Latest published values

92 served · 0 withheld

Each row is what the operator’s latest published dataset reports for one combination of direction, technology, measure, firmness and horizon. Hosting-capacity figures are indicative and reflect what operators publish. They are not a connection offer; only the operator can confirm capacity for a specific request.

Latest published capacity values, one row per series
DirectionTechnologyMeasureValueFirmnessHorizonSource date
InjectionGeneration (any)Allocated343.35 MWUnknownNow (snapshot)variant: mge9 Sep 2026
InjectionGeneration (any)Allocated343 MWUnknownNow (snapshot)variant: mge1 Sep 2026
InjectionGeneration (any)Allocated343 MWUnknownNow (snapshot)variant: gen1 Sep 2026
InjectionGeneration (any)Allocated331 MWUnknownNow (snapshot)variant: mpe1 Sep 2026
InjectionGeneration (any)Allocated320 MWUnknownNow (snapshot)variant: mpe_con_wscr1 Sep 2026
InjectionGeneration (any)Allocated12 MWUnknownNow (snapshot)variant: mges1 Sep 2026
InjectionGeneration (any)Allocated11 MWUnknownNow (snapshot)variant: mpe_sin_wscr1 Sep 2026
InjectionGeneration (any)Allocated0 MWUnknownNow (snapshot)variant: autoconsumo_mges1 Sep 2026
InjectionGeneration (any)Allocated0 MWUnknownNow (snapshot)variant: autoconsumo_mpe1 Sep 2026
InjectionGeneration (any)Available1,065 MWUnknownNow (snapshot)variant: estatico_margen1 Sep 2026
InjectionGeneration (any)Available758 MWUnknownNow (snapshot)variant: dinamico_margen1 Sep 2026
InjectionGeneration (any)Available758 MWUnknownNow (snapshot)variant: margen_total_mges1 Sep 2026
InjectionGeneration (any)Available597 MWUnknownNow (snapshot)variant: posicion_margen_mges1 Sep 2026
InjectionGeneration (any)Available219 MWUnknownNow (snapshot)variant: wscr_margen1 Sep 2026
InjectionGeneration (any)Available219 MWUnknownNow (snapshot)variant: posicion_margen_mpe1 Sep 2026
InjectionGeneration (any)Available219 MWUnknownNow (snapshot)variant: margen_total_mpe1 Sep 2026
InjectionGeneration (any)Available76 MWUnknownNow (snapshot)variant: autoconsumo_mges1 Sep 2026
InjectionGeneration (any)Available22 MWUnknownNow (snapshot)variant: autoconsumo_mpe1 Sep 2026
InjectionGeneration (any)Available0 MWUnknownNow (snapshot)variant: mpe_rdt9 Sep 2026
InjectionGeneration (any)Available0 MWUnknownNow (snapshot)variant: mges_rdt9 Sep 2026
InjectionGeneration (any)Available0 MWUnknownNow (snapshot)variant: mges_rdt1 Sep 2026
InjectionGeneration (any)Available0 MWUnknownNow (snapshot)variant: mpe_rdt1 Sep 2026
InjectionGeneration (any)Available0 MWUnknownNow (snapshot)variant: mges_rdd1 Sep 2026
InjectionGeneration (any)Available0 MWUnknownNow (snapshot)variant: mpe_rdd1 Sep 2026
InjectionGeneration (any)Requested11 MWUnknownNow (snapshot)variant: mge1 Sep 2026
InjectionGeneration (any)Requested11 MWUnknownNow (snapshot)variant: mpe_sin_wscr1 Sep 2026
InjectionGeneration (any)Requested11 MWUnknownNow (snapshot)variant: mpe1 Sep 2026
InjectionGeneration (any)Requested11 MWUnknownNow (snapshot)variant: gen1 Sep 2026
InjectionGeneration (any)Requested10.9 MWUnknownNow (snapshot)variant: mge9 Sep 2026
InjectionGeneration (any)Requested0 MWUnknownNow (snapshot)variant: mges1 Sep 2026
InjectionGeneration (any)Requested0 MWUnknownNow (snapshot)variant: mpe_con_wscr1 Sep 2026
InjectionGeneration (any)Total1,409 MWUnknownNow (snapshot)variant: estatico_nodal1 Sep 2026
InjectionGeneration (any)Total1,101 MWUnknownNow (snapshot)variant: dinamico_nodal1 Sep 2026
InjectionGeneration (any)Total800 MWUnknownNow (snapshot)variant: posicion_maximo1 Sep 2026
InjectionGeneration (any)Total539 MWUnknownNow (snapshot)variant: wscr_nodal1 Sep 2026
InjectionGeneration (any)Total76 MWUnknownNow (snapshot)variant: autoconsumo_mges1 Sep 2026
InjectionGeneration (any)Total22 MWUnknownNow (snapshot)variant: autoconsumo_mpe1 Sep 2026
InjectionGeneration (any)Totalnot statedUnknownNow (snapshot)variant: dinamico_limitacion_interna1 Sep 2026
InjectionGeneration (any)Unknown758 MWUnknownNow (snapshot)variant: no_disponible_mges1 Sep 2026
InjectionGeneration (any)Unknown219 MWUnknownNow (snapshot)variant: no_disponible_mpe1 Sep 2026
InjectionOther storageAllocated0 MWUnknownNow (snapshot)variant: alm1 Sep 2026
InjectionOther storageAvailable1,283 MWUnknownNow (snapshot)variant: estatico_margen1 Sep 2026
InjectionOther storageAvailable758 MWUnknownNow (snapshot)variant: margen_total_mges1 Sep 2026
InjectionOther storageAvailable219 MWUnknownNow (snapshot)variant: margen_total_mpe1 Sep 2026
InjectionOther storageAvailable0 MWUnknownNow (snapshot)variant: mpe_rdt9 Sep 2026
InjectionOther storageAvailable0 MWUnknownNow (snapshot)variant: mges_rdt9 Sep 2026
InjectionOther storageAvailable0 MWUnknownNow (snapshot)variant: mges_rdt1 Sep 2026
InjectionOther storageAvailable0 MWUnknownNow (snapshot)variant: mpe_rdt1 Sep 2026
InjectionOther storageAvailable0 MWUnknownNow (snapshot)variant: mges_rdd1 Sep 2026
InjectionOther storageAvailable0 MWUnknownNow (snapshot)variant: mpe_rdd1 Sep 2026
InjectionOther storageRequested0 MWUnknownNow (snapshot)variant: alm1 Sep 2026
InjectionOther storageTotal1,627 MWUnknownNow (snapshot)variant: estatico_nodal1 Sep 2026
InjectionOther storageUnknown758 MWUnknownNow (snapshot)variant: no_disponible_mges1 Sep 2026
InjectionOther storageUnknown219 MWUnknownNow (snapshot)variant: no_disponible_mpe1 Sep 2026
OfftakeLoad (any)Allocated0 MWUnknownNow (snapshot)variant: adicional_valor_referencia1 Sep 2026
OfftakeLoad (any)Allocated0 MWUnknownNow (snapshot)variant: cep_wscr1 Sep 2026
OfftakeLoad (any)Allocated0 MWUnknownNow (snapshot)variant: rdt1 Sep 2026
OfftakeLoad (any)Allocated0 MWUnknownNow (snapshot)variant: aceptabilidad_rdd1 Sep 2026
OfftakeLoad (any)Allocated0 MWUnknownNow (snapshot)variant: aceptabilidad_rdd_fuera_referencia1 Sep 2026
OfftakeLoad (any)Allocated0 MWUnknownNow (snapshot)variant: ch_rdt1 Sep 2026
OfftakeLoad (any)Allocated0 MWUnknownNow (snapshot)variant: sh_rdt1 Sep 2026
OfftakeLoad (any)Allocated0 MWUnknownNow (snapshot)variant: ch_aceptabilidad_rdd1 Sep 2026
OfftakeLoad (any)Allocated0 MWUnknownNow (snapshot)variant: sh_aceptabilidad_rdd1 Sep 2026
OfftakeLoad (any)Available427 MWUnknownNow (snapshot)variant: estatico_margen1 Sep 2026
OfftakeLoad (any)Available219 MWUnknownNow (snapshot)variant: wscr_margen1 Sep 2026
OfftakeLoad (any)Available0 MWUnknownNow (snapshot)variant: dinamico1_margen1 Sep 2026
OfftakeLoad (any)Available0 MWUnknownNow (snapshot)variant: dinamico2_margen1 Sep 2026
OfftakeLoad (any)Available0 MWUnknownNow (snapshot)variant: margen_total_cep_ch1 Sep 2026
OfftakeLoad (any)Available0 MWUnknownNow (snapshot)variant: margen_total_cep_sh1 Sep 2026
OfftakeLoad (any)Available0 MWUnknownNow (snapshot)variant: margen_total_no_cep1 Sep 2026
OfftakeLoad (any)Available0 MWUnknownNow (snapshot)variant: cep_ch1 Sep 2026
OfftakeLoad (any)Available0 MWUnknownNow (snapshot)variant: cep_sh1 Sep 2026
OfftakeLoad (any)Available0 MWUnknownNow (snapshot)variant: no_cep1 Sep 2026
OfftakeLoad (any)Requested0 MWUnknownNow (snapshot)variant: rdt1 Sep 2026
OfftakeLoad (any)Reserved195 MWUnknownNow (snapshot)variant: valor_referencia_rdd1 Sep 2026
OfftakeLoad (any)Total622 MWUnknownNow (snapshot)variant: estatico_nodal1 Sep 2026
OfftakeLoad (any)Total219 MWUnknownNow (snapshot)variant: wscr_nodal1 Sep 2026
OfftakeLoad (any)Unknown0 MWUnknownNow (snapshot)variant: no_otorgable_cep_ch1 Sep 2026
OfftakeLoad (any)Unknown0 MWUnknownNow (snapshot)variant: no_otorgable_cep_sh1 Sep 2026
OfftakeLoad (any)Unknown0 MWUnknownNow (snapshot)variant: no_otorgable_no_cep1 Sep 2026
OfftakeOther storageAllocated14 MWUnknownNow (snapshot)variant: adicional_valor_referencia1 Sep 2026
OfftakeOther storageAllocated14 MWUnknownNow (snapshot)variant: rdt1 Sep 2026
OfftakeOther storageAllocated0 MWUnknownNow (snapshot)variant: aceptabilidad_rdd1 Sep 2026
OfftakeOther storageAllocated0 MWUnknownNow (snapshot)variant: aceptabilidad_rdd_fuera_referencia1 Sep 2026
OfftakeOther storageAvailable808 MWUnknownNow (snapshot)variant: estatico_margen1 Sep 2026
OfftakeOther storageAvailable0 MWUnknownNow (snapshot)variant: margen_total_cep1 Sep 2026
OfftakeOther storageAvailable0 MWUnknownNow (snapshot)variant: margen_total_no_cep1 Sep 2026
OfftakeOther storageAvailable0 MWUnknownNow (snapshot)variant: cep1 Sep 2026
OfftakeOther storageAvailable0 MWUnknownNow (snapshot)variant: no_cep1 Sep 2026
OfftakeOther storageRequested0 MWUnknownNow (snapshot)variant: rdt1 Sep 2026
OfftakeOther storageTotal1,017 MWUnknownNow (snapshot)variant: estatico_nodal1 Sep 2026
OfftakeOther storageUnknown0 MWUnknownNow (snapshot)variant: no_otorgable_cep1 Sep 2026
OfftakeOther storageUnknown0 MWUnknownNow (snapshot)variant: no_otorgable_no_cep1 Sep 2026

Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)Origen de los datos: Comisión Nacional de los Mercados y la Competencia (CNMC) (last updated 2026-09-09)

What each value means

Methodology, both clocks, provenance and rights

Injection · Generation (any) · Allocated

343.35 MW

Granted

The operator's latest published dataset reports 343.35 MW under methodology es_cnmc_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: mge
Methodology
es_cnmc_gen_rdt_2026Generation access capacity at the transmission network (REE's figures in CNMC's map)basis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
9 Sep 2026
Retrieved / confirmed
2026-09-26 05:57 UTClast confirmed unchanged 2026-10-02 07:46 UTC
Source health
Healthy
Provenance
es_cnmc_generation_capacityrecord rdt:SERNA 220 · payload sha256 c172b42b0599…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Origen de los datos: Comisión Nacional de los Mercados y la Competencia (CNMC) (last updated 2026-09-09)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
CAP_OCUPADA

Injection · Generation (any) · Allocated

343 MW

Granted

The operator's latest published dataset reports 343 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: mge
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-10-02 05:04 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord SERNA 220 · payload sha256 0929eb859818…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: module scope
MGE: all power-generating modules (MGES + MPE, generation and storage)

Injection · Generation (any) · Allocated

343 MW

Granted

The operator's latest published dataset reports 343 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: gen
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-10-02 05:04 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord SERNA 220 · payload sha256 0929eb859818…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: module scope
GEN: generation installations, storage excluded

Injection · Generation (any) · Allocated

331 MW

Granted

The operator's latest published dataset reports 331 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: mpe
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-10-02 05:04 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord SERNA 220 · payload sha256 0929eb859818…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required

Injection · Generation (any) · Allocated

320 MW

Granted

The operator's latest published dataset reports 320 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: mpe_con_wscr
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-10-02 05:04 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord SERNA 220 · payload sha256 0929eb859818…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required

Injection · Generation (any) · Allocated

12 MW

Granted

The operator's latest published dataset reports 12 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: mges
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-10-02 05:04 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord SERNA 220 · payload sha256 0929eb859818…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required

Injection · Generation (any) · Allocated

11 MW

Granted

The operator's latest published dataset reports 11 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: mpe_sin_wscr
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-10-02 05:04 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord SERNA 220 · payload sha256 0929eb859818…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required

Injection · Generation (any) · Allocated

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: autoconsumo_mges
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-10-02 05:04 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord SERNA 220 · payload sha256 0929eb859818…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: eligibility
self-consumption requests only (RDL 7/2026)

Injection · Generation (any) · Allocated

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: autoconsumo_mpe
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-10-02 05:04 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord SERNA 220 · payload sha256 0929eb859818…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: eligibility
self-consumption requests only (RDL 7/2026)

Injection · Generation (any) · Available

1,065 MW

Granted

The operator's latest published dataset reports 1065 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: estatico_margen
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-10-02 05:04 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord SERNA 220 · payload sha256 0929eb859818…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: criterion
static (N and N-X)
Operator note: shared capacity zone
E138_SEPE

Injection · Generation (any) · Available

758 MW

Granted

The operator's latest published dataset reports 758 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: dinamico_margen
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-10-02 05:04 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord SERNA 220 · payload sha256 0929eb859818…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: criterion
dynamic stability

Injection · Generation (any) · Available

758 MW

Granted

The operator's latest published dataset reports 758 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: margen_total_mges
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-10-02 05:04 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord SERNA 220 · payload sha256 0929eb859818…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: limiting criteria
D_Nudo
Operator note: reason not available
Concurso por resolución SEE. Margen zonal reservado concurso por resolución SEE/posible concurso/NTJ.
Operator note: reservation
Concurso
Operator note: scope
gross margin, before capacity not available for requests

Injection · Generation (any) · Available

597 MW

Granted

The operator's latest published dataset reports 597 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: posicion_margen_mges
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-10-02 05:04 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord SERNA 220 · payload sha256 0929eb859818…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required

Injection · Generation (any) · Available

219 MW

Granted

The operator's latest published dataset reports 219 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: wscr_margen
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-10-02 05:04 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord SERNA 220 · payload sha256 0929eb859818…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: criterion
short-circuit power (WSCR); applies to power park modules (MPE) only
Operator note: system security effect
Superación valor máx Icc

Injection · Generation (any) · Available

219 MW

Granted

The operator's latest published dataset reports 219 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: posicion_margen_mpe
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-10-02 05:04 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord SERNA 220 · payload sha256 0929eb859818…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required

Injection · Generation (any) · Available

219 MW

Granted

The operator's latest published dataset reports 219 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: margen_total_mpe
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-10-02 05:04 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord SERNA 220 · payload sha256 0929eb859818…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: limiting criteria
WSCR_Nudo
Operator note: reason not available
Concurso por resolución SEE. Margen zonal reservado concurso por resolución SEE/posible concurso/NTJ.
Operator note: reservation
Concurso
Operator note: scope
gross margin, before capacity not available for requests

Injection · Generation (any) · Available

76 MW

Granted

The operator's latest published dataset reports 76 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: autoconsumo_mges
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-10-02 05:04 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord SERNA 220 · payload sha256 0929eb859818…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: eligibility
self-consumption requests only (RDL 7/2026)

Injection · Generation (any) · Available

22 MW

Granted

The operator's latest published dataset reports 22 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: autoconsumo_mpe
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-10-02 05:04 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord SERNA 220 · payload sha256 0929eb859818…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: eligibility
self-consumption requests only (RDL 7/2026)

Injection · Generation (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_cnmc_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: mpe_rdt
Methodology
es_cnmc_gen_rdt_2026Generation access capacity at the transmission network (REE's figures in CNMC's map)basis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
9 Sep 2026
Retrieved / confirmed
2026-09-26 05:57 UTClast confirmed unchanged 2026-10-02 07:46 UTC
Source health
Healthy
Provenance
es_cnmc_generation_capacityrecord rdt:SERNA 220 · payload sha256 c172b42b0599…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Origen de los datos: Comisión Nacional de los Mercados y la Competencia (CNMC) (last updated 2026-09-09)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: limited by short circuit power
true
Operator note: regulatory reservation
true
Operator note: source field
CAP_DISPONIBLE_MPE

Injection · Generation (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_cnmc_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: mges_rdt
Methodology
es_cnmc_gen_rdt_2026Generation access capacity at the transmission network (REE's figures in CNMC's map)basis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
9 Sep 2026
Retrieved / confirmed
2026-09-26 05:57 UTClast confirmed unchanged 2026-10-02 07:46 UTC
Source health
Healthy
Provenance
es_cnmc_generation_capacityrecord rdt:SERNA 220 · payload sha256 c172b42b0599…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Origen de los datos: Comisión Nacional de los Mercados y la Competencia (CNMC) (last updated 2026-09-09)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: limited by short circuit power
true
Operator note: regulatory reservation
true
Operator note: source field
CAP_DISPONIBLE_MGES

Injection · Generation (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: mges_rdt
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-10-02 05:04 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord SERNA 220 · payload sha256 0929eb859818…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: limiting criteria
D_Nudo
Operator note: reason not available
Concurso por resolución SEE. Margen zonal reservado concurso por resolución SEE/posible concurso/NTJ.
Operator note: reservation
Concurso

Injection · Generation (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: mpe_rdt
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-10-02 05:04 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord SERNA 220 · payload sha256 0929eb859818…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: limiting criteria
WSCR_Nudo
Operator note: reason not available
Concurso por resolución SEE. Margen zonal reservado concurso por resolución SEE/posible concurso/NTJ.
Operator note: reservation
Concurso

Injection · Generation (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: mges_rdd
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-10-02 05:04 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord SERNA 220 · payload sha256 0929eb859818…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: limiting criteria
D_Nudo
Operator note: reason not available
Concurso por resolución SEE. Margen zonal reservado concurso por resolución SEE/posible concurso/NTJ.
Operator note: reservation
Concurso

Injection · Generation (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: mpe_rdd
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-10-02 05:04 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord SERNA 220 · payload sha256 0929eb859818…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: limiting criteria
WSCR_Nudo
Operator note: reason not available
Concurso por resolución SEE. Margen zonal reservado concurso por resolución SEE/posible concurso/NTJ.
Operator note: reservation
Concurso

Injection · Generation (any) · Requested

11 MW

Granted

The operator's latest published dataset reports 11 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: mge
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-10-02 05:04 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord SERNA 220 · payload sha256 0929eb859818…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required

Injection · Generation (any) · Requested

11 MW

Granted

The operator's latest published dataset reports 11 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: mpe_sin_wscr
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-10-02 05:04 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord SERNA 220 · payload sha256 0929eb859818…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required

Injection · Generation (any) · Requested

11 MW

Granted

The operator's latest published dataset reports 11 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: mpe
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-10-02 05:04 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord SERNA 220 · payload sha256 0929eb859818…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required

Injection · Generation (any) · Requested

11 MW

Granted

The operator's latest published dataset reports 11 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: gen
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-10-02 05:04 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord SERNA 220 · payload sha256 0929eb859818…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required

Injection · Generation (any) · Requested

10.9 MW

Granted

The operator's latest published dataset reports 10.9 MW under methodology es_cnmc_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: mge
Methodology
es_cnmc_gen_rdt_2026Generation access capacity at the transmission network (REE's figures in CNMC's map)basis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
9 Sep 2026
Retrieved / confirmed
2026-09-26 05:57 UTClast confirmed unchanged 2026-10-02 07:46 UTC
Source health
Healthy
Provenance
es_cnmc_generation_capacityrecord rdt:SERNA 220 · payload sha256 c172b42b0599…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Origen de los datos: Comisión Nacional de los Mercados y la Competencia (CNMC) (last updated 2026-09-09)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
CAP_ADMITIDA_NO_RESUELTA

Injection · Generation (any) · Requested

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: mges
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-10-02 05:04 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord SERNA 220 · payload sha256 0929eb859818…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required

Injection · Generation (any) · Requested

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: mpe_con_wscr
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-10-02 05:04 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord SERNA 220 · payload sha256 0929eb859818…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required

Injection · Generation (any) · Total

1,409 MW

Granted

The operator's latest published dataset reports 1409 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: estatico_nodal
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-10-02 05:04 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord SERNA 220 · payload sha256 0929eb859818…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: criterion
static (N and N-X)
Operator note: shared capacity zone
E138_SEPE

Injection · Generation (any) · Total

1,101 MW

Granted

The operator's latest published dataset reports 1101 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: dinamico_nodal
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-10-02 05:04 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord SERNA 220 · payload sha256 0929eb859818…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: criterion
dynamic stability

Injection · Generation (any) · Total

800 MW

Granted

The operator's latest published dataset reports 800 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: posicion_maximo
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-10-02 05:04 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord SERNA 220 · payload sha256 0929eb859818…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required

Injection · Generation (any) · Total

539 MW

Granted

The operator's latest published dataset reports 539 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: wscr_nodal
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-10-02 05:04 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord SERNA 220 · payload sha256 0929eb859818…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: criterion
short-circuit power (WSCR); applies to power park modules (MPE) only
Operator note: system security effect
Superación valor máx Icc

Injection · Generation (any) · Total

76 MW

Granted

The operator's latest published dataset reports 76 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: autoconsumo_mges
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-10-02 05:04 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord SERNA 220 · payload sha256 0929eb859818…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: eligibility
self-consumption requests only (RDL 7/2026)

Injection · Generation (any) · Total

22 MW

Granted

The operator's latest published dataset reports 22 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: autoconsumo_mpe
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-10-02 05:04 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord SERNA 220 · payload sha256 0929eb859818…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: eligibility
self-consumption requests only (RDL 7/2026)

Injection · Generation (any) · Total

not stated

Published in MW; no MW figure is derived from it.

Granted

The operator's latest published dataset reports no value (published as unknown) under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: dinamico_limitacion_interna
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-10-02 05:04 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord SERNA 220 · payload sha256 0929eb859818…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: criterion
dynamic stability
Operator note: source label
N/A

Injection · Generation (any) · Unknown

758 MW

Granted

The operator's latest published dataset reports 758 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: no_disponible_mges
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-10-02 05:04 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord SERNA 220 · payload sha256 0929eb859818…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: reason not available
Concurso por resolución SEE. Margen zonal reservado concurso por resolución SEE/posible concurso/NTJ.
Operator note: reservation
Concurso

Injection · Generation (any) · Unknown

219 MW

Granted

The operator's latest published dataset reports 219 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: no_disponible_mpe
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-10-02 05:04 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord SERNA 220 · payload sha256 0929eb859818…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: reason not available
Concurso por resolución SEE. Margen zonal reservado concurso por resolución SEE/posible concurso/NTJ.
Operator note: reservation
Concurso

Injection · Other storage · Allocated

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: alm
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-10-02 05:04 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord SERNA 220 · payload sha256 0929eb859818…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required

Injection · Other storage · Available

1,283 MW

Granted

The operator's latest published dataset reports 1283 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: estatico_margen
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-10-02 05:04 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord SERNA 220 · payload sha256 0929eb859818…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: criterion
static (N and N-X)
Operator note: shared capacity zone
E138_SEPE

Injection · Other storage · Available

758 MW

Granted

The operator's latest published dataset reports 758 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: margen_total_mges
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-10-02 05:04 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord SERNA 220 · payload sha256 0929eb859818…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: limiting criteria
D_Nudo
Operator note: reason not available
Concurso por resolución SEE. Margen zonal reservado concurso por resolución SEE/posible concurso/NTJ.
Operator note: reservation
Concurso
Operator note: scope
gross margin, before capacity not available for requests

Injection · Other storage · Available

219 MW

Granted

The operator's latest published dataset reports 219 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: margen_total_mpe
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-10-02 05:04 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord SERNA 220 · payload sha256 0929eb859818…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: limiting criteria
WSCR_Nudo
Operator note: reason not available
Concurso por resolución SEE. Margen zonal reservado concurso por resolución SEE/posible concurso/NTJ.
Operator note: reservation
Concurso
Operator note: scope
gross margin, before capacity not available for requests

Injection · Other storage · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_cnmc_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: mpe_rdt
Methodology
es_cnmc_gen_rdt_2026Generation access capacity at the transmission network (REE's figures in CNMC's map)basis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
9 Sep 2026
Retrieved / confirmed
2026-09-26 05:57 UTClast confirmed unchanged 2026-10-02 07:46 UTC
Source health
Healthy
Provenance
es_cnmc_generation_capacityrecord rdt:SERNA 220 · payload sha256 c172b42b0599…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Origen de los datos: Comisión Nacional de los Mercados y la Competencia (CNMC) (last updated 2026-09-09)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: limited by short circuit power
true
Operator note: regulatory reservation
true
Operator note: source field
CAP_ALM_DISPONIBLE_MPE

Injection · Other storage · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_cnmc_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: mges_rdt
Methodology
es_cnmc_gen_rdt_2026Generation access capacity at the transmission network (REE's figures in CNMC's map)basis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
9 Sep 2026
Retrieved / confirmed
2026-09-26 05:57 UTClast confirmed unchanged 2026-10-02 07:46 UTC
Source health
Healthy
Provenance
es_cnmc_generation_capacityrecord rdt:SERNA 220 · payload sha256 c172b42b0599…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Origen de los datos: Comisión Nacional de los Mercados y la Competencia (CNMC) (last updated 2026-09-09)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: limited by short circuit power
true
Operator note: regulatory reservation
true
Operator note: source field
CAP_ALM_DISPONIBLE_MGES

Injection · Other storage · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: mges_rdt
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-10-02 05:04 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord SERNA 220 · payload sha256 0929eb859818…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: limiting criteria
D_Nudo
Operator note: reason not available
Concurso por resolución SEE. Margen zonal reservado concurso por resolución SEE/posible concurso/NTJ.
Operator note: reservation
Concurso

Injection · Other storage · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: mpe_rdt
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-10-02 05:04 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord SERNA 220 · payload sha256 0929eb859818…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: limiting criteria
WSCR_Nudo
Operator note: reason not available
Concurso por resolución SEE. Margen zonal reservado concurso por resolución SEE/posible concurso/NTJ.
Operator note: reservation
Concurso

Injection · Other storage · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: mges_rdd
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-10-02 05:04 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord SERNA 220 · payload sha256 0929eb859818…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: limiting criteria
D_Nudo
Operator note: reason not available
Concurso por resolución SEE. Margen zonal reservado concurso por resolución SEE/posible concurso/NTJ.
Operator note: reservation
Concurso

Injection · Other storage · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: mpe_rdd
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-10-02 05:04 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord SERNA 220 · payload sha256 0929eb859818…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: limiting criteria
WSCR_Nudo
Operator note: reason not available
Concurso por resolución SEE. Margen zonal reservado concurso por resolución SEE/posible concurso/NTJ.
Operator note: reservation
Concurso

Injection · Other storage · Requested

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: alm
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-10-02 05:04 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord SERNA 220 · payload sha256 0929eb859818…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required

Injection · Other storage · Total

1,627 MW

Granted

The operator's latest published dataset reports 1627 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: estatico_nodal
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-10-02 05:04 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord SERNA 220 · payload sha256 0929eb859818…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: criterion
static (N and N-X)
Operator note: shared capacity zone
E138_SEPE

Injection · Other storage · Unknown

758 MW

Granted

The operator's latest published dataset reports 758 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: no_disponible_mges
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-10-02 05:04 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord SERNA 220 · payload sha256 0929eb859818…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: reason not available
Concurso por resolución SEE. Margen zonal reservado concurso por resolución SEE/posible concurso/NTJ.
Operator note: reservation
Concurso

Injection · Other storage · Unknown

219 MW

Granted

The operator's latest published dataset reports 219 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: no_disponible_mpe
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-10-02 05:04 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord SERNA 220 · payload sha256 0929eb859818…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: reason not available
Concurso por resolución SEE. Margen zonal reservado concurso por resolución SEE/posible concurso/NTJ.
Operator note: reservation
Concurso

Offtake · Load (any) · Allocated

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_dem_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: adicional_valor_referencia
Methodology
es_ree_dem_rdt_2026REE demand access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_demand_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-09-30 09:22 UTC
Source health
Healthy
Provenance
es_ree_demand_access_capacityrecord SERNA 220 · payload sha256 149dbaf707f0…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required

Offtake · Load (any) · Allocated

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_dem_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: cep_wscr
Methodology
es_ree_dem_rdt_2026REE demand access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_demand_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-09-30 09:22 UTC
Source health
Healthy
Provenance
es_ree_demand_access_capacityrecord SERNA 220 · payload sha256 149dbaf707f0…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required

Offtake · Load (any) · Allocated

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_dem_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: rdt
Methodology
es_ree_dem_rdt_2026REE demand access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_demand_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-09-30 09:22 UTC
Source health
Healthy
Provenance
es_ree_demand_access_capacityrecord SERNA 220 · payload sha256 149dbaf707f0…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required

Offtake · Load (any) · Allocated

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_dem_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: aceptabilidad_rdd
Methodology
es_ree_dem_rdt_2026REE demand access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_demand_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-09-30 09:22 UTC
Source health
Healthy
Provenance
es_ree_demand_access_capacityrecord SERNA 220 · payload sha256 149dbaf707f0…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required

Offtake · Load (any) · Allocated

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_dem_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: aceptabilidad_rdd_fuera_referencia
Methodology
es_ree_dem_rdt_2026REE demand access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_demand_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-09-30 09:22 UTC
Source health
Healthy
Provenance
es_ree_demand_access_capacityrecord SERNA 220 · payload sha256 149dbaf707f0…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required

Offtake · Load (any) · Allocated

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_dem_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: ch_rdt
Methodology
es_ree_dem_rdt_2026REE demand access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_demand_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-09-30 09:22 UTC
Source health
Healthy
Provenance
es_ree_demand_access_capacityrecord SERNA 220 · payload sha256 149dbaf707f0…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required

Offtake · Load (any) · Allocated

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_dem_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: sh_rdt
Methodology
es_ree_dem_rdt_2026REE demand access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_demand_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-09-30 09:22 UTC
Source health
Healthy
Provenance
es_ree_demand_access_capacityrecord SERNA 220 · payload sha256 149dbaf707f0…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required

Offtake · Load (any) · Allocated

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_dem_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: ch_aceptabilidad_rdd
Methodology
es_ree_dem_rdt_2026REE demand access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_demand_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-09-30 09:22 UTC
Source health
Healthy
Provenance
es_ree_demand_access_capacityrecord SERNA 220 · payload sha256 149dbaf707f0…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required

Offtake · Load (any) · Allocated

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_dem_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: sh_aceptabilidad_rdd
Methodology
es_ree_dem_rdt_2026REE demand access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_demand_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-09-30 09:22 UTC
Source health
Healthy
Provenance
es_ree_demand_access_capacityrecord SERNA 220 · payload sha256 149dbaf707f0…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required

Offtake · Load (any) · Available

427 MW

Granted

The operator's latest published dataset reports 427 MW under methodology es_ree_dem_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: estatico_margen
Methodology
es_ree_dem_rdt_2026REE demand access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_demand_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-09-30 09:22 UTC
Source health
Healthy
Provenance
es_ree_demand_access_capacityrecord SERNA 220 · payload sha256 149dbaf707f0…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: criterion
static (N and N-X)
Operator note: temporary access limitation
No

Offtake · Load (any) · Available

219 MW

Granted

The operator's latest published dataset reports 219 MW under methodology es_ree_dem_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: wscr_margen
Methodology
es_ree_dem_rdt_2026REE demand access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_demand_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-09-30 09:22 UTC
Source health
Healthy
Provenance
es_ree_demand_access_capacityrecord SERNA 220 · payload sha256 149dbaf707f0…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: criterion
short-circuit power (WSCR); applies to demand with a power-electronics interface (CEP) only
Operator note: system security effect
Superación valor máx Icc

Offtake · Load (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_dem_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: dinamico1_margen
Methodology
es_ree_dem_rdt_2026REE demand access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_demand_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-09-30 09:22 UTC
Source health
Healthy
Provenance
es_ree_demand_access_capacityrecord SERNA 220 · payload sha256 149dbaf707f0…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: criterion
dynamic 1: CEP demand with voltage-dip ride-through, and non-CEP demand

Offtake · Load (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_dem_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: dinamico2_margen
Methodology
es_ree_dem_rdt_2026REE demand access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_demand_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-09-30 09:22 UTC
Source health
Healthy
Provenance
es_ree_demand_access_capacityrecord SERNA 220 · payload sha256 149dbaf707f0…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: criterion
dynamic 2: CEP demand without voltage-dip ride-through

Offtake · Load (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_dem_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: margen_total_cep_ch
Methodology
es_ree_dem_rdt_2026REE demand access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_demand_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-09-30 09:22 UTC
Source health
Healthy
Provenance
es_ree_demand_access_capacityrecord SERNA 220 · payload sha256 149dbaf707f0…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: limiting criteria
Din1_Zona
Operator note: scope
gross margin, before capacity not grantable at the transmission network
Operator note: temporary access limitation
No

Offtake · Load (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_dem_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: margen_total_cep_sh
Methodology
es_ree_dem_rdt_2026REE demand access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_demand_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-09-30 09:22 UTC
Source health
Healthy
Provenance
es_ree_demand_access_capacityrecord SERNA 220 · payload sha256 149dbaf707f0…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: limiting criteria
Din2_Zona
Operator note: scope
gross margin, before capacity not grantable at the transmission network
Operator note: temporary access limitation
No

Offtake · Load (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_dem_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: margen_total_no_cep
Methodology
es_ree_dem_rdt_2026REE demand access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_demand_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-09-30 09:22 UTC
Source health
Healthy
Provenance
es_ree_demand_access_capacityrecord SERNA 220 · payload sha256 149dbaf707f0…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: limiting criteria
Din1_Zona
Operator note: scope
gross margin, before capacity not grantable at the transmission network
Operator note: temporary access limitation
No

Offtake · Load (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_dem_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: cep_ch
Methodology
es_ree_dem_rdt_2026REE demand access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_demand_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-09-30 09:22 UTC
Source health
Healthy
Provenance
es_ree_demand_access_capacityrecord SERNA 220 · payload sha256 149dbaf707f0…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: limiting criteria
Din1_Zona
Operator note: temporary access limitation
No

Offtake · Load (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_dem_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: cep_sh
Methodology
es_ree_dem_rdt_2026REE demand access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_demand_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-09-30 09:22 UTC
Source health
Healthy
Provenance
es_ree_demand_access_capacityrecord SERNA 220 · payload sha256 149dbaf707f0…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: limiting criteria
Din2_Zona
Operator note: temporary access limitation
No

Offtake · Load (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_dem_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: no_cep
Methodology
es_ree_dem_rdt_2026REE demand access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_demand_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-09-30 09:22 UTC
Source health
Healthy
Provenance
es_ree_demand_access_capacityrecord SERNA 220 · payload sha256 149dbaf707f0…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: limiting criteria
Din1_Zona
Operator note: temporary access limitation
No

Offtake · Load (any) · Requested

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_dem_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: rdt
Methodology
es_ree_dem_rdt_2026REE demand access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_demand_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-09-30 09:22 UTC
Source health
Healthy
Provenance
es_ree_demand_access_capacityrecord SERNA 220 · payload sha256 149dbaf707f0…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required

Offtake · Load (any) · Reserved

195 MW

Granted

The operator's latest published dataset reports 195 MW under methodology es_ree_dem_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: valor_referencia_rdd
Methodology
es_ree_dem_rdt_2026REE demand access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_demand_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-09-30 09:22 UTC
Source health
Healthy
Provenance
es_ree_demand_access_capacityrecord SERNA 220 · payload sha256 149dbaf707f0…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: reference value agreed with dso
SI
Operator note: reserved for
consumption of the underlying distribution network (reference value)

Offtake · Load (any) · Total

622 MW

Granted

The operator's latest published dataset reports 622 MW under methodology es_ree_dem_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: estatico_nodal
Methodology
es_ree_dem_rdt_2026REE demand access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_demand_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-09-30 09:22 UTC
Source health
Healthy
Provenance
es_ree_demand_access_capacityrecord SERNA 220 · payload sha256 149dbaf707f0…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: criterion
static (N and N-X)
Operator note: temporary access limitation
No

Offtake · Load (any) · Total

219 MW

Granted

The operator's latest published dataset reports 219 MW under methodology es_ree_dem_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: wscr_nodal
Methodology
es_ree_dem_rdt_2026REE demand access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_demand_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-09-30 09:22 UTC
Source health
Healthy
Provenance
es_ree_demand_access_capacityrecord SERNA 220 · payload sha256 149dbaf707f0…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: criterion
short-circuit power (WSCR); applies to demand with a power-electronics interface (CEP) only
Operator note: system security effect
Superación valor máx Icc

Offtake · Load (any) · Unknown

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_dem_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: no_otorgable_cep_ch
Methodology
es_ree_dem_rdt_2026REE demand access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_demand_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-09-30 09:22 UTC
Source health
Healthy
Provenance
es_ree_demand_access_capacityrecord SERNA 220 · payload sha256 149dbaf707f0…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required

Offtake · Load (any) · Unknown

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_dem_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: no_otorgable_cep_sh
Methodology
es_ree_dem_rdt_2026REE demand access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_demand_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-09-30 09:22 UTC
Source health
Healthy
Provenance
es_ree_demand_access_capacityrecord SERNA 220 · payload sha256 149dbaf707f0…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required

Offtake · Load (any) · Unknown

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_dem_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: no_otorgable_no_cep
Methodology
es_ree_dem_rdt_2026REE demand access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_demand_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-09-30 09:22 UTC
Source health
Healthy
Provenance
es_ree_demand_access_capacityrecord SERNA 220 · payload sha256 149dbaf707f0…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required

Offtake · Other storage · Allocated

14 MW

Granted

The operator's latest published dataset reports 14 MW under methodology es_ree_dem_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: adicional_valor_referencia
Methodology
es_ree_dem_rdt_2026REE demand access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_demand_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-09-30 09:22 UTC
Source health
Healthy
Provenance
es_ree_demand_access_capacityrecord SERNA 220 · payload sha256 149dbaf707f0…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required

Offtake · Other storage · Allocated

14 MW

Granted

The operator's latest published dataset reports 14 MW under methodology es_ree_dem_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: rdt
Methodology
es_ree_dem_rdt_2026REE demand access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_demand_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-09-30 09:22 UTC
Source health
Healthy
Provenance
es_ree_demand_access_capacityrecord SERNA 220 · payload sha256 149dbaf707f0…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required

Offtake · Other storage · Allocated

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_dem_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: aceptabilidad_rdd
Methodology
es_ree_dem_rdt_2026REE demand access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_demand_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-09-30 09:22 UTC
Source health
Healthy
Provenance
es_ree_demand_access_capacityrecord SERNA 220 · payload sha256 149dbaf707f0…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required

Offtake · Other storage · Allocated

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_dem_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: aceptabilidad_rdd_fuera_referencia
Methodology
es_ree_dem_rdt_2026REE demand access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_demand_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-09-30 09:22 UTC
Source health
Healthy
Provenance
es_ree_demand_access_capacityrecord SERNA 220 · payload sha256 149dbaf707f0…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required

Offtake · Other storage · Available

808 MW

Granted

The operator's latest published dataset reports 808 MW under methodology es_ree_dem_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: estatico_margen
Methodology
es_ree_dem_rdt_2026REE demand access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_demand_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-09-30 09:22 UTC
Source health
Healthy
Provenance
es_ree_demand_access_capacityrecord SERNA 220 · payload sha256 149dbaf707f0…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: criterion
static (N and N-X)

Offtake · Other storage · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_dem_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: margen_total_cep
Methodology
es_ree_dem_rdt_2026REE demand access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_demand_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-09-30 09:22 UTC
Source health
Healthy
Provenance
es_ree_demand_access_capacityrecord SERNA 220 · payload sha256 149dbaf707f0…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: limiting criteria
Din1_Zona
Operator note: scope
gross margin, before capacity not grantable at the transmission network
Operator note: temporary access limitation
No

Offtake · Other storage · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_dem_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: margen_total_no_cep
Methodology
es_ree_dem_rdt_2026REE demand access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_demand_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-09-30 09:22 UTC
Source health
Healthy
Provenance
es_ree_demand_access_capacityrecord SERNA 220 · payload sha256 149dbaf707f0…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: limiting criteria
Din1_Zona
Operator note: scope
gross margin, before capacity not grantable at the transmission network
Operator note: temporary access limitation
No

Offtake · Other storage · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_dem_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: cep
Methodology
es_ree_dem_rdt_2026REE demand access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_demand_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-09-30 09:22 UTC
Source health
Healthy
Provenance
es_ree_demand_access_capacityrecord SERNA 220 · payload sha256 149dbaf707f0…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: limiting criteria
Din1_Zona
Operator note: temporary access limitation
No

Offtake · Other storage · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_dem_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: no_cep
Methodology
es_ree_dem_rdt_2026REE demand access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_demand_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-09-30 09:22 UTC
Source health
Healthy
Provenance
es_ree_demand_access_capacityrecord SERNA 220 · payload sha256 149dbaf707f0…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: limiting criteria
Din1_Zona
Operator note: temporary access limitation
No

Offtake · Other storage · Requested

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_dem_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: rdt
Methodology
es_ree_dem_rdt_2026REE demand access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_demand_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-09-30 09:22 UTC
Source health
Healthy
Provenance
es_ree_demand_access_capacityrecord SERNA 220 · payload sha256 149dbaf707f0…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required

Offtake · Other storage · Total

1,017 MW

Granted

The operator's latest published dataset reports 1017 MW under methodology es_ree_dem_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: estatico_nodal
Methodology
es_ree_dem_rdt_2026REE demand access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_demand_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-09-30 09:22 UTC
Source health
Healthy
Provenance
es_ree_demand_access_capacityrecord SERNA 220 · payload sha256 149dbaf707f0…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: criterion
static (N and N-X)

Offtake · Other storage · Unknown

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_dem_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: no_otorgable_cep
Methodology
es_ree_dem_rdt_2026REE demand access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_demand_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-09-30 09:22 UTC
Source health
Healthy
Provenance
es_ree_demand_access_capacityrecord SERNA 220 · payload sha256 149dbaf707f0…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required

Offtake · Other storage · Unknown

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_dem_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: no_otorgable_no_cep
Methodology
es_ree_dem_rdt_2026REE demand access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_demand_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-09-30 09:22 UTC
Source health
Healthy
Provenance
es_ree_demand_access_capacityrecord SERNA 220 · payload sha256 149dbaf707f0…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required

History

Served series only

Injection · Generation (any) · Available

current 0 MW

26 Sep 2026: 0 MW
26 Sep 2026range 0 to 0 MW2 Oct 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current0 MW

Time axis: when we observed each value, not the operator’s effective date.

Injection · Generation (any) · Available

current 0 MW

26 Sep 2026: 0 MW
26 Sep 2026range 0 to 0 MW2 Oct 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current0 MW

Time axis: when we observed each value, not the operator’s effective date.

Injection · Other storage · Available

current 0 MW

26 Sep 2026: 0 MW
26 Sep 2026range 0 to 0 MW2 Oct 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current0 MW

Time axis: when we observed each value, not the operator’s effective date.

Injection · Other storage · Available

current 0 MW

26 Sep 2026: 0 MW
26 Sep 2026range 0 to 0 MW2 Oct 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current0 MW

Time axis: when we observed each value, not the operator’s effective date.

Injection · Generation (any) · Allocated

current 343.35 MW

26 Sep 2026: 343.35 MW
26 Sep 2026range 343.35 to 343.35 MW2 Oct 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current343.35 MW

Time axis: when we observed each value, not the operator’s effective date.

Injection · Generation (any) · Requested

current 10.9 MW

26 Sep 2026: 10.9 MW
26 Sep 2026range 10.9 to 10.9 MW2 Oct 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current10.9 MW

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Load (any) · Total

current 219 MW

26 Sep 2026: 219 MW
26 Sep 2026range 219 to 219 MW2 Oct 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current219 MW

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Load (any) · Available

current 219 MW

26 Sep 2026: 219 MW
26 Sep 2026range 219 to 219 MW2 Oct 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current219 MW

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Load (any) · Total

current 622 MW

26 Sep 2026: 622 MW
26 Sep 2026range 622 to 622 MW2 Oct 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current622 MW

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Load (any) · Available

current 427 MW

26 Sep 2026: 427 MW
26 Sep 2026range 427 to 427 MW2 Oct 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current427 MW

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Other storage · Total

current 1,017 MW

26 Sep 2026: 1,017 MW
26 Sep 2026range 1,017 to 1,017 MW2 Oct 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current1,017 MW

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Other storage · Available

current 808 MW

26 Sep 2026: 808 MW
26 Sep 2026range 808 to 808 MW2 Oct 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current808 MW

Time axis: when we observed each value, not the operator’s effective date.

The first 12 of 92 served series with a history. The history route returns every one of them.

Through the API

curl "https://api.gridcapacityapi.com/v1/grid-assets/node_06gdrjgzj1vzkcs39bb7z2mfe8/capacity" \  -H "Authorization: Bearer gc_live_..."
SERNA 220 kV node: grid capacity (Red Eléctrica de España, S.A.U.) · GridCapacity API