Congestion zone · mv

GLTK Gasselte Kraanlanden

Enexis Netbeheer · Drenthe, Netherlands

Latest published values

8 served · 0 withheld

Each row is what the operator’s latest published dataset reports for one combination of direction, technology, measure, firmness and horizon. Hosting-capacity figures are indicative and reflect what operators publish. They are not a connection offer; only the operator can confirm capacity for a specific request.

Latest published capacity values, one row per series
DirectionTechnologyMeasureValueFirmnessHorizonSource date
InjectionGeneration (any)Contracted99.383401 MWFirmNow (snapshot)7 Sep 2026
InjectionGeneration (any)Total113.16 MWFirmNow (snapshot)7 Sep 2026
InjectionGeneration (any)Waitlisted4.822 MWFirmNow (snapshot)7 Sep 2026
InjectionGeneration (any)Waitlisted22FirmNow (snapshot)variant: requests7 Sep 2026
OfftakeLoad (any)Contracted51.198188 MWFirmNow (snapshot)7 Sep 2026
OfftakeLoad (any)Total116.98 MWFirmNow (snapshot)7 Sep 2026
OfftakeLoad (any)Waitlisted2.303 MWFirmNow (snapshot)7 Sep 2026
OfftakeLoad (any)Waitlisted14FirmNow (snapshot)variant: requests7 Sep 2026

gezamenlijke netbeheerders 2026 — de gezamenlijke regionale netbeheerders behouden hun intellectuele eigendomsrechten (zoals het databankenrecht) (last updated 2026-09-07)

What each value means

Methodology, both clocks, provenance and rights

Injection · Generation (any) · Contracted

99.383401 MW

Granted

The operator's latest published dataset reports 99.38340149000001 MW under methodology nl_nbnl_voedingsgebieden_v2.

Firmness
Firm
Horizon
Now (snapshot)
Methodology
nl_nbnl_voedingsgebieden_v2Capaciteitskaart: DSO transport capacity, contracted peak need and queue per supply areabasis operator published · network state unknown · comparability class nl_capaciteitskaart_rnb_mvNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: no
Operator’s date
7 Sep 2026
Retrieved / confirmed
2026-09-26 02:49 UTClast confirmed unchanged 2026-09-26 08:57 UTC
Source health
Healthy
Provenance
nl_nbnl_voedingsgebiedenrecord GLTK · payload sha256 34e962bd747f…Operator’s publication (opens the operator’s site)
Licence
Energie Dataportaal — Algemene gebruiksvoorwaarden (Open omgeving)Attribution: gezamenlijke netbeheerders 2026 — de gezamenlijke regionale netbeheerders behouden hun intellectuele eigendomsrechten (zoals het databankenrecht) (last updated 2026-09-07)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: jaar
2026
Operator note: jaartal opgelost
2030

Injection · Generation (any) · Total

113.16 MW

Granted

The operator's latest published dataset reports 113.16 MW under methodology nl_nbnl_voedingsgebieden_v2.

Firmness
Firm
Horizon
Now (snapshot)
Methodology
nl_nbnl_voedingsgebieden_v2Capaciteitskaart: DSO transport capacity, contracted peak need and queue per supply areabasis operator published · network state unknown · comparability class nl_capaciteitskaart_rnb_mvNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: no
Operator’s date
7 Sep 2026
Retrieved / confirmed
2026-09-26 02:49 UTClast confirmed unchanged 2026-09-26 08:57 UTC
Source health
Healthy
Provenance
nl_nbnl_voedingsgebiedenrecord GLTK · payload sha256 34e962bd747f…Operator’s publication (opens the operator’s site)
Licence
Energie Dataportaal — Algemene gebruiksvoorwaarden (Open omgeving)Attribution: gezamenlijke netbeheerders 2026 — de gezamenlijke regionale netbeheerders behouden hun intellectuele eigendomsrechten (zoals het databankenrecht) (last updated 2026-09-07)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: jaar
2026
Operator note: jaartal opgelost
2030

Injection · Generation (any) · Waitlisted

4.822 MW

Granted

The operator's latest published dataset reports 4.822 MW under methodology nl_nbnl_voedingsgebieden_v2.

Firmness
Firm
Horizon
Now (snapshot)
Methodology
nl_nbnl_voedingsgebieden_v2Capaciteitskaart: DSO transport capacity, contracted peak need and queue per supply areabasis operator published · network state unknown · comparability class nl_capaciteitskaart_rnb_mvNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: no
Operator’s date
7 Sep 2026
Retrieved / confirmed
2026-09-26 02:49 UTClast confirmed unchanged 2026-09-26 08:57 UTC
Source health
Healthy
Provenance
nl_nbnl_voedingsgebiedenrecord GLTK · payload sha256 34e962bd747f…Operator’s publication (opens the operator’s site)
Licence
Energie Dataportaal — Algemene gebruiksvoorwaarden (Open omgeving)Attribution: gezamenlijke netbeheerders 2026 — de gezamenlijke regionale netbeheerders behouden hun intellectuele eigendomsrechten (zoals het databankenrecht) (last updated 2026-09-07)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: jaar
2026
Operator note: jaartal opgelost
2030

Injection · Generation (any) · Waitlisted

22

Published in count; no MW figure is derived from it.

Granted

The operator's latest published dataset reports 22 count under methodology nl_nbnl_voedingsgebieden_v2.

Firmness
Firm
Horizon
Now (snapshot) · variant: requests
Methodology
nl_nbnl_voedingsgebieden_v2Capaciteitskaart: DSO transport capacity, contracted peak need and queue per supply areabasis operator published · network state unknown · comparability class nl_capaciteitskaart_rnb_mvNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: no
Operator’s date
7 Sep 2026
Retrieved / confirmed
2026-09-26 02:49 UTClast confirmed unchanged 2026-09-26 08:57 UTC
Source health
Healthy
Provenance
nl_nbnl_voedingsgebiedenrecord GLTK · payload sha256 34e962bd747f…Operator’s publication (opens the operator’s site)
Licence
Energie Dataportaal — Algemene gebruiksvoorwaarden (Open omgeving)Attribution: gezamenlijke netbeheerders 2026 — de gezamenlijke regionale netbeheerders behouden hun intellectuele eigendomsrechten (zoals het databankenrecht) (last updated 2026-09-07)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: jaar
2026
Operator note: jaartal opgelost
2030
Operator note: variant
requests

Offtake · Load (any) · Contracted

51.198188 MW

Granted

The operator's latest published dataset reports 51.19818802598817 MW under methodology nl_nbnl_voedingsgebieden_v2.

Firmness
Firm
Horizon
Now (snapshot)
Methodology
nl_nbnl_voedingsgebieden_v2Capaciteitskaart: DSO transport capacity, contracted peak need and queue per supply areabasis operator published · network state unknown · comparability class nl_capaciteitskaart_rnb_mvNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: no
Operator’s date
7 Sep 2026
Retrieved / confirmed
2026-09-26 02:49 UTClast confirmed unchanged 2026-09-26 08:57 UTC
Source health
Healthy
Provenance
nl_nbnl_voedingsgebiedenrecord GLTK · payload sha256 34e962bd747f…Operator’s publication (opens the operator’s site)
Licence
Energie Dataportaal — Algemene gebruiksvoorwaarden (Open omgeving)Attribution: gezamenlijke netbeheerders 2026 — de gezamenlijke regionale netbeheerders behouden hun intellectuele eigendomsrechten (zoals het databankenrecht) (last updated 2026-09-07)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: jaar
2026
Operator note: jaartal opgelost
2026

Offtake · Load (any) · Total

116.98 MW

Granted

The operator's latest published dataset reports 116.98 MW under methodology nl_nbnl_voedingsgebieden_v2.

Firmness
Firm
Horizon
Now (snapshot)
Methodology
nl_nbnl_voedingsgebieden_v2Capaciteitskaart: DSO transport capacity, contracted peak need and queue per supply areabasis operator published · network state unknown · comparability class nl_capaciteitskaart_rnb_mvNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: no
Operator’s date
7 Sep 2026
Retrieved / confirmed
2026-09-26 02:49 UTClast confirmed unchanged 2026-09-26 08:57 UTC
Source health
Healthy
Provenance
nl_nbnl_voedingsgebiedenrecord GLTK · payload sha256 34e962bd747f…Operator’s publication (opens the operator’s site)
Licence
Energie Dataportaal — Algemene gebruiksvoorwaarden (Open omgeving)Attribution: gezamenlijke netbeheerders 2026 — de gezamenlijke regionale netbeheerders behouden hun intellectuele eigendomsrechten (zoals het databankenrecht) (last updated 2026-09-07)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: jaar
2026
Operator note: jaartal opgelost
2026

Offtake · Load (any) · Waitlisted

2.303 MW

Granted

The operator's latest published dataset reports 2.303 MW under methodology nl_nbnl_voedingsgebieden_v2.

Firmness
Firm
Horizon
Now (snapshot)
Methodology
nl_nbnl_voedingsgebieden_v2Capaciteitskaart: DSO transport capacity, contracted peak need and queue per supply areabasis operator published · network state unknown · comparability class nl_capaciteitskaart_rnb_mvNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: no
Operator’s date
7 Sep 2026
Retrieved / confirmed
2026-09-26 02:49 UTClast confirmed unchanged 2026-09-26 08:57 UTC
Source health
Healthy
Provenance
nl_nbnl_voedingsgebiedenrecord GLTK · payload sha256 34e962bd747f…Operator’s publication (opens the operator’s site)
Licence
Energie Dataportaal — Algemene gebruiksvoorwaarden (Open omgeving)Attribution: gezamenlijke netbeheerders 2026 — de gezamenlijke regionale netbeheerders behouden hun intellectuele eigendomsrechten (zoals het databankenrecht) (last updated 2026-09-07)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: jaar
2026
Operator note: jaartal opgelost
2026

Offtake · Load (any) · Waitlisted

14

Published in count; no MW figure is derived from it.

Granted

The operator's latest published dataset reports 14 count under methodology nl_nbnl_voedingsgebieden_v2.

Firmness
Firm
Horizon
Now (snapshot) · variant: requests
Methodology
nl_nbnl_voedingsgebieden_v2Capaciteitskaart: DSO transport capacity, contracted peak need and queue per supply areabasis operator published · network state unknown · comparability class nl_capaciteitskaart_rnb_mvNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: no
Operator’s date
7 Sep 2026
Retrieved / confirmed
2026-09-26 02:49 UTClast confirmed unchanged 2026-09-26 08:57 UTC
Source health
Healthy
Provenance
nl_nbnl_voedingsgebiedenrecord GLTK · payload sha256 34e962bd747f…Operator’s publication (opens the operator’s site)
Licence
Energie Dataportaal — Algemene gebruiksvoorwaarden (Open omgeving)Attribution: gezamenlijke netbeheerders 2026 — de gezamenlijke regionale netbeheerders behouden hun intellectuele eigendomsrechten (zoals het databankenrecht) (last updated 2026-09-07)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: jaar
2026
Operator note: jaartal opgelost
2026
Operator note: variant
requests

History

Served series only

Offtake · Load (any) · Total

current 116.98 MW

26 Sep 2026: 116.98 MW
26 Sep 2026range 116.98–116.98 MW26 Sep 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current116.98 MW

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Load (any) · Contracted

current 51.198188 MW

26 Sep 2026: 51.198188 MW
26 Sep 2026range 51.198188–51.198188 MW26 Sep 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current51.198188 MW

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Load (any) · Waitlisted

current 2.303 MW

26 Sep 2026: 2.303 MW
26 Sep 2026range 2.303–2.303 MW26 Sep 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current2.303 MW

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Load (any) · Waitlisted

current 14

26 Sep 2026: 14
26 Sep 2026range 14–1426 Sep 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current14

Time axis: when we observed each value, not the operator’s effective date.

Injection · Generation (any) · Total

current 113.16 MW

26 Sep 2026: 113.16 MW
26 Sep 2026range 113.16–113.16 MW26 Sep 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current113.16 MW

Time axis: when we observed each value, not the operator’s effective date.

Injection · Generation (any) · Contracted

current 99.383401 MW

26 Sep 2026: 99.383401 MW
26 Sep 2026range 99.383401–99.383401 MW26 Sep 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current99.383401 MW

Time axis: when we observed each value, not the operator’s effective date.

Injection · Generation (any) · Waitlisted

current 4.822 MW

26 Sep 2026: 4.822 MW
26 Sep 2026range 4.822–4.822 MW26 Sep 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current4.822 MW

Time axis: when we observed each value, not the operator’s effective date.

Injection · Generation (any) · Waitlisted

current 22

26 Sep 2026: 22
26 Sep 2026range 22–2226 Sep 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current22

Time axis: when we observed each value, not the operator’s effective date.

Through the API

curl "https://api.gridcapacityapi.com/v1/grid-assets/zone_06gdq773yntdk4sw2481c6n5y8/capacity" \  -H "Authorization: Bearer gc_live_..."
GLTK Gasselte Kraanlanden congestion zone: grid capacity (Enexis Netbeheer) · GridCapacity API