Latest published values

8 served · 0 withheld

Each row is what the operator’s latest published dataset reports for one combination of direction, technology, measure, firmness and horizon. Hosting-capacity figures are indicative and reflect what operators publish. They are not a connection offer; only the operator can confirm capacity for a specific request.

Latest published capacity values, one row per series
DirectionTechnologyMeasureValueFirmnessHorizonSource date
InjectionGeneration (any)Contracted49.44953 MWFirmNow (snapshot)7 Sep 2026
InjectionGeneration (any)Total123.49 MWFirmNow (snapshot)7 Sep 2026
InjectionGeneration (any)Waitlisted25.45 MWFirmNow (snapshot)7 Sep 2026
InjectionGeneration (any)Waitlisted50FirmNow (snapshot)variant: requests7 Sep 2026
OfftakeLoad (any)Contracted83.661896 MWFirmNow (snapshot)7 Sep 2026
OfftakeLoad (any)Total123.49 MWFirmNow (snapshot)7 Sep 2026
OfftakeLoad (any)Waitlisted38.953 MWFirmNow (snapshot)7 Sep 2026
OfftakeLoad (any)Waitlisted49FirmNow (snapshot)variant: requests7 Sep 2026

gezamenlijke netbeheerders 2026 — de gezamenlijke regionale netbeheerders behouden hun intellectuele eigendomsrechten (zoals het databankenrecht) (last updated 2026-09-07)

What each value means

Methodology, both clocks, provenance and rights

Injection · Generation (any) · Contracted

49.44953 MW

Granted

The operator's latest published dataset reports 49.4495302689693 MW under methodology nl_nbnl_voedingsgebieden_v2.

Firmness
Firm
Horizon
Now (snapshot)
Methodology
nl_nbnl_voedingsgebieden_v2Capaciteitskaart: DSO transport capacity, contracted peak need and queue per supply areabasis operator published · network state unknown · comparability class nl_capaciteitskaart_rnb_mvNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: no
Operator’s date
7 Sep 2026
Retrieved / confirmed
2026-09-26 02:49 UTClast confirmed unchanged 2026-09-26 08:57 UTC
Source health
Healthy
Provenance
nl_nbnl_voedingsgebiedenrecord KWD · payload sha256 1e2ad34c7875…Operator’s publication (opens the operator’s site)
Licence
Energie Dataportaal — Algemene gebruiksvoorwaarden (Open omgeving)Attribution: gezamenlijke netbeheerders 2026 — de gezamenlijke regionale netbeheerders behouden hun intellectuele eigendomsrechten (zoals het databankenrecht) (last updated 2026-09-07)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: jaar
2026
Operator note: jaartal opgelost
2026

Injection · Generation (any) · Total

123.49 MW

Granted

The operator's latest published dataset reports 123.49 MW under methodology nl_nbnl_voedingsgebieden_v2.

Firmness
Firm
Horizon
Now (snapshot)
Methodology
nl_nbnl_voedingsgebieden_v2Capaciteitskaart: DSO transport capacity, contracted peak need and queue per supply areabasis operator published · network state unknown · comparability class nl_capaciteitskaart_rnb_mvNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: no
Operator’s date
7 Sep 2026
Retrieved / confirmed
2026-09-26 02:49 UTClast confirmed unchanged 2026-09-26 08:57 UTC
Source health
Healthy
Provenance
nl_nbnl_voedingsgebiedenrecord KWD · payload sha256 1e2ad34c7875…Operator’s publication (opens the operator’s site)
Licence
Energie Dataportaal — Algemene gebruiksvoorwaarden (Open omgeving)Attribution: gezamenlijke netbeheerders 2026 — de gezamenlijke regionale netbeheerders behouden hun intellectuele eigendomsrechten (zoals het databankenrecht) (last updated 2026-09-07)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: jaar
2026
Operator note: jaartal opgelost
2026

Injection · Generation (any) · Waitlisted

25.45 MW

Granted

The operator's latest published dataset reports 25.45 MW under methodology nl_nbnl_voedingsgebieden_v2.

Firmness
Firm
Horizon
Now (snapshot)
Methodology
nl_nbnl_voedingsgebieden_v2Capaciteitskaart: DSO transport capacity, contracted peak need and queue per supply areabasis operator published · network state unknown · comparability class nl_capaciteitskaart_rnb_mvNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: no
Operator’s date
7 Sep 2026
Retrieved / confirmed
2026-09-26 02:49 UTClast confirmed unchanged 2026-09-26 08:57 UTC
Source health
Healthy
Provenance
nl_nbnl_voedingsgebiedenrecord KWD · payload sha256 1e2ad34c7875…Operator’s publication (opens the operator’s site)
Licence
Energie Dataportaal — Algemene gebruiksvoorwaarden (Open omgeving)Attribution: gezamenlijke netbeheerders 2026 — de gezamenlijke regionale netbeheerders behouden hun intellectuele eigendomsrechten (zoals het databankenrecht) (last updated 2026-09-07)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: jaar
2026
Operator note: jaartal opgelost
2026

Injection · Generation (any) · Waitlisted

50

Published in count; no MW figure is derived from it.

Granted

The operator's latest published dataset reports 50 count under methodology nl_nbnl_voedingsgebieden_v2.

Firmness
Firm
Horizon
Now (snapshot) · variant: requests
Methodology
nl_nbnl_voedingsgebieden_v2Capaciteitskaart: DSO transport capacity, contracted peak need and queue per supply areabasis operator published · network state unknown · comparability class nl_capaciteitskaart_rnb_mvNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: no
Operator’s date
7 Sep 2026
Retrieved / confirmed
2026-09-26 02:49 UTClast confirmed unchanged 2026-09-26 08:57 UTC
Source health
Healthy
Provenance
nl_nbnl_voedingsgebiedenrecord KWD · payload sha256 1e2ad34c7875…Operator’s publication (opens the operator’s site)
Licence
Energie Dataportaal — Algemene gebruiksvoorwaarden (Open omgeving)Attribution: gezamenlijke netbeheerders 2026 — de gezamenlijke regionale netbeheerders behouden hun intellectuele eigendomsrechten (zoals het databankenrecht) (last updated 2026-09-07)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: jaar
2026
Operator note: jaartal opgelost
2026
Operator note: variant
requests

Offtake · Load (any) · Contracted

83.661896 MW

Granted

The operator's latest published dataset reports 83.661896467316 MW under methodology nl_nbnl_voedingsgebieden_v2.

Firmness
Firm
Horizon
Now (snapshot)
Methodology
nl_nbnl_voedingsgebieden_v2Capaciteitskaart: DSO transport capacity, contracted peak need and queue per supply areabasis operator published · network state unknown · comparability class nl_capaciteitskaart_rnb_mvNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: no
Operator’s date
7 Sep 2026
Retrieved / confirmed
2026-09-26 02:49 UTClast confirmed unchanged 2026-09-26 08:57 UTC
Source health
Healthy
Provenance
nl_nbnl_voedingsgebiedenrecord KWD · payload sha256 1e2ad34c7875…Operator’s publication (opens the operator’s site)
Licence
Energie Dataportaal — Algemene gebruiksvoorwaarden (Open omgeving)Attribution: gezamenlijke netbeheerders 2026 — de gezamenlijke regionale netbeheerders behouden hun intellectuele eigendomsrechten (zoals het databankenrecht) (last updated 2026-09-07)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: jaar
2026
Operator note: jaartal opgelost
2029

Offtake · Load (any) · Total

123.49 MW

Granted

The operator's latest published dataset reports 123.49 MW under methodology nl_nbnl_voedingsgebieden_v2.

Firmness
Firm
Horizon
Now (snapshot)
Methodology
nl_nbnl_voedingsgebieden_v2Capaciteitskaart: DSO transport capacity, contracted peak need and queue per supply areabasis operator published · network state unknown · comparability class nl_capaciteitskaart_rnb_mvNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: no
Operator’s date
7 Sep 2026
Retrieved / confirmed
2026-09-26 02:49 UTClast confirmed unchanged 2026-09-26 08:57 UTC
Source health
Healthy
Provenance
nl_nbnl_voedingsgebiedenrecord KWD · payload sha256 1e2ad34c7875…Operator’s publication (opens the operator’s site)
Licence
Energie Dataportaal — Algemene gebruiksvoorwaarden (Open omgeving)Attribution: gezamenlijke netbeheerders 2026 — de gezamenlijke regionale netbeheerders behouden hun intellectuele eigendomsrechten (zoals het databankenrecht) (last updated 2026-09-07)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: jaar
2026
Operator note: jaartal opgelost
2029

Offtake · Load (any) · Waitlisted

38.953 MW

Granted

The operator's latest published dataset reports 38.953 MW under methodology nl_nbnl_voedingsgebieden_v2.

Firmness
Firm
Horizon
Now (snapshot)
Methodology
nl_nbnl_voedingsgebieden_v2Capaciteitskaart: DSO transport capacity, contracted peak need and queue per supply areabasis operator published · network state unknown · comparability class nl_capaciteitskaart_rnb_mvNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: no
Operator’s date
7 Sep 2026
Retrieved / confirmed
2026-09-26 02:49 UTClast confirmed unchanged 2026-09-26 08:57 UTC
Source health
Healthy
Provenance
nl_nbnl_voedingsgebiedenrecord KWD · payload sha256 1e2ad34c7875…Operator’s publication (opens the operator’s site)
Licence
Energie Dataportaal — Algemene gebruiksvoorwaarden (Open omgeving)Attribution: gezamenlijke netbeheerders 2026 — de gezamenlijke regionale netbeheerders behouden hun intellectuele eigendomsrechten (zoals het databankenrecht) (last updated 2026-09-07)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: jaar
2026
Operator note: jaartal opgelost
2029

Offtake · Load (any) · Waitlisted

49

Published in count; no MW figure is derived from it.

Granted

The operator's latest published dataset reports 49 count under methodology nl_nbnl_voedingsgebieden_v2.

Firmness
Firm
Horizon
Now (snapshot) · variant: requests
Methodology
nl_nbnl_voedingsgebieden_v2Capaciteitskaart: DSO transport capacity, contracted peak need and queue per supply areabasis operator published · network state unknown · comparability class nl_capaciteitskaart_rnb_mvNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: no
Operator’s date
7 Sep 2026
Retrieved / confirmed
2026-09-26 02:49 UTClast confirmed unchanged 2026-09-26 08:57 UTC
Source health
Healthy
Provenance
nl_nbnl_voedingsgebiedenrecord KWD · payload sha256 1e2ad34c7875…Operator’s publication (opens the operator’s site)
Licence
Energie Dataportaal — Algemene gebruiksvoorwaarden (Open omgeving)Attribution: gezamenlijke netbeheerders 2026 — de gezamenlijke regionale netbeheerders behouden hun intellectuele eigendomsrechten (zoals het databankenrecht) (last updated 2026-09-07)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: jaar
2026
Operator note: jaartal opgelost
2029
Operator note: variant
requests

History

Served series only

Offtake · Load (any) · Total

current 123.49 MW

26 Sep 2026: 123.49 MW
26 Sep 2026range 123.49–123.49 MW26 Sep 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current123.49 MW

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Load (any) · Contracted

current 83.661896 MW

26 Sep 2026: 83.661896 MW
26 Sep 2026range 83.661896–83.661896 MW26 Sep 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current83.661896 MW

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Load (any) · Waitlisted

current 38.953 MW

26 Sep 2026: 38.953 MW
26 Sep 2026range 38.953–38.953 MW26 Sep 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current38.953 MW

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Load (any) · Waitlisted

current 49

26 Sep 2026: 49
26 Sep 2026range 49–4926 Sep 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current49

Time axis: when we observed each value, not the operator’s effective date.

Injection · Generation (any) · Total

current 123.49 MW

26 Sep 2026: 123.49 MW
26 Sep 2026range 123.49–123.49 MW26 Sep 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current123.49 MW

Time axis: when we observed each value, not the operator’s effective date.

Injection · Generation (any) · Contracted

current 49.44953 MW

26 Sep 2026: 49.44953 MW
26 Sep 2026range 49.44953–49.44953 MW26 Sep 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current49.44953 MW

Time axis: when we observed each value, not the operator’s effective date.

Injection · Generation (any) · Waitlisted

current 25.45 MW

26 Sep 2026: 25.45 MW
26 Sep 2026range 25.45–25.45 MW26 Sep 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current25.45 MW

Time axis: when we observed each value, not the operator’s effective date.

Injection · Generation (any) · Waitlisted

current 50

26 Sep 2026: 50
26 Sep 2026range 50–5026 Sep 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current50

Time axis: when we observed each value, not the operator’s effective date.

Through the API

curl "https://api.gridcapacityapi.com/v1/grid-assets/zone_06gdq77401rp7911t5xnje8vxc/capacity" \  -H "Authorization: Bearer gc_live_..."
KWD Kropswolde congestion zone: grid capacity (Enexis Netbeheer) · GridCapacity API