| Injection | Generation (any) | Available | 300 MW | Firm, ≤ 0 % curtailment a year | 2029 (2029)variant: 380kv | 17 Nov 2026 |
| Injection | Generation (any) | Available | 13.3 MW | Firm, ≤ 0 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Injection | Generation (any) | Available | 300 MW | Flexible, ≤ 5 % curtailment a year | 2029 (2029)variant: 380kv | 17 Nov 2026 |
| Injection | Generation (any) | Available | 20.8 MW | Flexible, ≤ 5 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Injection | Generation (any) | Available | 300 MW | Flexible, ≤ 10 % curtailment a year | 2029 (2029)variant: 380kv | 17 Nov 2026 |
| Injection | Generation (any) | Available | 40.4 MW | Flexible, ≤ 10 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Injection | Generation (any) | Available | 300 MW | Flexible, ≤ 20 % curtailment a year | 2029 (2029)variant: 380kv | 17 Nov 2026 |
| Injection | Generation (any) | Available | 144.4 MW | Flexible, ≤ 20 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Injection | Generation (any) | Available | 300 MW | Firm, ≤ 0 % curtailment a year | 2033 (2033)variant: 380kv | 17 Nov 2026 |
| Injection | Generation (any) | Available | 82.6 MW | Firm, ≤ 0 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |
| Injection | Generation (any) | Available | 300 MW | Flexible, ≤ 5 % curtailment a year | 2033 (2033)variant: 380kv | 17 Nov 2026 |
| Injection | Generation (any) | Available | 175 MW | Flexible, ≤ 5 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |
| Injection | Generation (any) | Available | 300 MW | Flexible, ≤ 10 % curtailment a year | 2033 (2033)variant: 380kv | 17 Nov 2026 |
| Injection | Generation (any) | Available | 175 MW | Flexible, ≤ 10 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |
| Injection | Generation (any) | Available | 300 MW | Flexible, ≤ 20 % curtailment a year | 2033 (2033)variant: 380kv | 17 Nov 2026 |
| Injection | Generation (any) | Available | 175 MW | Flexible, ≤ 20 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |
| Injection | Solar PV | Available | 300 MW | Firm, ≤ 0 % curtailment a year | 2029 (2029)variant: 380kv | 17 Nov 2026 |
| Injection | Solar PV | Available | 175 MW | Firm, ≤ 0 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Injection | Solar PV | Available | 300 MW | Flexible, ≤ 5 % curtailment a year | 2029 (2029)variant: 380kv | 17 Nov 2026 |
| Injection | Solar PV | Available | 175 MW | Flexible, ≤ 5 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Injection | Solar PV | Available | 300 MW | Flexible, ≤ 10 % curtailment a year | 2029 (2029)variant: 380kv | 17 Nov 2026 |
| Injection | Solar PV | Available | 175 MW | Flexible, ≤ 10 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Injection | Solar PV | Available | 300 MW | Flexible, ≤ 20 % curtailment a year | 2029 (2029)variant: 380kv | 17 Nov 2026 |
| Injection | Solar PV | Available | 175 MW | Flexible, ≤ 20 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Injection | Solar PV | Available | 300 MW | Firm, ≤ 0 % curtailment a year | 2033 (2033)variant: 380kv | 17 Nov 2026 |
| Injection | Solar PV | Available | 175 MW | Firm, ≤ 0 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |
| Injection | Solar PV | Available | 300 MW | Flexible, ≤ 5 % curtailment a year | 2033 (2033)variant: 380kv | 17 Nov 2026 |
| Injection | Solar PV | Available | 175 MW | Flexible, ≤ 5 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |
| Injection | Solar PV | Available | 300 MW | Flexible, ≤ 10 % curtailment a year | 2033 (2033)variant: 380kv | 17 Nov 2026 |
| Injection | Solar PV | Available | 175 MW | Flexible, ≤ 10 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |
| Injection | Solar PV | Available | 300 MW | Flexible, ≤ 20 % curtailment a year | 2033 (2033)variant: 380kv | 17 Nov 2026 |
| Injection | Solar PV | Available | 175 MW | Flexible, ≤ 20 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |
| Injection | Onshore wind | Available | 300 MW | Firm, ≤ 0 % curtailment a year | 2029 (2029)variant: 380kv | 17 Nov 2026 |
| Injection | Onshore wind | Available | 19.6 MW | Firm, ≤ 0 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Injection | Onshore wind | Available | 300 MW | Flexible, ≤ 5 % curtailment a year | 2029 (2029)variant: 380kv | 17 Nov 2026 |
| Injection | Onshore wind | Available | 51 MW | Flexible, ≤ 5 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Injection | Onshore wind | Available | 300 MW | Flexible, ≤ 10 % curtailment a year | 2029 (2029)variant: 380kv | 17 Nov 2026 |
| Injection | Onshore wind | Available | 85.4 MW | Flexible, ≤ 10 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Injection | Onshore wind | Available | 300 MW | Flexible, ≤ 20 % curtailment a year | 2029 (2029)variant: 380kv | 17 Nov 2026 |
| Injection | Onshore wind | Available | 175 MW | Flexible, ≤ 20 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Injection | Onshore wind | Available | 300 MW | Firm, ≤ 0 % curtailment a year | 2033 (2033)variant: 380kv | 17 Nov 2026 |
| Injection | Onshore wind | Available | 175 MW | Firm, ≤ 0 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |
| Injection | Onshore wind | Available | 300 MW | Flexible, ≤ 5 % curtailment a year | 2033 (2033)variant: 380kv | 17 Nov 2026 |
| Injection | Onshore wind | Available | 175 MW | Flexible, ≤ 5 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |
| Injection | Onshore wind | Available | 300 MW | Flexible, ≤ 10 % curtailment a year | 2033 (2033)variant: 380kv | 17 Nov 2026 |
| Injection | Onshore wind | Available | 175 MW | Flexible, ≤ 10 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |
| Injection | Onshore wind | Available | 300 MW | Flexible, ≤ 20 % curtailment a year | 2033 (2033)variant: 380kv | 17 Nov 2026 |
| Injection | Onshore wind | Available | 175 MW | Flexible, ≤ 20 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |
| Offtake | Load (any) | Available | 116.6 MW | Firm, ≤ 0 % curtailment a year | 2029 (2029)variant: 380kv | 17 Nov 2026 |
| Offtake | Load (any) | Available | 8.9 MW | Firm, ≤ 0 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Offtake | Load (any) | Available | 300 MW | Flexible, ≤ 5 % curtailment a year | 2029 (2029)variant: 380kv | 17 Nov 2026 |
| Offtake | Load (any) | Available | 15.7 MW | Flexible, ≤ 5 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Offtake | Load (any) | Available | 300 MW | Flexible, ≤ 10 % curtailment a year | 2029 (2029)variant: 380kv | 17 Nov 2026 |
| Offtake | Load (any) | Available | 49.1 MW | Flexible, ≤ 10 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Offtake | Load (any) | Available | 300 MW | Flexible, ≤ 20 % curtailment a year | 2029 (2029)variant: 380kv | 17 Nov 2026 |
| Offtake | Load (any) | Available | 175 MW | Flexible, ≤ 20 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Offtake | Load (any) | Available | 116.6 MW | Firm, ≤ 0 % curtailment a year | 2033 (2033)variant: 380kv | 17 Nov 2026 |
| Offtake | Load (any) | Available | 10.8 MW | Firm, ≤ 0 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |
| Offtake | Load (any) | Available | 300 MW | Flexible, ≤ 5 % curtailment a year | 2033 (2033)variant: 380kv | 17 Nov 2026 |
| Offtake | Load (any) | Available | 161.7 MW | Flexible, ≤ 5 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |
| Offtake | Load (any) | Available | 300 MW | Flexible, ≤ 10 % curtailment a year | 2033 (2033)variant: 380kv | 17 Nov 2026 |
| Offtake | Load (any) | Available | 175 MW | Flexible, ≤ 10 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |
| Offtake | Load (any) | Available | 300 MW | Flexible, ≤ 20 % curtailment a year | 2033 (2033)variant: 380kv | 17 Nov 2026 |
| Offtake | Load (any) | Available | 175 MW | Flexible, ≤ 20 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |
| Bidirectional | Battery | Available | 103.7 MW | Firm, ≤ 0 % curtailment a year | 2029 (2029)variant: 380kv | 17 Nov 2026 |
| Bidirectional | Battery | Available | 7.7 MW | Firm, ≤ 0 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Bidirectional | Battery | Available | 131.5 MW | Flexible, ≤ 5 % curtailment a year | 2029 (2029)variant: 380kv | 17 Nov 2026 |
| Bidirectional | Battery | Available | 11.3 MW | Flexible, ≤ 5 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Bidirectional | Battery | Available | 159.2 MW | Flexible, ≤ 10 % curtailment a year | 2029 (2029)variant: 380kv | 17 Nov 2026 |
| Bidirectional | Battery | Available | 16 MW | Flexible, ≤ 10 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Bidirectional | Battery | Available | 264.1 MW | Flexible, ≤ 20 % curtailment a year | 2029 (2029)variant: 380kv | 17 Nov 2026 |
| Bidirectional | Battery | Available | 68.2 MW | Flexible, ≤ 20 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Bidirectional | Battery | Available | 103.7 MW | Firm, ≤ 0 % curtailment a year | 2033 (2033)variant: 380kv | 17 Nov 2026 |
| Bidirectional | Battery | Available | 7.7 MW | Firm, ≤ 0 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |
| Bidirectional | Battery | Available | 131.5 MW | Flexible, ≤ 5 % curtailment a year | 2033 (2033)variant: 380kv | 17 Nov 2026 |
| Bidirectional | Battery | Available | 50.9 MW | Flexible, ≤ 5 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |
| Bidirectional | Battery | Available | 159.2 MW | Flexible, ≤ 10 % curtailment a year | 2033 (2033)variant: 380kv | 17 Nov 2026 |
| Bidirectional | Battery | Available | 123.8 MW | Flexible, ≤ 10 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |
| Bidirectional | Battery | Available | 264.1 MW | Flexible, ≤ 20 % curtailment a year | 2033 (2033)variant: 380kv | 17 Nov 2026 |
| Bidirectional | Battery | Available | 175 MW | Flexible, ≤ 20 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |