| Injection | Generation (any) | Available | 141.6 MW | Firm, ≤ 0 % curtailment a year | 2027 (2027)variant: 380kv | 26 Sep 2026 |
| Injection | Generation (any) | Available | 6.8 MW | Firm, ≤ 0 % curtailment a year | 2027 (2027)variant: 150kv | 26 Sep 2026 |
| Injection | Generation (any) | Available | 300 MW | Flexible, ≤ 5 % curtailment a year | 2027 (2027)variant: 380kv | 26 Sep 2026 |
| Injection | Generation (any) | Available | 12.7 MW | Flexible, ≤ 5 % curtailment a year | 2027 (2027)variant: 150kv | 26 Sep 2026 |
| Injection | Generation (any) | Available | 300 MW | Flexible, ≤ 10 % curtailment a year | 2027 (2027)variant: 380kv | 26 Sep 2026 |
| Injection | Generation (any) | Available | 17.5 MW | Flexible, ≤ 10 % curtailment a year | 2027 (2027)variant: 150kv | 26 Sep 2026 |
| Injection | Generation (any) | Available | 300 MW | Flexible, ≤ 20 % curtailment a year | 2027 (2027)variant: 380kv | 26 Sep 2026 |
| Injection | Generation (any) | Available | 40.9 MW | Flexible, ≤ 20 % curtailment a year | 2027 (2027)variant: 150kv | 26 Sep 2026 |
| Injection | Generation (any) | Available | 217.4 MW | Firm, ≤ 0 % curtailment a year | 2031 (2031)variant: 380kv | 26 Sep 2026 |
| Injection | Generation (any) | Available | 6.8 MW | Firm, ≤ 0 % curtailment a year | 2031 (2031)variant: 150kv | 26 Sep 2026 |
| Injection | Generation (any) | Available | 300 MW | Flexible, ≤ 5 % curtailment a year | 2031 (2031)variant: 380kv | 26 Sep 2026 |
| Injection | Generation (any) | Available | 13.8 MW | Flexible, ≤ 5 % curtailment a year | 2031 (2031)variant: 150kv | 26 Sep 2026 |
| Injection | Generation (any) | Available | 300 MW | Flexible, ≤ 10 % curtailment a year | 2031 (2031)variant: 380kv | 26 Sep 2026 |
| Injection | Generation (any) | Available | 19.3 MW | Flexible, ≤ 10 % curtailment a year | 2031 (2031)variant: 150kv | 26 Sep 2026 |
| Injection | Generation (any) | Available | 300 MW | Flexible, ≤ 20 % curtailment a year | 2031 (2031)variant: 380kv | 26 Sep 2026 |
| Injection | Generation (any) | Available | 56 MW | Flexible, ≤ 20 % curtailment a year | 2031 (2031)variant: 150kv | 26 Sep 2026 |
| Injection | Solar PV | Available | 258 MW | Firm, ≤ 0 % curtailment a year | 2027 (2027)variant: 380kv | 26 Sep 2026 |
| Injection | Solar PV | Available | 11.1 MW | Firm, ≤ 0 % curtailment a year | 2027 (2027)variant: 150kv | 26 Sep 2026 |
| Injection | Solar PV | Available | 300 MW | Flexible, ≤ 5 % curtailment a year | 2027 (2027)variant: 380kv | 26 Sep 2026 |
| Injection | Solar PV | Available | 21.1 MW | Flexible, ≤ 5 % curtailment a year | 2027 (2027)variant: 150kv | 26 Sep 2026 |
| Injection | Solar PV | Available | 300 MW | Flexible, ≤ 10 % curtailment a year | 2027 (2027)variant: 380kv | 26 Sep 2026 |
| Injection | Solar PV | Available | 26.8 MW | Flexible, ≤ 10 % curtailment a year | 2027 (2027)variant: 150kv | 26 Sep 2026 |
| Injection | Solar PV | Available | 300 MW | Flexible, ≤ 20 % curtailment a year | 2027 (2027)variant: 380kv | 26 Sep 2026 |
| Injection | Solar PV | Available | 41.4 MW | Flexible, ≤ 20 % curtailment a year | 2027 (2027)variant: 150kv | 26 Sep 2026 |
| Injection | Solar PV | Available | 300 MW | Firm, ≤ 0 % curtailment a year | 2031 (2031)variant: 380kv | 26 Sep 2026 |
| Injection | Solar PV | Available | 12.2 MW | Firm, ≤ 0 % curtailment a year | 2031 (2031)variant: 150kv | 26 Sep 2026 |
| Injection | Solar PV | Available | 300 MW | Flexible, ≤ 5 % curtailment a year | 2031 (2031)variant: 380kv | 26 Sep 2026 |
| Injection | Solar PV | Available | 24.1 MW | Flexible, ≤ 5 % curtailment a year | 2031 (2031)variant: 150kv | 26 Sep 2026 |
| Injection | Solar PV | Available | 300 MW | Flexible, ≤ 10 % curtailment a year | 2031 (2031)variant: 380kv | 26 Sep 2026 |
| Injection | Solar PV | Available | 30.9 MW | Flexible, ≤ 10 % curtailment a year | 2031 (2031)variant: 150kv | 26 Sep 2026 |
| Injection | Solar PV | Available | 300 MW | Flexible, ≤ 20 % curtailment a year | 2031 (2031)variant: 380kv | 26 Sep 2026 |
| Injection | Solar PV | Available | 52.7 MW | Flexible, ≤ 20 % curtailment a year | 2031 (2031)variant: 150kv | 26 Sep 2026 |
| Injection | Onshore wind | Available | 205.6 MW | Firm, ≤ 0 % curtailment a year | 2027 (2027)variant: 380kv | 26 Sep 2026 |
| Injection | Onshore wind | Available | 9.5 MW | Firm, ≤ 0 % curtailment a year | 2027 (2027)variant: 150kv | 26 Sep 2026 |
| Injection | Onshore wind | Available | 300 MW | Flexible, ≤ 5 % curtailment a year | 2027 (2027)variant: 380kv | 26 Sep 2026 |
| Injection | Onshore wind | Available | 19.4 MW | Flexible, ≤ 5 % curtailment a year | 2027 (2027)variant: 150kv | 26 Sep 2026 |
| Injection | Onshore wind | Available | 300 MW | Flexible, ≤ 10 % curtailment a year | 2027 (2027)variant: 380kv | 26 Sep 2026 |
| Injection | Onshore wind | Available | 33.3 MW | Flexible, ≤ 10 % curtailment a year | 2027 (2027)variant: 150kv | 26 Sep 2026 |
| Injection | Onshore wind | Available | 300 MW | Flexible, ≤ 20 % curtailment a year | 2027 (2027)variant: 380kv | 26 Sep 2026 |
| Injection | Onshore wind | Available | 74.9 MW | Flexible, ≤ 20 % curtailment a year | 2027 (2027)variant: 150kv | 26 Sep 2026 |
| Injection | Onshore wind | Available | 300 MW | Firm, ≤ 0 % curtailment a year | 2031 (2031)variant: 380kv | 26 Sep 2026 |
| Injection | Onshore wind | Available | 9.5 MW | Firm, ≤ 0 % curtailment a year | 2031 (2031)variant: 150kv | 26 Sep 2026 |
| Injection | Onshore wind | Available | 300 MW | Flexible, ≤ 5 % curtailment a year | 2031 (2031)variant: 380kv | 26 Sep 2026 |
| Injection | Onshore wind | Available | 27 MW | Flexible, ≤ 5 % curtailment a year | 2031 (2031)variant: 150kv | 26 Sep 2026 |
| Injection | Onshore wind | Available | 300 MW | Flexible, ≤ 10 % curtailment a year | 2031 (2031)variant: 380kv | 26 Sep 2026 |
| Injection | Onshore wind | Available | 45.6 MW | Flexible, ≤ 10 % curtailment a year | 2031 (2031)variant: 150kv | 26 Sep 2026 |
| Injection | Onshore wind | Available | 300 MW | Flexible, ≤ 20 % curtailment a year | 2031 (2031)variant: 380kv | 26 Sep 2026 |
| Injection | Onshore wind | Available | 143 MW | Flexible, ≤ 20 % curtailment a year | 2031 (2031)variant: 150kv | 26 Sep 2026 |
| Offtake | Load (any) | Available | 37.7 MW | Firm, ≤ 0 % curtailment a year | 2027 (2027)variant: 380kv | 26 Sep 2026 |
| Offtake | Load (any) | Available | 7.5 MW | Firm, ≤ 0 % curtailment a year | 2027 (2027)variant: 150kv | 26 Sep 2026 |
| Offtake | Load (any) | Available | 136.7 MW | Flexible, ≤ 5 % curtailment a year | 2027 (2027)variant: 380kv | 26 Sep 2026 |
| Offtake | Load (any) | Available | 18 MW | Flexible, ≤ 5 % curtailment a year | 2027 (2027)variant: 150kv | 26 Sep 2026 |
| Offtake | Load (any) | Available | 298.3 MW | Flexible, ≤ 10 % curtailment a year | 2027 (2027)variant: 380kv | 26 Sep 2026 |
| Offtake | Load (any) | Available | 32.3 MW | Flexible, ≤ 10 % curtailment a year | 2027 (2027)variant: 150kv | 26 Sep 2026 |
| Offtake | Load (any) | Available | 300 MW | Flexible, ≤ 20 % curtailment a year | 2027 (2027)variant: 380kv | 26 Sep 2026 |
| Offtake | Load (any) | Available | 162.7 MW | Flexible, ≤ 20 % curtailment a year | 2027 (2027)variant: 150kv | 26 Sep 2026 |
| Offtake | Load (any) | Available | 71.1 MW | Firm, ≤ 0 % curtailment a year | 2031 (2031)variant: 380kv | 26 Sep 2026 |
| Offtake | Load (any) | Available | 7.5 MW | Firm, ≤ 0 % curtailment a year | 2031 (2031)variant: 150kv | 26 Sep 2026 |
| Offtake | Load (any) | Available | 136.7 MW | Flexible, ≤ 5 % curtailment a year | 2031 (2031)variant: 380kv | 26 Sep 2026 |
| Offtake | Load (any) | Available | 20.6 MW | Flexible, ≤ 5 % curtailment a year | 2031 (2031)variant: 150kv | 26 Sep 2026 |
| Offtake | Load (any) | Available | 298.3 MW | Flexible, ≤ 10 % curtailment a year | 2031 (2031)variant: 380kv | 26 Sep 2026 |
| Offtake | Load (any) | Available | 37.8 MW | Flexible, ≤ 10 % curtailment a year | 2031 (2031)variant: 150kv | 26 Sep 2026 |
| Offtake | Load (any) | Available | 300 MW | Flexible, ≤ 20 % curtailment a year | 2031 (2031)variant: 380kv | 26 Sep 2026 |
| Offtake | Load (any) | Available | 175 MW | Flexible, ≤ 20 % curtailment a year | 2031 (2031)variant: 150kv | 26 Sep 2026 |
| Bidirectional | Battery | Available | 37.7 MW | Firm, ≤ 0 % curtailment a year | 2027 (2027)variant: 380kv | 26 Sep 2026 |
| Bidirectional | Battery | Available | 6.8 MW | Firm, ≤ 0 % curtailment a year | 2027 (2027)variant: 150kv | 26 Sep 2026 |
| Bidirectional | Battery | Available | 126.5 MW | Flexible, ≤ 5 % curtailment a year | 2027 (2027)variant: 380kv | 26 Sep 2026 |
| Bidirectional | Battery | Available | 12.7 MW | Flexible, ≤ 5 % curtailment a year | 2027 (2027)variant: 150kv | 26 Sep 2026 |
| Bidirectional | Battery | Available | 227.2 MW | Flexible, ≤ 10 % curtailment a year | 2027 (2027)variant: 380kv | 26 Sep 2026 |
| Bidirectional | Battery | Available | 17.5 MW | Flexible, ≤ 10 % curtailment a year | 2027 (2027)variant: 150kv | 26 Sep 2026 |
| Bidirectional | Battery | Available | 300 MW | Flexible, ≤ 20 % curtailment a year | 2027 (2027)variant: 380kv | 26 Sep 2026 |
| Bidirectional | Battery | Available | 40.9 MW | Flexible, ≤ 20 % curtailment a year | 2027 (2027)variant: 150kv | 26 Sep 2026 |
| Bidirectional | Battery | Available | 71.1 MW | Firm, ≤ 0 % curtailment a year | 2031 (2031)variant: 380kv | 26 Sep 2026 |
| Bidirectional | Battery | Available | 6.8 MW | Firm, ≤ 0 % curtailment a year | 2031 (2031)variant: 150kv | 26 Sep 2026 |
| Bidirectional | Battery | Available | 126.5 MW | Flexible, ≤ 5 % curtailment a year | 2031 (2031)variant: 380kv | 26 Sep 2026 |
| Bidirectional | Battery | Available | 13.8 MW | Flexible, ≤ 5 % curtailment a year | 2031 (2031)variant: 150kv | 26 Sep 2026 |
| Bidirectional | Battery | Available | 227.2 MW | Flexible, ≤ 10 % curtailment a year | 2031 (2031)variant: 380kv | 26 Sep 2026 |
| Bidirectional | Battery | Available | 19.3 MW | Flexible, ≤ 10 % curtailment a year | 2031 (2031)variant: 150kv | 26 Sep 2026 |
| Bidirectional | Battery | Available | 300 MW | Flexible, ≤ 20 % curtailment a year | 2031 (2031)variant: 380kv | 26 Sep 2026 |
| Bidirectional | Battery | Available | 56 MW | Flexible, ≤ 20 % curtailment a year | 2031 (2031)variant: 150kv | 26 Sep 2026 |