Substation

DOEL

Elia Transmission Belgium / Belgium

Latest published values

80 served · 0 withheld

Each row is what the operator’s latest published dataset reports for one combination of direction, technology, measure, firmness and horizon. Hosting-capacity figures are indicative and reflect what operators publish. They are not a connection offer; only the operator can confirm capacity for a specific request.

Latest published capacity values, one row per series
DirectionTechnologyMeasureValueFirmnessHorizonSource date
InjectionGeneration (any)Available300 MWFirm, ≤ 0 % curtailment a year2029 (2029)variant: 380kv17 Nov 2026
InjectionGeneration (any)Available16.5 MWFirm, ≤ 0 % curtailment a year2029 (2029)variant: 150kv17 Nov 2026
InjectionGeneration (any)Available300 MWFlexible, ≤ 5 % curtailment a year2029 (2029)variant: 380kv17 Nov 2026
InjectionGeneration (any)Available28.8 MWFlexible, ≤ 5 % curtailment a year2029 (2029)variant: 150kv17 Nov 2026
InjectionGeneration (any)Available300 MWFlexible, ≤ 10 % curtailment a year2029 (2029)variant: 380kv17 Nov 2026
InjectionGeneration (any)Available32.7 MWFlexible, ≤ 10 % curtailment a year2029 (2029)variant: 150kv17 Nov 2026
InjectionGeneration (any)Available300 MWFlexible, ≤ 20 % curtailment a year2029 (2029)variant: 380kv17 Nov 2026
InjectionGeneration (any)Available44.7 MWFlexible, ≤ 20 % curtailment a year2029 (2029)variant: 150kv17 Nov 2026
InjectionGeneration (any)Available300 MWFirm, ≤ 0 % curtailment a year2033 (2033)variant: 380kv17 Nov 2026
InjectionGeneration (any)Available25.6 MWFirm, ≤ 0 % curtailment a year2033 (2033)variant: 150kv17 Nov 2026
InjectionGeneration (any)Available300 MWFlexible, ≤ 5 % curtailment a year2033 (2033)variant: 380kv17 Nov 2026
InjectionGeneration (any)Available28.8 MWFlexible, ≤ 5 % curtailment a year2033 (2033)variant: 150kv17 Nov 2026
InjectionGeneration (any)Available300 MWFlexible, ≤ 10 % curtailment a year2033 (2033)variant: 380kv17 Nov 2026
InjectionGeneration (any)Available32.7 MWFlexible, ≤ 10 % curtailment a year2033 (2033)variant: 150kv17 Nov 2026
InjectionGeneration (any)Available300 MWFlexible, ≤ 20 % curtailment a year2033 (2033)variant: 380kv17 Nov 2026
InjectionGeneration (any)Available44.7 MWFlexible, ≤ 20 % curtailment a year2033 (2033)variant: 150kv17 Nov 2026
InjectionSolar PVAvailable300 MWFirm, ≤ 0 % curtailment a year2029 (2029)variant: 380kv17 Nov 2026
InjectionSolar PVAvailable37.9 MWFirm, ≤ 0 % curtailment a year2029 (2029)variant: 150kv17 Nov 2026
InjectionSolar PVAvailable300 MWFlexible, ≤ 5 % curtailment a year2029 (2029)variant: 380kv17 Nov 2026
InjectionSolar PVAvailable53 MWFlexible, ≤ 5 % curtailment a year2029 (2029)variant: 150kv17 Nov 2026
InjectionSolar PVAvailable300 MWFlexible, ≤ 10 % curtailment a year2029 (2029)variant: 380kv17 Nov 2026
InjectionSolar PVAvailable62 MWFlexible, ≤ 10 % curtailment a year2029 (2029)variant: 150kv17 Nov 2026
InjectionSolar PVAvailable300 MWFlexible, ≤ 20 % curtailment a year2029 (2029)variant: 380kv17 Nov 2026
InjectionSolar PVAvailable79.1 MWFlexible, ≤ 20 % curtailment a year2029 (2029)variant: 150kv17 Nov 2026
InjectionSolar PVAvailable300 MWFirm, ≤ 0 % curtailment a year2033 (2033)variant: 380kv17 Nov 2026
InjectionSolar PVAvailable37.9 MWFirm, ≤ 0 % curtailment a year2033 (2033)variant: 150kv17 Nov 2026
InjectionSolar PVAvailable300 MWFlexible, ≤ 5 % curtailment a year2033 (2033)variant: 380kv17 Nov 2026
InjectionSolar PVAvailable53 MWFlexible, ≤ 5 % curtailment a year2033 (2033)variant: 150kv17 Nov 2026
InjectionSolar PVAvailable300 MWFlexible, ≤ 10 % curtailment a year2033 (2033)variant: 380kv17 Nov 2026
InjectionSolar PVAvailable62 MWFlexible, ≤ 10 % curtailment a year2033 (2033)variant: 150kv17 Nov 2026
InjectionSolar PVAvailable300 MWFlexible, ≤ 20 % curtailment a year2033 (2033)variant: 380kv17 Nov 2026
InjectionSolar PVAvailable79.1 MWFlexible, ≤ 20 % curtailment a year2033 (2033)variant: 150kv17 Nov 2026
InjectionOnshore windAvailable300 MWFirm, ≤ 0 % curtailment a year2029 (2029)variant: 380kv17 Nov 2026
InjectionOnshore windAvailable35.5 MWFirm, ≤ 0 % curtailment a year2029 (2029)variant: 150kv17 Nov 2026
InjectionOnshore windAvailable300 MWFlexible, ≤ 5 % curtailment a year2029 (2029)variant: 380kv17 Nov 2026
InjectionOnshore windAvailable46.7 MWFlexible, ≤ 5 % curtailment a year2029 (2029)variant: 150kv17 Nov 2026
InjectionOnshore windAvailable300 MWFlexible, ≤ 10 % curtailment a year2029 (2029)variant: 380kv17 Nov 2026
InjectionOnshore windAvailable57.4 MWFlexible, ≤ 10 % curtailment a year2029 (2029)variant: 150kv17 Nov 2026
InjectionOnshore windAvailable300 MWFlexible, ≤ 20 % curtailment a year2029 (2029)variant: 380kv17 Nov 2026
InjectionOnshore windAvailable83.1 MWFlexible, ≤ 20 % curtailment a year2029 (2029)variant: 150kv17 Nov 2026
InjectionOnshore windAvailable300 MWFirm, ≤ 0 % curtailment a year2033 (2033)variant: 380kv17 Nov 2026
InjectionOnshore windAvailable35.5 MWFirm, ≤ 0 % curtailment a year2033 (2033)variant: 150kv17 Nov 2026
InjectionOnshore windAvailable300 MWFlexible, ≤ 5 % curtailment a year2033 (2033)variant: 380kv17 Nov 2026
InjectionOnshore windAvailable46.7 MWFlexible, ≤ 5 % curtailment a year2033 (2033)variant: 150kv17 Nov 2026
InjectionOnshore windAvailable300 MWFlexible, ≤ 10 % curtailment a year2033 (2033)variant: 380kv17 Nov 2026
InjectionOnshore windAvailable57.4 MWFlexible, ≤ 10 % curtailment a year2033 (2033)variant: 150kv17 Nov 2026
InjectionOnshore windAvailable300 MWFlexible, ≤ 20 % curtailment a year2033 (2033)variant: 380kv17 Nov 2026
InjectionOnshore windAvailable83.1 MWFlexible, ≤ 20 % curtailment a year2033 (2033)variant: 150kv17 Nov 2026
OfftakeLoad (any)Available101.4 MWFirm, ≤ 0 % curtailment a year2029 (2029)variant: 380kv17 Nov 2026
OfftakeLoad (any)Available7.6 MWFirm, ≤ 0 % curtailment a year2029 (2029)variant: 150kv17 Nov 2026
OfftakeLoad (any)Available300 MWFlexible, ≤ 5 % curtailment a year2029 (2029)variant: 380kv17 Nov 2026
OfftakeLoad (any)Available11.6 MWFlexible, ≤ 5 % curtailment a year2029 (2029)variant: 150kv17 Nov 2026
OfftakeLoad (any)Available300 MWFlexible, ≤ 10 % curtailment a year2029 (2029)variant: 380kv17 Nov 2026
OfftakeLoad (any)Available22.7 MWFlexible, ≤ 10 % curtailment a year2029 (2029)variant: 150kv17 Nov 2026
OfftakeLoad (any)Available300 MWFlexible, ≤ 20 % curtailment a year2029 (2029)variant: 380kv17 Nov 2026
OfftakeLoad (any)Available79 MWFlexible, ≤ 20 % curtailment a year2029 (2029)variant: 150kv17 Nov 2026
OfftakeLoad (any)Available101.4 MWFirm, ≤ 0 % curtailment a year2033 (2033)variant: 380kv17 Nov 2026
OfftakeLoad (any)Available11.7 MWFirm, ≤ 0 % curtailment a year2033 (2033)variant: 150kv17 Nov 2026
OfftakeLoad (any)Available300 MWFlexible, ≤ 5 % curtailment a year2033 (2033)variant: 380kv17 Nov 2026
OfftakeLoad (any)Available92.1 MWFlexible, ≤ 5 % curtailment a year2033 (2033)variant: 150kv17 Nov 2026
OfftakeLoad (any)Available300 MWFlexible, ≤ 10 % curtailment a year2033 (2033)variant: 380kv17 Nov 2026
OfftakeLoad (any)Available105.8 MWFlexible, ≤ 10 % curtailment a year2033 (2033)variant: 150kv17 Nov 2026
OfftakeLoad (any)Available300 MWFlexible, ≤ 20 % curtailment a year2033 (2033)variant: 380kv17 Nov 2026
OfftakeLoad (any)Available123.8 MWFlexible, ≤ 20 % curtailment a year2033 (2033)variant: 150kv17 Nov 2026
BidirectionalBatteryAvailable91.1 MWFirm, ≤ 0 % curtailment a year2029 (2029)variant: 380kv17 Nov 2026
BidirectionalBatteryAvailable1.9 MWFirm, ≤ 0 % curtailment a year2029 (2029)variant: 150kv17 Nov 2026
BidirectionalBatteryAvailable113 MWFlexible, ≤ 5 % curtailment a year2029 (2029)variant: 380kv17 Nov 2026
BidirectionalBatteryAvailable2.2 MWFlexible, ≤ 5 % curtailment a year2029 (2029)variant: 150kv17 Nov 2026
BidirectionalBatteryAvailable132.1 MWFlexible, ≤ 10 % curtailment a year2029 (2029)variant: 380kv17 Nov 2026
BidirectionalBatteryAvailable2.3 MWFlexible, ≤ 10 % curtailment a year2029 (2029)variant: 150kv17 Nov 2026
BidirectionalBatteryAvailable191.6 MWFlexible, ≤ 20 % curtailment a year2029 (2029)variant: 380kv17 Nov 2026
BidirectionalBatteryAvailable2.6 MWFlexible, ≤ 20 % curtailment a year2029 (2029)variant: 150kv17 Nov 2026
BidirectionalBatteryAvailable91.1 MWFirm, ≤ 0 % curtailment a year2033 (2033)variant: 380kv17 Nov 2026
BidirectionalBatteryAvailable1.9 MWFirm, ≤ 0 % curtailment a year2033 (2033)variant: 150kv17 Nov 2026
BidirectionalBatteryAvailable113 MWFlexible, ≤ 5 % curtailment a year2033 (2033)variant: 380kv17 Nov 2026
BidirectionalBatteryAvailable2.2 MWFlexible, ≤ 5 % curtailment a year2033 (2033)variant: 150kv17 Nov 2026
BidirectionalBatteryAvailable132.1 MWFlexible, ≤ 10 % curtailment a year2033 (2033)variant: 380kv17 Nov 2026
BidirectionalBatteryAvailable2.3 MWFlexible, ≤ 10 % curtailment a year2033 (2033)variant: 150kv17 Nov 2026
BidirectionalBatteryAvailable191.6 MWFlexible, ≤ 20 % curtailment a year2033 (2033)variant: 380kv17 Nov 2026
BidirectionalBatteryAvailable2.6 MWFlexible, ≤ 20 % curtailment a year2033 (2033)variant: 150kv17 Nov 2026

Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map

What each value means

Methodology, both clocks, provenance and rights

Injection · Generation (any) · Available

300 MW

Granted

The operator's latest published dataset reports 300 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2029 (2029) · variant: 380kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/DOEL 380 · payload sha256 2a662dbb6e25…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at published maximum mw
300
Operator note: at voltage level cap
true
Operator note: code
DOEL 380
Operator note: flexibilityLevel
0%_flex
Operator note: variant
380kv
Operator note: voltage kv
380

Injection · Generation (any) · Available

16.5 MW

Granted

The operator's latest published dataset reports 16.5 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2029 (2029) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/DOEL 150 · payload sha256 10bacc802190…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
DOEL 150
Operator note: flexibilityLevel
0%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Injection · Generation (any) · Available

300 MW

Granted

The operator's latest published dataset reports 300 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2029 (2029) · variant: 380kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/DOEL 380 · payload sha256 2a662dbb6e25…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at published maximum mw
300
Operator note: at voltage level cap
true
Operator note: code
DOEL 380
Operator note: flexibilityLevel
5%_flex
Operator note: variant
380kv
Operator note: voltage kv
380

Injection · Generation (any) · Available

28.8 MW

Granted

The operator's latest published dataset reports 28.8 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2029 (2029) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/DOEL 150 · payload sha256 10bacc802190…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
DOEL 150
Operator note: flexibilityLevel
5%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Injection · Generation (any) · Available

300 MW

Granted

The operator's latest published dataset reports 300 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2029 (2029) · variant: 380kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/DOEL 380 · payload sha256 2a662dbb6e25…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at published maximum mw
300
Operator note: at voltage level cap
true
Operator note: code
DOEL 380
Operator note: flexibilityLevel
10%_flex
Operator note: variant
380kv
Operator note: voltage kv
380

Injection · Generation (any) · Available

32.7 MW

Granted

The operator's latest published dataset reports 32.7 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2029 (2029) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/DOEL 150 · payload sha256 10bacc802190…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
DOEL 150
Operator note: flexibilityLevel
10%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Injection · Generation (any) · Available

300 MW

Granted

The operator's latest published dataset reports 300 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2029 (2029) · variant: 380kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/DOEL 380 · payload sha256 2a662dbb6e25…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at published maximum mw
300
Operator note: at voltage level cap
true
Operator note: code
DOEL 380
Operator note: flexibilityLevel
20%_flex
Operator note: variant
380kv
Operator note: voltage kv
380

Injection · Generation (any) · Available

44.7 MW

Granted

The operator's latest published dataset reports 44.7 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2029 (2029) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/DOEL 150 · payload sha256 10bacc802190…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
DOEL 150
Operator note: flexibilityLevel
20%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Injection · Generation (any) · Available

300 MW

Granted

The operator's latest published dataset reports 300 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2033 (2033) · variant: 380kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/DOEL 380 · payload sha256 2a662dbb6e25…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at published maximum mw
300
Operator note: at voltage level cap
true
Operator note: code
DOEL 380
Operator note: flexibilityLevel
0%_flex
Operator note: variant
380kv
Operator note: voltage kv
380

Injection · Generation (any) · Available

25.6 MW

Granted

The operator's latest published dataset reports 25.6 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2033 (2033) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/DOEL 150 · payload sha256 377ed26012d4…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
DOEL 150
Operator note: flexibilityLevel
0%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Injection · Generation (any) · Available

300 MW

Granted

The operator's latest published dataset reports 300 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2033 (2033) · variant: 380kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/DOEL 380 · payload sha256 2a662dbb6e25…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at published maximum mw
300
Operator note: at voltage level cap
true
Operator note: code
DOEL 380
Operator note: flexibilityLevel
5%_flex
Operator note: variant
380kv
Operator note: voltage kv
380

Injection · Generation (any) · Available

28.8 MW

Granted

The operator's latest published dataset reports 28.8 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2033 (2033) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/DOEL 150 · payload sha256 377ed26012d4…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
DOEL 150
Operator note: flexibilityLevel
5%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Injection · Generation (any) · Available

300 MW

Granted

The operator's latest published dataset reports 300 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2033 (2033) · variant: 380kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/DOEL 380 · payload sha256 2a662dbb6e25…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at published maximum mw
300
Operator note: at voltage level cap
true
Operator note: code
DOEL 380
Operator note: flexibilityLevel
10%_flex
Operator note: variant
380kv
Operator note: voltage kv
380

Injection · Generation (any) · Available

32.7 MW

Granted

The operator's latest published dataset reports 32.7 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2033 (2033) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/DOEL 150 · payload sha256 377ed26012d4…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
DOEL 150
Operator note: flexibilityLevel
10%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Injection · Generation (any) · Available

300 MW

Granted

The operator's latest published dataset reports 300 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2033 (2033) · variant: 380kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/DOEL 380 · payload sha256 2a662dbb6e25…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at published maximum mw
300
Operator note: at voltage level cap
true
Operator note: code
DOEL 380
Operator note: flexibilityLevel
20%_flex
Operator note: variant
380kv
Operator note: voltage kv
380

Injection · Generation (any) · Available

44.7 MW

Granted

The operator's latest published dataset reports 44.7 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2033 (2033) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/DOEL 150 · payload sha256 377ed26012d4…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
DOEL 150
Operator note: flexibilityLevel
20%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Injection · Solar PV · Available

300 MW

Granted

The operator's latest published dataset reports 300 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2029 (2029) · variant: 380kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/DOEL 380 · payload sha256 2a662dbb6e25…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at published maximum mw
300
Operator note: at voltage level cap
true
Operator note: code
DOEL 380
Operator note: flexibilityLevel
0%_flex
Operator note: variant
380kv
Operator note: voltage kv
380

Injection · Solar PV · Available

37.9 MW

Granted

The operator's latest published dataset reports 37.9 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2029 (2029) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/DOEL 150 · payload sha256 10bacc802190…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
DOEL 150
Operator note: flexibilityLevel
0%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Injection · Solar PV · Available

300 MW

Granted

The operator's latest published dataset reports 300 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2029 (2029) · variant: 380kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/DOEL 380 · payload sha256 2a662dbb6e25…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at published maximum mw
300
Operator note: at voltage level cap
true
Operator note: code
DOEL 380
Operator note: flexibilityLevel
5%_flex
Operator note: variant
380kv
Operator note: voltage kv
380

Injection · Solar PV · Available

53 MW

Granted

The operator's latest published dataset reports 53 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2029 (2029) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/DOEL 150 · payload sha256 10bacc802190…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
DOEL 150
Operator note: flexibilityLevel
5%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Injection · Solar PV · Available

300 MW

Granted

The operator's latest published dataset reports 300 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2029 (2029) · variant: 380kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/DOEL 380 · payload sha256 2a662dbb6e25…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at published maximum mw
300
Operator note: at voltage level cap
true
Operator note: code
DOEL 380
Operator note: flexibilityLevel
10%_flex
Operator note: variant
380kv
Operator note: voltage kv
380

Injection · Solar PV · Available

62 MW

Granted

The operator's latest published dataset reports 62 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2029 (2029) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/DOEL 150 · payload sha256 10bacc802190…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
DOEL 150
Operator note: flexibilityLevel
10%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Injection · Solar PV · Available

300 MW

Granted

The operator's latest published dataset reports 300 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2029 (2029) · variant: 380kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/DOEL 380 · payload sha256 2a662dbb6e25…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at published maximum mw
300
Operator note: at voltage level cap
true
Operator note: code
DOEL 380
Operator note: flexibilityLevel
20%_flex
Operator note: variant
380kv
Operator note: voltage kv
380

Injection · Solar PV · Available

79.1 MW

Granted

The operator's latest published dataset reports 79.1 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2029 (2029) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/DOEL 150 · payload sha256 10bacc802190…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
DOEL 150
Operator note: flexibilityLevel
20%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Injection · Solar PV · Available

300 MW

Granted

The operator's latest published dataset reports 300 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2033 (2033) · variant: 380kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/DOEL 380 · payload sha256 2a662dbb6e25…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at published maximum mw
300
Operator note: at voltage level cap
true
Operator note: code
DOEL 380
Operator note: flexibilityLevel
0%_flex
Operator note: variant
380kv
Operator note: voltage kv
380

Injection · Solar PV · Available

37.9 MW

Granted

The operator's latest published dataset reports 37.9 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2033 (2033) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/DOEL 150 · payload sha256 377ed26012d4…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
DOEL 150
Operator note: flexibilityLevel
0%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Injection · Solar PV · Available

300 MW

Granted

The operator's latest published dataset reports 300 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2033 (2033) · variant: 380kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/DOEL 380 · payload sha256 2a662dbb6e25…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at published maximum mw
300
Operator note: at voltage level cap
true
Operator note: code
DOEL 380
Operator note: flexibilityLevel
5%_flex
Operator note: variant
380kv
Operator note: voltage kv
380

Injection · Solar PV · Available

53 MW

Granted

The operator's latest published dataset reports 53 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2033 (2033) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/DOEL 150 · payload sha256 377ed26012d4…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
DOEL 150
Operator note: flexibilityLevel
5%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Injection · Solar PV · Available

300 MW

Granted

The operator's latest published dataset reports 300 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2033 (2033) · variant: 380kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/DOEL 380 · payload sha256 2a662dbb6e25…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at published maximum mw
300
Operator note: at voltage level cap
true
Operator note: code
DOEL 380
Operator note: flexibilityLevel
10%_flex
Operator note: variant
380kv
Operator note: voltage kv
380

Injection · Solar PV · Available

62 MW

Granted

The operator's latest published dataset reports 62 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2033 (2033) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/DOEL 150 · payload sha256 377ed26012d4…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
DOEL 150
Operator note: flexibilityLevel
10%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Injection · Solar PV · Available

300 MW

Granted

The operator's latest published dataset reports 300 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2033 (2033) · variant: 380kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/DOEL 380 · payload sha256 2a662dbb6e25…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at published maximum mw
300
Operator note: at voltage level cap
true
Operator note: code
DOEL 380
Operator note: flexibilityLevel
20%_flex
Operator note: variant
380kv
Operator note: voltage kv
380

Injection · Solar PV · Available

79.1 MW

Granted

The operator's latest published dataset reports 79.1 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2033 (2033) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/DOEL 150 · payload sha256 377ed26012d4…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
DOEL 150
Operator note: flexibilityLevel
20%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Injection · Onshore wind · Available

300 MW

Granted

The operator's latest published dataset reports 300 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2029 (2029) · variant: 380kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/DOEL 380 · payload sha256 2a662dbb6e25…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at published maximum mw
300
Operator note: at voltage level cap
true
Operator note: code
DOEL 380
Operator note: flexibilityLevel
0%_flex
Operator note: variant
380kv
Operator note: voltage kv
380

Injection · Onshore wind · Available

35.5 MW

Granted

The operator's latest published dataset reports 35.5 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2029 (2029) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/DOEL 150 · payload sha256 10bacc802190…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
DOEL 150
Operator note: flexibilityLevel
0%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Injection · Onshore wind · Available

300 MW

Granted

The operator's latest published dataset reports 300 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2029 (2029) · variant: 380kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/DOEL 380 · payload sha256 2a662dbb6e25…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at published maximum mw
300
Operator note: at voltage level cap
true
Operator note: code
DOEL 380
Operator note: flexibilityLevel
5%_flex
Operator note: variant
380kv
Operator note: voltage kv
380

Injection · Onshore wind · Available

46.7 MW

Granted

The operator's latest published dataset reports 46.7 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2029 (2029) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/DOEL 150 · payload sha256 10bacc802190…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
DOEL 150
Operator note: flexibilityLevel
5%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Injection · Onshore wind · Available

300 MW

Granted

The operator's latest published dataset reports 300 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2029 (2029) · variant: 380kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/DOEL 380 · payload sha256 2a662dbb6e25…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at published maximum mw
300
Operator note: at voltage level cap
true
Operator note: code
DOEL 380
Operator note: flexibilityLevel
10%_flex
Operator note: variant
380kv
Operator note: voltage kv
380

Injection · Onshore wind · Available

57.4 MW

Granted

The operator's latest published dataset reports 57.4 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2029 (2029) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/DOEL 150 · payload sha256 10bacc802190…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
DOEL 150
Operator note: flexibilityLevel
10%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Injection · Onshore wind · Available

300 MW

Granted

The operator's latest published dataset reports 300 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2029 (2029) · variant: 380kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/DOEL 380 · payload sha256 2a662dbb6e25…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at published maximum mw
300
Operator note: at voltage level cap
true
Operator note: code
DOEL 380
Operator note: flexibilityLevel
20%_flex
Operator note: variant
380kv
Operator note: voltage kv
380

Injection · Onshore wind · Available

83.1 MW

Granted

The operator's latest published dataset reports 83.1 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2029 (2029) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/DOEL 150 · payload sha256 10bacc802190…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
DOEL 150
Operator note: flexibilityLevel
20%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Injection · Onshore wind · Available

300 MW

Granted

The operator's latest published dataset reports 300 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2033 (2033) · variant: 380kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/DOEL 380 · payload sha256 2a662dbb6e25…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at published maximum mw
300
Operator note: at voltage level cap
true
Operator note: code
DOEL 380
Operator note: flexibilityLevel
0%_flex
Operator note: variant
380kv
Operator note: voltage kv
380

Injection · Onshore wind · Available

35.5 MW

Granted

The operator's latest published dataset reports 35.5 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2033 (2033) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/DOEL 150 · payload sha256 377ed26012d4…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
DOEL 150
Operator note: flexibilityLevel
0%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Injection · Onshore wind · Available

300 MW

Granted

The operator's latest published dataset reports 300 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2033 (2033) · variant: 380kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/DOEL 380 · payload sha256 2a662dbb6e25…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at published maximum mw
300
Operator note: at voltage level cap
true
Operator note: code
DOEL 380
Operator note: flexibilityLevel
5%_flex
Operator note: variant
380kv
Operator note: voltage kv
380

Injection · Onshore wind · Available

46.7 MW

Granted

The operator's latest published dataset reports 46.7 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2033 (2033) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/DOEL 150 · payload sha256 377ed26012d4…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
DOEL 150
Operator note: flexibilityLevel
5%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Injection · Onshore wind · Available

300 MW

Granted

The operator's latest published dataset reports 300 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2033 (2033) · variant: 380kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/DOEL 380 · payload sha256 2a662dbb6e25…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at published maximum mw
300
Operator note: at voltage level cap
true
Operator note: code
DOEL 380
Operator note: flexibilityLevel
10%_flex
Operator note: variant
380kv
Operator note: voltage kv
380

Injection · Onshore wind · Available

57.4 MW

Granted

The operator's latest published dataset reports 57.4 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2033 (2033) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/DOEL 150 · payload sha256 377ed26012d4…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
DOEL 150
Operator note: flexibilityLevel
10%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Injection · Onshore wind · Available

300 MW

Granted

The operator's latest published dataset reports 300 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2033 (2033) · variant: 380kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/DOEL 380 · payload sha256 2a662dbb6e25…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at published maximum mw
300
Operator note: at voltage level cap
true
Operator note: code
DOEL 380
Operator note: flexibilityLevel
20%_flex
Operator note: variant
380kv
Operator note: voltage kv
380

Injection · Onshore wind · Available

83.1 MW

Granted

The operator's latest published dataset reports 83.1 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2033 (2033) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/DOEL 150 · payload sha256 377ed26012d4…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
DOEL 150
Operator note: flexibilityLevel
20%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Offtake · Load (any) · Available

101.4 MW

Granted

The operator's latest published dataset reports 101.4 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2029 (2029) · variant: 380kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/DOEL 380 · payload sha256 2a662dbb6e25…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
DOEL 380
Operator note: flexibilityLevel
0%_flex
Operator note: variant
380kv
Operator note: voltage kv
380

Offtake · Load (any) · Available

7.6 MW

Granted

The operator's latest published dataset reports 7.6 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2029 (2029) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/DOEL 150 · payload sha256 10bacc802190…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
DOEL 150
Operator note: flexibilityLevel
0%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Offtake · Load (any) · Available

300 MW

Granted

The operator's latest published dataset reports 300 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2029 (2029) · variant: 380kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/DOEL 380 · payload sha256 2a662dbb6e25…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at published maximum mw
300
Operator note: at voltage level cap
true
Operator note: code
DOEL 380
Operator note: flexibilityLevel
5%_flex
Operator note: variant
380kv
Operator note: voltage kv
380

Offtake · Load (any) · Available

11.6 MW

Granted

The operator's latest published dataset reports 11.6 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2029 (2029) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/DOEL 150 · payload sha256 10bacc802190…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
DOEL 150
Operator note: flexibilityLevel
5%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Offtake · Load (any) · Available

300 MW

Granted

The operator's latest published dataset reports 300 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2029 (2029) · variant: 380kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/DOEL 380 · payload sha256 2a662dbb6e25…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at published maximum mw
300
Operator note: at voltage level cap
true
Operator note: code
DOEL 380
Operator note: flexibilityLevel
10%_flex
Operator note: variant
380kv
Operator note: voltage kv
380

Offtake · Load (any) · Available

22.7 MW

Granted

The operator's latest published dataset reports 22.7 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2029 (2029) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/DOEL 150 · payload sha256 10bacc802190…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
DOEL 150
Operator note: flexibilityLevel
10%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Offtake · Load (any) · Available

300 MW

Granted

The operator's latest published dataset reports 300 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2029 (2029) · variant: 380kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/DOEL 380 · payload sha256 2a662dbb6e25…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at published maximum mw
300
Operator note: at voltage level cap
true
Operator note: code
DOEL 380
Operator note: flexibilityLevel
20%_flex
Operator note: variant
380kv
Operator note: voltage kv
380

Offtake · Load (any) · Available

79 MW

Granted

The operator's latest published dataset reports 79 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2029 (2029) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/DOEL 150 · payload sha256 10bacc802190…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
DOEL 150
Operator note: flexibilityLevel
20%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Offtake · Load (any) · Available

101.4 MW

Granted

The operator's latest published dataset reports 101.4 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2033 (2033) · variant: 380kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/DOEL 380 · payload sha256 2a662dbb6e25…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
DOEL 380
Operator note: flexibilityLevel
0%_flex
Operator note: variant
380kv
Operator note: voltage kv
380

Offtake · Load (any) · Available

11.7 MW

Granted

The operator's latest published dataset reports 11.7 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2033 (2033) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/DOEL 150 · payload sha256 377ed26012d4…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
DOEL 150
Operator note: flexibilityLevel
0%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Offtake · Load (any) · Available

300 MW

Granted

The operator's latest published dataset reports 300 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2033 (2033) · variant: 380kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/DOEL 380 · payload sha256 2a662dbb6e25…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at published maximum mw
300
Operator note: at voltage level cap
true
Operator note: code
DOEL 380
Operator note: flexibilityLevel
5%_flex
Operator note: variant
380kv
Operator note: voltage kv
380

Offtake · Load (any) · Available

92.1 MW

Granted

The operator's latest published dataset reports 92.1 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2033 (2033) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/DOEL 150 · payload sha256 377ed26012d4…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
DOEL 150
Operator note: flexibilityLevel
5%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Offtake · Load (any) · Available

300 MW

Granted

The operator's latest published dataset reports 300 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2033 (2033) · variant: 380kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/DOEL 380 · payload sha256 2a662dbb6e25…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at published maximum mw
300
Operator note: at voltage level cap
true
Operator note: code
DOEL 380
Operator note: flexibilityLevel
10%_flex
Operator note: variant
380kv
Operator note: voltage kv
380

Offtake · Load (any) · Available

105.8 MW

Granted

The operator's latest published dataset reports 105.8 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2033 (2033) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/DOEL 150 · payload sha256 377ed26012d4…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
DOEL 150
Operator note: flexibilityLevel
10%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Offtake · Load (any) · Available

300 MW

Granted

The operator's latest published dataset reports 300 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2033 (2033) · variant: 380kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/DOEL 380 · payload sha256 2a662dbb6e25…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at published maximum mw
300
Operator note: at voltage level cap
true
Operator note: code
DOEL 380
Operator note: flexibilityLevel
20%_flex
Operator note: variant
380kv
Operator note: voltage kv
380

Offtake · Load (any) · Available

123.8 MW

Granted

The operator's latest published dataset reports 123.8 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2033 (2033) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/DOEL 150 · payload sha256 377ed26012d4…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
DOEL 150
Operator note: flexibilityLevel
20%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Bidirectional · Battery · Available

91.1 MW

Granted

The operator's latest published dataset reports 91.1 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2029 (2029) · variant: 380kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/DOEL 380 · payload sha256 2a662dbb6e25…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
DOEL 380
Operator note: flexibilityLevel
0%_flex
Operator note: variant
380kv
Operator note: voltage kv
380

Bidirectional · Battery · Available

1.9 MW

Granted

The operator's latest published dataset reports 1.9 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2029 (2029) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/DOEL 150 · payload sha256 10bacc802190…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
DOEL 150
Operator note: flexibilityLevel
0%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Bidirectional · Battery · Available

113 MW

Granted

The operator's latest published dataset reports 113 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2029 (2029) · variant: 380kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/DOEL 380 · payload sha256 2a662dbb6e25…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
DOEL 380
Operator note: flexibilityLevel
5%_flex
Operator note: variant
380kv
Operator note: voltage kv
380

Bidirectional · Battery · Available

2.2 MW

Granted

The operator's latest published dataset reports 2.2 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2029 (2029) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/DOEL 150 · payload sha256 10bacc802190…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
DOEL 150
Operator note: flexibilityLevel
5%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Bidirectional · Battery · Available

132.1 MW

Granted

The operator's latest published dataset reports 132.1 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2029 (2029) · variant: 380kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/DOEL 380 · payload sha256 2a662dbb6e25…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
DOEL 380
Operator note: flexibilityLevel
10%_flex
Operator note: variant
380kv
Operator note: voltage kv
380

Bidirectional · Battery · Available

2.3 MW

Granted

The operator's latest published dataset reports 2.3 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2029 (2029) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/DOEL 150 · payload sha256 10bacc802190…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
DOEL 150
Operator note: flexibilityLevel
10%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Bidirectional · Battery · Available

191.6 MW

Granted

The operator's latest published dataset reports 191.6 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2029 (2029) · variant: 380kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/DOEL 380 · payload sha256 2a662dbb6e25…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
DOEL 380
Operator note: flexibilityLevel
20%_flex
Operator note: variant
380kv
Operator note: voltage kv
380

Bidirectional · Battery · Available

2.6 MW

Granted

The operator's latest published dataset reports 2.6 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2029 (2029) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/DOEL 150 · payload sha256 10bacc802190…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
DOEL 150
Operator note: flexibilityLevel
20%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Bidirectional · Battery · Available

91.1 MW

Granted

The operator's latest published dataset reports 91.1 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2033 (2033) · variant: 380kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/DOEL 380 · payload sha256 2a662dbb6e25…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
DOEL 380
Operator note: flexibilityLevel
0%_flex
Operator note: variant
380kv
Operator note: voltage kv
380

Bidirectional · Battery · Available

1.9 MW

Granted

The operator's latest published dataset reports 1.9 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2033 (2033) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/DOEL 150 · payload sha256 377ed26012d4…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
DOEL 150
Operator note: flexibilityLevel
0%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Bidirectional · Battery · Available

113 MW

Granted

The operator's latest published dataset reports 113 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2033 (2033) · variant: 380kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/DOEL 380 · payload sha256 2a662dbb6e25…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
DOEL 380
Operator note: flexibilityLevel
5%_flex
Operator note: variant
380kv
Operator note: voltage kv
380

Bidirectional · Battery · Available

2.2 MW

Granted

The operator's latest published dataset reports 2.2 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2033 (2033) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/DOEL 150 · payload sha256 377ed26012d4…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
DOEL 150
Operator note: flexibilityLevel
5%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Bidirectional · Battery · Available

132.1 MW

Granted

The operator's latest published dataset reports 132.1 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2033 (2033) · variant: 380kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/DOEL 380 · payload sha256 2a662dbb6e25…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
DOEL 380
Operator note: flexibilityLevel
10%_flex
Operator note: variant
380kv
Operator note: voltage kv
380

Bidirectional · Battery · Available

2.3 MW

Granted

The operator's latest published dataset reports 2.3 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2033 (2033) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/DOEL 150 · payload sha256 377ed26012d4…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
DOEL 150
Operator note: flexibilityLevel
10%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Bidirectional · Battery · Available

191.6 MW

Granted

The operator's latest published dataset reports 191.6 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2033 (2033) · variant: 380kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/DOEL 380 · payload sha256 2a662dbb6e25…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
DOEL 380
Operator note: flexibilityLevel
20%_flex
Operator note: variant
380kv
Operator note: voltage kv
380

Bidirectional · Battery · Available

2.6 MW

Granted

The operator's latest published dataset reports 2.6 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2033 (2033) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/DOEL 150 · payload sha256 377ed26012d4…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
DOEL 150
Operator note: flexibilityLevel
20%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

History

Served series only

Bidirectional · Battery · Available · 2027

last, until 17 Nov 2026: 80.5 MW

26 Sep 2026: 80.6 MW17 Oct 2026: 80.5 MW
26 Sep 2026range 80.5 to 80.6 MW24 Nov 2026
2 published values, as a table
Observed fromUntilValue
26 Sep 202617 Oct 202680.6 MW
17 Oct 202617 Nov 202680.5 MW

Time axis: when we observed each value, not the operator’s effective date.

Bidirectional · Battery · Available · 2027

last, until 17 Nov 2026: 151.8 MW

26 Sep 2026: 151.9 MW17 Oct 2026: 151.8 MW
26 Sep 2026range 151.8 to 151.9 MW24 Nov 2026
2 published values, as a table
Observed fromUntilValue
26 Sep 202617 Oct 2026151.9 MW
17 Oct 202617 Nov 2026151.8 MW

Time axis: when we observed each value, not the operator’s effective date.

Bidirectional · Battery · Available · 2027

last, until 17 Nov 2026: 175 MW

26 Sep 2026: 175 MW
26 Sep 2026range 175 to 175 MW24 Nov 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 202617 Nov 2026175 MW

Time axis: when we observed each value, not the operator’s effective date.

Bidirectional · Battery · Available · 2027

last, until 17 Nov 2026: 175 MW

26 Sep 2026: 175 MW
26 Sep 2026range 175 to 175 MW24 Nov 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 202617 Nov 2026175 MW

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Load (any) · Available · 2027

last, until 17 Nov 2026: 83.4 MW

26 Sep 2026: 83.4 MW
26 Sep 2026range 83.4 to 83.4 MW24 Nov 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 202617 Nov 202683.4 MW

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Load (any) · Available · 2027

last, until 17 Nov 2026: 153.4 MW

26 Sep 2026: 153.3 MW17 Oct 2026: 153.4 MW
26 Sep 2026range 153.3 to 153.4 MW24 Nov 2026
2 published values, as a table
Observed fromUntilValue
26 Sep 202617 Oct 2026153.3 MW
17 Oct 202617 Nov 2026153.4 MW

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Load (any) · Available · 2027

last, until 17 Nov 2026: 175 MW

26 Sep 2026: 175 MW
26 Sep 2026range 175 to 175 MW24 Nov 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 202617 Nov 2026175 MW

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Load (any) · Available · 2027

last, until 17 Nov 2026: 175 MW

26 Sep 2026: 175 MW
26 Sep 2026range 175 to 175 MW24 Nov 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 202617 Nov 2026175 MW

Time axis: when we observed each value, not the operator’s effective date.

Injection · Generation (any) · Available · 2027

last, until 17 Nov 2026: 118.8 MW

26 Sep 2026: 118.8 MW
26 Sep 2026range 118.8 to 118.8 MW24 Nov 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 202617 Nov 2026118.8 MW

Time axis: when we observed each value, not the operator’s effective date.

Injection · Generation (any) · Available · 2027

last, until 17 Nov 2026: 175 MW

26 Sep 2026: 175 MW
26 Sep 2026range 175 to 175 MW24 Nov 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 202617 Nov 2026175 MW

Time axis: when we observed each value, not the operator’s effective date.

Injection · Generation (any) · Available · 2027

last, until 17 Nov 2026: 175 MW

26 Sep 2026: 175 MW
26 Sep 2026range 175 to 175 MW24 Nov 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 202617 Nov 2026175 MW

Time axis: when we observed each value, not the operator’s effective date.

Injection · Generation (any) · Available · 2027

last, until 17 Nov 2026: 175 MW

26 Sep 2026: 175 MW
26 Sep 2026range 175 to 175 MW24 Nov 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 202617 Nov 2026175 MW

Time axis: when we observed each value, not the operator’s effective date.

The first 12 of 160 served series with a history. The history route returns every one of them.

Through the API

curl "https://api.gridcapacityapi.com/v1/substations/sub_06gdq69rg1ss3578838sywv5a8/capacity" \  -H "Authorization: Bearer gc_live_..."