
Methodology
nl_nbnl_voedingsgebieden_v2Capaciteitskaart: DSO transport capacity, contracted peak need and queue per supply areabasis operator published · network state unknown · comparability class nl_capaciteitskaart_rnb_mvNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: no
Operator’s date
7 Sep 2026
Retrieved / confirmed
2026-09-26 02:49 UTClast confirmed unchanged 2026-09-26 08:57 UTC
Source health
Healthy
Provenance
nl_nbnl_voedingsgebiedenrecord OS HARDERWIJK 10-2i · payload sha256 e9d16ce9be92…Operator’s publication (opens the operator’s site)
Licence
Energie Dataportaal — Algemene gebruiksvoorwaarden (Open omgeving)Attribution: gezamenlijke netbeheerders 2026 — de gezamenlijke regionale netbeheerders behouden hun intellectuele eigendomsrechten (zoals het databankenrecht) (last updated 2026-09-07)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: jaar
2026

Injection · Generation (any) · Waitlisted

38

Published in count; no MW figure is derived from it.

Granted

The operator's latest published dataset reports 38 count under methodology nl_nbnl_voedingsgebieden_v2.

Firmness
Firm
Horizon
Now (snapshot) · variant: requests
Methodology
nl_nbnl_voedingsgebieden_v2Capaciteitskaart: DSO transport capacity, contracted peak need and queue per supply areabasis operator published · network state unknown · comparability class nl_capaciteitskaart_rnb_mvNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: no
Operator’s date
7 Sep 2026
Retrieved / confirmed
2026-09-26 02:49 UTClast confirmed unchanged 2026-09-26 08:57 UTC
Source health
Healthy
Provenance
nl_nbnl_voedingsgebiedenrecord OS HARDERWIJK 10-2i · payload sha256 e9d16ce9be92…Operator’s publication (opens the operator’s site)
Licence
Energie Dataportaal — Algemene gebruiksvoorwaarden (Open omgeving)Attribution: gezamenlijke netbeheerders 2026 — de gezamenlijke regionale netbeheerders behouden hun intellectuele eigendomsrechten (zoals het databankenrecht) (last updated 2026-09-07)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: jaar
2026
Operator note: variant
requests

Offtake · Load (any) · Contracted

67 MW

Granted

The operator's latest published dataset reports 67 MW under methodology nl_nbnl_voedingsgebieden_v2.

Firmness
Firm
Horizon
Now (snapshot)
Methodology
nl_nbnl_voedingsgebieden_v2Capaciteitskaart: DSO transport capacity, contracted peak need and queue per supply areabasis operator published · network state unknown · comparability class nl_capaciteitskaart_rnb_mvNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: no
Operator’s date
7 Sep 2026
Retrieved / confirmed
2026-09-26 02:49 UTClast confirmed unchanged 2026-09-26 08:57 UTC
Source health
Healthy
Provenance
nl_nbnl_voedingsgebiedenrecord OS HARDERWIJK 10-2i · payload sha256 e9d16ce9be92…Operator’s publication (opens the operator’s site)
Licence
Energie Dataportaal — Algemene gebruiksvoorwaarden (Open omgeving)Attribution: gezamenlijke netbeheerders 2026 — de gezamenlijke regionale netbeheerders behouden hun intellectuele eigendomsrechten (zoals het databankenrecht) (last updated 2026-09-07)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: jaar
2026

Offtake · Load (any) · Total

73 MW

Granted

The operator's latest published dataset reports 73 MW under methodology nl_nbnl_voedingsgebieden_v2.

Firmness
Firm
Horizon
Now (snapshot)
Methodology
nl_nbnl_voedingsgebieden_v2Capaciteitskaart: DSO transport capacity, contracted peak need and queue per supply areabasis operator published · network state unknown · comparability class nl_capaciteitskaart_rnb_mvNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: no
Operator’s date
7 Sep 2026
Retrieved / confirmed
2026-09-26 02:49 UTClast confirmed unchanged 2026-09-26 08:57 UTC
Source health
Healthy
Provenance
nl_nbnl_voedingsgebiedenrecord OS HARDERWIJK 10-2i · payload sha256 e9d16ce9be92…Operator’s publication (opens the operator’s site)
Licence
Energie Dataportaal — Algemene gebruiksvoorwaarden (Open omgeving)Attribution: gezamenlijke netbeheerders 2026 — de gezamenlijke regionale netbeheerders behouden hun intellectuele eigendomsrechten (zoals het databankenrecht) (last updated 2026-09-07)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: jaar
2026

Offtake · Load (any) · Waitlisted

9.79177 MW

Granted

The operator's latest published dataset reports 9.79177 MW under methodology nl_nbnl_voedingsgebieden_v2.

Firmness
Firm
Horizon
Now (snapshot)
Methodology
nl_nbnl_voedingsgebieden_v2Capaciteitskaart: DSO transport capacity, contracted peak need and queue per supply areabasis operator published · network state unknown · comparability class nl_capaciteitskaart_rnb_mvNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: no
Operator’s date
7 Sep 2026
Retrieved / confirmed
2026-09-26 02:49 UTClast confirmed unchanged 2026-09-26 08:57 UTC
Source health
Healthy
Provenance
nl_nbnl_voedingsgebiedenrecord OS HARDERWIJK 10-2i · payload sha256 e9d16ce9be92…Operator’s publication (opens the operator’s site)
Licence
Energie Dataportaal — Algemene gebruiksvoorwaarden (Open omgeving)Attribution: gezamenlijke netbeheerders 2026 — de gezamenlijke regionale netbeheerders behouden hun intellectuele eigendomsrechten (zoals het databankenrecht) (last updated 2026-09-07)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: jaar
2026

Offtake · Load (any) · Waitlisted

56

Published in count; no MW figure is derived from it.

Granted

The operator's latest published dataset reports 56 count under methodology nl_nbnl_voedingsgebieden_v2.

Firmness
Firm
Horizon
Now (snapshot) · variant: requests
Methodology
nl_nbnl_voedingsgebieden_v2Capaciteitskaart: DSO transport capacity, contracted peak need and queue per supply areabasis operator published · network state unknown · comparability class nl_capaciteitskaart_rnb_mvNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: no
Operator’s date
7 Sep 2026
Retrieved / confirmed
2026-09-26 02:49 UTClast confirmed unchanged 2026-09-26 08:57 UTC
Source health
Healthy
Provenance
nl_nbnl_voedingsgebiedenrecord OS HARDERWIJK 10-2i · payload sha256 e9d16ce9be92…Operator’s publication (opens the operator’s site)
Licence
Energie Dataportaal — Algemene gebruiksvoorwaarden (Open omgeving)Attribution: gezamenlijke netbeheerders 2026 — de gezamenlijke regionale netbeheerders behouden hun intellectuele eigendomsrechten (zoals het databankenrecht) (last updated 2026-09-07)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: jaar
2026
Operator note: variant
requests

History

Served series only

Offtake · Load (any) · Total

current 73 MW

26 Sep 2026: 73 MW
26 Sep 2026range 73–73 MW26 Sep 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current73 MW

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Load (any) · Contracted

current 67 MW

26 Sep 2026: 67 MW
26 Sep 2026range 67–67 MW26 Sep 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current67 MW

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Load (any) · Waitlisted

current 9.79177 MW

26 Sep 2026: 9.79177 MW
26 Sep 2026range 9.79177–9.79177 MW26 Sep 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current9.79177 MW

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Load (any) · Waitlisted

current 56

26 Sep 2026: 56
26 Sep 2026range 56–5626 Sep 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current56

Time axis: when we observed each value, not the operator’s effective date.

Injection · Generation (any) · Total

current 97 MW

26 Sep 2026: 97 MW
26 Sep 2026range 97–97 MW26 Sep 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current97 MW

Time axis: when we observed each value, not the operator’s effective date.

Injection · Generation (any) · Contracted

current 37 MW

26 Sep 2026: 37 MW
26 Sep 2026range 37–37 MW26 Sep 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current37 MW

Time axis: when we observed each value, not the operator’s effective date.

Injection · Generation (any) · Waitlisted

current 8.328 MW

26 Sep 2026: 8.328 MW
26 Sep 2026range 8.328–8.328 MW26 Sep 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current8.328 MW

Time axis: when we observed each value, not the operator’s effective date.

Injection · Generation (any) · Waitlisted

current 38

26 Sep 2026: 38
26 Sep 2026range 38–3826 Sep 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current38

Time axis: when we observed each value, not the operator’s effective date.

Through the API

curl "https://api.gridcapacityapi.com/v1/grid-assets/zone_06gdq7744hrnzb70ppx078vbem/capacity" \  -H "Authorization: Bearer gc_live_..."
OS HARDERWIJK 10-2i congestion zone: grid capacity (Liander) · GridCapacity API