Skip to content

Node / 220 kV / transmission

PALENCIA

Red Eléctrica de España, S.A.U. / Palencia, Palencia, Spain

Latest published values

92 served · 0 withheld

Each row is what the operator’s latest published dataset reports for one combination of direction, technology, measure, firmness and horizon. Hosting-capacity figures are indicative and reflect what operators publish. They are not a connection offer; only the operator can confirm capacity for a specific request.

Latest published capacity values, one row per series
DirectionTechnologyMeasureValueFirmnessHorizonSource date
InjectionGeneration (any)Allocated358.21 MWUnknownNow (snapshot)variant: mge9 Sep 2026
InjectionGeneration (any)Allocated358 MWUnknownNow (snapshot)variant: mge1 Sep 2026
InjectionGeneration (any)Allocated358 MWUnknownNow (snapshot)variant: mpe1 Sep 2026
InjectionGeneration (any)Allocated358 MWUnknownNow (snapshot)variant: gen1 Sep 2026
InjectionGeneration (any)Allocated272 MWUnknownNow (snapshot)variant: mpe_con_wscr1 Sep 2026
InjectionGeneration (any)Allocated86 MWUnknownNow (snapshot)variant: mpe_sin_wscr1 Sep 2026
InjectionGeneration (any)Allocated0 MWUnknownNow (snapshot)variant: mges1 Sep 2026
InjectionGeneration (any)Allocated0 MWUnknownNow (snapshot)variant: autoconsumo_mges1 Sep 2026
InjectionGeneration (any)Allocated0 MWUnknownNow (snapshot)variant: autoconsumo_mpe1 Sep 2026
InjectionGeneration (any)Available1,138 MWUnknownNow (snapshot)variant: estatico_margen1 Sep 2026
InjectionGeneration (any)Available827 MWUnknownNow (snapshot)variant: dinamico_margen1 Sep 2026
InjectionGeneration (any)Available827 MWUnknownNow (snapshot)variant: margen_total_mges1 Sep 2026
InjectionGeneration (any)Available221 MWUnknownNow (snapshot)variant: posicion_margen_mges1 Sep 2026
InjectionGeneration (any)Available195 MWUnknownNow (snapshot)variant: wscr_margen1 Sep 2026
InjectionGeneration (any)Available195 MWUnknownNow (snapshot)variant: posicion_margen_mpe1 Sep 2026
InjectionGeneration (any)Available195 MWUnknownNow (snapshot)variant: margen_total_mpe1 Sep 2026
InjectionGeneration (any)Available83 MWUnknownNow (snapshot)variant: autoconsumo_mges1 Sep 2026
InjectionGeneration (any)Available19 MWUnknownNow (snapshot)variant: autoconsumo_mpe1 Sep 2026
InjectionGeneration (any)Available0 MWUnknownNow (snapshot)variant: mpe_rdt9 Sep 2026
InjectionGeneration (any)Available0 MWUnknownNow (snapshot)variant: mges_rdt9 Sep 2026
InjectionGeneration (any)Available0 MWUnknownNow (snapshot)variant: mges_rdt1 Sep 2026
InjectionGeneration (any)Available0 MWUnknownNow (snapshot)variant: mpe_rdt1 Sep 2026
InjectionGeneration (any)Available0 MWUnknownNow (snapshot)variant: mges_rdd1 Sep 2026
InjectionGeneration (any)Available0 MWUnknownNow (snapshot)variant: mpe_rdd1 Sep 2026
InjectionGeneration (any)Requested224.06 MWUnknownNow (snapshot)variant: mge9 Sep 2026
InjectionGeneration (any)Requested224 MWUnknownNow (snapshot)variant: mge1 Sep 2026
InjectionGeneration (any)Requested224 MWUnknownNow (snapshot)variant: mpe1 Sep 2026
InjectionGeneration (any)Requested224 MWUnknownNow (snapshot)variant: gen1 Sep 2026
InjectionGeneration (any)Requested187 MWUnknownNow (snapshot)variant: mpe_con_wscr1 Sep 2026
InjectionGeneration (any)Requested37 MWUnknownNow (snapshot)variant: mpe_sin_wscr1 Sep 2026
InjectionGeneration (any)Requested0 MWUnknownNow (snapshot)variant: mges1 Sep 2026
InjectionGeneration (any)Total1,497 MWUnknownNow (snapshot)variant: estatico_nodal1 Sep 2026
InjectionGeneration (any)Total1,186 MWUnknownNow (snapshot)variant: dinamico_nodal1 Sep 2026
InjectionGeneration (any)Total467 MWUnknownNow (snapshot)variant: wscr_nodal1 Sep 2026
InjectionGeneration (any)Total400 MWUnknownNow (snapshot)variant: posicion_maximo1 Sep 2026
InjectionGeneration (any)Total83 MWUnknownNow (snapshot)variant: autoconsumo_mges1 Sep 2026
InjectionGeneration (any)Total19 MWUnknownNow (snapshot)variant: autoconsumo_mpe1 Sep 2026
InjectionGeneration (any)Totalnot statedUnknownNow (snapshot)variant: dinamico_limitacion_interna1 Sep 2026
InjectionGeneration (any)Unknown827 MWUnknownNow (snapshot)variant: no_disponible_mges1 Sep 2026
InjectionGeneration (any)Unknown195 MWUnknownNow (snapshot)variant: no_disponible_mpe1 Sep 2026
InjectionOther storageAllocated0 MWUnknownNow (snapshot)variant: alm1 Sep 2026
InjectionOther storageAvailable1,406 MWUnknownNow (snapshot)variant: estatico_margen1 Sep 2026
InjectionOther storageAvailable827 MWUnknownNow (snapshot)variant: margen_total_mges1 Sep 2026
InjectionOther storageAvailable195 MWUnknownNow (snapshot)variant: margen_total_mpe1 Sep 2026
InjectionOther storageAvailable0 MWUnknownNow (snapshot)variant: mpe_rdt9 Sep 2026
InjectionOther storageAvailable0 MWUnknownNow (snapshot)variant: mges_rdt9 Sep 2026
InjectionOther storageAvailable0 MWUnknownNow (snapshot)variant: mges_rdt1 Sep 2026
InjectionOther storageAvailable0 MWUnknownNow (snapshot)variant: mpe_rdt1 Sep 2026
InjectionOther storageAvailable0 MWUnknownNow (snapshot)variant: mges_rdd1 Sep 2026
InjectionOther storageAvailable0 MWUnknownNow (snapshot)variant: mpe_rdd1 Sep 2026
InjectionOther storageRequested0 MWUnknownNow (snapshot)variant: alm1 Sep 2026
InjectionOther storageTotal1,764 MWUnknownNow (snapshot)variant: estatico_nodal1 Sep 2026
InjectionOther storageUnknown827 MWUnknownNow (snapshot)variant: no_disponible_mges1 Sep 2026
InjectionOther storageUnknown195 MWUnknownNow (snapshot)variant: no_disponible_mpe1 Sep 2026
OfftakeLoad (any)Allocated0 MWUnknownNow (snapshot)variant: adicional_valor_referencia1 Sep 2026
OfftakeLoad (any)Allocated0 MWUnknownNow (snapshot)variant: cep_wscr1 Sep 2026
OfftakeLoad (any)Allocated0 MWUnknownNow (snapshot)variant: rdt1 Sep 2026
OfftakeLoad (any)Allocated0 MWUnknownNow (snapshot)variant: aceptabilidad_rdd1 Sep 2026
OfftakeLoad (any)Allocated0 MWUnknownNow (snapshot)variant: aceptabilidad_rdd_fuera_referencia1 Sep 2026
OfftakeLoad (any)Allocated0 MWUnknownNow (snapshot)variant: ch_rdt1 Sep 2026
OfftakeLoad (any)Allocated0 MWUnknownNow (snapshot)variant: sh_rdt1 Sep 2026
OfftakeLoad (any)Allocated0 MWUnknownNow (snapshot)variant: ch_aceptabilidad_rdd1 Sep 2026
OfftakeLoad (any)Allocated0 MWUnknownNow (snapshot)variant: sh_aceptabilidad_rdd1 Sep 2026
OfftakeLoad (any)Available1,167 MWUnknownNow (snapshot)variant: dinamico1_margen1 Sep 2026
OfftakeLoad (any)Available325 MWUnknownNow (snapshot)variant: estatico_margen1 Sep 2026
OfftakeLoad (any)Available325 MWUnknownNow (snapshot)variant: margen_total_no_cep1 Sep 2026
OfftakeLoad (any)Available295 MWUnknownNow (snapshot)variant: wscr_margen1 Sep 2026
OfftakeLoad (any)Available295 MWUnknownNow (snapshot)variant: margen_total_cep_ch1 Sep 2026
OfftakeLoad (any)Available0 MWUnknownNow (snapshot)variant: dinamico2_margen1 Sep 2026
OfftakeLoad (any)Available0 MWUnknownNow (snapshot)variant: margen_total_cep_sh1 Sep 2026
OfftakeLoad (any)Available0 MWUnknownNow (snapshot)variant: cep_ch1 Sep 2026
OfftakeLoad (any)Available0 MWUnknownNow (snapshot)variant: cep_sh1 Sep 2026
OfftakeLoad (any)Available0 MWUnknownNow (snapshot)variant: no_cep1 Sep 2026
OfftakeLoad (any)Requested169 MWUnknownNow (snapshot)variant: rdt1 Sep 2026
OfftakeLoad (any)Reserved259 MWUnknownNow (snapshot)variant: valor_referencia_rdd1 Sep 2026
OfftakeLoad (any)Total584 MWUnknownNow (snapshot)variant: estatico_nodal1 Sep 2026
OfftakeLoad (any)Total295 MWUnknownNow (snapshot)variant: wscr_nodal1 Sep 2026
OfftakeLoad (any)Unknown325 MWUnknownNow (snapshot)variant: no_otorgable_no_cep1 Sep 2026
OfftakeLoad (any)Unknown295 MWUnknownNow (snapshot)variant: no_otorgable_cep_ch1 Sep 2026
OfftakeLoad (any)Unknown0 MWUnknownNow (snapshot)variant: no_otorgable_cep_sh1 Sep 2026
OfftakeOther storageAllocated0 MWUnknownNow (snapshot)variant: adicional_valor_referencia1 Sep 2026
OfftakeOther storageAllocated0 MWUnknownNow (snapshot)variant: rdt1 Sep 2026
OfftakeOther storageAllocated0 MWUnknownNow (snapshot)variant: aceptabilidad_rdd1 Sep 2026
OfftakeOther storageAllocated0 MWUnknownNow (snapshot)variant: aceptabilidad_rdd_fuera_referencia1 Sep 2026
OfftakeOther storageAvailable564 MWUnknownNow (snapshot)variant: estatico_margen1 Sep 2026
OfftakeOther storageAvailable564 MWUnknownNow (snapshot)variant: margen_total_cep1 Sep 2026
OfftakeOther storageAvailable564 MWUnknownNow (snapshot)variant: margen_total_no_cep1 Sep 2026
OfftakeOther storageAvailable0 MWUnknownNow (snapshot)variant: cep1 Sep 2026
OfftakeOther storageAvailable0 MWUnknownNow (snapshot)variant: no_cep1 Sep 2026
OfftakeOther storageRequested20 MWUnknownNow (snapshot)variant: rdt1 Sep 2026
OfftakeOther storageTotal823 MWUnknownNow (snapshot)variant: estatico_nodal1 Sep 2026
OfftakeOther storageUnknown564 MWUnknownNow (snapshot)variant: no_otorgable_cep1 Sep 2026
OfftakeOther storageUnknown564 MWUnknownNow (snapshot)variant: no_otorgable_no_cep1 Sep 2026

Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)Origen de los datos: Comisión Nacional de los Mercados y la Competencia (CNMC) (last updated 2026-09-09)

What each value means

Methodology, both clocks, provenance and rights

Injection · Generation (any) · Allocated

358.21 MW

Granted

The operator's latest published dataset reports 358.21 MW under methodology es_cnmc_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: mge
Methodology
es_cnmc_gen_rdt_2026Generation access capacity at the transmission network (REE's figures in CNMC's map)basis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
9 Sep 2026
Retrieved / confirmed
2026-09-26 05:57 UTClast confirmed unchanged 2026-10-02 07:46 UTC
Source health
Healthy
Provenance
es_cnmc_generation_capacityrecord rdt:PALENCIA 220 · payload sha256 c8edec61051d…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Origen de los datos: Comisión Nacional de los Mercados y la Competencia (CNMC) (last updated 2026-09-09)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
CAP_OCUPADA

Injection · Generation (any) · Allocated

358 MW

Granted

The operator's latest published dataset reports 358 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: mge
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-10-02 05:04 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord PALENCIA 220 · payload sha256 986b4e234b81…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: module scope
MGE: all power-generating modules (MGES + MPE, generation and storage)

Injection · Generation (any) · Allocated

358 MW

Granted

The operator's latest published dataset reports 358 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: mpe
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-10-02 05:04 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord PALENCIA 220 · payload sha256 986b4e234b81…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required

Injection · Generation (any) · Allocated

358 MW

Granted

The operator's latest published dataset reports 358 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: gen
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-10-02 05:04 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord PALENCIA 220 · payload sha256 986b4e234b81…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: module scope
GEN: generation installations, storage excluded

Injection · Generation (any) · Allocated

272 MW

Granted

The operator's latest published dataset reports 272 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: mpe_con_wscr
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-10-02 05:04 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord PALENCIA 220 · payload sha256 986b4e234b81…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required

Injection · Generation (any) · Allocated

86 MW

Granted

The operator's latest published dataset reports 86 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: mpe_sin_wscr
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-10-02 05:04 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord PALENCIA 220 · payload sha256 986b4e234b81…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required

Injection · Generation (any) · Allocated

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: mges
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-10-02 05:04 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord PALENCIA 220 · payload sha256 986b4e234b81…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required

Injection · Generation (any) · Allocated

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: autoconsumo_mges
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-10-02 05:04 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord PALENCIA 220 · payload sha256 986b4e234b81…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: eligibility
self-consumption requests only (RDL 7/2026)

Injection · Generation (any) · Allocated

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: autoconsumo_mpe
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-10-02 05:04 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord PALENCIA 220 · payload sha256 986b4e234b81…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: eligibility
self-consumption requests only (RDL 7/2026)

Injection · Generation (any) · Available

1,138 MW

Granted

The operator's latest published dataset reports 1138 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: estatico_margen
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-10-02 05:04 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord PALENCIA 220 · payload sha256 986b4e234b81…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: criterion
static (N and N-X)

Injection · Generation (any) · Available

827 MW

Granted

The operator's latest published dataset reports 827 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: dinamico_margen
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-10-02 05:04 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord PALENCIA 220 · payload sha256 986b4e234b81…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: criterion
dynamic stability

Injection · Generation (any) · Available

827 MW

Granted

The operator's latest published dataset reports 827 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: margen_total_mges
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-10-02 05:04 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord PALENCIA 220 · payload sha256 986b4e234b81…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: limiting criteria
D_Nudo
Operator note: reason not available
Concurso por resolución SEE.
Operator note: reservation
Concurso
Operator note: scope
gross margin, before capacity not available for requests

Injection · Generation (any) · Available

221 MW

Granted

The operator's latest published dataset reports 221 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: posicion_margen_mges
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-10-02 05:04 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord PALENCIA 220 · payload sha256 986b4e234b81…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required

Injection · Generation (any) · Available

195 MW

Granted

The operator's latest published dataset reports 195 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: wscr_margen
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-10-02 05:04 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord PALENCIA 220 · payload sha256 986b4e234b81…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: criterion
short-circuit power (WSCR); applies to power park modules (MPE) only

Injection · Generation (any) · Available

195 MW

Granted

The operator's latest published dataset reports 195 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: posicion_margen_mpe
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-10-02 05:04 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord PALENCIA 220 · payload sha256 986b4e234b81…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required

Injection · Generation (any) · Available

195 MW

Granted

The operator's latest published dataset reports 195 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: margen_total_mpe
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-10-02 05:04 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord PALENCIA 220 · payload sha256 986b4e234b81…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: limiting criteria
WSCR_Nudo
Operator note: reason not available
Concurso por resolución SEE.
Operator note: reservation
Concurso
Operator note: scope
gross margin, before capacity not available for requests

Injection · Generation (any) · Available

83 MW

Granted

The operator's latest published dataset reports 83 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: autoconsumo_mges
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-10-02 05:04 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord PALENCIA 220 · payload sha256 986b4e234b81…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: eligibility
self-consumption requests only (RDL 7/2026)

Injection · Generation (any) · Available

19 MW

Granted

The operator's latest published dataset reports 19 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: autoconsumo_mpe
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-10-02 05:04 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord PALENCIA 220 · payload sha256 986b4e234b81…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: eligibility
self-consumption requests only (RDL 7/2026)

Injection · Generation (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_cnmc_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: mpe_rdt
Methodology
es_cnmc_gen_rdt_2026Generation access capacity at the transmission network (REE's figures in CNMC's map)basis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
9 Sep 2026
Retrieved / confirmed
2026-09-26 05:57 UTClast confirmed unchanged 2026-10-02 07:46 UTC
Source health
Healthy
Provenance
es_cnmc_generation_capacityrecord rdt:PALENCIA 220 · payload sha256 c8edec61051d…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Origen de los datos: Comisión Nacional de los Mercados y la Competencia (CNMC) (last updated 2026-09-09)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: limited by short circuit power
true
Operator note: regulatory reservation
true
Operator note: source field
CAP_DISPONIBLE_MPE

Injection · Generation (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_cnmc_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: mges_rdt
Methodology
es_cnmc_gen_rdt_2026Generation access capacity at the transmission network (REE's figures in CNMC's map)basis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
9 Sep 2026
Retrieved / confirmed
2026-09-26 05:57 UTClast confirmed unchanged 2026-10-02 07:46 UTC
Source health
Healthy
Provenance
es_cnmc_generation_capacityrecord rdt:PALENCIA 220 · payload sha256 c8edec61051d…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Origen de los datos: Comisión Nacional de los Mercados y la Competencia (CNMC) (last updated 2026-09-09)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: limited by short circuit power
true
Operator note: regulatory reservation
true
Operator note: source field
CAP_DISPONIBLE_MGES

Injection · Generation (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: mges_rdt
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-10-02 05:04 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord PALENCIA 220 · payload sha256 986b4e234b81…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: limiting criteria
D_Nudo
Operator note: reason not available
Concurso por resolución SEE.
Operator note: reservation
Concurso

Injection · Generation (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: mpe_rdt
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-10-02 05:04 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord PALENCIA 220 · payload sha256 986b4e234b81…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: limiting criteria
WSCR_Nudo
Operator note: reason not available
Concurso por resolución SEE.
Operator note: reservation
Concurso

Injection · Generation (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: mges_rdd
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-10-02 05:04 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord PALENCIA 220 · payload sha256 986b4e234b81…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: limiting criteria
D_Nudo
Operator note: reason not available
Concurso por resolución SEE.
Operator note: reservation
Concurso

Injection · Generation (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: mpe_rdd
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-10-02 05:04 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord PALENCIA 220 · payload sha256 986b4e234b81…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: limiting criteria
WSCR_Nudo
Operator note: reason not available
Concurso por resolución SEE.
Operator note: reservation
Concurso

Injection · Generation (any) · Requested

224.06 MW

Granted

The operator's latest published dataset reports 224.06 MW under methodology es_cnmc_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: mge
Methodology
es_cnmc_gen_rdt_2026Generation access capacity at the transmission network (REE's figures in CNMC's map)basis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
9 Sep 2026
Retrieved / confirmed
2026-09-26 05:57 UTClast confirmed unchanged 2026-10-02 07:46 UTC
Source health
Healthy
Provenance
es_cnmc_generation_capacityrecord rdt:PALENCIA 220 · payload sha256 c8edec61051d…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Origen de los datos: Comisión Nacional de los Mercados y la Competencia (CNMC) (last updated 2026-09-09)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
CAP_ADMITIDA_NO_RESUELTA

Injection · Generation (any) · Requested

224 MW

Granted

The operator's latest published dataset reports 224 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: mge
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-10-02 05:04 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord PALENCIA 220 · payload sha256 986b4e234b81…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required

Injection · Generation (any) · Requested

224 MW

Granted

The operator's latest published dataset reports 224 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: mpe
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-10-02 05:04 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord PALENCIA 220 · payload sha256 986b4e234b81…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required

Injection · Generation (any) · Requested

224 MW

Granted

The operator's latest published dataset reports 224 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: gen
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-10-02 05:04 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord PALENCIA 220 · payload sha256 986b4e234b81…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required

Injection · Generation (any) · Requested

187 MW

Granted

The operator's latest published dataset reports 187 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: mpe_con_wscr
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-10-02 05:04 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord PALENCIA 220 · payload sha256 986b4e234b81…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required

Injection · Generation (any) · Requested

37 MW

Granted

The operator's latest published dataset reports 37 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: mpe_sin_wscr
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-10-02 05:04 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord PALENCIA 220 · payload sha256 986b4e234b81…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required

Injection · Generation (any) · Requested

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: mges
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-10-02 05:04 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord PALENCIA 220 · payload sha256 986b4e234b81…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required

Injection · Generation (any) · Total

1,497 MW

Granted

The operator's latest published dataset reports 1497 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: estatico_nodal
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-10-02 05:04 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord PALENCIA 220 · payload sha256 986b4e234b81…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: criterion
static (N and N-X)

Injection · Generation (any) · Total

1,186 MW

Granted

The operator's latest published dataset reports 1186 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: dinamico_nodal
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-10-02 05:04 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord PALENCIA 220 · payload sha256 986b4e234b81…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: criterion
dynamic stability

Injection · Generation (any) · Total

467 MW

Granted

The operator's latest published dataset reports 467 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: wscr_nodal
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-10-02 05:04 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord PALENCIA 220 · payload sha256 986b4e234b81…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: criterion
short-circuit power (WSCR); applies to power park modules (MPE) only

Injection · Generation (any) · Total

400 MW

Granted

The operator's latest published dataset reports 400 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: posicion_maximo
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-10-02 05:04 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord PALENCIA 220 · payload sha256 986b4e234b81…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required

Injection · Generation (any) · Total

83 MW

Granted

The operator's latest published dataset reports 83 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: autoconsumo_mges
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-10-02 05:04 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord PALENCIA 220 · payload sha256 986b4e234b81…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: eligibility
self-consumption requests only (RDL 7/2026)

Injection · Generation (any) · Total

19 MW

Granted

The operator's latest published dataset reports 19 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: autoconsumo_mpe
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-10-02 05:04 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord PALENCIA 220 · payload sha256 986b4e234b81…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: eligibility
self-consumption requests only (RDL 7/2026)

Injection · Generation (any) · Total

not stated

Published in MW; no MW figure is derived from it.

Granted

The operator's latest published dataset reports no value (published as unknown) under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: dinamico_limitacion_interna
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-10-02 05:04 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord PALENCIA 220 · payload sha256 986b4e234b81…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: criterion
dynamic stability
Operator note: source label
N/A

Injection · Generation (any) · Unknown

827 MW

Granted

The operator's latest published dataset reports 827 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: no_disponible_mges
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-10-02 05:04 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord PALENCIA 220 · payload sha256 986b4e234b81…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: reason not available
Concurso por resolución SEE.
Operator note: reservation
Concurso

Injection · Generation (any) · Unknown

195 MW

Granted

The operator's latest published dataset reports 195 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: no_disponible_mpe
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-10-02 05:04 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord PALENCIA 220 · payload sha256 986b4e234b81…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: reason not available
Concurso por resolución SEE.
Operator note: reservation
Concurso

Injection · Other storage · Allocated

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: alm
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-10-02 05:04 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord PALENCIA 220 · payload sha256 986b4e234b81…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required

Injection · Other storage · Available

1,406 MW

Granted

The operator's latest published dataset reports 1406 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: estatico_margen
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-10-02 05:04 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord PALENCIA 220 · payload sha256 986b4e234b81…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: criterion
static (N and N-X)

Injection · Other storage · Available

827 MW

Granted

The operator's latest published dataset reports 827 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: margen_total_mges
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-10-02 05:04 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord PALENCIA 220 · payload sha256 986b4e234b81…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: limiting criteria
D_Nudo
Operator note: reason not available
Concurso por resolución SEE.
Operator note: reservation
Concurso
Operator note: scope
gross margin, before capacity not available for requests

Injection · Other storage · Available

195 MW

Granted

The operator's latest published dataset reports 195 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: margen_total_mpe
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-10-02 05:04 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord PALENCIA 220 · payload sha256 986b4e234b81…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: limiting criteria
WSCR_Nudo
Operator note: reason not available
Concurso por resolución SEE.
Operator note: reservation
Concurso
Operator note: scope
gross margin, before capacity not available for requests

Injection · Other storage · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_cnmc_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: mpe_rdt
Methodology
es_cnmc_gen_rdt_2026Generation access capacity at the transmission network (REE's figures in CNMC's map)basis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
9 Sep 2026
Retrieved / confirmed
2026-09-26 05:57 UTClast confirmed unchanged 2026-10-02 07:46 UTC
Source health
Healthy
Provenance
es_cnmc_generation_capacityrecord rdt:PALENCIA 220 · payload sha256 c8edec61051d…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Origen de los datos: Comisión Nacional de los Mercados y la Competencia (CNMC) (last updated 2026-09-09)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: limited by short circuit power
true
Operator note: regulatory reservation
true
Operator note: source field
CAP_ALM_DISPONIBLE_MPE

Injection · Other storage · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_cnmc_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: mges_rdt
Methodology
es_cnmc_gen_rdt_2026Generation access capacity at the transmission network (REE's figures in CNMC's map)basis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
9 Sep 2026
Retrieved / confirmed
2026-09-26 05:57 UTClast confirmed unchanged 2026-10-02 07:46 UTC
Source health
Healthy
Provenance
es_cnmc_generation_capacityrecord rdt:PALENCIA 220 · payload sha256 c8edec61051d…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Origen de los datos: Comisión Nacional de los Mercados y la Competencia (CNMC) (last updated 2026-09-09)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: limited by short circuit power
true
Operator note: regulatory reservation
true
Operator note: source field
CAP_ALM_DISPONIBLE_MGES

Injection · Other storage · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: mges_rdt
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-10-02 05:04 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord PALENCIA 220 · payload sha256 986b4e234b81…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: limiting criteria
D_Nudo
Operator note: reason not available
Concurso por resolución SEE.
Operator note: reservation
Concurso

Injection · Other storage · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: mpe_rdt
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-10-02 05:04 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord PALENCIA 220 · payload sha256 986b4e234b81…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: limiting criteria
WSCR_Nudo
Operator note: reason not available
Concurso por resolución SEE.
Operator note: reservation
Concurso

Injection · Other storage · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: mges_rdd
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-10-02 05:04 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord PALENCIA 220 · payload sha256 986b4e234b81…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: limiting criteria
D_Nudo
Operator note: reason not available
Concurso por resolución SEE.
Operator note: reservation
Concurso

Injection · Other storage · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: mpe_rdd
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-10-02 05:04 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord PALENCIA 220 · payload sha256 986b4e234b81…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: limiting criteria
WSCR_Nudo
Operator note: reason not available
Concurso por resolución SEE.
Operator note: reservation
Concurso

Injection · Other storage · Requested

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: alm
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-10-02 05:04 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord PALENCIA 220 · payload sha256 986b4e234b81…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required

Injection · Other storage · Total

1,764 MW

Granted

The operator's latest published dataset reports 1764 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: estatico_nodal
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-10-02 05:04 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord PALENCIA 220 · payload sha256 986b4e234b81…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: criterion
static (N and N-X)

Injection · Other storage · Unknown

827 MW

Granted

The operator's latest published dataset reports 827 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: no_disponible_mges
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-10-02 05:04 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord PALENCIA 220 · payload sha256 986b4e234b81…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: reason not available
Concurso por resolución SEE.
Operator note: reservation
Concurso

Injection · Other storage · Unknown

195 MW

Granted

The operator's latest published dataset reports 195 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: no_disponible_mpe
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-10-02 05:04 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord PALENCIA 220 · payload sha256 986b4e234b81…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: reason not available
Concurso por resolución SEE.
Operator note: reservation
Concurso

Offtake · Load (any) · Allocated

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_dem_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: adicional_valor_referencia
Methodology
es_ree_dem_rdt_2026REE demand access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_demand_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-09-30 09:22 UTC
Source health
Healthy
Provenance
es_ree_demand_access_capacityrecord PALENCIA 220 · payload sha256 5d1236aef6d7…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required

Offtake · Load (any) · Allocated

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_dem_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: cep_wscr
Methodology
es_ree_dem_rdt_2026REE demand access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_demand_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-09-30 09:22 UTC
Source health
Healthy
Provenance
es_ree_demand_access_capacityrecord PALENCIA 220 · payload sha256 5d1236aef6d7…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required

Offtake · Load (any) · Allocated

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_dem_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: rdt
Methodology
es_ree_dem_rdt_2026REE demand access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_demand_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-09-30 09:22 UTC
Source health
Healthy
Provenance
es_ree_demand_access_capacityrecord PALENCIA 220 · payload sha256 5d1236aef6d7…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required

Offtake · Load (any) · Allocated

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_dem_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: aceptabilidad_rdd
Methodology
es_ree_dem_rdt_2026REE demand access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_demand_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-09-30 09:22 UTC
Source health
Healthy
Provenance
es_ree_demand_access_capacityrecord PALENCIA 220 · payload sha256 5d1236aef6d7…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required

Offtake · Load (any) · Allocated

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_dem_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: aceptabilidad_rdd_fuera_referencia
Methodology
es_ree_dem_rdt_2026REE demand access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_demand_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-09-30 09:22 UTC
Source health
Healthy
Provenance
es_ree_demand_access_capacityrecord PALENCIA 220 · payload sha256 5d1236aef6d7…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required

Offtake · Load (any) · Allocated

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_dem_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: ch_rdt
Methodology
es_ree_dem_rdt_2026REE demand access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_demand_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-09-30 09:22 UTC
Source health
Healthy
Provenance
es_ree_demand_access_capacityrecord PALENCIA 220 · payload sha256 5d1236aef6d7…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required

Offtake · Load (any) · Allocated

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_dem_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: sh_rdt
Methodology
es_ree_dem_rdt_2026REE demand access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_demand_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-09-30 09:22 UTC
Source health
Healthy
Provenance
es_ree_demand_access_capacityrecord PALENCIA 220 · payload sha256 5d1236aef6d7…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required

Offtake · Load (any) · Allocated

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_dem_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: ch_aceptabilidad_rdd
Methodology
es_ree_dem_rdt_2026REE demand access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_demand_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-09-30 09:22 UTC
Source health
Healthy
Provenance
es_ree_demand_access_capacityrecord PALENCIA 220 · payload sha256 5d1236aef6d7…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required

Offtake · Load (any) · Allocated

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_dem_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: sh_aceptabilidad_rdd
Methodology
es_ree_dem_rdt_2026REE demand access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_demand_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-09-30 09:22 UTC
Source health
Healthy
Provenance
es_ree_demand_access_capacityrecord PALENCIA 220 · payload sha256 5d1236aef6d7…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required

Offtake · Load (any) · Available

1,167 MW

Granted

The operator's latest published dataset reports 1167 MW under methodology es_ree_dem_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: dinamico1_margen
Methodology
es_ree_dem_rdt_2026REE demand access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_demand_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-09-30 09:22 UTC
Source health
Healthy
Provenance
es_ree_demand_access_capacityrecord PALENCIA 220 · payload sha256 5d1236aef6d7…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: criterion
dynamic 1: CEP demand with voltage-dip ride-through, and non-CEP demand

Offtake · Load (any) · Available

325 MW

Granted

The operator's latest published dataset reports 325 MW under methodology es_ree_dem_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: estatico_margen
Methodology
es_ree_dem_rdt_2026REE demand access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_demand_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-09-30 09:22 UTC
Source health
Healthy
Provenance
es_ree_demand_access_capacityrecord PALENCIA 220 · payload sha256 5d1236aef6d7…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: criterion
static (N and N-X)
Operator note: reason not grantable
Nudo de concurso.
Operator note: temporary access limitation
No

Offtake · Load (any) · Available

325 MW

Granted

The operator's latest published dataset reports 325 MW under methodology es_ree_dem_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: margen_total_no_cep
Methodology
es_ree_dem_rdt_2026REE demand access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_demand_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-09-30 09:22 UTC
Source health
Healthy
Provenance
es_ree_demand_access_capacityrecord PALENCIA 220 · payload sha256 5d1236aef6d7…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: limiting criteria
Est_Dem_Nudo
Operator note: reason not grantable
Nudo de concurso.
Operator note: scope
gross margin, before capacity not grantable at the transmission network
Operator note: temporary access limitation
No
Operator note: tender node
SI

Offtake · Load (any) · Available

295 MW

Granted

The operator's latest published dataset reports 295 MW under methodology es_ree_dem_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: wscr_margen
Methodology
es_ree_dem_rdt_2026REE demand access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_demand_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-09-30 09:22 UTC
Source health
Healthy
Provenance
es_ree_demand_access_capacityrecord PALENCIA 220 · payload sha256 5d1236aef6d7…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: criterion
short-circuit power (WSCR); applies to demand with a power-electronics interface (CEP) only

Offtake · Load (any) · Available

295 MW

Granted

The operator's latest published dataset reports 295 MW under methodology es_ree_dem_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: margen_total_cep_ch
Methodology
es_ree_dem_rdt_2026REE demand access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_demand_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-09-30 09:22 UTC
Source health
Healthy
Provenance
es_ree_demand_access_capacityrecord PALENCIA 220 · payload sha256 5d1236aef6d7…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: limiting criteria
WSCR_Nudo
Operator note: reason not grantable
Nudo de concurso.
Operator note: scope
gross margin, before capacity not grantable at the transmission network
Operator note: temporary access limitation
No
Operator note: tender node
SI

Offtake · Load (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_dem_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: dinamico2_margen
Methodology
es_ree_dem_rdt_2026REE demand access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_demand_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-09-30 09:22 UTC
Source health
Healthy
Provenance
es_ree_demand_access_capacityrecord PALENCIA 220 · payload sha256 5d1236aef6d7…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: criterion
dynamic 2: CEP demand without voltage-dip ride-through

Offtake · Load (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_dem_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: margen_total_cep_sh
Methodology
es_ree_dem_rdt_2026REE demand access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_demand_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-09-30 09:22 UTC
Source health
Healthy
Provenance
es_ree_demand_access_capacityrecord PALENCIA 220 · payload sha256 5d1236aef6d7…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: limiting criteria
Din2_Zona
Operator note: reason not grantable
Nudo de concurso.
Operator note: scope
gross margin, before capacity not grantable at the transmission network
Operator note: temporary access limitation
No
Operator note: tender node
SI

Offtake · Load (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_dem_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: cep_ch
Methodology
es_ree_dem_rdt_2026REE demand access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_demand_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-09-30 09:22 UTC
Source health
Healthy
Provenance
es_ree_demand_access_capacityrecord PALENCIA 220 · payload sha256 5d1236aef6d7…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: limiting criteria
WSCR_Nudo
Operator note: reason not grantable
Nudo de concurso.
Operator note: temporary access limitation
No
Operator note: tender node
SI

Offtake · Load (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_dem_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: cep_sh
Methodology
es_ree_dem_rdt_2026REE demand access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_demand_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-09-30 09:22 UTC
Source health
Healthy
Provenance
es_ree_demand_access_capacityrecord PALENCIA 220 · payload sha256 5d1236aef6d7…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: limiting criteria
Din2_Zona
Operator note: reason not grantable
Nudo de concurso.
Operator note: temporary access limitation
No
Operator note: tender node
SI

Offtake · Load (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_dem_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: no_cep
Methodology
es_ree_dem_rdt_2026REE demand access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_demand_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-09-30 09:22 UTC
Source health
Healthy
Provenance
es_ree_demand_access_capacityrecord PALENCIA 220 · payload sha256 5d1236aef6d7…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: limiting criteria
Est_Dem_Nudo
Operator note: reason not grantable
Nudo de concurso.
Operator note: temporary access limitation
No
Operator note: tender node
SI

Offtake · Load (any) · Requested

169 MW

Granted

The operator's latest published dataset reports 169 MW under methodology es_ree_dem_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: rdt
Methodology
es_ree_dem_rdt_2026REE demand access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_demand_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-09-30 09:22 UTC
Source health
Healthy
Provenance
es_ree_demand_access_capacityrecord PALENCIA 220 · payload sha256 5d1236aef6d7…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required

Offtake · Load (any) · Reserved

259 MW

Granted

The operator's latest published dataset reports 259 MW under methodology es_ree_dem_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: valor_referencia_rdd
Methodology
es_ree_dem_rdt_2026REE demand access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_demand_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-09-30 09:22 UTC
Source health
Healthy
Provenance
es_ree_demand_access_capacityrecord PALENCIA 220 · payload sha256 5d1236aef6d7…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: reference value agreed with dso
SI
Operator note: reserved for
consumption of the underlying distribution network (reference value)

Offtake · Load (any) · Total

584 MW

Granted

The operator's latest published dataset reports 584 MW under methodology es_ree_dem_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: estatico_nodal
Methodology
es_ree_dem_rdt_2026REE demand access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_demand_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-09-30 09:22 UTC
Source health
Healthy
Provenance
es_ree_demand_access_capacityrecord PALENCIA 220 · payload sha256 5d1236aef6d7…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: criterion
static (N and N-X)
Operator note: temporary access limitation
No

Offtake · Load (any) · Total

295 MW

Granted

The operator's latest published dataset reports 295 MW under methodology es_ree_dem_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: wscr_nodal
Methodology
es_ree_dem_rdt_2026REE demand access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_demand_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-09-30 09:22 UTC
Source health
Healthy
Provenance
es_ree_demand_access_capacityrecord PALENCIA 220 · payload sha256 5d1236aef6d7…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: criterion
short-circuit power (WSCR); applies to demand with a power-electronics interface (CEP) only

Offtake · Load (any) · Unknown

325 MW

Granted

The operator's latest published dataset reports 325 MW under methodology es_ree_dem_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: no_otorgable_no_cep
Methodology
es_ree_dem_rdt_2026REE demand access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_demand_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-09-30 09:22 UTC
Source health
Healthy
Provenance
es_ree_demand_access_capacityrecord PALENCIA 220 · payload sha256 5d1236aef6d7…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: reason not grantable
Nudo de concurso.
Operator note: tender node
SI

Offtake · Load (any) · Unknown

295 MW

Granted

The operator's latest published dataset reports 295 MW under methodology es_ree_dem_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: no_otorgable_cep_ch
Methodology
es_ree_dem_rdt_2026REE demand access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_demand_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-09-30 09:22 UTC
Source health
Healthy
Provenance
es_ree_demand_access_capacityrecord PALENCIA 220 · payload sha256 5d1236aef6d7…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: reason not grantable
Nudo de concurso.
Operator note: tender node
SI

Offtake · Load (any) · Unknown

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_dem_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: no_otorgable_cep_sh
Methodology
es_ree_dem_rdt_2026REE demand access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_demand_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-09-30 09:22 UTC
Source health
Healthy
Provenance
es_ree_demand_access_capacityrecord PALENCIA 220 · payload sha256 5d1236aef6d7…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: reason not grantable
Nudo de concurso.
Operator note: tender node
SI

Offtake · Other storage · Allocated

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_dem_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: adicional_valor_referencia
Methodology
es_ree_dem_rdt_2026REE demand access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_demand_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-09-30 09:22 UTC
Source health
Healthy
Provenance
es_ree_demand_access_capacityrecord PALENCIA 220 · payload sha256 5d1236aef6d7…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required

Offtake · Other storage · Allocated

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_dem_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: rdt
Methodology
es_ree_dem_rdt_2026REE demand access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_demand_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-09-30 09:22 UTC
Source health
Healthy
Provenance
es_ree_demand_access_capacityrecord PALENCIA 220 · payload sha256 5d1236aef6d7…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required

Offtake · Other storage · Allocated

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_dem_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: aceptabilidad_rdd
Methodology
es_ree_dem_rdt_2026REE demand access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_demand_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-09-30 09:22 UTC
Source health
Healthy
Provenance
es_ree_demand_access_capacityrecord PALENCIA 220 · payload sha256 5d1236aef6d7…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required

Offtake · Other storage · Allocated

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_dem_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: aceptabilidad_rdd_fuera_referencia
Methodology
es_ree_dem_rdt_2026REE demand access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_demand_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-09-30 09:22 UTC
Source health
Healthy
Provenance
es_ree_demand_access_capacityrecord PALENCIA 220 · payload sha256 5d1236aef6d7…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required

Offtake · Other storage · Available

564 MW

Granted

The operator's latest published dataset reports 564 MW under methodology es_ree_dem_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: estatico_margen
Methodology
es_ree_dem_rdt_2026REE demand access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_demand_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-09-30 09:22 UTC
Source health
Healthy
Provenance
es_ree_demand_access_capacityrecord PALENCIA 220 · payload sha256 5d1236aef6d7…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: criterion
static (N and N-X)

Offtake · Other storage · Available

564 MW

Granted

The operator's latest published dataset reports 564 MW under methodology es_ree_dem_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: margen_total_cep
Methodology
es_ree_dem_rdt_2026REE demand access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_demand_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-09-30 09:22 UTC
Source health
Healthy
Provenance
es_ree_demand_access_capacityrecord PALENCIA 220 · payload sha256 5d1236aef6d7…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: limiting criteria
Est_Alm_Nudo
Operator note: reason not grantable
Nudo de concurso.
Operator note: scope
gross margin, before capacity not grantable at the transmission network
Operator note: temporary access limitation
No
Operator note: tender node
SI

Offtake · Other storage · Available

564 MW

Granted

The operator's latest published dataset reports 564 MW under methodology es_ree_dem_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: margen_total_no_cep
Methodology
es_ree_dem_rdt_2026REE demand access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_demand_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-09-30 09:22 UTC
Source health
Healthy
Provenance
es_ree_demand_access_capacityrecord PALENCIA 220 · payload sha256 5d1236aef6d7…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: limiting criteria
Est_Alm_Nudo
Operator note: reason not grantable
Nudo de concurso.
Operator note: scope
gross margin, before capacity not grantable at the transmission network
Operator note: temporary access limitation
No
Operator note: tender node
SI

Offtake · Other storage · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_dem_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: cep
Methodology
es_ree_dem_rdt_2026REE demand access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_demand_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-09-30 09:22 UTC
Source health
Healthy
Provenance
es_ree_demand_access_capacityrecord PALENCIA 220 · payload sha256 5d1236aef6d7…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: limiting criteria
Est_Alm_Nudo
Operator note: reason not grantable
Nudo de concurso.
Operator note: temporary access limitation
No
Operator note: tender node
SI

Offtake · Other storage · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_dem_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: no_cep
Methodology
es_ree_dem_rdt_2026REE demand access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_demand_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-09-30 09:22 UTC
Source health
Healthy
Provenance
es_ree_demand_access_capacityrecord PALENCIA 220 · payload sha256 5d1236aef6d7…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: limiting criteria
Est_Alm_Nudo
Operator note: reason not grantable
Nudo de concurso.
Operator note: temporary access limitation
No
Operator note: tender node
SI

Offtake · Other storage · Requested

20 MW

Granted

The operator's latest published dataset reports 20 MW under methodology es_ree_dem_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: rdt
Methodology
es_ree_dem_rdt_2026REE demand access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_demand_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-09-30 09:22 UTC
Source health
Healthy
Provenance
es_ree_demand_access_capacityrecord PALENCIA 220 · payload sha256 5d1236aef6d7…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required

Offtake · Other storage · Total

823 MW

Granted

The operator's latest published dataset reports 823 MW under methodology es_ree_dem_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: estatico_nodal
Methodology
es_ree_dem_rdt_2026REE demand access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_demand_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-09-30 09:22 UTC
Source health
Healthy
Provenance
es_ree_demand_access_capacityrecord PALENCIA 220 · payload sha256 5d1236aef6d7…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: criterion
static (N and N-X)

Offtake · Other storage · Unknown

564 MW

Granted

The operator's latest published dataset reports 564 MW under methodology es_ree_dem_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: no_otorgable_cep
Methodology
es_ree_dem_rdt_2026REE demand access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_demand_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-09-30 09:22 UTC
Source health
Healthy
Provenance
es_ree_demand_access_capacityrecord PALENCIA 220 · payload sha256 5d1236aef6d7…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: reason not grantable
Nudo de concurso.
Operator note: tender node
SI

Offtake · Other storage · Unknown

564 MW

Granted

The operator's latest published dataset reports 564 MW under methodology es_ree_dem_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: no_otorgable_no_cep
Methodology
es_ree_dem_rdt_2026REE demand access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_demand_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-09-30 09:22 UTC
Source health
Healthy
Provenance
es_ree_demand_access_capacityrecord PALENCIA 220 · payload sha256 5d1236aef6d7…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: reason not grantable
Nudo de concurso.
Operator note: tender node
SI

History

Served series only

Injection · Generation (any) · Available

current 0 MW

26 Sep 2026: 0 MW
26 Sep 2026range 0 to 0 MW2 Oct 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current0 MW

Time axis: when we observed each value, not the operator’s effective date.

Injection · Generation (any) · Available

current 0 MW

26 Sep 2026: 0 MW
26 Sep 2026range 0 to 0 MW2 Oct 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current0 MW

Time axis: when we observed each value, not the operator’s effective date.

Injection · Other storage · Available

current 0 MW

26 Sep 2026: 0 MW
26 Sep 2026range 0 to 0 MW2 Oct 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current0 MW

Time axis: when we observed each value, not the operator’s effective date.

Injection · Other storage · Available

current 0 MW

26 Sep 2026: 0 MW
26 Sep 2026range 0 to 0 MW2 Oct 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current0 MW

Time axis: when we observed each value, not the operator’s effective date.

Injection · Generation (any) · Allocated

current 358.21 MW

26 Sep 2026: 358.21 MW
26 Sep 2026range 358.21 to 358.21 MW2 Oct 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current358.21 MW

Time axis: when we observed each value, not the operator’s effective date.

Injection · Generation (any) · Requested

current 224.06 MW

26 Sep 2026: 224.06 MW
26 Sep 2026range 224.06 to 224.06 MW2 Oct 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current224.06 MW

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Load (any) · Total

current 295 MW

26 Sep 2026: 295 MW
26 Sep 2026range 295 to 295 MW2 Oct 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current295 MW

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Load (any) · Available

current 295 MW

26 Sep 2026: 295 MW
26 Sep 2026range 295 to 295 MW2 Oct 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current295 MW

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Load (any) · Total

current 584 MW

26 Sep 2026: 584 MW
26 Sep 2026range 584 to 584 MW2 Oct 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current584 MW

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Load (any) · Available

current 325 MW

26 Sep 2026: 325 MW
26 Sep 2026range 325 to 325 MW2 Oct 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current325 MW

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Other storage · Total

current 823 MW

26 Sep 2026: 823 MW
26 Sep 2026range 823 to 823 MW2 Oct 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current823 MW

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Other storage · Available

current 564 MW

26 Sep 2026: 564 MW
26 Sep 2026range 564 to 564 MW2 Oct 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current564 MW

Time axis: when we observed each value, not the operator’s effective date.

The first 12 of 92 served series with a history. The history route returns every one of them.

Through the API

curl "https://api.gridcapacityapi.com/v1/grid-assets/node_06gdrjgwm5s7bdpbpdcn4wga2g/capacity" \  -H "Authorization: Bearer gc_live_..."
PALENCIA 220 kV node: grid capacity (Red Eléctrica de España, S.A.U.) · GridCapacity API