| Injection | Generation (any) | Available | 300 MW | Firm, ≤ 0 % curtailment a year | 2029 (2029)variant: 380kv | 17 Nov 2026 |
| Injection | Generation (any) | Available | 11.7 MW | Firm, ≤ 0 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Injection | Generation (any) | Available | 300 MW | Flexible, ≤ 5 % curtailment a year | 2029 (2029)variant: 380kv | 17 Nov 2026 |
| Injection | Generation (any) | Available | 23.2 MW | Flexible, ≤ 5 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Injection | Generation (any) | Available | 300 MW | Flexible, ≤ 10 % curtailment a year | 2029 (2029)variant: 380kv | 17 Nov 2026 |
| Injection | Generation (any) | Available | 50.7 MW | Flexible, ≤ 10 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Injection | Generation (any) | Available | 300 MW | Flexible, ≤ 20 % curtailment a year | 2029 (2029)variant: 380kv | 17 Nov 2026 |
| Injection | Generation (any) | Available | 238.2 MW | Flexible, ≤ 20 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Injection | Generation (any) | Available | 300 MW | Firm, ≤ 0 % curtailment a year | 2033 (2033)variant: 380kv | 17 Nov 2026 |
| Injection | Generation (any) | Available | 208.5 MW | Firm, ≤ 0 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |
| Injection | Generation (any) | Available | 300 MW | Flexible, ≤ 5 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |
| Injection | Generation (any) | Available | 300 MW | Flexible, ≤ 5 % curtailment a year | 2033 (2033)variant: 380kv | 17 Nov 2026 |
| Injection | Generation (any) | Available | 300 MW | Flexible, ≤ 10 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |
| Injection | Generation (any) | Available | 300 MW | Flexible, ≤ 10 % curtailment a year | 2033 (2033)variant: 380kv | 17 Nov 2026 |
| Injection | Generation (any) | Available | 300 MW | Flexible, ≤ 20 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |
| Injection | Generation (any) | Available | 300 MW | Flexible, ≤ 20 % curtailment a year | 2033 (2033)variant: 380kv | 17 Nov 2026 |
| Injection | Solar PV | Available | 300 MW | Firm, ≤ 0 % curtailment a year | 2029 (2029)variant: 380kv | 17 Nov 2026 |
| Injection | Solar PV | Available | 103.6 MW | Firm, ≤ 0 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Injection | Solar PV | Available | 300 MW | Flexible, ≤ 5 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Injection | Solar PV | Available | 300 MW | Flexible, ≤ 5 % curtailment a year | 2029 (2029)variant: 380kv | 17 Nov 2026 |
| Injection | Solar PV | Available | 300 MW | Flexible, ≤ 10 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Injection | Solar PV | Available | 300 MW | Flexible, ≤ 10 % curtailment a year | 2029 (2029)variant: 380kv | 17 Nov 2026 |
| Injection | Solar PV | Available | 300 MW | Flexible, ≤ 20 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Injection | Solar PV | Available | 300 MW | Flexible, ≤ 20 % curtailment a year | 2029 (2029)variant: 380kv | 17 Nov 2026 |
| Injection | Solar PV | Available | 300 MW | Firm, ≤ 0 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |
| Injection | Solar PV | Available | 300 MW | Firm, ≤ 0 % curtailment a year | 2033 (2033)variant: 380kv | 17 Nov 2026 |
| Injection | Solar PV | Available | 300 MW | Flexible, ≤ 5 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |
| Injection | Solar PV | Available | 300 MW | Flexible, ≤ 5 % curtailment a year | 2033 (2033)variant: 380kv | 17 Nov 2026 |
| Injection | Solar PV | Available | 300 MW | Flexible, ≤ 10 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |
| Injection | Solar PV | Available | 300 MW | Flexible, ≤ 10 % curtailment a year | 2033 (2033)variant: 380kv | 17 Nov 2026 |
| Injection | Solar PV | Available | 300 MW | Flexible, ≤ 20 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |
| Injection | Solar PV | Available | 300 MW | Flexible, ≤ 20 % curtailment a year | 2033 (2033)variant: 380kv | 17 Nov 2026 |
| Injection | Onshore wind | Available | 300 MW | Firm, ≤ 0 % curtailment a year | 2029 (2029)variant: 380kv | 17 Nov 2026 |
| Injection | Onshore wind | Available | 15.9 MW | Firm, ≤ 0 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Injection | Onshore wind | Available | 300 MW | Flexible, ≤ 5 % curtailment a year | 2029 (2029)variant: 380kv | 17 Nov 2026 |
| Injection | Onshore wind | Available | 34.3 MW | Flexible, ≤ 5 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Injection | Onshore wind | Available | 300 MW | Flexible, ≤ 10 % curtailment a year | 2029 (2029)variant: 380kv | 17 Nov 2026 |
| Injection | Onshore wind | Available | 49.8 MW | Flexible, ≤ 10 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Injection | Onshore wind | Available | 300 MW | Flexible, ≤ 20 % curtailment a year | 2029 (2029)variant: 380kv | 17 Nov 2026 |
| Injection | Onshore wind | Available | 132.9 MW | Flexible, ≤ 20 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Injection | Onshore wind | Available | 300 MW | Firm, ≤ 0 % curtailment a year | 2033 (2033)variant: 380kv | 17 Nov 2026 |
| Injection | Onshore wind | Available | 202.5 MW | Firm, ≤ 0 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |
| Injection | Onshore wind | Available | 300 MW | Flexible, ≤ 5 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |
| Injection | Onshore wind | Available | 300 MW | Flexible, ≤ 5 % curtailment a year | 2033 (2033)variant: 380kv | 17 Nov 2026 |
| Injection | Onshore wind | Available | 300 MW | Flexible, ≤ 10 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |
| Injection | Onshore wind | Available | 300 MW | Flexible, ≤ 10 % curtailment a year | 2033 (2033)variant: 380kv | 17 Nov 2026 |
| Injection | Onshore wind | Available | 300 MW | Flexible, ≤ 20 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |
| Injection | Onshore wind | Available | 300 MW | Flexible, ≤ 20 % curtailment a year | 2033 (2033)variant: 380kv | 17 Nov 2026 |
| Offtake | Load (any) | Available | 87.6 MW | Firm, ≤ 0 % curtailment a year | 2029 (2029)variant: 380kv | 17 Nov 2026 |
| Offtake | Load (any) | Available | 9.1 MW | Firm, ≤ 0 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Offtake | Load (any) | Available | 123 MW | Flexible, ≤ 5 % curtailment a year | 2029 (2029)variant: 380kv | 17 Nov 2026 |
| Offtake | Load (any) | Available | 10.7 MW | Flexible, ≤ 5 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Offtake | Load (any) | Available | 172.7 MW | Flexible, ≤ 10 % curtailment a year | 2029 (2029)variant: 380kv | 17 Nov 2026 |
| Offtake | Load (any) | Available | 12.2 MW | Flexible, ≤ 10 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Offtake | Load (any) | Available | 300 MW | Flexible, ≤ 20 % curtailment a year | 2029 (2029)variant: 380kv | 17 Nov 2026 |
| Offtake | Load (any) | Available | 17 MW | Flexible, ≤ 20 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Offtake | Load (any) | Available | 87.6 MW | Firm, ≤ 0 % curtailment a year | 2033 (2033)variant: 380kv | 17 Nov 2026 |
| Offtake | Load (any) | Available | 10.5 MW | Firm, ≤ 0 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |
| Offtake | Load (any) | Available | 123 MW | Flexible, ≤ 5 % curtailment a year | 2033 (2033)variant: 380kv | 17 Nov 2026 |
| Offtake | Load (any) | Available | 24.1 MW | Flexible, ≤ 5 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |
| Offtake | Load (any) | Available | 172.7 MW | Flexible, ≤ 10 % curtailment a year | 2033 (2033)variant: 380kv | 17 Nov 2026 |
| Offtake | Load (any) | Available | 72.2 MW | Flexible, ≤ 10 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |
| Offtake | Load (any) | Available | 300 MW | Flexible, ≤ 20 % curtailment a year | 2033 (2033)variant: 380kv | 17 Nov 2026 |
| Offtake | Load (any) | Available | 149.4 MW | Flexible, ≤ 20 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |
| Bidirectional | Battery | Available | 86 MW | Firm, ≤ 0 % curtailment a year | 2029 (2029)variant: 380kv | 17 Nov 2026 |
| Bidirectional | Battery | Available | 9 MW | Firm, ≤ 0 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Bidirectional | Battery | Available | 102.9 MW | Flexible, ≤ 5 % curtailment a year | 2029 (2029)variant: 380kv | 17 Nov 2026 |
| Bidirectional | Battery | Available | 10.4 MW | Flexible, ≤ 5 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Bidirectional | Battery | Available | 115.2 MW | Flexible, ≤ 10 % curtailment a year | 2029 (2029)variant: 380kv | 17 Nov 2026 |
| Bidirectional | Battery | Available | 11.6 MW | Flexible, ≤ 10 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Bidirectional | Battery | Available | 151.6 MW | Flexible, ≤ 20 % curtailment a year | 2029 (2029)variant: 380kv | 17 Nov 2026 |
| Bidirectional | Battery | Available | 14.9 MW | Flexible, ≤ 20 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Bidirectional | Battery | Available | 86 MW | Firm, ≤ 0 % curtailment a year | 2033 (2033)variant: 380kv | 17 Nov 2026 |
| Bidirectional | Battery | Available | 10.2 MW | Firm, ≤ 0 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |
| Bidirectional | Battery | Available | 102.9 MW | Flexible, ≤ 5 % curtailment a year | 2033 (2033)variant: 380kv | 17 Nov 2026 |
| Bidirectional | Battery | Available | 14.5 MW | Flexible, ≤ 5 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |
| Bidirectional | Battery | Available | 115.2 MW | Flexible, ≤ 10 % curtailment a year | 2033 (2033)variant: 380kv | 17 Nov 2026 |
| Bidirectional | Battery | Available | 22 MW | Flexible, ≤ 10 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |
| Bidirectional | Battery | Available | 151.6 MW | Flexible, ≤ 20 % curtailment a year | 2033 (2033)variant: 380kv | 17 Nov 2026 |
| Bidirectional | Battery | Available | 66.2 MW | Flexible, ≤ 20 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |