GridCapacityAPI.com

Congestion zone · mv

HUSK Huskensweg

Enexis Netbeheer · Limburg, Netherlands

Latest published values

8 served · 0 withheld

Each row is what the operator’s latest published dataset reports for one combination of direction, technology, measure, firmness and horizon. Hosting-capacity figures are indicative and reflect what operators publish. They are not a connection offer; only the operator can confirm capacity for a specific request.

Latest published capacity values, one row per series
DirectionTechnologyMeasureValueFirmnessHorizonSource date
InjectionGeneration (any)Contracted7.545358 MWFirmNow (snapshot)7 Sep 2026
InjectionGeneration (any)Total55.1 MWFirmNow (snapshot)7 Sep 2026
InjectionGeneration (any)Waitlisted5.039 MWFirmNow (snapshot)7 Sep 2026
InjectionGeneration (any)Waitlisted27FirmNow (snapshot)variant: requests7 Sep 2026
OfftakeLoad (any)Contracted43.339439 MWFirmNow (snapshot)7 Sep 2026
OfftakeLoad (any)Total66.12 MWFirmNow (snapshot)7 Sep 2026
OfftakeLoad (any)Waitlisted11.888 MWFirmNow (snapshot)7 Sep 2026
OfftakeLoad (any)Waitlisted50FirmNow (snapshot)variant: requests7 Sep 2026

gezamenlijke netbeheerders 2026 — de gezamenlijke regionale netbeheerders behouden hun intellectuele eigendomsrechten (zoals het databankenrecht) (last updated 2026-09-07)

What each value means

Methodology, both clocks, provenance and rights

Injection · Generation (any) · Contracted

7.545358 MW

Granted

The operator's latest published dataset reports 7.5453580978636 MW under methodology nl_nbnl_voedingsgebieden_v2.

Firmness
Firm
Horizon
Now (snapshot)
Methodology
nl_nbnl_voedingsgebieden_v2Capaciteitskaart: DSO transport capacity, contracted peak need and queue per supply areabasis operator published · network state unknown · comparability class nl_capaciteitskaart_rnb_mvNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: no
Operator’s date
7 Sep 2026
Retrieved / confirmed
2026-09-26 02:49 UTClast confirmed unchanged 2026-09-26 08:57 UTC
Source health
Healthy
Provenance
nl_nbnl_voedingsgebiedenrecord HUSK · payload sha256 2f8d525f28b5…Operator’s publication (opens the operator’s site)
Licence
Energie Dataportaal — Algemene gebruiksvoorwaarden (Open omgeving)Attribution: gezamenlijke netbeheerders 2026 — de gezamenlijke regionale netbeheerders behouden hun intellectuele eigendomsrechten (zoals het databankenrecht) (last updated 2026-09-07)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: jaar
2026
Operator note: jaartal opgelost
2026

Injection · Generation (any) · Total

55.1 MW

Granted

The operator's latest published dataset reports 55.1 MW under methodology nl_nbnl_voedingsgebieden_v2.

Firmness
Firm
Horizon
Now (snapshot)
Methodology
nl_nbnl_voedingsgebieden_v2Capaciteitskaart: DSO transport capacity, contracted peak need and queue per supply areabasis operator published · network state unknown · comparability class nl_capaciteitskaart_rnb_mvNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: no
Operator’s date
7 Sep 2026
Retrieved / confirmed
2026-09-26 02:49 UTClast confirmed unchanged 2026-09-26 08:57 UTC
Source health
Healthy
Provenance
nl_nbnl_voedingsgebiedenrecord HUSK · payload sha256 2f8d525f28b5…Operator’s publication (opens the operator’s site)
Licence
Energie Dataportaal — Algemene gebruiksvoorwaarden (Open omgeving)Attribution: gezamenlijke netbeheerders 2026 — de gezamenlijke regionale netbeheerders behouden hun intellectuele eigendomsrechten (zoals het databankenrecht) (last updated 2026-09-07)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: jaar
2026
Operator note: jaartal opgelost
2026

Injection · Generation (any) · Waitlisted

5.039 MW

Granted

The operator's latest published dataset reports 5.039 MW under methodology nl_nbnl_voedingsgebieden_v2.

Firmness
Firm
Horizon
Now (snapshot)
Methodology
nl_nbnl_voedingsgebieden_v2Capaciteitskaart: DSO transport capacity, contracted peak need and queue per supply areabasis operator published · network state unknown · comparability class nl_capaciteitskaart_rnb_mvNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: no
Operator’s date
7 Sep 2026
Retrieved / confirmed
2026-09-26 02:49 UTClast confirmed unchanged 2026-09-26 08:57 UTC
Source health
Healthy
Provenance
nl_nbnl_voedingsgebiedenrecord HUSK · payload sha256 2f8d525f28b5…Operator’s publication (opens the operator’s site)
Licence
Energie Dataportaal — Algemene gebruiksvoorwaarden (Open omgeving)Attribution: gezamenlijke netbeheerders 2026 — de gezamenlijke regionale netbeheerders behouden hun intellectuele eigendomsrechten (zoals het databankenrecht) (last updated 2026-09-07)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: jaar
2026
Operator note: jaartal opgelost
2026

Injection · Generation (any) · Waitlisted

27

Published in count; no MW figure is derived from it.

Granted

The operator's latest published dataset reports 27 count under methodology nl_nbnl_voedingsgebieden_v2.

Firmness
Firm
Horizon
Now (snapshot) · variant: requests
Methodology
nl_nbnl_voedingsgebieden_v2Capaciteitskaart: DSO transport capacity, contracted peak need and queue per supply areabasis operator published · network state unknown · comparability class nl_capaciteitskaart_rnb_mvNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: no
Operator’s date
7 Sep 2026
Retrieved / confirmed
2026-09-26 02:49 UTClast confirmed unchanged 2026-09-26 08:57 UTC
Source health
Healthy
Provenance
nl_nbnl_voedingsgebiedenrecord HUSK · payload sha256 2f8d525f28b5…Operator’s publication (opens the operator’s site)
Licence
Energie Dataportaal — Algemene gebruiksvoorwaarden (Open omgeving)Attribution: gezamenlijke netbeheerders 2026 — de gezamenlijke regionale netbeheerders behouden hun intellectuele eigendomsrechten (zoals het databankenrecht) (last updated 2026-09-07)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: jaar
2026
Operator note: jaartal opgelost
2026
Operator note: variant
requests

Offtake · Load (any) · Contracted

43.339439 MW

Granted

The operator's latest published dataset reports 43.33943946810361 MW under methodology nl_nbnl_voedingsgebieden_v2.

Firmness
Firm
Horizon
Now (snapshot)
Methodology
nl_nbnl_voedingsgebieden_v2Capaciteitskaart: DSO transport capacity, contracted peak need and queue per supply areabasis operator published · network state unknown · comparability class nl_capaciteitskaart_rnb_mvNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: no
Operator’s date
7 Sep 2026
Retrieved / confirmed
2026-09-26 02:49 UTClast confirmed unchanged 2026-09-26 08:57 UTC
Source health
Healthy
Provenance
nl_nbnl_voedingsgebiedenrecord HUSK · payload sha256 2f8d525f28b5…Operator’s publication (opens the operator’s site)
Licence
Energie Dataportaal — Algemene gebruiksvoorwaarden (Open omgeving)Attribution: gezamenlijke netbeheerders 2026 — de gezamenlijke regionale netbeheerders behouden hun intellectuele eigendomsrechten (zoals het databankenrecht) (last updated 2026-09-07)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: jaar
2026

Offtake · Load (any) · Total

66.12 MW

Granted

The operator's latest published dataset reports 66.12 MW under methodology nl_nbnl_voedingsgebieden_v2.

Firmness
Firm
Horizon
Now (snapshot)
Methodology
nl_nbnl_voedingsgebieden_v2Capaciteitskaart: DSO transport capacity, contracted peak need and queue per supply areabasis operator published · network state unknown · comparability class nl_capaciteitskaart_rnb_mvNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: no
Operator’s date
7 Sep 2026
Retrieved / confirmed
2026-09-26 02:49 UTClast confirmed unchanged 2026-09-26 08:57 UTC
Source health
Healthy
Provenance
nl_nbnl_voedingsgebiedenrecord HUSK · payload sha256 2f8d525f28b5…Operator’s publication (opens the operator’s site)
Licence
Energie Dataportaal — Algemene gebruiksvoorwaarden (Open omgeving)Attribution: gezamenlijke netbeheerders 2026 — de gezamenlijke regionale netbeheerders behouden hun intellectuele eigendomsrechten (zoals het databankenrecht) (last updated 2026-09-07)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: jaar
2026

Offtake · Load (any) · Waitlisted

11.888 MW

Granted

The operator's latest published dataset reports 11.888 MW under methodology nl_nbnl_voedingsgebieden_v2.

Firmness
Firm
Horizon
Now (snapshot)
Methodology
nl_nbnl_voedingsgebieden_v2Capaciteitskaart: DSO transport capacity, contracted peak need and queue per supply areabasis operator published · network state unknown · comparability class nl_capaciteitskaart_rnb_mvNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: no
Operator’s date
7 Sep 2026
Retrieved / confirmed
2026-09-26 02:49 UTClast confirmed unchanged 2026-09-26 08:57 UTC
Source health
Healthy
Provenance
nl_nbnl_voedingsgebiedenrecord HUSK · payload sha256 2f8d525f28b5…Operator’s publication (opens the operator’s site)
Licence
Energie Dataportaal — Algemene gebruiksvoorwaarden (Open omgeving)Attribution: gezamenlijke netbeheerders 2026 — de gezamenlijke regionale netbeheerders behouden hun intellectuele eigendomsrechten (zoals het databankenrecht) (last updated 2026-09-07)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: jaar
2026

Offtake · Load (any) · Waitlisted

50

Published in count; no MW figure is derived from it.

Granted

The operator's latest published dataset reports 50 count under methodology nl_nbnl_voedingsgebieden_v2.

Firmness
Firm
Horizon
Now (snapshot) · variant: requests
Methodology
nl_nbnl_voedingsgebieden_v2Capaciteitskaart: DSO transport capacity, contracted peak need and queue per supply areabasis operator published · network state unknown · comparability class nl_capaciteitskaart_rnb_mvNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: no
Operator’s date
7 Sep 2026
Retrieved / confirmed
2026-09-26 02:49 UTClast confirmed unchanged 2026-09-26 08:57 UTC
Source health
Healthy
Provenance
nl_nbnl_voedingsgebiedenrecord HUSK · payload sha256 2f8d525f28b5…Operator’s publication (opens the operator’s site)
Licence
Energie Dataportaal — Algemene gebruiksvoorwaarden (Open omgeving)Attribution: gezamenlijke netbeheerders 2026 — de gezamenlijke regionale netbeheerders behouden hun intellectuele eigendomsrechten (zoals het databankenrecht) (last updated 2026-09-07)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: jaar
2026
Operator note: variant
requests

History

Served series only

Offtake · Load (any) · Total

current 66.12 MW

26 Sep 2026: 66.12 MW
26 Sep 2026range 66.12–66.12 MW26 Sep 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current66.12 MW

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Load (any) · Contracted

current 43.339439 MW

26 Sep 2026: 43.339439 MW
26 Sep 2026range 43.339439–43.339439 MW26 Sep 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current43.339439 MW

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Load (any) · Waitlisted

current 11.888 MW

26 Sep 2026: 11.888 MW
26 Sep 2026range 11.888–11.888 MW26 Sep 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current11.888 MW

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Load (any) · Waitlisted

current 50

26 Sep 2026: 50
26 Sep 2026range 50–5026 Sep 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current50

Time axis: when we observed each value, not the operator’s effective date.

Injection · Generation (any) · Total

current 55.1 MW

26 Sep 2026: 55.1 MW
26 Sep 2026range 55.1–55.1 MW26 Sep 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current55.1 MW

Time axis: when we observed each value, not the operator’s effective date.

Injection · Generation (any) · Contracted

current 7.545358 MW

26 Sep 2026: 7.545358 MW
26 Sep 2026range 7.545358–7.545358 MW26 Sep 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current7.545358 MW

Time axis: when we observed each value, not the operator’s effective date.

Injection · Generation (any) · Waitlisted

current 5.039 MW

26 Sep 2026: 5.039 MW
26 Sep 2026range 5.039–5.039 MW26 Sep 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current5.039 MW

Time axis: when we observed each value, not the operator’s effective date.

Injection · Generation (any) · Waitlisted

current 27

26 Sep 2026: 27
26 Sep 2026range 27–2726 Sep 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current27

Time axis: when we observed each value, not the operator’s effective date.

Through the API

curl "https://api.gridcapacityapi.com/v1/grid-assets/zone_06gdq773zsvy9fba667zecvg8c/capacity" \  -H "Authorization: Bearer gc_live_..."
HUSK Huskensweg congestion zone: grid capacity (Enexis Netbeheer) · GridCapacity API