UKPN LTDS Capacity Heatmap: headroom from the Network Scenario Headroom Report
gb_ukpn_ltds_heatmap_2026 · v2026-05 (LTDS May 2026, v1.0 files)Demand and generation available capacity per primary substation, derived from UKPN's Network Scenario Headroom Report (DFES 2025, baseline utilisation and network ratings from the November 2025 LTDS, including planned developments and operational flexibility). Firm capacity is LTDS Table 3A/3B; generation firm capacity is available plus existing generation; reverse power flow total is the N-1 reverse capability of the transformers (LTDS Tables 2A/2B, 50% assumed where rated "<100").
- Capacity basis
- operator calculated
- Network state
- n minus 1
- Binding
- No
- Additive across assets
- No — do not sum these figures
- The method accounts for
- reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
- Comparability class
- gb_ukpn_ltds_heatmap
- Documentation
- Operator’s method (opens the operator’s site)
The operator’s own caveats
- "You should make your own checks before relying on it." (UKPN portal terms)
- "Unused capacity may be contractually committed to customers. Those seeking connection should contact our connections gateway" (UKPN, Network Scenario Headroom Report, the source of available capacity)