Substation · 33 kV · primary

Newhaven Grid 33kV

UK Power Networks · United Kingdom

Latest published values

10 served · 0 withheld

Each row is what the operator’s latest published dataset reports for one combination of direction, technology, measure, firmness and horizon. Hosting-capacity figures are indicative and reflect what operators publish. They are not a connection offer; only the operator can confirm capacity for a specific request.

Latest published capacity values, one row per series
DirectionTechnologyMeasureValueFirmnessHorizonSource date
InjectionGeneration (any)Available53 MVAFirmNow (snapshot)1 Mar 2025
InjectionGeneration (any)Available63.5 MVAUnknownNow (snapshot)variant: reverse_power_flow1 Mar 2025
InjectionGeneration (any)Requested4 MVAUnknownpast_connection_activityvariant: budget_estimates_provided1 Mar 2025
InjectionGeneration (any)Requested2Unknownpast_connection_activityvariant: budget_estimates_provided_count1 Mar 2025
InjectionGeneration (any)Total84 MVAFirmNow (snapshot)1 Mar 2025
InjectionGeneration (any)Total63.5 MVAFirmNow (snapshot)variant: reverse_power_flow1 Mar 2025
OfftakeLoad (any)Available28.7 MVAFirmNow (snapshot)1 Mar 2025
OfftakeLoad (any)Requested27.9 MVAUnknownpast_connection_activityvariant: budget_estimates_provided1 Mar 2025
OfftakeLoad (any)Requested2Unknownpast_connection_activityvariant: budget_estimates_provided_count1 Mar 2025
OfftakeLoad (any)Total63.5 MVAFirmNow (snapshot)1 Mar 2025

UK Power Networks, Long Term Development Statement (LTDS) Capacity Heatmap, https://ukpowernetworks.opendatasoft.com/explore/dataset/ukpn-capacity-heatmap/ (last updated 2025-03-01)

What each value means

Methodology, both clocks, provenance and rights

Injection · Generation (any) · Available

53 MVA

Published in MVA; no MW figure is derived from it.

Granted

The operator's latest published dataset reports 53 MVA under methodology gb_ukpn_ltds_heatmap_2026.

Firmness
Firm
Horizon
Now (snapshot)
Methodology
gb_ukpn_ltds_heatmap_2026UKPN LTDS Capacity Heatmap: headroom from the Network Scenario Headroom Reportbasis operator calculated · network state n minus 1 · comparability class gb_ukpn_ltds_heatmapNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Mar 2025
Retrieved / confirmed
2026-09-26 02:47 UTClast confirmed unchanged 2026-09-26 02:47 UTC
Source health
Healthy
Provenance
gb_ukpn_ltds_heatmaprecord 8f4834e6-f8e2-53c0-ac37-10fa5180d157 · payload sha256 cdc3da01dc9c…Operator’s publication (opens the operator’s site)
Licence
CC BY 4.0Attribution: UK Power Networks, Long Term Development Statement (LTDS) Capacity Heatmap, https://ukpowernetworks.opendatasoft.com/explore/dataset/ukpn-capacity-heatmap/ (last updated 2025-03-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: limiting factor
Thermal
Operator note: rag
GREEN
Operator note: rag colour
green
Operator note: source field
generationAvailableCapacity

Injection · Generation (any) · Available

63.5 MVA

Published in MVA; no MW figure is derived from it.

Granted

The operator's latest published dataset reports 63.5 MVA under methodology gb_ukpn_ltds_heatmap_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: reverse_power_flow
Methodology
gb_ukpn_ltds_heatmap_2026UKPN LTDS Capacity Heatmap: headroom from the Network Scenario Headroom Reportbasis operator calculated · network state n minus 1 · comparability class gb_ukpn_ltds_heatmapNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Mar 2025
Retrieved / confirmed
2026-09-26 02:47 UTClast confirmed unchanged 2026-09-26 02:47 UTC
Source health
Healthy
Provenance
gb_ukpn_ltds_heatmaprecord 8f4834e6-f8e2-53c0-ac37-10fa5180d157 · payload sha256 cdc3da01dc9c…Operator’s publication (opens the operator’s site)
Licence
CC BY 4.0Attribution: UK Power Networks, Long Term Development Statement (LTDS) Capacity Heatmap, https://ukpowernetworks.opendatasoft.com/explore/dataset/ukpn-capacity-heatmap/ (last updated 2025-03-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: equals published total
reversePowerFlowTotalCapacity
Operator note: source field
reversePowerFlowAvailableCapacity

Injection · Generation (any) · Requested

4 MVA

Published in MVA; no MW figure is derived from it.

Granted

The operator's latest published dataset reports 4 MVA under methodology gb_ukpn_ltds_heatmap_activity_2026.

Firmness
Unknown
Horizon
past_connection_activity · variant: budget_estimates_provided
Methodology
gb_ukpn_ltds_heatmap_activity_2026UKPN past connection activity (LTDS Capacity Heatmap)basis operator published · network state unknown · comparability class gb_ukpn_connection_activityNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Mar 2025
Retrieved / confirmed
2026-09-26 02:47 UTClast confirmed unchanged 2026-09-26 02:47 UTC
Source health
Healthy
Provenance
gb_ukpn_ltds_heatmaprecord 8f4834e6-f8e2-53c0-ac37-10fa5180d157/PastConnectionActivity/33kV · payload sha256 01bda17fd8c3…Operator’s publication (opens the operator’s site)
Licence
CC BY 4.0Attribution: UK Power Networks, Long Term Development Statement (LTDS) Capacity Heatmap, https://ukpowernetworks.opendatasoft.com/explore/dataset/ukpn-capacity-heatmap/ (last updated 2025-03-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: connection voltage kv
33
Operator note: source field
generationBudgetEstimatesProvidedCapacity

Injection · Generation (any) · Requested

2

Published in count; no MW figure is derived from it.

Granted

The operator's latest published dataset reports 2 count under methodology gb_ukpn_ltds_heatmap_activity_2026.

Firmness
Unknown
Horizon
past_connection_activity · variant: budget_estimates_provided_count
Methodology
gb_ukpn_ltds_heatmap_activity_2026UKPN past connection activity (LTDS Capacity Heatmap)basis operator published · network state unknown · comparability class gb_ukpn_connection_activityNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Mar 2025
Retrieved / confirmed
2026-09-26 02:47 UTClast confirmed unchanged 2026-09-26 02:47 UTC
Source health
Healthy
Provenance
gb_ukpn_ltds_heatmaprecord 8f4834e6-f8e2-53c0-ac37-10fa5180d157/PastConnectionActivity/33kV · payload sha256 01bda17fd8c3…Operator’s publication (opens the operator’s site)
Licence
CC BY 4.0Attribution: UK Power Networks, Long Term Development Statement (LTDS) Capacity Heatmap, https://ukpowernetworks.opendatasoft.com/explore/dataset/ukpn-capacity-heatmap/ (last updated 2025-03-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: connection voltage kv
33
Operator note: source field
generationBudgetEstimatesProvidedCount

Injection · Generation (any) · Total

84 MVA

Published in MVA; no MW figure is derived from it.

Granted

The operator's latest published dataset reports 84 MVA under methodology gb_ukpn_ltds_heatmap_2026.

Firmness
Firm
Horizon
Now (snapshot)
Methodology
gb_ukpn_ltds_heatmap_2026UKPN LTDS Capacity Heatmap: headroom from the Network Scenario Headroom Reportbasis operator calculated · network state n minus 1 · comparability class gb_ukpn_ltds_heatmapNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Mar 2025
Retrieved / confirmed
2026-09-26 02:47 UTClast confirmed unchanged 2026-09-26 02:47 UTC
Source health
Healthy
Provenance
gb_ukpn_ltds_heatmaprecord 8f4834e6-f8e2-53c0-ac37-10fa5180d157 · payload sha256 cdc3da01dc9c…Operator’s publication (opens the operator’s site)
Licence
CC BY 4.0Attribution: UK Power Networks, Long Term Development Statement (LTDS) Capacity Heatmap, https://ukpowernetworks.opendatasoft.com/explore/dataset/ukpn-capacity-heatmap/ (last updated 2025-03-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
generationFirmCapacity

Injection · Generation (any) · Total

63.5 MVA

Published in MVA; no MW figure is derived from it.

Granted

The operator's latest published dataset reports 63.5 MVA under methodology gb_ukpn_ltds_heatmap_2026.

Firmness
Firm
Horizon
Now (snapshot) · variant: reverse_power_flow
Methodology
gb_ukpn_ltds_heatmap_2026UKPN LTDS Capacity Heatmap: headroom from the Network Scenario Headroom Reportbasis operator calculated · network state n minus 1 · comparability class gb_ukpn_ltds_heatmapNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Mar 2025
Retrieved / confirmed
2026-09-26 02:47 UTClast confirmed unchanged 2026-09-26 02:47 UTC
Source health
Healthy
Provenance
gb_ukpn_ltds_heatmaprecord 8f4834e6-f8e2-53c0-ac37-10fa5180d157 · payload sha256 cdc3da01dc9c…Operator’s publication (opens the operator’s site)
Licence
CC BY 4.0Attribution: UK Power Networks, Long Term Development Statement (LTDS) Capacity Heatmap, https://ukpowernetworks.opendatasoft.com/explore/dataset/ukpn-capacity-heatmap/ (last updated 2025-03-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
reversePowerFlowTotalCapacity

Offtake · Load (any) · Available

28.7 MVA

Published in MVA; no MW figure is derived from it.

Granted

The operator's latest published dataset reports 28.7 MVA under methodology gb_ukpn_ltds_heatmap_2026.

Firmness
Firm
Horizon
Now (snapshot)
Methodology
gb_ukpn_ltds_heatmap_2026UKPN LTDS Capacity Heatmap: headroom from the Network Scenario Headroom Reportbasis operator calculated · network state n minus 1 · comparability class gb_ukpn_ltds_heatmapNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Mar 2025
Retrieved / confirmed
2026-09-26 02:47 UTClast confirmed unchanged 2026-09-26 02:47 UTC
Source health
Healthy
Provenance
gb_ukpn_ltds_heatmaprecord 8f4834e6-f8e2-53c0-ac37-10fa5180d157 · payload sha256 cdc3da01dc9c…Operator’s publication (opens the operator’s site)
Licence
CC BY 4.0Attribution: UK Power Networks, Long Term Development Statement (LTDS) Capacity Heatmap, https://ukpowernetworks.opendatasoft.com/explore/dataset/ukpn-capacity-heatmap/ (last updated 2025-03-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: limiting factor
Thermal
Operator note: rag
GREEN
Operator note: rag colour
green
Operator note: source field
demandAvailableCapacity

Offtake · Load (any) · Requested

27.9 MVA

Published in MVA; no MW figure is derived from it.

Granted

The operator's latest published dataset reports 27.9 MVA under methodology gb_ukpn_ltds_heatmap_activity_2026.

Firmness
Unknown
Horizon
past_connection_activity · variant: budget_estimates_provided
Methodology
gb_ukpn_ltds_heatmap_activity_2026UKPN past connection activity (LTDS Capacity Heatmap)basis operator published · network state unknown · comparability class gb_ukpn_connection_activityNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Mar 2025
Retrieved / confirmed
2026-09-26 02:47 UTClast confirmed unchanged 2026-09-26 02:47 UTC
Source health
Healthy
Provenance
gb_ukpn_ltds_heatmaprecord 8f4834e6-f8e2-53c0-ac37-10fa5180d157/PastConnectionActivity/33kV · payload sha256 01bda17fd8c3…Operator’s publication (opens the operator’s site)
Licence
CC BY 4.0Attribution: UK Power Networks, Long Term Development Statement (LTDS) Capacity Heatmap, https://ukpowernetworks.opendatasoft.com/explore/dataset/ukpn-capacity-heatmap/ (last updated 2025-03-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: connection voltage kv
33
Operator note: source field
loadBudgetEstimatesProvidedCapacity

Offtake · Load (any) · Requested

2

Published in count; no MW figure is derived from it.

Granted

The operator's latest published dataset reports 2 count under methodology gb_ukpn_ltds_heatmap_activity_2026.

Firmness
Unknown
Horizon
past_connection_activity · variant: budget_estimates_provided_count
Methodology
gb_ukpn_ltds_heatmap_activity_2026UKPN past connection activity (LTDS Capacity Heatmap)basis operator published · network state unknown · comparability class gb_ukpn_connection_activityNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Mar 2025
Retrieved / confirmed
2026-09-26 02:47 UTClast confirmed unchanged 2026-09-26 02:47 UTC
Source health
Healthy
Provenance
gb_ukpn_ltds_heatmaprecord 8f4834e6-f8e2-53c0-ac37-10fa5180d157/PastConnectionActivity/33kV · payload sha256 01bda17fd8c3…Operator’s publication (opens the operator’s site)
Licence
CC BY 4.0Attribution: UK Power Networks, Long Term Development Statement (LTDS) Capacity Heatmap, https://ukpowernetworks.opendatasoft.com/explore/dataset/ukpn-capacity-heatmap/ (last updated 2025-03-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: connection voltage kv
33
Operator note: source field
loadBudgetEstimatesProvidedCount

Offtake · Load (any) · Total

63.5 MVA

Published in MVA; no MW figure is derived from it.

Granted

The operator's latest published dataset reports 63.5 MVA under methodology gb_ukpn_ltds_heatmap_2026.

Firmness
Firm
Horizon
Now (snapshot)
Methodology
gb_ukpn_ltds_heatmap_2026UKPN LTDS Capacity Heatmap: headroom from the Network Scenario Headroom Reportbasis operator calculated · network state n minus 1 · comparability class gb_ukpn_ltds_heatmapNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Mar 2025
Retrieved / confirmed
2026-09-26 02:47 UTClast confirmed unchanged 2026-09-26 02:47 UTC
Source health
Healthy
Provenance
gb_ukpn_ltds_heatmaprecord 8f4834e6-f8e2-53c0-ac37-10fa5180d157 · payload sha256 cdc3da01dc9c…Operator’s publication (opens the operator’s site)
Licence
CC BY 4.0Attribution: UK Power Networks, Long Term Development Statement (LTDS) Capacity Heatmap, https://ukpowernetworks.opendatasoft.com/explore/dataset/ukpn-capacity-heatmap/ (last updated 2025-03-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
demandFirmCapacity

History

Served series only

Offtake · Load (any) · Available

current 28.7 MVA

26 Sep 2026: 28.7 MVA
26 Sep 2026range 28.7–28.7 MVA26 Sep 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current28.7 MVA

Time axis: when we observed each value, not the operator’s effective date.

Injection · Generation (any) · Available

current 53 MVA

26 Sep 2026: 53 MVA
26 Sep 2026range 53–53 MVA26 Sep 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current53 MVA

Time axis: when we observed each value, not the operator’s effective date.

Injection · Generation (any) · Available

current 63.5 MVA

26 Sep 2026: 63.5 MVA
26 Sep 2026range 63.5–63.5 MVA26 Sep 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current63.5 MVA

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Load (any) · Total

current 63.5 MVA

26 Sep 2026: 63.5 MVA
26 Sep 2026range 63.5–63.5 MVA26 Sep 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current63.5 MVA

Time axis: when we observed each value, not the operator’s effective date.

Injection · Generation (any) · Total

current 84 MVA

26 Sep 2026: 84 MVA
26 Sep 2026range 84–84 MVA26 Sep 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current84 MVA

Time axis: when we observed each value, not the operator’s effective date.

Injection · Generation (any) · Total

current 63.5 MVA

26 Sep 2026: 63.5 MVA
26 Sep 2026range 63.5–63.5 MVA26 Sep 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current63.5 MVA

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Load (any) · Requested · past_connection_activity

current 27.9 MVA

26 Sep 2026: 27.9 MVA
26 Sep 2026range 27.9–27.9 MVA26 Sep 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current27.9 MVA

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Load (any) · Requested · past_connection_activity

current 2

26 Sep 2026: 2
26 Sep 2026range 2–226 Sep 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current2

Time axis: when we observed each value, not the operator’s effective date.

Injection · Generation (any) · Requested · past_connection_activity

current 4 MVA

26 Sep 2026: 4 MVA
26 Sep 2026range 4–4 MVA26 Sep 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current4 MVA

Time axis: when we observed each value, not the operator’s effective date.

Injection · Generation (any) · Requested · past_connection_activity

current 2

26 Sep 2026: 2
26 Sep 2026range 2–226 Sep 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current2

Time axis: when we observed each value, not the operator’s effective date.

Through the API

curl "https://api.gridcapacityapi.com/v1/substations/sub_06gdq75qqsvrf5g7pf7wn30590/capacity" \  -H "Authorization: Bearer gc_live_..."
Newhaven Grid 33kV substation: grid capacity (UK Power Networks) · GridCapacity API