| Injection | Generation (any) | Available | 68.2 MW | Firm, ≤ 0 % curtailment a year | 2027 (2027)variant: 380kv | 26 Sep 2026 |
| Injection | Generation (any) | Available | 1.9 MW | Firm, ≤ 0 % curtailment a year | 2027 (2027)variant: 70kv | 26 Sep 2026 |
| Injection | Generation (any) | Available | 162.6 MW | Flexible, ≤ 5 % curtailment a year | 2027 (2027)variant: 380kv | 26 Sep 2026 |
| Injection | Generation (any) | Available | 4.4 MW | Flexible, ≤ 5 % curtailment a year | 2027 (2027)variant: 70kv | 26 Sep 2026 |
| Injection | Generation (any) | Available | 272.6 MW | Flexible, ≤ 10 % curtailment a year | 2027 (2027)variant: 380kv | 26 Sep 2026 |
| Injection | Generation (any) | Available | 5.6 MW | Flexible, ≤ 10 % curtailment a year | 2027 (2027)variant: 70kv | 17 Oct 2026 |
| Injection | Generation (any) | Available | 300 MW | Flexible, ≤ 20 % curtailment a year | 2027 (2027)variant: 380kv | 26 Sep 2026 |
| Injection | Generation (any) | Available | 9.6 MW | Flexible, ≤ 20 % curtailment a year | 2027 (2027)variant: 70kv | 17 Oct 2026 |
| Injection | Generation (any) | Available | 68.2 MW | Firm, ≤ 0 % curtailment a year | 2031 (2031)variant: 380kv | 26 Sep 2026 |
| Injection | Generation (any) | Available | 1.9 MW | Firm, ≤ 0 % curtailment a year | 2031 (2031)variant: 70kv | 26 Sep 2026 |
| Injection | Generation (any) | Available | 162.6 MW | Flexible, ≤ 5 % curtailment a year | 2031 (2031)variant: 380kv | 26 Sep 2026 |
| Injection | Generation (any) | Available | 6.5 MW | Flexible, ≤ 5 % curtailment a year | 2031 (2031)variant: 70kv | 17 Oct 2026 |
| Injection | Generation (any) | Available | 272.6 MW | Flexible, ≤ 10 % curtailment a year | 2031 (2031)variant: 380kv | 26 Sep 2026 |
| Injection | Generation (any) | Available | 21.4 MW | Flexible, ≤ 10 % curtailment a year | 2031 (2031)variant: 70kv | 17 Oct 2026 |
| Injection | Generation (any) | Available | 300 MW | Flexible, ≤ 20 % curtailment a year | 2031 (2031)variant: 380kv | 26 Sep 2026 |
| Injection | Generation (any) | Available | 60 MW | Flexible, ≤ 20 % curtailment a year | 2031 (2031)variant: 70kv | 26 Sep 2026 |
| Injection | Solar PV | Available | 156.7 MW | Firm, ≤ 0 % curtailment a year | 2027 (2027)variant: 380kv | 26 Sep 2026 |
| Injection | Solar PV | Available | 3.3 MW | Firm, ≤ 0 % curtailment a year | 2027 (2027)variant: 70kv | 26 Sep 2026 |
| Injection | Solar PV | Available | 300 MW | Flexible, ≤ 5 % curtailment a year | 2027 (2027)variant: 380kv | 26 Sep 2026 |
| Injection | Solar PV | Available | 48.1 MW | Flexible, ≤ 5 % curtailment a year | 2027 (2027)variant: 70kv | 17 Oct 2026 |
| Injection | Solar PV | Available | 300 MW | Flexible, ≤ 10 % curtailment a year | 2027 (2027)variant: 380kv | 26 Sep 2026 |
| Injection | Solar PV | Available | 60 MW | Flexible, ≤ 10 % curtailment a year | 2027 (2027)variant: 70kv | 26 Sep 2026 |
| Injection | Solar PV | Available | 300 MW | Flexible, ≤ 20 % curtailment a year | 2027 (2027)variant: 380kv | 26 Sep 2026 |
| Injection | Solar PV | Available | 60 MW | Flexible, ≤ 20 % curtailment a year | 2027 (2027)variant: 70kv | 26 Sep 2026 |
| Injection | Solar PV | Available | 156.7 MW | Firm, ≤ 0 % curtailment a year | 2031 (2031)variant: 380kv | 26 Sep 2026 |
| Injection | Solar PV | Available | 3.3 MW | Firm, ≤ 0 % curtailment a year | 2031 (2031)variant: 70kv | 26 Sep 2026 |
| Injection | Solar PV | Available | 300 MW | Flexible, ≤ 5 % curtailment a year | 2031 (2031)variant: 380kv | 26 Sep 2026 |
| Injection | Solar PV | Available | 48.1 MW | Flexible, ≤ 5 % curtailment a year | 2031 (2031)variant: 70kv | 17 Oct 2026 |
| Injection | Solar PV | Available | 300 MW | Flexible, ≤ 10 % curtailment a year | 2031 (2031)variant: 380kv | 26 Sep 2026 |
| Injection | Solar PV | Available | 60 MW | Flexible, ≤ 10 % curtailment a year | 2031 (2031)variant: 70kv | 26 Sep 2026 |
| Injection | Solar PV | Available | 300 MW | Flexible, ≤ 20 % curtailment a year | 2031 (2031)variant: 380kv | 26 Sep 2026 |
| Injection | Solar PV | Available | 60 MW | Flexible, ≤ 20 % curtailment a year | 2031 (2031)variant: 70kv | 26 Sep 2026 |
| Injection | Onshore wind | Available | 143 MW | Firm, ≤ 0 % curtailment a year | 2027 (2027)variant: 380kv | 26 Sep 2026 |
| Injection | Onshore wind | Available | 2.3 MW | Firm, ≤ 0 % curtailment a year | 2027 (2027)variant: 70kv | 26 Sep 2026 |
| Injection | Onshore wind | Available | 300 MW | Flexible, ≤ 5 % curtailment a year | 2027 (2027)variant: 380kv | 26 Sep 2026 |
| Injection | Onshore wind | Available | 4.5 MW | Flexible, ≤ 5 % curtailment a year | 2027 (2027)variant: 70kv | 26 Sep 2026 |
| Injection | Onshore wind | Available | 300 MW | Flexible, ≤ 10 % curtailment a year | 2027 (2027)variant: 380kv | 26 Sep 2026 |
| Injection | Onshore wind | Available | 6 MW | Flexible, ≤ 10 % curtailment a year | 2027 (2027)variant: 70kv | 26 Sep 2026 |
| Injection | Onshore wind | Available | 300 MW | Flexible, ≤ 20 % curtailment a year | 2027 (2027)variant: 380kv | 26 Sep 2026 |
| Injection | Onshore wind | Available | 11 MW | Flexible, ≤ 20 % curtailment a year | 2027 (2027)variant: 70kv | 26 Sep 2026 |
| Injection | Onshore wind | Available | 143 MW | Firm, ≤ 0 % curtailment a year | 2031 (2031)variant: 380kv | 26 Sep 2026 |
| Injection | Onshore wind | Available | 2.3 MW | Firm, ≤ 0 % curtailment a year | 2031 (2031)variant: 70kv | 26 Sep 2026 |
| Injection | Onshore wind | Available | 300 MW | Flexible, ≤ 5 % curtailment a year | 2031 (2031)variant: 380kv | 26 Sep 2026 |
| Injection | Onshore wind | Available | 7 MW | Flexible, ≤ 5 % curtailment a year | 2031 (2031)variant: 70kv | 26 Sep 2026 |
| Injection | Onshore wind | Available | 300 MW | Flexible, ≤ 10 % curtailment a year | 2031 (2031)variant: 380kv | 26 Sep 2026 |
| Injection | Onshore wind | Available | 13.4 MW | Flexible, ≤ 10 % curtailment a year | 2031 (2031)variant: 70kv | 17 Oct 2026 |
| Injection | Onshore wind | Available | 300 MW | Flexible, ≤ 20 % curtailment a year | 2031 (2031)variant: 380kv | 26 Sep 2026 |
| Injection | Onshore wind | Available | 60 MW | Flexible, ≤ 20 % curtailment a year | 2031 (2031)variant: 70kv | 26 Sep 2026 |
| Offtake | Load (any) | Available | 52.5 MW | Firm, ≤ 0 % curtailment a year | 2027 (2027)variant: 380kv | 26 Sep 2026 |
| Offtake | Load (any) | Available | 2.3 MW | Firm, ≤ 0 % curtailment a year | 2027 (2027)variant: 70kv | 26 Sep 2026 |
| Offtake | Load (any) | Available | 300 MW | Flexible, ≤ 5 % curtailment a year | 2027 (2027)variant: 380kv | 26 Sep 2026 |
| Offtake | Load (any) | Available | 5.8 MW | Flexible, ≤ 5 % curtailment a year | 2027 (2027)variant: 70kv | 26 Sep 2026 |
| Offtake | Load (any) | Available | 300 MW | Flexible, ≤ 10 % curtailment a year | 2027 (2027)variant: 380kv | 26 Sep 2026 |
| Offtake | Load (any) | Available | 8.8 MW | Flexible, ≤ 10 % curtailment a year | 2027 (2027)variant: 70kv | 17 Oct 2026 |
| Offtake | Load (any) | Available | 300 MW | Flexible, ≤ 20 % curtailment a year | 2027 (2027)variant: 380kv | 26 Sep 2026 |
| Offtake | Load (any) | Available | 37.3 MW | Flexible, ≤ 20 % curtailment a year | 2027 (2027)variant: 70kv | 17 Oct 2026 |
| Offtake | Load (any) | Available | 52.5 MW | Firm, ≤ 0 % curtailment a year | 2031 (2031)variant: 380kv | 26 Sep 2026 |
| Offtake | Load (any) | Available | 3.9 MW | Firm, ≤ 0 % curtailment a year | 2031 (2031)variant: 70kv | 26 Sep 2026 |
| Offtake | Load (any) | Available | 300 MW | Flexible, ≤ 5 % curtailment a year | 2031 (2031)variant: 380kv | 26 Sep 2026 |
| Offtake | Load (any) | Available | 25.5 MW | Flexible, ≤ 5 % curtailment a year | 2031 (2031)variant: 70kv | 26 Sep 2026 |
| Offtake | Load (any) | Available | 300 MW | Flexible, ≤ 10 % curtailment a year | 2031 (2031)variant: 380kv | 26 Sep 2026 |
| Offtake | Load (any) | Available | 60 MW | Flexible, ≤ 10 % curtailment a year | 2031 (2031)variant: 70kv | 26 Sep 2026 |
| Offtake | Load (any) | Available | 300 MW | Flexible, ≤ 20 % curtailment a year | 2031 (2031)variant: 380kv | 26 Sep 2026 |
| Offtake | Load (any) | Available | 60 MW | Flexible, ≤ 20 % curtailment a year | 2031 (2031)variant: 70kv | 26 Sep 2026 |
| Bidirectional | Battery | Available | 52.5 MW | Firm, ≤ 0 % curtailment a year | 2027 (2027)variant: 380kv | 26 Sep 2026 |
| Bidirectional | Battery | Available | 1.9 MW | Firm, ≤ 0 % curtailment a year | 2027 (2027)variant: 70kv | 26 Sep 2026 |
| Bidirectional | Battery | Available | 162.6 MW | Flexible, ≤ 5 % curtailment a year | 2027 (2027)variant: 380kv | 26 Sep 2026 |
| Bidirectional | Battery | Available | 4.4 MW | Flexible, ≤ 5 % curtailment a year | 2027 (2027)variant: 70kv | 26 Sep 2026 |
| Bidirectional | Battery | Available | 272.6 MW | Flexible, ≤ 10 % curtailment a year | 2027 (2027)variant: 380kv | 26 Sep 2026 |
| Bidirectional | Battery | Available | 5.6 MW | Flexible, ≤ 10 % curtailment a year | 2027 (2027)variant: 70kv | 17 Oct 2026 |
| Bidirectional | Battery | Available | 300 MW | Flexible, ≤ 20 % curtailment a year | 2027 (2027)variant: 380kv | 26 Sep 2026 |
| Bidirectional | Battery | Available | 9.6 MW | Flexible, ≤ 20 % curtailment a year | 2027 (2027)variant: 70kv | 17 Oct 2026 |
| Bidirectional | Battery | Available | 52.5 MW | Firm, ≤ 0 % curtailment a year | 2031 (2031)variant: 380kv | 26 Sep 2026 |
| Bidirectional | Battery | Available | 1.9 MW | Firm, ≤ 0 % curtailment a year | 2031 (2031)variant: 70kv | 26 Sep 2026 |
| Bidirectional | Battery | Available | 162.6 MW | Flexible, ≤ 5 % curtailment a year | 2031 (2031)variant: 380kv | 26 Sep 2026 |
| Bidirectional | Battery | Available | 6.5 MW | Flexible, ≤ 5 % curtailment a year | 2031 (2031)variant: 70kv | 17 Oct 2026 |
| Bidirectional | Battery | Available | 272.6 MW | Flexible, ≤ 10 % curtailment a year | 2031 (2031)variant: 380kv | 26 Sep 2026 |
| Bidirectional | Battery | Available | 21.4 MW | Flexible, ≤ 10 % curtailment a year | 2031 (2031)variant: 70kv | 17 Oct 2026 |
| Bidirectional | Battery | Available | 300 MW | Flexible, ≤ 20 % curtailment a year | 2031 (2031)variant: 380kv | 26 Sep 2026 |
| Bidirectional | Battery | Available | 60 MW | Flexible, ≤ 20 % curtailment a year | 2031 (2031)variant: 70kv | 26 Sep 2026 |