Skip to content

Node / 220 kV / transmission

GUARDO

Red Eléctrica de España, S.A.U. / Velilla del Río Carrión, Palencia, Spain

Latest published values

92 served · 0 withheld

Each row is what the operator’s latest published dataset reports for one combination of direction, technology, measure, firmness and horizon. Hosting-capacity figures are indicative and reflect what operators publish. They are not a connection offer; only the operator can confirm capacity for a specific request.

Latest published capacity values, one row per series
DirectionTechnologyMeasureValueFirmnessHorizonSource date
InjectionGeneration (any)Allocated203 MWUnknownNow (snapshot)variant: mge1 Sep 2026
InjectionGeneration (any)Allocated203 MWUnknownNow (snapshot)variant: gen1 Sep 2026
InjectionGeneration (any)Allocated202.9 MWUnknownNow (snapshot)variant: mge9 Sep 2026
InjectionGeneration (any)Allocated135 MWUnknownNow (snapshot)variant: mges1 Sep 2026
InjectionGeneration (any)Allocated68 MWUnknownNow (snapshot)variant: mpe_con_wscr1 Sep 2026
InjectionGeneration (any)Allocated68 MWUnknownNow (snapshot)variant: mpe1 Sep 2026
InjectionGeneration (any)Allocated0 MWUnknownNow (snapshot)variant: mpe_sin_wscr1 Sep 2026
InjectionGeneration (any)Allocated0 MWUnknownNow (snapshot)variant: autoconsumo_mges1 Sep 2026
InjectionGeneration (any)Allocated0 MWUnknownNow (snapshot)variant: autoconsumo_mpe1 Sep 2026
InjectionGeneration (any)Available1,035 MWUnknownNow (snapshot)variant: dinamico_margen1 Sep 2026
InjectionGeneration (any)Available629 MWUnknownNow (snapshot)variant: margen_total_mges1 Sep 2026
InjectionGeneration (any)Available557 MWUnknownNow (snapshot)variant: estatico_margen1 Sep 2026
InjectionGeneration (any)Available417 MWUnknownNow (snapshot)variant: wscr_margen1 Oct 2026
InjectionGeneration (any)Available417 MWUnknownNow (snapshot)variant: margen_total_mpe1 Oct 2026
InjectionGeneration (any)Available315 MWUnknownNow (snapshot)variant: posicion_margen_mges1 Sep 2026
InjectionGeneration (any)Available315 MWUnknownNow (snapshot)variant: posicion_margen_mpe1 Sep 2026
InjectionGeneration (any)Available0 MWUnknownNow (snapshot)variant: mpe_rdt9 Sep 2026
InjectionGeneration (any)Available0 MWUnknownNow (snapshot)variant: mges_rdt9 Sep 2026
InjectionGeneration (any)Available0 MWUnknownNow (snapshot)variant: mges_rdt1 Sep 2026
InjectionGeneration (any)Available0 MWUnknownNow (snapshot)variant: mpe_rdt1 Sep 2026
InjectionGeneration (any)Available0 MWUnknownNow (snapshot)variant: mges_rdd1 Sep 2026
InjectionGeneration (any)Available0 MWUnknownNow (snapshot)variant: mpe_rdd1 Sep 2026
InjectionGeneration (any)Available0 MWUnknownNow (snapshot)variant: autoconsumo_mges1 Sep 2026
InjectionGeneration (any)Available0 MWUnknownNow (snapshot)variant: autoconsumo_mpe1 Sep 2026
InjectionGeneration (any)Requested0 MWUnknownNow (snapshot)variant: mge9 Sep 2026
InjectionGeneration (any)Requested0 MWUnknownNow (snapshot)variant: mge1 Sep 2026
InjectionGeneration (any)Requested0 MWUnknownNow (snapshot)variant: mges1 Sep 2026
InjectionGeneration (any)Requested0 MWUnknownNow (snapshot)variant: mpe_con_wscr1 Sep 2026
InjectionGeneration (any)Requested0 MWUnknownNow (snapshot)variant: mpe_sin_wscr1 Sep 2026
InjectionGeneration (any)Requested0 MWUnknownNow (snapshot)variant: mpe1 Sep 2026
InjectionGeneration (any)Requested0 MWUnknownNow (snapshot)variant: gen1 Sep 2026
InjectionGeneration (any)Total1,238 MWUnknownNow (snapshot)variant: dinamico_nodal1 Sep 2026
InjectionGeneration (any)Total760 MWUnknownNow (snapshot)variant: estatico_nodal1 Sep 2026
InjectionGeneration (any)Total485 MWUnknownNow (snapshot)variant: wscr_nodal1 Oct 2026
InjectionGeneration (any)Total400 MWUnknownNow (snapshot)variant: posicion_maximo1 Sep 2026
InjectionGeneration (any)Total0 MWUnknownNow (snapshot)variant: autoconsumo_mges1 Sep 2026
InjectionGeneration (any)Total0 MWUnknownNow (snapshot)variant: autoconsumo_mpe1 Sep 2026
InjectionGeneration (any)Totalnot statedUnknownNow (snapshot)variant: dinamico_limitacion_interna1 Sep 2026
InjectionGeneration (any)Unknown629 MWUnknownNow (snapshot)variant: no_disponible_mges1 Sep 2026
InjectionGeneration (any)Unknown417 MWUnknownNow (snapshot)variant: no_disponible_mpe1 Oct 2026
InjectionOther storageAllocated0 MWUnknownNow (snapshot)variant: alm1 Sep 2026
InjectionOther storageAvailable629 MWUnknownNow (snapshot)variant: margen_total_mges1 Sep 2026
InjectionOther storageAvailable579 MWUnknownNow (snapshot)variant: estatico_margen1 Sep 2026
InjectionOther storageAvailable417 MWUnknownNow (snapshot)variant: margen_total_mpe1 Oct 2026
InjectionOther storageAvailable0 MWUnknownNow (snapshot)variant: mpe_rdt9 Sep 2026
InjectionOther storageAvailable0 MWUnknownNow (snapshot)variant: mges_rdt9 Sep 2026
InjectionOther storageAvailable0 MWUnknownNow (snapshot)variant: mges_rdt1 Sep 2026
InjectionOther storageAvailable0 MWUnknownNow (snapshot)variant: mpe_rdt1 Sep 2026
InjectionOther storageAvailable0 MWUnknownNow (snapshot)variant: mges_rdd1 Sep 2026
InjectionOther storageAvailable0 MWUnknownNow (snapshot)variant: mpe_rdd1 Sep 2026
InjectionOther storageRequested0 MWUnknownNow (snapshot)variant: alm1 Sep 2026
InjectionOther storageTotal782 MWUnknownNow (snapshot)variant: estatico_nodal1 Sep 2026
InjectionOther storageUnknown629 MWUnknownNow (snapshot)variant: no_disponible_mges1 Sep 2026
InjectionOther storageUnknown417 MWUnknownNow (snapshot)variant: no_disponible_mpe1 Oct 2026
OfftakeLoad (any)Allocated0 MWUnknownNow (snapshot)variant: adicional_valor_referencia1 Sep 2026
OfftakeLoad (any)Allocated0 MWUnknownNow (snapshot)variant: cep_wscr1 Sep 2026
OfftakeLoad (any)Allocated0 MWUnknownNow (snapshot)variant: rdt1 Sep 2026
OfftakeLoad (any)Allocated0 MWUnknownNow (snapshot)variant: aceptabilidad_rdd1 Sep 2026
OfftakeLoad (any)Allocated0 MWUnknownNow (snapshot)variant: aceptabilidad_rdd_fuera_referencia1 Sep 2026
OfftakeLoad (any)Allocated0 MWUnknownNow (snapshot)variant: ch_rdt1 Sep 2026
OfftakeLoad (any)Allocated0 MWUnknownNow (snapshot)variant: sh_rdt1 Sep 2026
OfftakeLoad (any)Allocated0 MWUnknownNow (snapshot)variant: ch_aceptabilidad_rdd1 Sep 2026
OfftakeLoad (any)Allocated0 MWUnknownNow (snapshot)variant: sh_aceptabilidad_rdd1 Sep 2026
OfftakeLoad (any)Available1,300 MWUnknownNow (snapshot)variant: dinamico1_margen1 Sep 2026
OfftakeLoad (any)Available150 MWUnknownNow (snapshot)variant: estatico_margen1 Sep 2026
OfftakeLoad (any)Available150 MWUnknownNow (snapshot)variant: margen_total_no_cep1 Sep 2026
OfftakeLoad (any)Available150 MWUnknownNow (snapshot)variant: no_cep1 Sep 2026
OfftakeLoad (any)Available0 MWUnknownNow (snapshot)variant: wscr_margen1 Sep 2026
OfftakeLoad (any)Available0 MWUnknownNow (snapshot)variant: dinamico2_margen1 Sep 2026
OfftakeLoad (any)Available0 MWUnknownNow (snapshot)variant: margen_total_cep_ch1 Sep 2026
OfftakeLoad (any)Available0 MWUnknownNow (snapshot)variant: margen_total_cep_sh1 Sep 2026
OfftakeLoad (any)Available0 MWUnknownNow (snapshot)variant: cep_ch1 Sep 2026
OfftakeLoad (any)Available0 MWUnknownNow (snapshot)variant: cep_sh1 Sep 2026
OfftakeLoad (any)Requested0 MWUnknownNow (snapshot)variant: rdt1 Sep 2026
OfftakeLoad (any)Reserved270 MWUnknownNow (snapshot)variant: valor_referencia_rdd1 Sep 2026
OfftakeLoad (any)Total420 MWUnknownNow (snapshot)variant: estatico_nodal1 Sep 2026
OfftakeLoad (any)Total0 MWUnknownNow (snapshot)variant: wscr_nodal1 Sep 2026
OfftakeLoad (any)Unknown0 MWUnknownNow (snapshot)variant: no_otorgable_cep_ch1 Sep 2026
OfftakeLoad (any)Unknown0 MWUnknownNow (snapshot)variant: no_otorgable_cep_sh1 Sep 2026
OfftakeLoad (any)Unknown0 MWUnknownNow (snapshot)variant: no_otorgable_no_cep1 Sep 2026
OfftakeOther storageAllocated0 MWUnknownNow (snapshot)variant: adicional_valor_referencia1 Sep 2026
OfftakeOther storageAllocated0 MWUnknownNow (snapshot)variant: rdt1 Sep 2026
OfftakeOther storageAllocated0 MWUnknownNow (snapshot)variant: aceptabilidad_rdd1 Sep 2026
OfftakeOther storageAllocated0 MWUnknownNow (snapshot)variant: aceptabilidad_rdd_fuera_referencia1 Sep 2026
OfftakeOther storageAvailable332 MWUnknownNow (snapshot)variant: estatico_margen1 Sep 2026
OfftakeOther storageAvailable332 MWUnknownNow (snapshot)variant: margen_total_cep1 Sep 2026
OfftakeOther storageAvailable332 MWUnknownNow (snapshot)variant: margen_total_no_cep1 Sep 2026
OfftakeOther storageAvailable332 MWUnknownNow (snapshot)variant: cep1 Sep 2026
OfftakeOther storageAvailable332 MWUnknownNow (snapshot)variant: no_cep1 Sep 2026
OfftakeOther storageRequested0 MWUnknownNow (snapshot)variant: rdt1 Sep 2026
OfftakeOther storageTotal602 MWUnknownNow (snapshot)variant: estatico_nodal1 Sep 2026
OfftakeOther storageUnknown0 MWUnknownNow (snapshot)variant: no_otorgable_cep1 Sep 2026
OfftakeOther storageUnknown0 MWUnknownNow (snapshot)variant: no_otorgable_no_cep1 Sep 2026

Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-10-01)Origen de los datos: Comisión Nacional de los Mercados y la Competencia (CNMC) (last updated 2026-09-09)

What each value means

Methodology, both clocks, provenance and rights

Injection · Generation (any) · Allocated

203 MW

Granted

The operator's latest published dataset reports 203 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: mge
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-10-02 05:04 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord GUARDO 220 · payload sha256 30407711d504…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: module scope
MGE: all power-generating modules (MGES + MPE, generation and storage)

Injection · Generation (any) · Allocated

203 MW

Granted

The operator's latest published dataset reports 203 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: gen
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-10-02 05:04 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord GUARDO 220 · payload sha256 30407711d504…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: module scope
GEN: generation installations, storage excluded

Injection · Generation (any) · Allocated

202.9 MW

Granted

The operator's latest published dataset reports 202.9 MW under methodology es_cnmc_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: mge
Methodology
es_cnmc_gen_rdt_2026Generation access capacity at the transmission network (REE's figures in CNMC's map)basis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
9 Sep 2026
Retrieved / confirmed
2026-09-26 05:57 UTClast confirmed unchanged 2026-10-02 07:46 UTC
Source health
Healthy
Provenance
es_cnmc_generation_capacityrecord rdt:GUARDO 220 · payload sha256 997e2968bb3a…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Origen de los datos: Comisión Nacional de los Mercados y la Competencia (CNMC) (last updated 2026-09-09)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
CAP_OCUPADA

Injection · Generation (any) · Allocated

135 MW

Granted

The operator's latest published dataset reports 135 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: mges
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-10-02 05:04 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord GUARDO 220 · payload sha256 30407711d504…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required

Injection · Generation (any) · Allocated

68 MW

Granted

The operator's latest published dataset reports 68 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: mpe_con_wscr
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-10-02 05:04 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord GUARDO 220 · payload sha256 30407711d504…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required

Injection · Generation (any) · Allocated

68 MW

Granted

The operator's latest published dataset reports 68 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: mpe
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-10-02 05:04 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord GUARDO 220 · payload sha256 30407711d504…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required

Injection · Generation (any) · Allocated

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: mpe_sin_wscr
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-10-02 05:04 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord GUARDO 220 · payload sha256 30407711d504…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required

Injection · Generation (any) · Allocated

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: autoconsumo_mges
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-10-02 05:04 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord GUARDO 220 · payload sha256 30407711d504…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: eligibility
self-consumption requests only (RDL 7/2026)

Injection · Generation (any) · Allocated

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: autoconsumo_mpe
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-10-02 05:04 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord GUARDO 220 · payload sha256 30407711d504…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: eligibility
self-consumption requests only (RDL 7/2026)

Injection · Generation (any) · Available

1,035 MW

Granted

The operator's latest published dataset reports 1035 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: dinamico_margen
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-10-02 05:04 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord GUARDO 220 · payload sha256 30407711d504…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: criterion
dynamic stability

Injection · Generation (any) · Available

629 MW

Granted

The operator's latest published dataset reports 629 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: margen_total_mges
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-10-02 05:04 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord GUARDO 220 · payload sha256 30407711d504…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: limiting criteria
Est_Gen_Nudo
Operator note: reason not available
Nudo de Transición Justa.
Operator note: reservation
NTJ
Operator note: scope
gross margin, before capacity not available for requests
Operator note: specific regulation
Orden TED/345/2024

Injection · Generation (any) · Available

557 MW

Granted

The operator's latest published dataset reports 557 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: estatico_margen
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-10-02 05:04 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord GUARDO 220 · payload sha256 30407711d504…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: criterion
static (N and N-X)

Injection · Generation (any) · Available

417 MW

Granted

The operator's latest published dataset reports 417 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: wscr_margen
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Oct 2026
Retrieved / confirmed
2026-10-01 07:14 UTClast confirmed unchanged 2026-10-02 05:04 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord GUARDO 220 · payload sha256 5f1b9f59d2c5…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-10-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: criterion
short-circuit power (WSCR); applies to power park modules (MPE) only

Injection · Generation (any) · Available

417 MW

Granted

The operator's latest published dataset reports 417 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: margen_total_mpe
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Oct 2026
Retrieved / confirmed
2026-10-01 07:14 UTClast confirmed unchanged 2026-10-02 05:04 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord GUARDO 220 · payload sha256 5f1b9f59d2c5…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-10-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: limiting criteria
WSCR_Nudo
Operator note: reason not available
Nudo de Transición Justa.
Operator note: reservation
NTJ
Operator note: scope
gross margin, before capacity not available for requests
Operator note: specific regulation
Orden TED/345/2024

Injection · Generation (any) · Available

315 MW

Granted

The operator's latest published dataset reports 315 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: posicion_margen_mges
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-10-02 05:04 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord GUARDO 220 · payload sha256 30407711d504…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required

Injection · Generation (any) · Available

315 MW

Granted

The operator's latest published dataset reports 315 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: posicion_margen_mpe
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-10-02 05:04 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord GUARDO 220 · payload sha256 30407711d504…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required

Injection · Generation (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_cnmc_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: mpe_rdt
Methodology
es_cnmc_gen_rdt_2026Generation access capacity at the transmission network (REE's figures in CNMC's map)basis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
9 Sep 2026
Retrieved / confirmed
2026-09-26 05:57 UTClast confirmed unchanged 2026-10-02 07:46 UTC
Source health
Healthy
Provenance
es_cnmc_generation_capacityrecord rdt:GUARDO 220 · payload sha256 997e2968bb3a…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Origen de los datos: Comisión Nacional de los Mercados y la Competencia (CNMC) (last updated 2026-09-09)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: limited by short circuit power
true
Operator note: regulatory reservation
true
Operator note: source field
CAP_DISPONIBLE_MPE

Injection · Generation (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_cnmc_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: mges_rdt
Methodology
es_cnmc_gen_rdt_2026Generation access capacity at the transmission network (REE's figures in CNMC's map)basis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
9 Sep 2026
Retrieved / confirmed
2026-09-26 05:57 UTClast confirmed unchanged 2026-10-02 07:46 UTC
Source health
Healthy
Provenance
es_cnmc_generation_capacityrecord rdt:GUARDO 220 · payload sha256 997e2968bb3a…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Origen de los datos: Comisión Nacional de los Mercados y la Competencia (CNMC) (last updated 2026-09-09)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: limited by short circuit power
true
Operator note: regulatory reservation
true
Operator note: source field
CAP_DISPONIBLE_MGES

Injection · Generation (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: mges_rdt
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-10-02 05:04 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord GUARDO 220 · payload sha256 30407711d504…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: limiting criteria
Est_Gen_Nudo
Operator note: reason not available
Nudo de Transición Justa.
Operator note: reservation
NTJ
Operator note: specific regulation
Orden TED/345/2024

Injection · Generation (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: mpe_rdt
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-10-02 05:04 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord GUARDO 220 · payload sha256 30407711d504…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: limiting criteria
WSCR_Nudo
Operator note: reason not available
Nudo de Transición Justa.
Operator note: reservation
NTJ
Operator note: specific regulation
Orden TED/345/2024

Injection · Generation (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: mges_rdd
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-10-02 05:04 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord GUARDO 220 · payload sha256 30407711d504…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: limiting criteria
Est_Gen_Nudo
Operator note: reason not available
Nudo de Transición Justa.
Operator note: reservation
NTJ
Operator note: specific regulation
Orden TED/345/2024

Injection · Generation (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: mpe_rdd
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-10-02 05:04 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord GUARDO 220 · payload sha256 30407711d504…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: limiting criteria
WSCR_Nudo
Operator note: reason not available
Nudo de Transición Justa.
Operator note: reservation
NTJ
Operator note: specific regulation
Orden TED/345/2024

Injection · Generation (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: autoconsumo_mges
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-10-02 05:04 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord GUARDO 220 · payload sha256 30407711d504…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: eligibility
self-consumption requests only (RDL 7/2026)

Injection · Generation (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: autoconsumo_mpe
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-10-02 05:04 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord GUARDO 220 · payload sha256 30407711d504…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: eligibility
self-consumption requests only (RDL 7/2026)

Injection · Generation (any) · Requested

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_cnmc_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: mge
Methodology
es_cnmc_gen_rdt_2026Generation access capacity at the transmission network (REE's figures in CNMC's map)basis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
9 Sep 2026
Retrieved / confirmed
2026-09-26 05:57 UTClast confirmed unchanged 2026-10-02 07:46 UTC
Source health
Healthy
Provenance
es_cnmc_generation_capacityrecord rdt:GUARDO 220 · payload sha256 997e2968bb3a…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Origen de los datos: Comisión Nacional de los Mercados y la Competencia (CNMC) (last updated 2026-09-09)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
CAP_ADMITIDA_NO_RESUELTA

Injection · Generation (any) · Requested

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: mge
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-10-02 05:04 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord GUARDO 220 · payload sha256 30407711d504…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required

Injection · Generation (any) · Requested

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: mges
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-10-02 05:04 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord GUARDO 220 · payload sha256 30407711d504…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required

Injection · Generation (any) · Requested

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: mpe_con_wscr
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-10-02 05:04 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord GUARDO 220 · payload sha256 30407711d504…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required

Injection · Generation (any) · Requested

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: mpe_sin_wscr
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-10-02 05:04 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord GUARDO 220 · payload sha256 30407711d504…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required

Injection · Generation (any) · Requested

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: mpe
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-10-02 05:04 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord GUARDO 220 · payload sha256 30407711d504…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required

Injection · Generation (any) · Requested

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: gen
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-10-02 05:04 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord GUARDO 220 · payload sha256 30407711d504…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required

Injection · Generation (any) · Total

1,238 MW

Granted

The operator's latest published dataset reports 1238 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: dinamico_nodal
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-10-02 05:04 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord GUARDO 220 · payload sha256 30407711d504…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: criterion
dynamic stability

Injection · Generation (any) · Total

760 MW

Granted

The operator's latest published dataset reports 760 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: estatico_nodal
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-10-02 05:04 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord GUARDO 220 · payload sha256 30407711d504…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: criterion
static (N and N-X)

Injection · Generation (any) · Total

485 MW

Granted

The operator's latest published dataset reports 485 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: wscr_nodal
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Oct 2026
Retrieved / confirmed
2026-10-01 07:14 UTClast confirmed unchanged 2026-10-02 05:04 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord GUARDO 220 · payload sha256 5f1b9f59d2c5…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-10-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: criterion
short-circuit power (WSCR); applies to power park modules (MPE) only

Injection · Generation (any) · Total

400 MW

Granted

The operator's latest published dataset reports 400 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: posicion_maximo
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-10-02 05:04 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord GUARDO 220 · payload sha256 30407711d504…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required

Injection · Generation (any) · Total

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: autoconsumo_mges
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-10-02 05:04 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord GUARDO 220 · payload sha256 30407711d504…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: eligibility
self-consumption requests only (RDL 7/2026)

Injection · Generation (any) · Total

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: autoconsumo_mpe
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-10-02 05:04 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord GUARDO 220 · payload sha256 30407711d504…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: eligibility
self-consumption requests only (RDL 7/2026)

Injection · Generation (any) · Total

not stated

Published in MW; no MW figure is derived from it.

Granted

The operator's latest published dataset reports no value (published as unknown) under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: dinamico_limitacion_interna
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-10-02 05:04 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord GUARDO 220 · payload sha256 30407711d504…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: criterion
dynamic stability
Operator note: source label
N/A

Injection · Generation (any) · Unknown

629 MW

Granted

The operator's latest published dataset reports 629 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: no_disponible_mges
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-10-02 05:04 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord GUARDO 220 · payload sha256 30407711d504…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: reason not available
Nudo de Transición Justa.
Operator note: reservation
NTJ

Injection · Generation (any) · Unknown

417 MW

Granted

The operator's latest published dataset reports 417 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: no_disponible_mpe
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Oct 2026
Retrieved / confirmed
2026-10-01 07:14 UTClast confirmed unchanged 2026-10-02 05:04 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord GUARDO 220 · payload sha256 5f1b9f59d2c5…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-10-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: reason not available
Nudo de Transición Justa.
Operator note: reservation
NTJ

Injection · Other storage · Allocated

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: alm
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-10-02 05:04 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord GUARDO 220 · payload sha256 30407711d504…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required

Injection · Other storage · Available

629 MW

Granted

The operator's latest published dataset reports 629 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: margen_total_mges
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-10-02 05:04 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord GUARDO 220 · payload sha256 30407711d504…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: limiting criteria
Est_Alm_Nudo
Operator note: reason not available
Nudo de Transición Justa.
Operator note: reservation
NTJ
Operator note: scope
gross margin, before capacity not available for requests
Operator note: specific regulation
Orden TED/345/2024

Injection · Other storage · Available

579 MW

Granted

The operator's latest published dataset reports 579 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: estatico_margen
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-10-02 05:04 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord GUARDO 220 · payload sha256 30407711d504…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: criterion
static (N and N-X)

Injection · Other storage · Available

417 MW

Granted

The operator's latest published dataset reports 417 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: margen_total_mpe
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Oct 2026
Retrieved / confirmed
2026-10-01 07:14 UTClast confirmed unchanged 2026-10-02 05:04 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord GUARDO 220 · payload sha256 5f1b9f59d2c5…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-10-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: limiting criteria
WSCR_Nudo
Operator note: reason not available
Nudo de Transición Justa.
Operator note: reservation
NTJ
Operator note: scope
gross margin, before capacity not available for requests
Operator note: specific regulation
Orden TED/345/2024

Injection · Other storage · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_cnmc_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: mpe_rdt
Methodology
es_cnmc_gen_rdt_2026Generation access capacity at the transmission network (REE's figures in CNMC's map)basis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
9 Sep 2026
Retrieved / confirmed
2026-09-26 05:57 UTClast confirmed unchanged 2026-10-02 07:46 UTC
Source health
Healthy
Provenance
es_cnmc_generation_capacityrecord rdt:GUARDO 220 · payload sha256 997e2968bb3a…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Origen de los datos: Comisión Nacional de los Mercados y la Competencia (CNMC) (last updated 2026-09-09)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: limited by short circuit power
true
Operator note: regulatory reservation
true
Operator note: source field
CAP_ALM_DISPONIBLE_MPE

Injection · Other storage · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_cnmc_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: mges_rdt
Methodology
es_cnmc_gen_rdt_2026Generation access capacity at the transmission network (REE's figures in CNMC's map)basis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
9 Sep 2026
Retrieved / confirmed
2026-09-26 05:57 UTClast confirmed unchanged 2026-10-02 07:46 UTC
Source health
Healthy
Provenance
es_cnmc_generation_capacityrecord rdt:GUARDO 220 · payload sha256 997e2968bb3a…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Origen de los datos: Comisión Nacional de los Mercados y la Competencia (CNMC) (last updated 2026-09-09)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: limited by short circuit power
true
Operator note: regulatory reservation
true
Operator note: source field
CAP_ALM_DISPONIBLE_MGES

Injection · Other storage · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: mges_rdt
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-10-02 05:04 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord GUARDO 220 · payload sha256 30407711d504…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: limiting criteria
Est_Alm_Nudo
Operator note: reason not available
Nudo de Transición Justa.
Operator note: reservation
NTJ
Operator note: specific regulation
Orden TED/345/2024

Injection · Other storage · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: mpe_rdt
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-10-02 05:04 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord GUARDO 220 · payload sha256 30407711d504…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: limiting criteria
WSCR_Nudo
Operator note: reason not available
Nudo de Transición Justa.
Operator note: reservation
NTJ
Operator note: specific regulation
Orden TED/345/2024

Injection · Other storage · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: mges_rdd
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-10-02 05:04 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord GUARDO 220 · payload sha256 30407711d504…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: limiting criteria
Est_Alm_Nudo
Operator note: reason not available
Nudo de Transición Justa.
Operator note: reservation
NTJ
Operator note: specific regulation
Orden TED/345/2024

Injection · Other storage · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: mpe_rdd
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-10-02 05:04 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord GUARDO 220 · payload sha256 30407711d504…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: limiting criteria
WSCR_Nudo
Operator note: reason not available
Nudo de Transición Justa.
Operator note: reservation
NTJ
Operator note: specific regulation
Orden TED/345/2024

Injection · Other storage · Requested

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: alm
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-10-02 05:04 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord GUARDO 220 · payload sha256 30407711d504…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required

Injection · Other storage · Total

782 MW

Granted

The operator's latest published dataset reports 782 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: estatico_nodal
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-10-02 05:04 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord GUARDO 220 · payload sha256 30407711d504…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: criterion
static (N and N-X)

Injection · Other storage · Unknown

629 MW

Granted

The operator's latest published dataset reports 629 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: no_disponible_mges
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-10-02 05:04 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord GUARDO 220 · payload sha256 30407711d504…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: reason not available
Nudo de Transición Justa.
Operator note: reservation
NTJ

Injection · Other storage · Unknown

417 MW

Granted

The operator's latest published dataset reports 417 MW under methodology es_ree_gen_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: no_disponible_mpe
Methodology
es_ree_gen_rdt_2026REE generation access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Oct 2026
Retrieved / confirmed
2026-10-01 07:14 UTClast confirmed unchanged 2026-10-02 05:04 UTC
Source health
Healthy
Provenance
es_ree_generation_access_capacityrecord GUARDO 220 · payload sha256 5f1b9f59d2c5…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-10-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: reason not available
Nudo de Transición Justa.
Operator note: reservation
NTJ

Offtake · Load (any) · Allocated

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_dem_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: adicional_valor_referencia
Methodology
es_ree_dem_rdt_2026REE demand access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_demand_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-09-30 09:22 UTC
Source health
Healthy
Provenance
es_ree_demand_access_capacityrecord GUARDO 220 · payload sha256 3c49902dbd85…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required

Offtake · Load (any) · Allocated

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_dem_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: cep_wscr
Methodology
es_ree_dem_rdt_2026REE demand access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_demand_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-09-30 09:22 UTC
Source health
Healthy
Provenance
es_ree_demand_access_capacityrecord GUARDO 220 · payload sha256 3c49902dbd85…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required

Offtake · Load (any) · Allocated

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_dem_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: rdt
Methodology
es_ree_dem_rdt_2026REE demand access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_demand_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-09-30 09:22 UTC
Source health
Healthy
Provenance
es_ree_demand_access_capacityrecord GUARDO 220 · payload sha256 3c49902dbd85…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required

Offtake · Load (any) · Allocated

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_dem_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: aceptabilidad_rdd
Methodology
es_ree_dem_rdt_2026REE demand access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_demand_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-09-30 09:22 UTC
Source health
Healthy
Provenance
es_ree_demand_access_capacityrecord GUARDO 220 · payload sha256 3c49902dbd85…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required

Offtake · Load (any) · Allocated

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_dem_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: aceptabilidad_rdd_fuera_referencia
Methodology
es_ree_dem_rdt_2026REE demand access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_demand_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-09-30 09:22 UTC
Source health
Healthy
Provenance
es_ree_demand_access_capacityrecord GUARDO 220 · payload sha256 3c49902dbd85…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required

Offtake · Load (any) · Allocated

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_dem_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: ch_rdt
Methodology
es_ree_dem_rdt_2026REE demand access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_demand_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-09-30 09:22 UTC
Source health
Healthy
Provenance
es_ree_demand_access_capacityrecord GUARDO 220 · payload sha256 3c49902dbd85…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required

Offtake · Load (any) · Allocated

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_dem_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: sh_rdt
Methodology
es_ree_dem_rdt_2026REE demand access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_demand_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-09-30 09:22 UTC
Source health
Healthy
Provenance
es_ree_demand_access_capacityrecord GUARDO 220 · payload sha256 3c49902dbd85…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required

Offtake · Load (any) · Allocated

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_dem_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: ch_aceptabilidad_rdd
Methodology
es_ree_dem_rdt_2026REE demand access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_demand_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-09-30 09:22 UTC
Source health
Healthy
Provenance
es_ree_demand_access_capacityrecord GUARDO 220 · payload sha256 3c49902dbd85…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required

Offtake · Load (any) · Allocated

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_dem_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: sh_aceptabilidad_rdd
Methodology
es_ree_dem_rdt_2026REE demand access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_demand_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-09-30 09:22 UTC
Source health
Healthy
Provenance
es_ree_demand_access_capacityrecord GUARDO 220 · payload sha256 3c49902dbd85…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required

Offtake · Load (any) · Available

1,300 MW

Granted

The operator's latest published dataset reports 1300 MW under methodology es_ree_dem_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: dinamico1_margen
Methodology
es_ree_dem_rdt_2026REE demand access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_demand_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-09-30 09:22 UTC
Source health
Healthy
Provenance
es_ree_demand_access_capacityrecord GUARDO 220 · payload sha256 3c49902dbd85…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: criterion
dynamic 1: CEP demand with voltage-dip ride-through, and non-CEP demand

Offtake · Load (any) · Available

150 MW

Granted

The operator's latest published dataset reports 150 MW under methodology es_ree_dem_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: estatico_margen
Methodology
es_ree_dem_rdt_2026REE demand access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_demand_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-09-30 09:22 UTC
Source health
Healthy
Provenance
es_ree_demand_access_capacityrecord GUARDO 220 · payload sha256 3c49902dbd85…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: criterion
static (N and N-X)
Operator note: temporary access limitation
No

Offtake · Load (any) · Available

150 MW

Granted

The operator's latest published dataset reports 150 MW under methodology es_ree_dem_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: margen_total_no_cep
Methodology
es_ree_dem_rdt_2026REE demand access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_demand_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-09-30 09:22 UTC
Source health
Healthy
Provenance
es_ree_demand_access_capacityrecord GUARDO 220 · payload sha256 3c49902dbd85…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: limiting criteria
Est_Dem_Nudo
Operator note: scope
gross margin, before capacity not grantable at the transmission network
Operator note: temporary access limitation
No

Offtake · Load (any) · Available

150 MW

Granted

The operator's latest published dataset reports 150 MW under methodology es_ree_dem_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: no_cep
Methodology
es_ree_dem_rdt_2026REE demand access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_demand_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-09-30 09:22 UTC
Source health
Healthy
Provenance
es_ree_demand_access_capacityrecord GUARDO 220 · payload sha256 3c49902dbd85…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: limiting criteria
Est_Dem_Nudo
Operator note: temporary access limitation
No

Offtake · Load (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_dem_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: wscr_margen
Methodology
es_ree_dem_rdt_2026REE demand access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_demand_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-09-30 09:22 UTC
Source health
Healthy
Provenance
es_ree_demand_access_capacityrecord GUARDO 220 · payload sha256 3c49902dbd85…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: criterion
short-circuit power (WSCR); applies to demand with a power-electronics interface (CEP) only

Offtake · Load (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_dem_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: dinamico2_margen
Methodology
es_ree_dem_rdt_2026REE demand access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_demand_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-09-30 09:22 UTC
Source health
Healthy
Provenance
es_ree_demand_access_capacityrecord GUARDO 220 · payload sha256 3c49902dbd85…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: criterion
dynamic 2: CEP demand without voltage-dip ride-through

Offtake · Load (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_dem_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: margen_total_cep_ch
Methodology
es_ree_dem_rdt_2026REE demand access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_demand_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-09-30 09:22 UTC
Source health
Healthy
Provenance
es_ree_demand_access_capacityrecord GUARDO 220 · payload sha256 3c49902dbd85…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: limiting criteria
WSCR_Nudo
Operator note: scope
gross margin, before capacity not grantable at the transmission network
Operator note: temporary access limitation
No

Offtake · Load (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_dem_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: margen_total_cep_sh
Methodology
es_ree_dem_rdt_2026REE demand access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_demand_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-09-30 09:22 UTC
Source health
Healthy
Provenance
es_ree_demand_access_capacityrecord GUARDO 220 · payload sha256 3c49902dbd85…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: limiting criteria
Din2_Zona
Operator note: scope
gross margin, before capacity not grantable at the transmission network
Operator note: temporary access limitation
No

Offtake · Load (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_dem_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: cep_ch
Methodology
es_ree_dem_rdt_2026REE demand access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_demand_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-09-30 09:22 UTC
Source health
Healthy
Provenance
es_ree_demand_access_capacityrecord GUARDO 220 · payload sha256 3c49902dbd85…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: limiting criteria
WSCR_Nudo
Operator note: temporary access limitation
No

Offtake · Load (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_dem_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: cep_sh
Methodology
es_ree_dem_rdt_2026REE demand access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_demand_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-09-30 09:22 UTC
Source health
Healthy
Provenance
es_ree_demand_access_capacityrecord GUARDO 220 · payload sha256 3c49902dbd85…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: limiting criteria
Din2_Zona
Operator note: temporary access limitation
No

Offtake · Load (any) · Requested

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_dem_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: rdt
Methodology
es_ree_dem_rdt_2026REE demand access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_demand_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-09-30 09:22 UTC
Source health
Healthy
Provenance
es_ree_demand_access_capacityrecord GUARDO 220 · payload sha256 3c49902dbd85…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required

Offtake · Load (any) · Reserved

270 MW

Granted

The operator's latest published dataset reports 270 MW under methodology es_ree_dem_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: valor_referencia_rdd
Methodology
es_ree_dem_rdt_2026REE demand access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_demand_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-09-30 09:22 UTC
Source health
Healthy
Provenance
es_ree_demand_access_capacityrecord GUARDO 220 · payload sha256 3c49902dbd85…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: reference value agreed with dso
SI
Operator note: reserved for
consumption of the underlying distribution network (reference value)

Offtake · Load (any) · Total

420 MW

Granted

The operator's latest published dataset reports 420 MW under methodology es_ree_dem_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: estatico_nodal
Methodology
es_ree_dem_rdt_2026REE demand access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_demand_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-09-30 09:22 UTC
Source health
Healthy
Provenance
es_ree_demand_access_capacityrecord GUARDO 220 · payload sha256 3c49902dbd85…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: criterion
static (N and N-X)
Operator note: temporary access limitation
No

Offtake · Load (any) · Total

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_dem_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: wscr_nodal
Methodology
es_ree_dem_rdt_2026REE demand access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_demand_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-09-30 09:22 UTC
Source health
Healthy
Provenance
es_ree_demand_access_capacityrecord GUARDO 220 · payload sha256 3c49902dbd85…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: criterion
short-circuit power (WSCR); applies to demand with a power-electronics interface (CEP) only

Offtake · Load (any) · Unknown

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_dem_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: no_otorgable_cep_ch
Methodology
es_ree_dem_rdt_2026REE demand access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_demand_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-09-30 09:22 UTC
Source health
Healthy
Provenance
es_ree_demand_access_capacityrecord GUARDO 220 · payload sha256 3c49902dbd85…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required

Offtake · Load (any) · Unknown

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_dem_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: no_otorgable_cep_sh
Methodology
es_ree_dem_rdt_2026REE demand access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_demand_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-09-30 09:22 UTC
Source health
Healthy
Provenance
es_ree_demand_access_capacityrecord GUARDO 220 · payload sha256 3c49902dbd85…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required

Offtake · Load (any) · Unknown

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_dem_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: no_otorgable_no_cep
Methodology
es_ree_dem_rdt_2026REE demand access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_demand_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-09-30 09:22 UTC
Source health
Healthy
Provenance
es_ree_demand_access_capacityrecord GUARDO 220 · payload sha256 3c49902dbd85…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required

Offtake · Other storage · Allocated

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_dem_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: adicional_valor_referencia
Methodology
es_ree_dem_rdt_2026REE demand access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_demand_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-09-30 09:22 UTC
Source health
Healthy
Provenance
es_ree_demand_access_capacityrecord GUARDO 220 · payload sha256 3c49902dbd85…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required

Offtake · Other storage · Allocated

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_dem_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: rdt
Methodology
es_ree_dem_rdt_2026REE demand access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_demand_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-09-30 09:22 UTC
Source health
Healthy
Provenance
es_ree_demand_access_capacityrecord GUARDO 220 · payload sha256 3c49902dbd85…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required

Offtake · Other storage · Allocated

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_dem_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: aceptabilidad_rdd
Methodology
es_ree_dem_rdt_2026REE demand access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_demand_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-09-30 09:22 UTC
Source health
Healthy
Provenance
es_ree_demand_access_capacityrecord GUARDO 220 · payload sha256 3c49902dbd85…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required

Offtake · Other storage · Allocated

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_dem_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: aceptabilidad_rdd_fuera_referencia
Methodology
es_ree_dem_rdt_2026REE demand access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_demand_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-09-30 09:22 UTC
Source health
Healthy
Provenance
es_ree_demand_access_capacityrecord GUARDO 220 · payload sha256 3c49902dbd85…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required

Offtake · Other storage · Available

332 MW

Granted

The operator's latest published dataset reports 332 MW under methodology es_ree_dem_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: estatico_margen
Methodology
es_ree_dem_rdt_2026REE demand access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_demand_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-09-30 09:22 UTC
Source health
Healthy
Provenance
es_ree_demand_access_capacityrecord GUARDO 220 · payload sha256 3c49902dbd85…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: criterion
static (N and N-X)

Offtake · Other storage · Available

332 MW

Granted

The operator's latest published dataset reports 332 MW under methodology es_ree_dem_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: margen_total_cep
Methodology
es_ree_dem_rdt_2026REE demand access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_demand_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-09-30 09:22 UTC
Source health
Healthy
Provenance
es_ree_demand_access_capacityrecord GUARDO 220 · payload sha256 3c49902dbd85…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: limiting criteria
Est_Alm_Nudo
Operator note: scope
gross margin, before capacity not grantable at the transmission network
Operator note: temporary access limitation
No

Offtake · Other storage · Available

332 MW

Granted

The operator's latest published dataset reports 332 MW under methodology es_ree_dem_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: margen_total_no_cep
Methodology
es_ree_dem_rdt_2026REE demand access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_demand_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-09-30 09:22 UTC
Source health
Healthy
Provenance
es_ree_demand_access_capacityrecord GUARDO 220 · payload sha256 3c49902dbd85…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: limiting criteria
Est_Alm_Nudo
Operator note: scope
gross margin, before capacity not grantable at the transmission network
Operator note: temporary access limitation
No

Offtake · Other storage · Available

332 MW

Granted

The operator's latest published dataset reports 332 MW under methodology es_ree_dem_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: cep
Methodology
es_ree_dem_rdt_2026REE demand access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_demand_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-09-30 09:22 UTC
Source health
Healthy
Provenance
es_ree_demand_access_capacityrecord GUARDO 220 · payload sha256 3c49902dbd85…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: limiting criteria
Est_Alm_Nudo
Operator note: temporary access limitation
No

Offtake · Other storage · Available

332 MW

Granted

The operator's latest published dataset reports 332 MW under methodology es_ree_dem_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: no_cep
Methodology
es_ree_dem_rdt_2026REE demand access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_demand_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-09-30 09:22 UTC
Source health
Healthy
Provenance
es_ree_demand_access_capacityrecord GUARDO 220 · payload sha256 3c49902dbd85…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: limiting criteria
Est_Alm_Nudo
Operator note: temporary access limitation
No

Offtake · Other storage · Requested

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_dem_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: rdt
Methodology
es_ree_dem_rdt_2026REE demand access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_demand_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-09-30 09:22 UTC
Source health
Healthy
Provenance
es_ree_demand_access_capacityrecord GUARDO 220 · payload sha256 3c49902dbd85…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required

Offtake · Other storage · Total

602 MW

Granted

The operator's latest published dataset reports 602 MW under methodology es_ree_dem_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: estatico_nodal
Methodology
es_ree_dem_rdt_2026REE demand access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_demand_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-09-30 09:22 UTC
Source health
Healthy
Provenance
es_ree_demand_access_capacityrecord GUARDO 220 · payload sha256 3c49902dbd85…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: criterion
static (N and N-X)

Offtake · Other storage · Unknown

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_dem_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: no_otorgable_cep
Methodology
es_ree_dem_rdt_2026REE demand access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_demand_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-09-30 09:22 UTC
Source health
Healthy
Provenance
es_ree_demand_access_capacityrecord GUARDO 220 · payload sha256 3c49902dbd85…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required

Offtake · Other storage · Unknown

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_ree_dem_rdt_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: no_otorgable_no_cep
Methodology
es_ree_dem_rdt_2026REE demand access-capacity study, transmission nodesbasis operator calculated · network state unknown · comparability class es_rdt_demand_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Sep 2026
Retrieved / confirmed
2026-09-26 05:58 UTClast confirmed unchanged 2026-09-30 09:22 UTC
Source health
Healthy
Provenance
es_ree_demand_access_capacityrecord GUARDO 220 · payload sha256 3c49902dbd85…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Fuente: Red Eléctrica de España (REE), capacidad de acceso (last updated 2026-09-01)
Decision context
Not binding · indicative · a formal connection study is required

History

Served series only

Injection · Generation (any) · Available

current 0 MW

26 Sep 2026: 0 MW
26 Sep 2026range 0 to 0 MW2 Oct 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current0 MW

Time axis: when we observed each value, not the operator’s effective date.

Injection · Generation (any) · Available

current 0 MW

26 Sep 2026: 0 MW
26 Sep 2026range 0 to 0 MW2 Oct 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current0 MW

Time axis: when we observed each value, not the operator’s effective date.

Injection · Other storage · Available

current 0 MW

26 Sep 2026: 0 MW
26 Sep 2026range 0 to 0 MW2 Oct 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current0 MW

Time axis: when we observed each value, not the operator’s effective date.

Injection · Other storage · Available

current 0 MW

26 Sep 2026: 0 MW
26 Sep 2026range 0 to 0 MW2 Oct 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current0 MW

Time axis: when we observed each value, not the operator’s effective date.

Injection · Generation (any) · Allocated

current 202.9 MW

26 Sep 2026: 202.9 MW
26 Sep 2026range 202.9 to 202.9 MW2 Oct 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current202.9 MW

Time axis: when we observed each value, not the operator’s effective date.

Injection · Generation (any) · Requested

current 0 MW

26 Sep 2026: 0 MW
26 Sep 2026range 0 to 0 MW2 Oct 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current0 MW

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Load (any) · Total

current 0 MW

26 Sep 2026: 0 MW
26 Sep 2026range 0 to 0 MW2 Oct 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current0 MW

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Load (any) · Available

current 0 MW

26 Sep 2026: 0 MW
26 Sep 2026range 0 to 0 MW2 Oct 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current0 MW

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Load (any) · Total

current 420 MW

26 Sep 2026: 420 MW
26 Sep 2026range 420 to 420 MW2 Oct 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current420 MW

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Load (any) · Available

current 150 MW

26 Sep 2026: 150 MW
26 Sep 2026range 150 to 150 MW2 Oct 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current150 MW

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Other storage · Total

current 602 MW

26 Sep 2026: 602 MW
26 Sep 2026range 602 to 602 MW2 Oct 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current602 MW

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Other storage · Available

current 332 MW

26 Sep 2026: 332 MW
26 Sep 2026range 332 to 332 MW2 Oct 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current332 MW

Time axis: when we observed each value, not the operator’s effective date.

The first 12 of 92 served series with a history. The history route returns every one of them.

Through the API

curl "https://api.gridcapacityapi.com/v1/grid-assets/node_06gdrjgwmxte9bytf2m3c2xcyc/capacity" \  -H "Authorization: Bearer gc_live_..."
GUARDO 220 kV node: grid capacity (Red Eléctrica de España, S.A.U.) · GridCapacity API