es_ree_generation_access_capacity

REE: Capacidad de acceso de generación en la red de transporte

Published by Red Eléctrica de España, S.A.U. / ES / Monthly

Grantedcommercial_use_with_attributionHealthy

Generation and storage (injection) access capacity in MW at each of REE's 937 transmission nodes, from its monthly study: nodal capacity and unoccupied margin by criterion (short-circuit WSCR, static, dynamic, bay limits), granted and pending capacity by module type, gross margin, capacity not available to requests with the reason, net capacity available for requests by connection network, and capacity released for self-consumption.

REE: Capacidad de acceso de generación en la red de transporte on a map

The 936 located assets in this publication, coloured by the spare capacity Red Eléctrica de España, S.A.U. publishes for each today. Click a point for its figure.

The map of Europe →

Loading the map…

What is withheld, and why

Nothing is withheld. Values are served with the attribution the licence asks for: Fuente: Red Eléctrica de España (REE), capacidad de acceso. Keep it with any figure you show.

Switched to commercial_use_with_attribution on 2026-10-02 on the owner's report that the operator gave permission by telephone. No written confirmation is on file: ask for one, and an objection from the operator means rights_override = blocked the same day. The evidence below is the operator's published terms as read before the call. Before: REE's legal notice claims the site's information including its databases; exploitation needs prior written authorisation, and reuse citing REE is allowed only for informative, non-commercial purposes. A publication duty (Circular 1/2021 art. 12) is not a reuse licence. Archived, never served, until REE authorises commercial reuse in writing (research/dossiers/es.md §13 Q2).

Licence and rights evidence

Attribution
Fuente: Red Eléctrica de España (REE), capacidad de accesorequired
Technical access
Yes
Commercial use
Yes
May be cached
Yes
May be redistributed
Yes
Derived data allowed
Yes

Evidence

Methodology

1 version(s)

REE generation access-capacity study, transmission nodes

es_ree_gen_rdt_2026 · vCircular 1/2021 and its Especificaciones de Detalle (27-06-2024); RDL 7/2026

REE's monthly study of the generation access capacity of each transmission node for the final horizon year of the transmission plan: nodal capacity and margin under the short-circuit (WSCR), static (N and N-X) and dynamic criteria and the per-bay limits; the gross margin as their minimum; the capacity held back for tenders and Just Transition nodes; and the net capacity available for new requests by module type and connection network.

Capacity basis
operator calculated
Network state
unknown
Binding
No
Additive across assets
No. Do not sum these figures.
The method accounts for
reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Comparability class
es_rdt_generation_access_cir1_2021

The operator’s own caveats

  • REE: the publication is informative; the specific study of each individual request always prevails, and granted capacity is not a guaranteed production capacity.

How the publication maps to the model

availability types
["total","available","allocated","requested","unknown"]
binding
false
directions
["injection"]
firmness
["unknown"]
geometry precision
none
includes reserved projects
null
non additive
true
notes
["One node per 'Nombre y tensión del nudo' (unique; binudo halves are 'BEGUES (BEGUES B) 220'), identifier es_ree_node, which CNMC's transmission layer carries as NUDO_AFECCION_RDT (936/937 nodes join). The file has no coordinates; the CNMC layer does.","Every value is one column of the file, its series variant naming the column: per criterion the nodal capacity (total) and the unoccupied margin (available), in wscr_* (short-circuit criterion, power-park modules only), estatico_* (static, generation and storage separately), dinamico_* (dynamic, with the node's internal configuration limit), posicion_* (bay limits); granted (allocated) and pending (requested) by module type, for mge (all modules), mges (synchronous), mpe (power park, with/without WSCR effect), gen (generation), alm (storage); margen_total_* (the gross margin, the minimum over the criteria); no_disponible_* (capacity not available to ordinary requests: tender or Just-Transition reservations, 'no connection possible'; availability unknown, with REE's reason); the net capacity available for requests by connection network (mges_rdt, mpe_rdt, mges_rdd, mpe_rdd); autoconsumo_* (capacity released for self-consumption only, RDL 7/2026).","MGES is a synchronous power-generating module, MPE a power park module (inverter-connected: PV, wind, most batteries); the vocabulary has neither, so both are generic_generation (storage_other for storage) with the module type in the variant.","'N/A' is published as null with REE's label; a blank bay limit (501 nodes) is 'not published', never 0. The criteria that limit each margin, zone ids, the reservation reason and the governing regulation travel in details.","Numbers use '.' as a thousands separator ('2.406' is 2,406 MW, checked against the XLSX's numeric cell) and have no decimals."]
spatial scope
node
technologies
["generic_generation","storage_other"]
units
["MW"]

Query this source

curl "https://api.gridcapacityapi.com/v1/capacity/search?source=es_ree_generation_access_capacity&limit=20" \  -H "Authorization: Bearer gc_live_..."