Skip to content

Node / 400 kV / transmission

PUENTES G.R.

Red Eléctrica de España, S.A.U. / Pontes de García Rodríguez, As, Coruña, A, Spain

Latest published values

92 served · 0 withheld

Each row is what the operator’s latest published dataset reports for one combination of direction, technology, measure, firmness and horizon. Hosting-capacity figures are indicative and reflect what operators publish. They are not a connection offer; only the operator can confirm capacity for a specific request.

Latest published capacity values, one row per series
DirectionTechnologyMeasureValueFirmnessHorizonSource date
InjectionGeneration (any)Allocated2,193 MWUnknownNow (snapshot)variant: mge3 Nov 2026
InjectionGeneration (any)Allocated2,193 MWUnknownNow (snapshot)variant: gen3 Nov 2026
InjectionGeneration (any)Allocated2,192.92 MWUnknownNow (snapshot)variant: mge11 Nov 2026
InjectionGeneration (any)Allocated1,111 MWUnknownNow (snapshot)variant: mpe3 Nov 2026
InjectionGeneration (any)Allocated1,082 MWUnknownNow (snapshot)variant: mges1 Sep 2026
InjectionGeneration (any)Allocated651 MWUnknownNow (snapshot)variant: mpe_con_wscr3 Nov 2026
InjectionGeneration (any)Allocated460 MWUnknownNow (snapshot)variant: mpe_sin_wscr3 Nov 2026
InjectionGeneration (any)Allocated0 MWUnknownNow (snapshot)variant: autoconsumo_mges1 Sep 2026
InjectionGeneration (any)Allocated0 MWUnknownNow (snapshot)variant: autoconsumo_mpe1 Sep 2026
InjectionGeneration (any)Available1,165 MWUnknownNow (snapshot)variant: estatico_margen3 Nov 2026
InjectionGeneration (any)Available223 MWUnknownNow (snapshot)variant: wscr_margen3 Nov 2026
InjectionGeneration (any)Available0 MWUnknownNow (snapshot)variant: mpe_rdt9 Sep 2026
InjectionGeneration (any)Available0 MWUnknownNow (snapshot)variant: mges_rdt9 Sep 2026
InjectionGeneration (any)Available0 MWUnknownNow (snapshot)variant: dinamico_margen1 Sep 2026
InjectionGeneration (any)Available0 MWUnknownNow (snapshot)variant: posicion_margen_mges1 Sep 2026
InjectionGeneration (any)Available0 MWUnknownNow (snapshot)variant: posicion_margen_mpe1 Sep 2026
InjectionGeneration (any)Available0 MWUnknownNow (snapshot)variant: margen_total_mges1 Sep 2026
InjectionGeneration (any)Available0 MWUnknownNow (snapshot)variant: margen_total_mpe1 Sep 2026
InjectionGeneration (any)Available0 MWUnknownNow (snapshot)variant: mges_rdt1 Sep 2026
InjectionGeneration (any)Available0 MWUnknownNow (snapshot)variant: mpe_rdt1 Sep 2026
InjectionGeneration (any)Available0 MWUnknownNow (snapshot)variant: mges_rdd1 Sep 2026
InjectionGeneration (any)Available0 MWUnknownNow (snapshot)variant: mpe_rdd1 Sep 2026
InjectionGeneration (any)Available0 MWUnknownNow (snapshot)variant: autoconsumo_mges1 Sep 2026
InjectionGeneration (any)Available0 MWUnknownNow (snapshot)variant: autoconsumo_mpe1 Sep 2026
InjectionGeneration (any)Requested0 MWUnknownNow (snapshot)variant: mges1 Sep 2026
InjectionGeneration (any)Requested0 MWUnknownNow (snapshot)variant: mpe_con_wscr1 Sep 2026
InjectionGeneration (any)Requested0 MWUnknownNow (snapshot)variant: mge1 Oct 2026
InjectionGeneration (any)Requested0 MWUnknownNow (snapshot)variant: mpe_sin_wscr1 Oct 2026
InjectionGeneration (any)Requested0 MWUnknownNow (snapshot)variant: mpe1 Oct 2026
InjectionGeneration (any)Requested0 MWUnknownNow (snapshot)variant: gen1 Oct 2026
InjectionGeneration (any)Requested0 MWUnknownNow (snapshot)variant: mge14 Oct 2026
InjectionGeneration (any)Total4,200 MWUnknownNow (snapshot)variant: posicion_maximo1 Sep 2026
InjectionGeneration (any)Total3,358 MWUnknownNow (snapshot)variant: estatico_nodal1 Sep 2026
InjectionGeneration (any)Total873 MWUnknownNow (snapshot)variant: wscr_nodal1 Oct 2026
InjectionGeneration (any)Total459 MWUnknownNow (snapshot)variant: dinamico_nodal1 Sep 2026
InjectionGeneration (any)Total0 MWUnknownNow (snapshot)variant: autoconsumo_mges1 Sep 2026
InjectionGeneration (any)Total0 MWUnknownNow (snapshot)variant: autoconsumo_mpe1 Sep 2026
InjectionGeneration (any)Totalnot statedUnknownNow (snapshot)variant: dinamico_limitacion_interna1 Sep 2026
InjectionGeneration (any)Unknown0 MWUnknownNow (snapshot)variant: no_disponible_mges1 Sep 2026
InjectionGeneration (any)Unknown0 MWUnknownNow (snapshot)variant: no_disponible_mpe1 Sep 2026
InjectionOther storageAllocated0 MWUnknownNow (snapshot)variant: alm1 Sep 2026
InjectionOther storageAvailable1,583 MWUnknownNow (snapshot)variant: estatico_margen3 Nov 2026
InjectionOther storageAvailable0 MWUnknownNow (snapshot)variant: mpe_rdt9 Sep 2026
InjectionOther storageAvailable0 MWUnknownNow (snapshot)variant: mges_rdt9 Sep 2026
InjectionOther storageAvailable0 MWUnknownNow (snapshot)variant: margen_total_mges1 Sep 2026
InjectionOther storageAvailable0 MWUnknownNow (snapshot)variant: margen_total_mpe1 Sep 2026
InjectionOther storageAvailable0 MWUnknownNow (snapshot)variant: mges_rdt1 Sep 2026
InjectionOther storageAvailable0 MWUnknownNow (snapshot)variant: mpe_rdt1 Sep 2026
InjectionOther storageAvailable0 MWUnknownNow (snapshot)variant: mges_rdd1 Sep 2026
InjectionOther storageAvailable0 MWUnknownNow (snapshot)variant: mpe_rdd1 Sep 2026
InjectionOther storageRequested0 MWUnknownNow (snapshot)variant: alm1 Sep 2026
InjectionOther storageTotal3,776 MWUnknownNow (snapshot)variant: estatico_nodal1 Sep 2026
InjectionOther storageUnknown0 MWUnknownNow (snapshot)variant: no_disponible_mges1 Sep 2026
InjectionOther storageUnknown0 MWUnknownNow (snapshot)variant: no_disponible_mpe1 Sep 2026
OfftakeLoad (any)Allocated0 MWUnknownNow (snapshot)variant: adicional_valor_referencia1 Sep 2026
OfftakeLoad (any)Allocated0 MWUnknownNow (snapshot)variant: cep_wscr1 Sep 2026
OfftakeLoad (any)Allocated0 MWUnknownNow (snapshot)variant: rdt1 Sep 2026
OfftakeLoad (any)Allocated0 MWUnknownNow (snapshot)variant: aceptabilidad_rdd1 Sep 2026
OfftakeLoad (any)Allocated0 MWUnknownNow (snapshot)variant: aceptabilidad_rdd_fuera_referencia1 Sep 2026
OfftakeLoad (any)Allocated0 MWUnknownNow (snapshot)variant: ch_rdt1 Sep 2026
OfftakeLoad (any)Allocated0 MWUnknownNow (snapshot)variant: sh_rdt1 Sep 2026
OfftakeLoad (any)Allocated0 MWUnknownNow (snapshot)variant: ch_aceptabilidad_rdd1 Sep 2026
OfftakeLoad (any)Allocated0 MWUnknownNow (snapshot)variant: sh_aceptabilidad_rdd1 Sep 2026
OfftakeLoad (any)Available1,413 MWUnknownNow (snapshot)variant: estatico_margen1 Sep 2026
OfftakeLoad (any)Available458 MWUnknownNow (snapshot)variant: dinamico1_margen1 Sep 2026
OfftakeLoad (any)Available458 MWUnknownNow (snapshot)variant: margen_total_no_cep1 Sep 2026
OfftakeLoad (any)Available458 MWUnknownNow (snapshot)variant: no_cep1 Sep 2026
OfftakeLoad (any)Available346 MWUnknownNow (snapshot)variant: wscr_margen1 Sep 2026
OfftakeLoad (any)Available346 MWUnknownNow (snapshot)variant: margen_total_cep_ch1 Sep 2026
OfftakeLoad (any)Available346 MWUnknownNow (snapshot)variant: cep_ch1 Sep 2026
OfftakeLoad (any)Available0 MWUnknownNow (snapshot)variant: dinamico2_margen1 Sep 2026
OfftakeLoad (any)Available0 MWUnknownNow (snapshot)variant: margen_total_cep_sh1 Sep 2026
OfftakeLoad (any)Available0 MWUnknownNow (snapshot)variant: cep_sh1 Sep 2026
OfftakeLoad (any)Requested0 MWUnknownNow (snapshot)variant: rdt1 Sep 2026
OfftakeLoad (any)Reserved450 MWUnknownNow (snapshot)variant: valor_referencia_rdd1 Sep 2026
OfftakeLoad (any)Total1,863 MWUnknownNow (snapshot)variant: estatico_nodal1 Sep 2026
OfftakeLoad (any)Total346 MWUnknownNow (snapshot)variant: wscr_nodal1 Sep 2026
OfftakeLoad (any)Unknown0 MWUnknownNow (snapshot)variant: no_otorgable_cep_ch1 Sep 2026
OfftakeLoad (any)Unknown0 MWUnknownNow (snapshot)variant: no_otorgable_cep_sh1 Sep 2026
OfftakeLoad (any)Unknown0 MWUnknownNow (snapshot)variant: no_otorgable_no_cep1 Sep 2026
OfftakeOther storageAllocated0 MWUnknownNow (snapshot)variant: adicional_valor_referencia1 Sep 2026
OfftakeOther storageAllocated0 MWUnknownNow (snapshot)variant: rdt1 Sep 2026
OfftakeOther storageAllocated0 MWUnknownNow (snapshot)variant: aceptabilidad_rdd1 Sep 2026
OfftakeOther storageAllocated0 MWUnknownNow (snapshot)variant: aceptabilidad_rdd_fuera_referencia1 Sep 2026
OfftakeOther storageAvailable2,920 MWUnknownNow (snapshot)variant: estatico_margen1 Sep 2026
OfftakeOther storageAvailable458 MWUnknownNow (snapshot)variant: margen_total_cep1 Sep 2026
OfftakeOther storageAvailable458 MWUnknownNow (snapshot)variant: margen_total_no_cep1 Sep 2026
OfftakeOther storageAvailable458 MWUnknownNow (snapshot)variant: cep1 Sep 2026
OfftakeOther storageAvailable458 MWUnknownNow (snapshot)variant: no_cep1 Sep 2026
OfftakeOther storageRequested0 MWUnknownNow (snapshot)variant: rdt1 Sep 2026
OfftakeOther storageTotal3,370 MWUnknownNow (snapshot)variant: estatico_nodal1 Sep 2026
OfftakeOther storageUnknown0 MWUnknownNow (snapshot)variant: no_otorgable_cep1 Sep 2026
OfftakeOther storageUnknown0 MWUnknownNow (snapshot)variant: no_otorgable_no_cep1 Sep 2026

Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-11-03)Origen de los datos: Comisión Nacional de los Mercados y la Competencia (CNMC) (last updated 2026-11-11)Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-10-01)Origen de los datos: Comisión Nacional de los Mercados y la Competencia (CNMC) (last updated 2026-09-09)Origen de los datos: Comisión Nacional de los Mercados y la Competencia (CNMC) (last updated 2026-10-14)

What each value means

Methodology, both clocks, provenance and rights

Injection · Generation (any) · Allocated

2,193 MW

Granted

The operator's latest published dataset reports 2193 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: mge
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
3 Nov 2026
Retrieved / confirmed
2026-11-03 11:31 UTClast confirmed unchanged 2026-11-21 13:48 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord PUENTES G.R. 400 · payload sha256 b767e717e60b…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-11-03)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: module scope
MGE: all power-generating modules (MGES + MPE, generation and storage)

Injection · Generation (any) · Allocated

2,193 MW

Granted

The operator's latest published dataset reports 2193 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: gen
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
3 Nov 2026
Retrieved / confirmed
2026-11-03 11:31 UTClast confirmed unchanged 2026-11-21 13:48 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord PUENTES G.R. 400 · payload sha256 b767e717e60b…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-11-03)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: module scope
GEN: generation installations, storage excluded

Injection · Generation (any) · Allocated

2,192.92 MW

Granted

The operator's latest published dataset reports 2192.92 MW under methodology es_cnmc_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: mge
Methodology
es_cnmc_gen_rdt_2026Generation access capacity at the transmission network (REE's figures in CNMC's map)basis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
11 Nov 2026
Retrieved / confirmed
2026-11-12 01:53 UTClast confirmed unchanged 2026-11-21 11:03 UTC
Source health
Healthy
Provenance
es_cnmc_generation_capacityrecord rdt:PUENTES G.R. 400 · payload sha256 00b22e9a85e7…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Origen de los datos: Comisión Nacional de los Mercados y la Competencia (CNMC) (last updated 2026-11-11)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
CAP_OCUPADA

Injection · Generation (any) · Allocated

1,111 MW

Granted

The operator's latest published dataset reports 1111 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: mpe
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
3 Nov 2026
Retrieved / confirmed
2026-11-03 11:31 UTClast confirmed unchanged 2026-11-21 13:48 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord PUENTES G.R. 400 · payload sha256 b767e717e60b…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-11-03)
Decision context
Not binding · indicative · a formal connection study is required

Injection · Generation (any) · Allocated

1,082 MW

Granted

The operator's latest published dataset reports 1082 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: mges
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-11-21 13:48 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord PUENTES G.R. 400 · payload sha256 9453de37e5a3…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required

Injection · Generation (any) · Allocated

651 MW

Granted

The operator's latest published dataset reports 651 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: mpe_con_wscr
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
3 Nov 2026
Retrieved / confirmed
2026-11-03 11:31 UTClast confirmed unchanged 2026-11-21 13:48 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord PUENTES G.R. 400 · payload sha256 b767e717e60b…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-11-03)
Decision context
Not binding · indicative · a formal connection study is required

Injection · Generation (any) · Allocated

460 MW

Granted

The operator's latest published dataset reports 460 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: mpe_sin_wscr
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
3 Nov 2026
Retrieved / confirmed
2026-11-03 11:31 UTClast confirmed unchanged 2026-11-21 13:48 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord PUENTES G.R. 400 · payload sha256 b767e717e60b…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-11-03)
Decision context
Not binding · indicative · a formal connection study is required

Injection · Generation (any) · Allocated

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: autoconsumo_mges
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-11-21 13:48 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord PUENTES G.R. 400 · payload sha256 9453de37e5a3…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: eligibility
self-consumption requests only (RDL 7/2026)

Injection · Generation (any) · Allocated

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: autoconsumo_mpe
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-11-21 13:48 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord PUENTES G.R. 400 · payload sha256 9453de37e5a3…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: eligibility
self-consumption requests only (RDL 7/2026)

Injection · Generation (any) · Available

1,165 MW

Granted

The operator's latest published dataset reports 1165 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: estatico_margen
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
3 Nov 2026
Retrieved / confirmed
2026-11-03 11:31 UTClast confirmed unchanged 2026-11-21 13:48 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord PUENTES G.R. 400 · payload sha256 b767e717e60b…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-11-03)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: criterion
static (N and N-X)

Injection · Generation (any) · Available

223 MW

Granted

The operator's latest published dataset reports 223 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: wscr_margen
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
3 Nov 2026
Retrieved / confirmed
2026-11-03 11:31 UTClast confirmed unchanged 2026-11-21 13:48 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord PUENTES G.R. 400 · payload sha256 b767e717e60b…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-11-03)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: criterion
short-circuit power (WSCR); applies to power park modules (MPE) only

Injection · Generation (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_cnmc_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: mpe_rdt
Methodology
es_cnmc_gen_rdt_2026Generation access capacity at the transmission network (REE's figures in CNMC's map)basis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
9 Sep 2026
Retrieved / confirmed
2026-09-26 05:57 UTClast confirmed unchanged 2026-11-21 11:03 UTC
Source health
Healthy
Provenance
es_cnmc_generation_capacityrecord rdt:PUENTES G.R. 400 · payload sha256 1bf4a9e7e78c…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Origen de los datos: Comisión Nacional de los Mercados y la Competencia (CNMC) (last updated 2026-09-09)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: regulatory reservation
true
Operator note: source field
CAP_DISPONIBLE_MPE

Injection · Generation (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_cnmc_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: mges_rdt
Methodology
es_cnmc_gen_rdt_2026Generation access capacity at the transmission network (REE's figures in CNMC's map)basis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
9 Sep 2026
Retrieved / confirmed
2026-09-26 05:57 UTClast confirmed unchanged 2026-11-21 11:03 UTC
Source health
Healthy
Provenance
es_cnmc_generation_capacityrecord rdt:PUENTES G.R. 400 · payload sha256 1bf4a9e7e78c…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Origen de los datos: Comisión Nacional de los Mercados y la Competencia (CNMC) (last updated 2026-09-09)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: regulatory reservation
true
Operator note: source field
CAP_DISPONIBLE_MGES

Injection · Generation (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: dinamico_margen
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-11-21 13:48 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord PUENTES G.R. 400 · payload sha256 9453de37e5a3…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: criterion
dynamic stability

Injection · Generation (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: posicion_margen_mges
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-11-21 13:48 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord PUENTES G.R. 400 · payload sha256 9453de37e5a3…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required

Injection · Generation (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: posicion_margen_mpe
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-11-21 13:48 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord PUENTES G.R. 400 · payload sha256 9453de37e5a3…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required

Injection · Generation (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: margen_total_mges
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-11-21 13:48 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord PUENTES G.R. 400 · payload sha256 9453de37e5a3…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: limiting criteria
D_Nudo
Operator note: reservation
NTJ
Operator note: scope
gross margin, before capacity not available for requests

Injection · Generation (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: margen_total_mpe
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-11-21 13:48 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord PUENTES G.R. 400 · payload sha256 9453de37e5a3…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: limiting criteria
D_Nudo
Operator note: reservation
NTJ
Operator note: scope
gross margin, before capacity not available for requests

Injection · Generation (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: mges_rdt
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-11-21 13:48 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord PUENTES G.R. 400 · payload sha256 9453de37e5a3…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: limiting criteria
D_Nudo
Operator note: reservation
NTJ

Injection · Generation (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: mpe_rdt
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-11-21 13:48 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord PUENTES G.R. 400 · payload sha256 9453de37e5a3…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: limiting criteria
D_Nudo
Operator note: reservation
NTJ

Injection · Generation (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: mges_rdd
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-11-21 13:48 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord PUENTES G.R. 400 · payload sha256 9453de37e5a3…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: limiting criteria
D_Nudo
Operator note: reservation
NTJ

Injection · Generation (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: mpe_rdd
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-11-21 13:48 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord PUENTES G.R. 400 · payload sha256 9453de37e5a3…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: limiting criteria
D_Nudo
Operator note: reservation
NTJ

Injection · Generation (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: autoconsumo_mges
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-11-21 13:48 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord PUENTES G.R. 400 · payload sha256 9453de37e5a3…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: eligibility
self-consumption requests only (RDL 7/2026)

Injection · Generation (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: autoconsumo_mpe
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-11-21 13:48 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord PUENTES G.R. 400 · payload sha256 9453de37e5a3…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: eligibility
self-consumption requests only (RDL 7/2026)

Injection · Generation (any) · Requested

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: mges
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-11-21 13:48 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord PUENTES G.R. 400 · payload sha256 9453de37e5a3…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required

Injection · Generation (any) · Requested

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: mpe_con_wscr
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-11-21 13:48 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord PUENTES G.R. 400 · payload sha256 9453de37e5a3…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required

Injection · Generation (any) · Requested

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: mge
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Oct 2026
Retrieved / confirmed
2026-10-01 07:14 UTClast confirmed unchanged 2026-11-21 13:48 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord PUENTES G.R. 400 · payload sha256 9984c7e55781…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-10-01)
Decision context
Not binding · indicative · a formal connection study is required

Injection · Generation (any) · Requested

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: mpe_sin_wscr
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Oct 2026
Retrieved / confirmed
2026-10-01 07:14 UTClast confirmed unchanged 2026-11-21 13:48 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord PUENTES G.R. 400 · payload sha256 9984c7e55781…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-10-01)
Decision context
Not binding · indicative · a formal connection study is required

Injection · Generation (any) · Requested

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: mpe
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Oct 2026
Retrieved / confirmed
2026-10-01 07:14 UTClast confirmed unchanged 2026-11-21 13:48 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord PUENTES G.R. 400 · payload sha256 9984c7e55781…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-10-01)
Decision context
Not binding · indicative · a formal connection study is required

Injection · Generation (any) · Requested

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: gen
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Oct 2026
Retrieved / confirmed
2026-10-01 07:14 UTClast confirmed unchanged 2026-11-21 13:48 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord PUENTES G.R. 400 · payload sha256 9984c7e55781…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-10-01)
Decision context
Not binding · indicative · a formal connection study is required

Injection · Generation (any) · Requested

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_cnmc_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: mge
Methodology
es_cnmc_gen_rdt_2026Generation access capacity at the transmission network (REE's figures in CNMC's map)basis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
14 Oct 2026
Retrieved / confirmed
2026-10-14 11:09 UTClast confirmed unchanged 2026-11-21 11:03 UTC
Source health
Healthy
Provenance
es_cnmc_generation_capacityrecord rdt:PUENTES G.R. 400 · payload sha256 f60744bd414f…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Origen de los datos: Comisión Nacional de los Mercados y la Competencia (CNMC) (last updated 2026-10-14)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
CAP_ADMITIDA_NO_RESUELTA

Injection · Generation (any) · Total

4,200 MW

Granted

The operator's latest published dataset reports 4200 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: posicion_maximo
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-11-21 13:48 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord PUENTES G.R. 400 · payload sha256 9453de37e5a3…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required

Injection · Generation (any) · Total

3,358 MW

Granted

The operator's latest published dataset reports 3358 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: estatico_nodal
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-11-21 13:48 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord PUENTES G.R. 400 · payload sha256 9453de37e5a3…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: criterion
static (N and N-X)

Injection · Generation (any) · Total

873 MW

Granted

The operator's latest published dataset reports 873 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: wscr_nodal
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Oct 2026
Retrieved / confirmed
2026-10-01 07:14 UTClast confirmed unchanged 2026-11-21 13:48 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord PUENTES G.R. 400 · payload sha256 9984c7e55781…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-10-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: criterion
short-circuit power (WSCR); applies to power park modules (MPE) only

Injection · Generation (any) · Total

459 MW

Granted

The operator's latest published dataset reports 459 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: dinamico_nodal
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-11-21 13:48 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord PUENTES G.R. 400 · payload sha256 9453de37e5a3…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: criterion
dynamic stability

Injection · Generation (any) · Total

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: autoconsumo_mges
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-11-21 13:48 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord PUENTES G.R. 400 · payload sha256 9453de37e5a3…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: eligibility
self-consumption requests only (RDL 7/2026)

Injection · Generation (any) · Total

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: autoconsumo_mpe
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-11-21 13:48 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord PUENTES G.R. 400 · payload sha256 9453de37e5a3…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: eligibility
self-consumption requests only (RDL 7/2026)

Injection · Generation (any) · Total

not stated

Published in MW; no MW figure is derived from it.

Granted

The operator's latest published dataset reports no value (published as unknown) under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: dinamico_limitacion_interna
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-11-21 13:48 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord PUENTES G.R. 400 · payload sha256 9453de37e5a3…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: criterion
dynamic stability
Operator note: source label
N/A

Injection · Generation (any) · Unknown

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: no_disponible_mges
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-11-21 13:48 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord PUENTES G.R. 400 · payload sha256 9453de37e5a3…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: reservation
NTJ

Injection · Generation (any) · Unknown

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: no_disponible_mpe
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-11-21 13:48 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord PUENTES G.R. 400 · payload sha256 9453de37e5a3…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: reservation
NTJ

Injection · Other storage · Allocated

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: alm
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-11-21 13:48 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord PUENTES G.R. 400 · payload sha256 9453de37e5a3…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required

Injection · Other storage · Available

1,583 MW

Granted

The operator's latest published dataset reports 1583 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: estatico_margen
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
3 Nov 2026
Retrieved / confirmed
2026-11-03 11:31 UTClast confirmed unchanged 2026-11-21 13:48 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord PUENTES G.R. 400 · payload sha256 b767e717e60b…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-11-03)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: criterion
static (N and N-X)

Injection · Other storage · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_cnmc_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: mpe_rdt
Methodology
es_cnmc_gen_rdt_2026Generation access capacity at the transmission network (REE's figures in CNMC's map)basis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
9 Sep 2026
Retrieved / confirmed
2026-09-26 05:57 UTClast confirmed unchanged 2026-11-21 11:03 UTC
Source health
Healthy
Provenance
es_cnmc_generation_capacityrecord rdt:PUENTES G.R. 400 · payload sha256 1bf4a9e7e78c…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Origen de los datos: Comisión Nacional de los Mercados y la Competencia (CNMC) (last updated 2026-09-09)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: regulatory reservation
true
Operator note: source field
CAP_ALM_DISPONIBLE_MPE

Injection · Other storage · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_cnmc_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: mges_rdt
Methodology
es_cnmc_gen_rdt_2026Generation access capacity at the transmission network (REE's figures in CNMC's map)basis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
9 Sep 2026
Retrieved / confirmed
2026-09-26 05:57 UTClast confirmed unchanged 2026-11-21 11:03 UTC
Source health
Healthy
Provenance
es_cnmc_generation_capacityrecord rdt:PUENTES G.R. 400 · payload sha256 1bf4a9e7e78c…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Origen de los datos: Comisión Nacional de los Mercados y la Competencia (CNMC) (last updated 2026-09-09)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: regulatory reservation
true
Operator note: source field
CAP_ALM_DISPONIBLE_MGES

Injection · Other storage · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: margen_total_mges
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-11-21 13:48 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord PUENTES G.R. 400 · payload sha256 9453de37e5a3…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: limiting criteria
D_Nudo
Operator note: reservation
NTJ
Operator note: scope
gross margin, before capacity not available for requests

Injection · Other storage · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: margen_total_mpe
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-11-21 13:48 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord PUENTES G.R. 400 · payload sha256 9453de37e5a3…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: limiting criteria
D_Nudo
Operator note: reservation
NTJ
Operator note: scope
gross margin, before capacity not available for requests

Injection · Other storage · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: mges_rdt
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-11-21 13:48 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord PUENTES G.R. 400 · payload sha256 9453de37e5a3…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: limiting criteria
D_Nudo
Operator note: reservation
NTJ

Injection · Other storage · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: mpe_rdt
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-11-21 13:48 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord PUENTES G.R. 400 · payload sha256 9453de37e5a3…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: limiting criteria
D_Nudo
Operator note: reservation
NTJ

Injection · Other storage · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: mges_rdd
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-11-21 13:48 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord PUENTES G.R. 400 · payload sha256 9453de37e5a3…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: limiting criteria
D_Nudo
Operator note: reservation
NTJ

Injection · Other storage · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: mpe_rdd
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-11-21 13:48 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord PUENTES G.R. 400 · payload sha256 9453de37e5a3…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: limiting criteria
D_Nudo
Operator note: reservation
NTJ

Injection · Other storage · Requested

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: alm
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-11-21 13:48 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord PUENTES G.R. 400 · payload sha256 9453de37e5a3…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required

Injection · Other storage · Total

3,776 MW

Granted

The operator's latest published dataset reports 3776 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: estatico_nodal
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-11-21 13:48 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord PUENTES G.R. 400 · payload sha256 9453de37e5a3…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: criterion
static (N and N-X)

Injection · Other storage · Unknown

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: no_disponible_mges
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-11-21 13:48 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord PUENTES G.R. 400 · payload sha256 9453de37e5a3…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: reservation
NTJ

Injection · Other storage · Unknown

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: no_disponible_mpe
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-11-21 13:48 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord PUENTES G.R. 400 · payload sha256 9453de37e5a3…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: reservation
NTJ

Offtake · Load (any) · Allocated

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_dem_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: adicional_valor_referencia
Methodology
es_ree_dem_rdt_2026REE demand access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_demand_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-09-30 09:22 UTC
Source health
Failing
Provenance
es_ree_demand_access_capacityrecord PUENTES G.R. 400 · payload sha256 420b093d85d2…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required

Offtake · Load (any) · Allocated

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_dem_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: cep_wscr
Methodology
es_ree_dem_rdt_2026REE demand access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_demand_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-09-30 09:22 UTC
Source health
Failing
Provenance
es_ree_demand_access_capacityrecord PUENTES G.R. 400 · payload sha256 420b093d85d2…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required

Offtake · Load (any) · Allocated

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_dem_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: rdt
Methodology
es_ree_dem_rdt_2026REE demand access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_demand_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-09-30 09:22 UTC
Source health
Failing
Provenance
es_ree_demand_access_capacityrecord PUENTES G.R. 400 · payload sha256 420b093d85d2…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required

Offtake · Load (any) · Allocated

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_dem_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: aceptabilidad_rdd
Methodology
es_ree_dem_rdt_2026REE demand access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_demand_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-09-30 09:22 UTC
Source health
Failing
Provenance
es_ree_demand_access_capacityrecord PUENTES G.R. 400 · payload sha256 420b093d85d2…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required

Offtake · Load (any) · Allocated

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_dem_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: aceptabilidad_rdd_fuera_referencia
Methodology
es_ree_dem_rdt_2026REE demand access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_demand_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-09-30 09:22 UTC
Source health
Failing
Provenance
es_ree_demand_access_capacityrecord PUENTES G.R. 400 · payload sha256 420b093d85d2…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required

Offtake · Load (any) · Allocated

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_dem_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: ch_rdt
Methodology
es_ree_dem_rdt_2026REE demand access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_demand_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-09-30 09:22 UTC
Source health
Failing
Provenance
es_ree_demand_access_capacityrecord PUENTES G.R. 400 · payload sha256 420b093d85d2…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required

Offtake · Load (any) · Allocated

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_dem_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: sh_rdt
Methodology
es_ree_dem_rdt_2026REE demand access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_demand_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-09-30 09:22 UTC
Source health
Failing
Provenance
es_ree_demand_access_capacityrecord PUENTES G.R. 400 · payload sha256 420b093d85d2…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required

Offtake · Load (any) · Allocated

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_dem_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: ch_aceptabilidad_rdd
Methodology
es_ree_dem_rdt_2026REE demand access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_demand_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-09-30 09:22 UTC
Source health
Failing
Provenance
es_ree_demand_access_capacityrecord PUENTES G.R. 400 · payload sha256 420b093d85d2…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required

Offtake · Load (any) · Allocated

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_dem_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: sh_aceptabilidad_rdd
Methodology
es_ree_dem_rdt_2026REE demand access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_demand_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-09-30 09:22 UTC
Source health
Failing
Provenance
es_ree_demand_access_capacityrecord PUENTES G.R. 400 · payload sha256 420b093d85d2…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required

Offtake · Load (any) · Available

1,413 MW

Granted

The operator's latest published dataset reports 1413 MW under methodology es_ree_dem_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: estatico_margen
Methodology
es_ree_dem_rdt_2026REE demand access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_demand_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-09-30 09:22 UTC
Source health
Failing
Provenance
es_ree_demand_access_capacityrecord PUENTES G.R. 400 · payload sha256 420b093d85d2…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: criterion
static (N and N-X)
Operator note: temporary access limitation
No

Offtake · Load (any) · Available

458 MW

Granted

The operator's latest published dataset reports 458 MW under methodology es_ree_dem_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: dinamico1_margen
Methodology
es_ree_dem_rdt_2026REE demand access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_demand_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-09-30 09:22 UTC
Source health
Failing
Provenance
es_ree_demand_access_capacityrecord PUENTES G.R. 400 · payload sha256 420b093d85d2…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: criterion
dynamic 1: CEP demand with voltage-dip ride-through, and non-CEP demand

Offtake · Load (any) · Available

458 MW

Granted

The operator's latest published dataset reports 458 MW under methodology es_ree_dem_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: margen_total_no_cep
Methodology
es_ree_dem_rdt_2026REE demand access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_demand_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-09-30 09:22 UTC
Source health
Failing
Provenance
es_ree_demand_access_capacityrecord PUENTES G.R. 400 · payload sha256 420b093d85d2…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: limiting criteria
Din1_Zona
Operator note: scope
gross margin, before capacity not grantable at the transmission network
Operator note: temporary access limitation
No

Offtake · Load (any) · Available

458 MW

Granted

The operator's latest published dataset reports 458 MW under methodology es_ree_dem_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: no_cep
Methodology
es_ree_dem_rdt_2026REE demand access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_demand_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-09-30 09:22 UTC
Source health
Failing
Provenance
es_ree_demand_access_capacityrecord PUENTES G.R. 400 · payload sha256 420b093d85d2…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: limiting criteria
Din1_Zona
Operator note: temporary access limitation
No

Offtake · Load (any) · Available

346 MW

Granted

The operator's latest published dataset reports 346 MW under methodology es_ree_dem_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: wscr_margen
Methodology
es_ree_dem_rdt_2026REE demand access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_demand_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-09-30 09:22 UTC
Source health
Failing
Provenance
es_ree_demand_access_capacityrecord PUENTES G.R. 400 · payload sha256 420b093d85d2…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: criterion
short-circuit power (WSCR); applies to demand with a power-electronics interface (CEP) only

Offtake · Load (any) · Available

346 MW

Granted

The operator's latest published dataset reports 346 MW under methodology es_ree_dem_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: margen_total_cep_ch
Methodology
es_ree_dem_rdt_2026REE demand access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_demand_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-09-30 09:22 UTC
Source health
Failing
Provenance
es_ree_demand_access_capacityrecord PUENTES G.R. 400 · payload sha256 420b093d85d2…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: limiting criteria
WSCR_Nudo
Operator note: scope
gross margin, before capacity not grantable at the transmission network
Operator note: temporary access limitation
No

Offtake · Load (any) · Available

346 MW

Granted

The operator's latest published dataset reports 346 MW under methodology es_ree_dem_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: cep_ch
Methodology
es_ree_dem_rdt_2026REE demand access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_demand_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-09-30 09:22 UTC
Source health
Failing
Provenance
es_ree_demand_access_capacityrecord PUENTES G.R. 400 · payload sha256 420b093d85d2…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: limiting criteria
WSCR_Nudo
Operator note: temporary access limitation
No

Offtake · Load (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_dem_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: dinamico2_margen
Methodology
es_ree_dem_rdt_2026REE demand access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_demand_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-09-30 09:22 UTC
Source health
Failing
Provenance
es_ree_demand_access_capacityrecord PUENTES G.R. 400 · payload sha256 420b093d85d2…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: criterion
dynamic 2: CEP demand without voltage-dip ride-through

Offtake · Load (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_dem_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: margen_total_cep_sh
Methodology
es_ree_dem_rdt_2026REE demand access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_demand_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-09-30 09:22 UTC
Source health
Failing
Provenance
es_ree_demand_access_capacityrecord PUENTES G.R. 400 · payload sha256 420b093d85d2…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: limiting criteria
Din2_Zona
Operator note: scope
gross margin, before capacity not grantable at the transmission network
Operator note: temporary access limitation
No

Offtake · Load (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_dem_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: cep_sh
Methodology
es_ree_dem_rdt_2026REE demand access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_demand_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-09-30 09:22 UTC
Source health
Failing
Provenance
es_ree_demand_access_capacityrecord PUENTES G.R. 400 · payload sha256 420b093d85d2…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: limiting criteria
Din2_Zona
Operator note: temporary access limitation
No

Offtake · Load (any) · Requested

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_dem_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: rdt
Methodology
es_ree_dem_rdt_2026REE demand access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_demand_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-09-30 09:22 UTC
Source health
Failing
Provenance
es_ree_demand_access_capacityrecord PUENTES G.R. 400 · payload sha256 420b093d85d2…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required

Offtake · Load (any) · Reserved

450 MW

Granted

The operator's latest published dataset reports 450 MW under methodology es_ree_dem_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: valor_referencia_rdd
Methodology
es_ree_dem_rdt_2026REE demand access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_demand_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-09-30 09:22 UTC
Source health
Failing
Provenance
es_ree_demand_access_capacityrecord PUENTES G.R. 400 · payload sha256 420b093d85d2…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: reference value agreed with dso
SI
Operator note: reserved for
consumption of the underlying distribution network (reference value)

Offtake · Load (any) · Total

1,863 MW

Granted

The operator's latest published dataset reports 1863 MW under methodology es_ree_dem_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: estatico_nodal
Methodology
es_ree_dem_rdt_2026REE demand access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_demand_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-09-30 09:22 UTC
Source health
Failing
Provenance
es_ree_demand_access_capacityrecord PUENTES G.R. 400 · payload sha256 420b093d85d2…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: criterion
static (N and N-X)
Operator note: temporary access limitation
No

Offtake · Load (any) · Total

346 MW

Granted

The operator's latest published dataset reports 346 MW under methodology es_ree_dem_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: wscr_nodal
Methodology
es_ree_dem_rdt_2026REE demand access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_demand_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-09-30 09:22 UTC
Source health
Failing
Provenance
es_ree_demand_access_capacityrecord PUENTES G.R. 400 · payload sha256 420b093d85d2…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: criterion
short-circuit power (WSCR); applies to demand with a power-electronics interface (CEP) only

Offtake · Load (any) · Unknown

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_dem_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: no_otorgable_cep_ch
Methodology
es_ree_dem_rdt_2026REE demand access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_demand_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-09-30 09:22 UTC
Source health
Failing
Provenance
es_ree_demand_access_capacityrecord PUENTES G.R. 400 · payload sha256 420b093d85d2…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required

Offtake · Load (any) · Unknown

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_dem_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: no_otorgable_cep_sh
Methodology
es_ree_dem_rdt_2026REE demand access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_demand_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-09-30 09:22 UTC
Source health
Failing
Provenance
es_ree_demand_access_capacityrecord PUENTES G.R. 400 · payload sha256 420b093d85d2…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required

Offtake · Load (any) · Unknown

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_dem_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: no_otorgable_no_cep
Methodology
es_ree_dem_rdt_2026REE demand access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_demand_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-09-30 09:22 UTC
Source health
Failing
Provenance
es_ree_demand_access_capacityrecord PUENTES G.R. 400 · payload sha256 420b093d85d2…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required

Offtake · Other storage · Allocated

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_dem_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: adicional_valor_referencia
Methodology
es_ree_dem_rdt_2026REE demand access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_demand_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-09-30 09:22 UTC
Source health
Failing
Provenance
es_ree_demand_access_capacityrecord PUENTES G.R. 400 · payload sha256 420b093d85d2…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required

Offtake · Other storage · Allocated

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_dem_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: rdt
Methodology
es_ree_dem_rdt_2026REE demand access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_demand_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-09-30 09:22 UTC
Source health
Failing
Provenance
es_ree_demand_access_capacityrecord PUENTES G.R. 400 · payload sha256 420b093d85d2…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required

Offtake · Other storage · Allocated

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_dem_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: aceptabilidad_rdd
Methodology
es_ree_dem_rdt_2026REE demand access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_demand_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-09-30 09:22 UTC
Source health
Failing
Provenance
es_ree_demand_access_capacityrecord PUENTES G.R. 400 · payload sha256 420b093d85d2…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required

Offtake · Other storage · Allocated

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_dem_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: aceptabilidad_rdd_fuera_referencia
Methodology
es_ree_dem_rdt_2026REE demand access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_demand_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-09-30 09:22 UTC
Source health
Failing
Provenance
es_ree_demand_access_capacityrecord PUENTES G.R. 400 · payload sha256 420b093d85d2…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required

Offtake · Other storage · Available

2,920 MW

Granted

The operator's latest published dataset reports 2920 MW under methodology es_ree_dem_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: estatico_margen
Methodology
es_ree_dem_rdt_2026REE demand access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_demand_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-09-30 09:22 UTC
Source health
Failing
Provenance
es_ree_demand_access_capacityrecord PUENTES G.R. 400 · payload sha256 420b093d85d2…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: criterion
static (N and N-X)

Offtake · Other storage · Available

458 MW

Granted

The operator's latest published dataset reports 458 MW under methodology es_ree_dem_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: margen_total_cep
Methodology
es_ree_dem_rdt_2026REE demand access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_demand_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-09-30 09:22 UTC
Source health
Failing
Provenance
es_ree_demand_access_capacityrecord PUENTES G.R. 400 · payload sha256 420b093d85d2…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: limiting criteria
Din1_Zona
Operator note: scope
gross margin, before capacity not grantable at the transmission network
Operator note: temporary access limitation
No

Offtake · Other storage · Available

458 MW

Granted

The operator's latest published dataset reports 458 MW under methodology es_ree_dem_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: margen_total_no_cep
Methodology
es_ree_dem_rdt_2026REE demand access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_demand_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-09-30 09:22 UTC
Source health
Failing
Provenance
es_ree_demand_access_capacityrecord PUENTES G.R. 400 · payload sha256 420b093d85d2…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: limiting criteria
Din1_Zona
Operator note: scope
gross margin, before capacity not grantable at the transmission network
Operator note: temporary access limitation
No

Offtake · Other storage · Available

458 MW

Granted

The operator's latest published dataset reports 458 MW under methodology es_ree_dem_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: cep
Methodology
es_ree_dem_rdt_2026REE demand access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_demand_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-09-30 09:22 UTC
Source health
Failing
Provenance
es_ree_demand_access_capacityrecord PUENTES G.R. 400 · payload sha256 420b093d85d2…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: limiting criteria
Din1_Zona
Operator note: temporary access limitation
No

Offtake · Other storage · Available

458 MW

Granted

The operator's latest published dataset reports 458 MW under methodology es_ree_dem_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: no_cep
Methodology
es_ree_dem_rdt_2026REE demand access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_demand_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-09-30 09:22 UTC
Source health
Failing
Provenance
es_ree_demand_access_capacityrecord PUENTES G.R. 400 · payload sha256 420b093d85d2…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: limiting criteria
Din1_Zona
Operator note: temporary access limitation
No

Offtake · Other storage · Requested

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_dem_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: rdt
Methodology
es_ree_dem_rdt_2026REE demand access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_demand_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-09-30 09:22 UTC
Source health
Failing
Provenance
es_ree_demand_access_capacityrecord PUENTES G.R. 400 · payload sha256 420b093d85d2…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required

Offtake · Other storage · Total

3,370 MW

Granted

The operator's latest published dataset reports 3370 MW under methodology es_ree_dem_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: estatico_nodal
Methodology
es_ree_dem_rdt_2026REE demand access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_demand_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-09-30 09:22 UTC
Source health
Failing
Provenance
es_ree_demand_access_capacityrecord PUENTES G.R. 400 · payload sha256 420b093d85d2…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: criterion
static (N and N-X)

Offtake · Other storage · Unknown

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_dem_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: no_otorgable_cep
Methodology
es_ree_dem_rdt_2026REE demand access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_demand_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-09-30 09:22 UTC
Source health
Failing
Provenance
es_ree_demand_access_capacityrecord PUENTES G.R. 400 · payload sha256 420b093d85d2…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required

Offtake · Other storage · Unknown

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_dem_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: no_otorgable_no_cep
Methodology
es_ree_dem_rdt_2026REE demand access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_demand_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-09-30 09:22 UTC
Source health
Failing
Provenance
es_ree_demand_access_capacityrecord PUENTES G.R. 400 · payload sha256 420b093d85d2…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required

History

Served series only

Injection · Generation (any) · Available

current 0 MW

26 Sep 2026: 0 MW
26 Sep 2026range 0 to 0 MW24 Nov 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current0 MW

Time axis: when we observed each value, not the operator’s effective date.

Injection · Generation (any) · Available

current 0 MW

26 Sep 2026: 0 MW
26 Sep 2026range 0 to 0 MW24 Nov 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current0 MW

Time axis: when we observed each value, not the operator’s effective date.

Injection · Other storage · Available

current 0 MW

26 Sep 2026: 0 MW
26 Sep 2026range 0 to 0 MW24 Nov 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current0 MW

Time axis: when we observed each value, not the operator’s effective date.

Injection · Other storage · Available

current 0 MW

26 Sep 2026: 0 MW
26 Sep 2026range 0 to 0 MW24 Nov 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current0 MW

Time axis: when we observed each value, not the operator’s effective date.

Injection · Generation (any) · Allocated

current 2,192.92 MW

26 Sep 2026: 2,180.72 MW14 Oct 2026: 2,236.42 MW12 Nov 2026: 2,192.92 MW
26 Sep 2026range 2,180.72 to 2,236.42 MW24 Nov 2026
3 published values, as a table
Observed fromUntilValue
26 Sep 202614 Oct 20262,180.72 MW
14 Oct 202612 Nov 20262,236.42 MW
12 Nov 2026current2,192.92 MW

Time axis: when we observed each value, not the operator’s effective date.

Injection · Generation (any) · Requested

current 0 MW

26 Sep 2026: 47.3 MW14 Oct 2026: 0 MW
26 Sep 2026range 0 to 47.3 MW24 Nov 2026
2 published values, as a table
Observed fromUntilValue
26 Sep 202614 Oct 202647.3 MW
14 Oct 2026current0 MW

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Load (any) · Total

current 346 MW

26 Sep 2026: 346 MW
26 Sep 2026range 346 to 346 MW24 Nov 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current346 MW

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Load (any) · Available

current 346 MW

26 Sep 2026: 346 MW
26 Sep 2026range 346 to 346 MW24 Nov 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current346 MW

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Load (any) · Total

current 1,863 MW

26 Sep 2026: 1,863 MW
26 Sep 2026range 1,863 to 1,863 MW24 Nov 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current1,863 MW

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Load (any) · Available

current 1,413 MW

26 Sep 2026: 1,413 MW
26 Sep 2026range 1,413 to 1,413 MW24 Nov 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current1,413 MW

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Other storage · Total

current 3,370 MW

26 Sep 2026: 3,370 MW
26 Sep 2026range 3,370 to 3,370 MW24 Nov 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current3,370 MW

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Other storage · Available

current 2,920 MW

26 Sep 2026: 2,920 MW
26 Sep 2026range 2,920 to 2,920 MW24 Nov 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current2,920 MW

Time axis: when we observed each value, not the operator’s effective date.

The first 12 of 92 served series with a history. The history route returns every one of them.

Through the API

curl "https://api.gridcapacityapi.com/v1/grid-assets/node_06gdrjgyq1r1ncecpqfp67tgj8/capacity" \  -H "Authorization: Bearer gc_live_..."