Substation / hv

ROUSSAS

E-REDES, Distribuição de Eletricidade / Melgaço, Viana do Castelo, Portugal

Latest published values

22 served · 0 withheld

Each row is what the operator’s latest published dataset reports for one combination of direction, technology, measure, firmness and horizon. Hosting-capacity figures are indicative and reflect what operators publish. They are not a connection offer; only the operator can confirm capacity for a specific request.

Latest published capacity values, one row per series
DirectionTechnologyMeasureValueFirmnessHorizonSource date
InjectionGeneration (any)Allocated0.275 MVAUnknownNow (snapshot)30 Jun 2026
InjectionGeneration (any)Allocated0.275 MVAUnknownRARI31 Dec 2025
InjectionGeneration (any)Availablenot statedUnknownNow (snapshot)variant: mv_30kv30 Jun 2026
InjectionGeneration (any)Available0 MVAUnknownNow (snapshot)variant: mv_15kv30 Jun 2026
InjectionGeneration (any)Availablenot statedUnknownNow (snapshot)variant: mv_10kv30 Jun 2026
InjectionGeneration (any)Available0 MVAUnknownNow (snapshot)variant: hv30 Jun 2026
InjectionGeneration (any)Available0 MVAUnknownNow (snapshot)variant: mv_hv30 Jun 2026
InjectionGeneration (any)Available0 MVAUnknownNow (snapshot)variant: hv_group30 Jun 2026
InjectionGeneration (any)Availablenot statedUnknownRARIvariant: mv_30kv31 Dec 2025
InjectionGeneration (any)Available0 MVAUnknownRARIvariant: mv_15kv31 Dec 2025
InjectionGeneration (any)Availablenot statedUnknownRARIvariant: mv_10kv31 Dec 2025
InjectionGeneration (any)Available0 MVAUnknownRARIvariant: hv31 Dec 2025
InjectionGeneration (any)Available0 MVAUnknownRARIvariant: mv_hv31 Dec 2025
InjectionGeneration (any)Available0 MVAUnknownRARIvariant: hv_group31 Dec 2025
InjectionGeneration (any)Connected0.70937 MVAUnknownNow (snapshot)30 Jun 2026
InjectionGeneration (any)Connected0.70937 MVAUnknownRARI31 Dec 2025
InjectionGeneration (any)Requested5.8 MVAUnknownNow (snapshot)30 Jun 2026
InjectionGeneration (any)Requested5.8 MVAUnknownRARI31 Dec 2025
OfftakeLoad (any)Available10 MVAConditionalNow (snapshot)season: winter22 Apr 2026
OfftakeLoad (any)Available10 MVAConditionalNow (snapshot)season: summer22 Apr 2026
OfftakeLoad (any)Available3.298 MVAFirmNow (snapshot)season: winter22 Apr 2026
OfftakeLoad (any)Available5.055 MVAFirmNow (snapshot)season: summer22 Apr 2026
OfftakeLoad (any)Installed20 MVAUnknownNow (snapshot)season: winter22 Apr 2026
OfftakeLoad (any)Installed20 MVAUnknownNow (snapshot)season: summer22 Apr 2026
OfftakeLoad (any)Total10 MVAFirmNow (snapshot)season: winter22 Apr 2026
OfftakeLoad (any)Total10 MVAFirmNow (snapshot)season: summer22 Apr 2026

E-REDES (Distribuição de Eletricidade), "E-REDES Open Data Portal", https://e-redes.opendatasoft.com/pages/homepage/ (last updated 2026-06-30)E-REDES (Distribuição de Eletricidade), "E-REDES Open Data Portal", https://e-redes.opendatasoft.com/pages/homepage/ (last updated 2025-12-31)E-REDES (Distribuição de Eletricidade), "E-REDES Open Data Portal", https://e-redes.opendatasoft.com/pages/homepage/ (last updated 2026-04-22)

What each value means

Methodology, both clocks, provenance and rights

Injection · Generation (any) · Allocated

0.275 MVA

Published in MVA; no MW figure is derived from it.

Granted

The operator's latest published dataset reports 0.275 MVA under methodology pt_eredes_rececao_rnd.

Firmness
Unknown
Horizon
Now (snapshot)
Methodology
pt_eredes_rececao_rndE-REDES reception capacity for generation per HV/MV substationbasis operator calculated · network state unknown · comparability class pt_eredes_rececao_rndNot additive across assets. The method accounts for reserved: not stated · allocated: yes · pre-reserved: not stated · pending requests: not stated
Operator’s date
30 Jun 2026
Retrieved / confirmed
2026-09-26 02:49 UTClast confirmed unchanged 2026-10-02 01:19 UTC
Source health
Healthy
Provenance
pt_eredes_capacidade_rececaorecord 1603S5021700|Pedralva · payload sha256 c6a618414506…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: E-REDES (Distribuição de Eletricidade), "E-REDES Open Data Portal", https://e-redes.opendatasoft.com/pages/homepage/ (last updated 2026-06-30)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: horizon reference
2T2026
Operator note: justificacao
Saturação da corrente máxima admissível no TP 130/60kV da SE Lindoso
Operator note: notas
(bi)
Operator note: rnt busbar 60kv
Pedralva
Operator note: source field
potencia_de_ligacao_comprometido_mva_ultimo_trimestre

Injection · Generation (any) · Allocated

0.275 MVA

Published in MVA; no MW figure is derived from it.

Granted

The operator's latest published dataset reports 0.275 MVA under methodology pt_eredes_rececao_rnd.

Firmness
Unknown
Horizon
RARI
Methodology
pt_eredes_rececao_rndE-REDES reception capacity for generation per HV/MV substationbasis operator calculated · network state unknown · comparability class pt_eredes_rececao_rndNot additive across assets. The method accounts for reserved: not stated · allocated: yes · pre-reserved: not stated · pending requests: not stated
Operator’s date
31 Dec 2025
Retrieved / confirmed
2026-09-26 02:49 UTClast confirmed unchanged 2026-10-02 01:19 UTC
Source health
Healthy
Provenance
pt_eredes_capacidade_rececaorecord 1603S5021700|Pedralva · payload sha256 c6a618414506…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: E-REDES (Distribuição de Eletricidade), "E-REDES Open Data Portal", https://e-redes.opendatasoft.com/pages/homepage/ (last updated 2025-12-31)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: horizon reference
2025
Operator note: justificacao
Saturação da corrente máxima admissível no TP 130/60kV da SE Lindoso
Operator note: notas
(bi)
Operator note: rnt busbar 60kv
Pedralva
Operator note: source field
potencia_de_ligacao_comprometido_mva_rari

Injection · Generation (any) · Available

not stated

Published in MVA; no MW figure is derived from it.

Granted

The operator's latest published dataset reports no value (published as unknown) under methodology pt_eredes_rececao_rnd.

Firmness
Unknown
Horizon
Now (snapshot) · variant: mv_30kv
Methodology
pt_eredes_rececao_rndE-REDES reception capacity for generation per HV/MV substationbasis operator calculated · network state unknown · comparability class pt_eredes_rececao_rndNot additive across assets. The method accounts for reserved: not stated · allocated: yes · pre-reserved: not stated · pending requests: not stated
Operator’s date
30 Jun 2026
Retrieved / confirmed
2026-09-26 02:49 UTClast confirmed unchanged 2026-10-02 01:19 UTC
Source health
Healthy
Provenance
pt_eredes_capacidade_rececaorecord 1603S5021700|Pedralva · payload sha256 c6a618414506…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: E-REDES (Distribuição de Eletricidade), "E-REDES Open Data Portal", https://e-redes.opendatasoft.com/pages/homepage/ (last updated 2026-06-30)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: horizon reference
2T2026
Operator note: justificacao
Saturação da corrente máxima admissível no TP 130/60kV da SE Lindoso
Operator note: notas
(bi)
Operator note: rnt busbar 60kv
Pedralva
Operator note: source field
capacidade_de_recepcao_mt_30kv_mva_ultimo_trimestre
Operator note: source label
-

Injection · Generation (any) · Available

0 MVA

Published in MVA; no MW figure is derived from it.

Granted

The operator's latest published dataset reports 0 MVA under methodology pt_eredes_rececao_rnd.

Firmness
Unknown
Horizon
Now (snapshot) · variant: mv_15kv
Methodology
pt_eredes_rececao_rndE-REDES reception capacity for generation per HV/MV substationbasis operator calculated · network state unknown · comparability class pt_eredes_rececao_rndNot additive across assets. The method accounts for reserved: not stated · allocated: yes · pre-reserved: not stated · pending requests: not stated
Operator’s date
30 Jun 2026
Retrieved / confirmed
2026-09-26 02:49 UTClast confirmed unchanged 2026-10-02 01:19 UTC
Source health
Healthy
Provenance
pt_eredes_capacidade_rececaorecord 1603S5021700|Pedralva · payload sha256 c6a618414506…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: E-REDES (Distribuição de Eletricidade), "E-REDES Open Data Portal", https://e-redes.opendatasoft.com/pages/homepage/ (last updated 2026-06-30)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: horizon reference
2T2026
Operator note: justificacao
Saturação da corrente máxima admissível no TP 130/60kV da SE Lindoso
Operator note: notas
(bi)
Operator note: rnt busbar 60kv
Pedralva
Operator note: source field
capacidade_de_recepcao_mt_15kv_mva_ultimo_trimestre

Injection · Generation (any) · Available

not stated

Published in MVA; no MW figure is derived from it.

Granted

The operator's latest published dataset reports no value (published as unknown) under methodology pt_eredes_rececao_rnd.

Firmness
Unknown
Horizon
Now (snapshot) · variant: mv_10kv
Methodology
pt_eredes_rececao_rndE-REDES reception capacity for generation per HV/MV substationbasis operator calculated · network state unknown · comparability class pt_eredes_rececao_rndNot additive across assets. The method accounts for reserved: not stated · allocated: yes · pre-reserved: not stated · pending requests: not stated
Operator’s date
30 Jun 2026
Retrieved / confirmed
2026-09-26 02:49 UTClast confirmed unchanged 2026-10-02 01:19 UTC
Source health
Healthy
Provenance
pt_eredes_capacidade_rececaorecord 1603S5021700|Pedralva · payload sha256 c6a618414506…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: E-REDES (Distribuição de Eletricidade), "E-REDES Open Data Portal", https://e-redes.opendatasoft.com/pages/homepage/ (last updated 2026-06-30)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: horizon reference
2T2026
Operator note: justificacao
Saturação da corrente máxima admissível no TP 130/60kV da SE Lindoso
Operator note: notas
(bi)
Operator note: rnt busbar 60kv
Pedralva
Operator note: source field
capacidade_de_recepcao_mt_10kv_mva_ultimo_trimestre
Operator note: source label
-

Injection · Generation (any) · Available

0 MVA

Published in MVA; no MW figure is derived from it.

Granted

The operator's latest published dataset reports 0 MVA under methodology pt_eredes_rececao_rnd.

Firmness
Unknown
Horizon
Now (snapshot) · variant: hv
Methodology
pt_eredes_rececao_rndE-REDES reception capacity for generation per HV/MV substationbasis operator calculated · network state unknown · comparability class pt_eredes_rececao_rndNot additive across assets. The method accounts for reserved: not stated · allocated: yes · pre-reserved: not stated · pending requests: not stated
Operator’s date
30 Jun 2026
Retrieved / confirmed
2026-09-26 02:49 UTClast confirmed unchanged 2026-10-02 01:19 UTC
Source health
Healthy
Provenance
pt_eredes_capacidade_rececaorecord 1603S5021700|Pedralva · payload sha256 c6a618414506…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: E-REDES (Distribuição de Eletricidade), "E-REDES Open Data Portal", https://e-redes.opendatasoft.com/pages/homepage/ (last updated 2026-06-30)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: horizon reference
2T2026
Operator note: justificacao
Saturação da corrente máxima admissível no TP 130/60kV da SE Lindoso
Operator note: notas
(bi)
Operator note: rnt busbar 60kv
Pedralva
Operator note: source field
capacidade_de_recepcao_at_mva_ultimo_trimestre

Injection · Generation (any) · Available

0 MVA

Published in MVA; no MW figure is derived from it.

Granted

The operator's latest published dataset reports 0 MVA under methodology pt_eredes_rececao_rnd.

Firmness
Unknown
Horizon
Now (snapshot) · variant: mv_hv
Methodology
pt_eredes_rececao_rndE-REDES reception capacity for generation per HV/MV substationbasis operator calculated · network state unknown · comparability class pt_eredes_rececao_rndNot additive across assets. The method accounts for reserved: not stated · allocated: yes · pre-reserved: not stated · pending requests: not stated
Operator’s date
30 Jun 2026
Retrieved / confirmed
2026-09-26 02:49 UTClast confirmed unchanged 2026-10-02 01:19 UTC
Source health
Healthy
Provenance
pt_eredes_capacidade_rececaorecord 1603S5021700|Pedralva · payload sha256 c6a618414506…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: E-REDES (Distribuição de Eletricidade), "E-REDES Open Data Portal", https://e-redes.opendatasoft.com/pages/homepage/ (last updated 2026-06-30)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: horizon reference
2T2026
Operator note: justificacao
Saturação da corrente máxima admissível no TP 130/60kV da SE Lindoso
Operator note: notas
(bi)
Operator note: rnt busbar 60kv
Pedralva
Operator note: source field
capacidade_de_recepcao_mt_at_mva_ultimo_trimestre

Injection · Generation (any) · Available

0 MVA

Published in MVA; no MW figure is derived from it.

Granted

The operator's latest published dataset reports 0 MVA under methodology pt_eredes_rececao_rnd.

Firmness
Unknown
Horizon
Now (snapshot) · variant: hv_group
Methodology
pt_eredes_rececao_rndE-REDES reception capacity for generation per HV/MV substationbasis operator calculated · network state unknown · comparability class pt_eredes_rececao_rndNot additive across assets. The method accounts for reserved: not stated · allocated: yes · pre-reserved: not stated · pending requests: not stated
Operator’s date
30 Jun 2026
Retrieved / confirmed
2026-09-26 02:49 UTClast confirmed unchanged 2026-10-02 01:19 UTC
Source health
Healthy
Provenance
pt_eredes_capacidade_rececaorecord 1603S5021700|Pedralva · payload sha256 c6a618414506…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: E-REDES (Distribuição de Eletricidade), "E-REDES Open Data Portal", https://e-redes.opendatasoft.com/pages/homepage/ (last updated 2026-06-30)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: horizon reference
2T2026
Operator note: justificacao
Saturação da corrente máxima admissível no TP 130/60kV da SE Lindoso
Operator note: notas
(bi)
Operator note: rnt busbar 60kv
Pedralva
Operator note: shared by group
true
Operator note: source field
grupo_at_mva_ultimo_trimestre

Injection · Generation (any) · Available

not stated

Published in MVA; no MW figure is derived from it.

Granted

The operator's latest published dataset reports no value (published as unknown) under methodology pt_eredes_rececao_rnd.

Firmness
Unknown
Horizon
RARI · variant: mv_30kv
Methodology
pt_eredes_rececao_rndE-REDES reception capacity for generation per HV/MV substationbasis operator calculated · network state unknown · comparability class pt_eredes_rececao_rndNot additive across assets. The method accounts for reserved: not stated · allocated: yes · pre-reserved: not stated · pending requests: not stated
Operator’s date
31 Dec 2025
Retrieved / confirmed
2026-09-26 02:49 UTClast confirmed unchanged 2026-10-02 01:19 UTC
Source health
Healthy
Provenance
pt_eredes_capacidade_rececaorecord 1603S5021700|Pedralva · payload sha256 c6a618414506…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: E-REDES (Distribuição de Eletricidade), "E-REDES Open Data Portal", https://e-redes.opendatasoft.com/pages/homepage/ (last updated 2025-12-31)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: horizon reference
2025
Operator note: justificacao
Saturação da corrente máxima admissível no TP 130/60kV da SE Lindoso
Operator note: notas
(bi)
Operator note: rnt busbar 60kv
Pedralva
Operator note: source field
capacidade_de_recepcao_mt_30kv_mva_rari
Operator note: source label
-

Injection · Generation (any) · Available

0 MVA

Published in MVA; no MW figure is derived from it.

Granted

The operator's latest published dataset reports 0 MVA under methodology pt_eredes_rececao_rnd.

Firmness
Unknown
Horizon
RARI · variant: mv_15kv
Methodology
pt_eredes_rececao_rndE-REDES reception capacity for generation per HV/MV substationbasis operator calculated · network state unknown · comparability class pt_eredes_rececao_rndNot additive across assets. The method accounts for reserved: not stated · allocated: yes · pre-reserved: not stated · pending requests: not stated
Operator’s date
31 Dec 2025
Retrieved / confirmed
2026-09-26 02:49 UTClast confirmed unchanged 2026-10-02 01:19 UTC
Source health
Healthy
Provenance
pt_eredes_capacidade_rececaorecord 1603S5021700|Pedralva · payload sha256 c6a618414506…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: E-REDES (Distribuição de Eletricidade), "E-REDES Open Data Portal", https://e-redes.opendatasoft.com/pages/homepage/ (last updated 2025-12-31)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: horizon reference
2025
Operator note: justificacao
Saturação da corrente máxima admissível no TP 130/60kV da SE Lindoso
Operator note: notas
(bi)
Operator note: rnt busbar 60kv
Pedralva
Operator note: source field
capacidade_de_recepcao_mt_15kv_mva_rari

Injection · Generation (any) · Available

not stated

Published in MVA; no MW figure is derived from it.

Granted

The operator's latest published dataset reports no value (published as unknown) under methodology pt_eredes_rececao_rnd.

Firmness
Unknown
Horizon
RARI · variant: mv_10kv
Methodology
pt_eredes_rececao_rndE-REDES reception capacity for generation per HV/MV substationbasis operator calculated · network state unknown · comparability class pt_eredes_rececao_rndNot additive across assets. The method accounts for reserved: not stated · allocated: yes · pre-reserved: not stated · pending requests: not stated
Operator’s date
31 Dec 2025
Retrieved / confirmed
2026-09-26 02:49 UTClast confirmed unchanged 2026-10-02 01:19 UTC
Source health
Healthy
Provenance
pt_eredes_capacidade_rececaorecord 1603S5021700|Pedralva · payload sha256 c6a618414506…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: E-REDES (Distribuição de Eletricidade), "E-REDES Open Data Portal", https://e-redes.opendatasoft.com/pages/homepage/ (last updated 2025-12-31)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: horizon reference
2025
Operator note: justificacao
Saturação da corrente máxima admissível no TP 130/60kV da SE Lindoso
Operator note: notas
(bi)
Operator note: rnt busbar 60kv
Pedralva
Operator note: source field
capacidade_de_recepcao_mt_10kv_mva_rari
Operator note: source label
-

Injection · Generation (any) · Available

0 MVA

Published in MVA; no MW figure is derived from it.

Granted

The operator's latest published dataset reports 0 MVA under methodology pt_eredes_rececao_rnd.

Firmness
Unknown
Horizon
RARI · variant: hv
Methodology
pt_eredes_rececao_rndE-REDES reception capacity for generation per HV/MV substationbasis operator calculated · network state unknown · comparability class pt_eredes_rececao_rndNot additive across assets. The method accounts for reserved: not stated · allocated: yes · pre-reserved: not stated · pending requests: not stated
Operator’s date
31 Dec 2025
Retrieved / confirmed
2026-09-26 02:49 UTClast confirmed unchanged 2026-10-02 01:19 UTC
Source health
Healthy
Provenance
pt_eredes_capacidade_rececaorecord 1603S5021700|Pedralva · payload sha256 c6a618414506…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: E-REDES (Distribuição de Eletricidade), "E-REDES Open Data Portal", https://e-redes.opendatasoft.com/pages/homepage/ (last updated 2025-12-31)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: horizon reference
2025
Operator note: justificacao
Saturação da corrente máxima admissível no TP 130/60kV da SE Lindoso
Operator note: notas
(bi)
Operator note: rnt busbar 60kv
Pedralva
Operator note: source field
capacidade_de_recepcao_at_mva_rari

Injection · Generation (any) · Available

0 MVA

Published in MVA; no MW figure is derived from it.

Granted

The operator's latest published dataset reports 0 MVA under methodology pt_eredes_rececao_rnd.

Firmness
Unknown
Horizon
RARI · variant: mv_hv
Methodology
pt_eredes_rececao_rndE-REDES reception capacity for generation per HV/MV substationbasis operator calculated · network state unknown · comparability class pt_eredes_rececao_rndNot additive across assets. The method accounts for reserved: not stated · allocated: yes · pre-reserved: not stated · pending requests: not stated
Operator’s date
31 Dec 2025
Retrieved / confirmed
2026-09-26 02:49 UTClast confirmed unchanged 2026-10-02 01:19 UTC
Source health
Healthy
Provenance
pt_eredes_capacidade_rececaorecord 1603S5021700|Pedralva · payload sha256 c6a618414506…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: E-REDES (Distribuição de Eletricidade), "E-REDES Open Data Portal", https://e-redes.opendatasoft.com/pages/homepage/ (last updated 2025-12-31)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: horizon reference
2025
Operator note: justificacao
Saturação da corrente máxima admissível no TP 130/60kV da SE Lindoso
Operator note: notas
(bi)
Operator note: rnt busbar 60kv
Pedralva
Operator note: source field
capacidade_de_recepcao_mt_at_mva_rari

Injection · Generation (any) · Available

0 MVA

Published in MVA; no MW figure is derived from it.

Granted

The operator's latest published dataset reports 0 MVA under methodology pt_eredes_rececao_rnd.

Firmness
Unknown
Horizon
RARI · variant: hv_group
Methodology
pt_eredes_rececao_rndE-REDES reception capacity for generation per HV/MV substationbasis operator calculated · network state unknown · comparability class pt_eredes_rececao_rndNot additive across assets. The method accounts for reserved: not stated · allocated: yes · pre-reserved: not stated · pending requests: not stated
Operator’s date
31 Dec 2025
Retrieved / confirmed
2026-09-26 02:49 UTClast confirmed unchanged 2026-10-02 01:19 UTC
Source health
Healthy
Provenance
pt_eredes_capacidade_rececaorecord 1603S5021700|Pedralva · payload sha256 c6a618414506…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: E-REDES (Distribuição de Eletricidade), "E-REDES Open Data Portal", https://e-redes.opendatasoft.com/pages/homepage/ (last updated 2025-12-31)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: grupo de subestacoes rari
Roussas, Lindoso, Troviscoso, Touvedo, Mogueiras
Operator note: horizon reference
2025
Operator note: justificacao
Saturação da corrente máxima admissível no TP 130/60kV da SE Lindoso
Operator note: notas
(bi)
Operator note: rnt busbar 60kv
Pedralva
Operator note: shared by group
true
Operator note: source field
grupo_at_mva_rari

Injection · Generation (any) · Connected

0.70937 MVA

Published in MVA; no MW figure is derived from it.

Granted

The operator's latest published dataset reports 0.70937 MVA under methodology pt_eredes_rececao_rnd.

Firmness
Unknown
Horizon
Now (snapshot)
Methodology
pt_eredes_rececao_rndE-REDES reception capacity for generation per HV/MV substationbasis operator calculated · network state unknown · comparability class pt_eredes_rececao_rndNot additive across assets. The method accounts for reserved: not stated · allocated: yes · pre-reserved: not stated · pending requests: not stated
Operator’s date
30 Jun 2026
Retrieved / confirmed
2026-09-26 02:49 UTClast confirmed unchanged 2026-10-02 01:19 UTC
Source health
Healthy
Provenance
pt_eredes_capacidade_rececaorecord 1603S5021700|Pedralva · payload sha256 c6a618414506…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: E-REDES (Distribuição de Eletricidade), "E-REDES Open Data Portal", https://e-redes.opendatasoft.com/pages/homepage/ (last updated 2026-06-30)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: horizon reference
2T2026
Operator note: justificacao
Saturação da corrente máxima admissível no TP 130/60kV da SE Lindoso
Operator note: notas
(bi)
Operator note: rnt busbar 60kv
Pedralva
Operator note: source field
potencia_de_ligacao_ligado_mva_ultimo_trimestre

Injection · Generation (any) · Connected

0.70937 MVA

Published in MVA; no MW figure is derived from it.

Granted

The operator's latest published dataset reports 0.70937 MVA under methodology pt_eredes_rececao_rnd.

Firmness
Unknown
Horizon
RARI
Methodology
pt_eredes_rececao_rndE-REDES reception capacity for generation per HV/MV substationbasis operator calculated · network state unknown · comparability class pt_eredes_rececao_rndNot additive across assets. The method accounts for reserved: not stated · allocated: yes · pre-reserved: not stated · pending requests: not stated
Operator’s date
31 Dec 2025
Retrieved / confirmed
2026-09-26 02:49 UTClast confirmed unchanged 2026-10-02 01:19 UTC
Source health
Healthy
Provenance
pt_eredes_capacidade_rececaorecord 1603S5021700|Pedralva · payload sha256 c6a618414506…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: E-REDES (Distribuição de Eletricidade), "E-REDES Open Data Portal", https://e-redes.opendatasoft.com/pages/homepage/ (last updated 2025-12-31)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: horizon reference
2025
Operator note: justificacao
Saturação da corrente máxima admissível no TP 130/60kV da SE Lindoso
Operator note: notas
(bi)
Operator note: rnt busbar 60kv
Pedralva
Operator note: source field
potencia_de_ligacao_ligado_mva_rari

Injection · Generation (any) · Requested

5.8 MVA

Published in MVA; no MW figure is derived from it.

Granted

The operator's latest published dataset reports 5.8 MVA under methodology pt_eredes_rececao_rnd.

Firmness
Unknown
Horizon
Now (snapshot)
Methodology
pt_eredes_rececao_rndE-REDES reception capacity for generation per HV/MV substationbasis operator calculated · network state unknown · comparability class pt_eredes_rececao_rndNot additive across assets. The method accounts for reserved: not stated · allocated: yes · pre-reserved: not stated · pending requests: not stated
Operator’s date
30 Jun 2026
Retrieved / confirmed
2026-09-26 02:49 UTClast confirmed unchanged 2026-10-02 01:19 UTC
Source health
Healthy
Provenance
pt_eredes_capacidade_rececaorecord 1603S5021700|Pedralva · payload sha256 c6a618414506…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: E-REDES (Distribuição de Eletricidade), "E-REDES Open Data Portal", https://e-redes.opendatasoft.com/pages/homepage/ (last updated 2026-06-30)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: horizon reference
2T2026
Operator note: justificacao
Saturação da corrente máxima admissível no TP 130/60kV da SE Lindoso
Operator note: notas
(bi)
Operator note: rnt busbar 60kv
Pedralva
Operator note: source field
potencia_de_ligacao_em_confirmacao_mva_ultimo_trimestre

Injection · Generation (any) · Requested

5.8 MVA

Published in MVA; no MW figure is derived from it.

Granted

The operator's latest published dataset reports 5.8 MVA under methodology pt_eredes_rececao_rnd.

Firmness
Unknown
Horizon
RARI
Methodology
pt_eredes_rececao_rndE-REDES reception capacity for generation per HV/MV substationbasis operator calculated · network state unknown · comparability class pt_eredes_rececao_rndNot additive across assets. The method accounts for reserved: not stated · allocated: yes · pre-reserved: not stated · pending requests: not stated
Operator’s date
31 Dec 2025
Retrieved / confirmed
2026-09-26 02:49 UTClast confirmed unchanged 2026-10-02 01:19 UTC
Source health
Healthy
Provenance
pt_eredes_capacidade_rececaorecord 1603S5021700|Pedralva · payload sha256 c6a618414506…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: E-REDES (Distribuição de Eletricidade), "E-REDES Open Data Portal", https://e-redes.opendatasoft.com/pages/homepage/ (last updated 2025-12-31)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: horizon reference
2025
Operator note: justificacao
Saturação da corrente máxima admissível no TP 130/60kV da SE Lindoso
Operator note: notas
(bi)
Operator note: rnt busbar 60kv
Pedralva
Operator note: source field
potencia_de_ligacao_em_confirmacao_mva_rari

Offtake · Load (any) · Available

10 MVA

Published in MVA; no MW figure is derived from it.

Granted

The operator's latest published dataset reports 10 MVA under methodology pt_eredes_carga_nao_garantida.

Firmness
Conditional
Horizon
Now (snapshot) · season: winter
Methodology
pt_eredes_carga_nao_garantidaE-REDES substation load headroom without N-1 securitybasis operator calculated · network state n · comparability class pt_eredes_carga_nNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
22 Apr 2026
Retrieved / confirmed
2026-09-26 02:49 UTClast confirmed unchanged 2026-10-01 18:46 UTC
Source health
Healthy
Provenance
pt_eredes_carga_subestacaorecord 1603S5021700|Inverno · payload sha256 4982729314b9…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: E-REDES (Distribuição de Eletricidade), "E-REDES Open Data Portal", https://e-redes.opendatasoft.com/pages/homepage/ (last updated 2026-04-22)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: ano
2025
Operator note: source field
potencia_instalada_nao_garantida

Offtake · Load (any) · Available

10 MVA

Published in MVA; no MW figure is derived from it.

Granted

The operator's latest published dataset reports 10 MVA under methodology pt_eredes_carga_nao_garantida.

Firmness
Conditional
Horizon
Now (snapshot) · season: summer
Methodology
pt_eredes_carga_nao_garantidaE-REDES substation load headroom without N-1 securitybasis operator calculated · network state n · comparability class pt_eredes_carga_nNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
22 Apr 2026
Retrieved / confirmed
2026-09-26 02:49 UTClast confirmed unchanged 2026-10-01 18:46 UTC
Source health
Healthy
Provenance
pt_eredes_carga_subestacaorecord 1603S5021700|Verão · payload sha256 9a15cf387a1d…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: E-REDES (Distribuição de Eletricidade), "E-REDES Open Data Portal", https://e-redes.opendatasoft.com/pages/homepage/ (last updated 2026-04-22)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: ano
2025
Operator note: source field
potencia_instalada_nao_garantida

Offtake · Load (any) · Available

3.298 MVA

Published in MVA; no MW figure is derived from it.

Granted

The operator's latest published dataset reports 3.298 MVA under methodology pt_eredes_carga_n1.

Firmness
Firm
Horizon
Now (snapshot) · season: winter
Methodology
pt_eredes_carga_n1E-REDES substation load headroom with N-1 securitybasis operator calculated · network state n minus 1 · comparability class pt_eredes_carga_n1Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
22 Apr 2026
Retrieved / confirmed
2026-09-26 02:49 UTClast confirmed unchanged 2026-10-01 18:46 UTC
Source health
Healthy
Provenance
pt_eredes_carga_subestacaorecord 1603S5021700|Inverno · payload sha256 4982729314b9…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: E-REDES (Distribuição de Eletricidade), "E-REDES Open Data Portal", https://e-redes.opendatasoft.com/pages/homepage/ (last updated 2026-04-22)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: ano
2025
Operator note: source field
disponibilidade

Offtake · Load (any) · Available

5.055 MVA

Published in MVA; no MW figure is derived from it.

Granted

The operator's latest published dataset reports 5.055 MVA under methodology pt_eredes_carga_n1.

Firmness
Firm
Horizon
Now (snapshot) · season: summer
Methodology
pt_eredes_carga_n1E-REDES substation load headroom with N-1 securitybasis operator calculated · network state n minus 1 · comparability class pt_eredes_carga_n1Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
22 Apr 2026
Retrieved / confirmed
2026-09-26 02:49 UTClast confirmed unchanged 2026-10-01 18:46 UTC
Source health
Healthy
Provenance
pt_eredes_carga_subestacaorecord 1603S5021700|Verão · payload sha256 9a15cf387a1d…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: E-REDES (Distribuição de Eletricidade), "E-REDES Open Data Portal", https://e-redes.opendatasoft.com/pages/homepage/ (last updated 2026-04-22)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: ano
2025
Operator note: source field
disponibilidade

Offtake · Load (any) · Installed

20 MVA

Published in MVA; no MW figure is derived from it.

Granted

The operator's latest published dataset reports 20 MVA under methodology pt_eredes_carga_potencia_instalada.

Firmness
Unknown
Horizon
Now (snapshot) · season: winter
Methodology
pt_eredes_carga_potencia_instaladaE-REDES installed transformer power per substationbasis operator published · network state unknown · comparability class pt_eredes_transformer_ratingNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
22 Apr 2026
Retrieved / confirmed
2026-09-26 02:49 UTClast confirmed unchanged 2026-10-01 18:46 UTC
Source health
Healthy
Provenance
pt_eredes_carga_subestacaorecord 1603S5021700|Inverno · payload sha256 4982729314b9…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: E-REDES (Distribuição de Eletricidade), "E-REDES Open Data Portal", https://e-redes.opendatasoft.com/pages/homepage/ (last updated 2026-04-22)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: ano
2025
Operator note: source field
potencia_instalada

Offtake · Load (any) · Installed

20 MVA

Published in MVA; no MW figure is derived from it.

Granted

The operator's latest published dataset reports 20 MVA under methodology pt_eredes_carga_potencia_instalada.

Firmness
Unknown
Horizon
Now (snapshot) · season: summer
Methodology
pt_eredes_carga_potencia_instaladaE-REDES installed transformer power per substationbasis operator published · network state unknown · comparability class pt_eredes_transformer_ratingNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
22 Apr 2026
Retrieved / confirmed
2026-09-26 02:49 UTClast confirmed unchanged 2026-10-01 18:46 UTC
Source health
Healthy
Provenance
pt_eredes_carga_subestacaorecord 1603S5021700|Verão · payload sha256 9a15cf387a1d…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: E-REDES (Distribuição de Eletricidade), "E-REDES Open Data Portal", https://e-redes.opendatasoft.com/pages/homepage/ (last updated 2026-04-22)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: ano
2025
Operator note: source field
potencia_instalada

Offtake · Load (any) · Total

10 MVA

Published in MVA; no MW figure is derived from it.

Granted

The operator's latest published dataset reports 10 MVA under methodology pt_eredes_carga_n1.

Firmness
Firm
Horizon
Now (snapshot) · season: winter
Methodology
pt_eredes_carga_n1E-REDES substation load headroom with N-1 securitybasis operator calculated · network state n minus 1 · comparability class pt_eredes_carga_n1Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
22 Apr 2026
Retrieved / confirmed
2026-09-26 02:49 UTClast confirmed unchanged 2026-10-01 18:46 UTC
Source health
Healthy
Provenance
pt_eredes_carga_subestacaorecord 1603S5021700|Inverno · payload sha256 4982729314b9…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: E-REDES (Distribuição de Eletricidade), "E-REDES Open Data Portal", https://e-redes.opendatasoft.com/pages/homepage/ (last updated 2026-04-22)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: ano
2025
Operator note: source field
potencia_garantida

Offtake · Load (any) · Total

10 MVA

Published in MVA; no MW figure is derived from it.

Granted

The operator's latest published dataset reports 10 MVA under methodology pt_eredes_carga_n1.

Firmness
Firm
Horizon
Now (snapshot) · season: summer
Methodology
pt_eredes_carga_n1E-REDES substation load headroom with N-1 securitybasis operator calculated · network state n minus 1 · comparability class pt_eredes_carga_n1Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
22 Apr 2026
Retrieved / confirmed
2026-09-26 02:49 UTClast confirmed unchanged 2026-10-01 18:46 UTC
Source health
Healthy
Provenance
pt_eredes_carga_subestacaorecord 1603S5021700|Verão · payload sha256 9a15cf387a1d…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: E-REDES (Distribuição de Eletricidade), "E-REDES Open Data Portal", https://e-redes.opendatasoft.com/pages/homepage/ (last updated 2026-04-22)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: ano
2025
Operator note: source field
potencia_garantida

History

Served series only

Injection · Generation (any) · Connected

current 0.70937 MVA

26 Sep 2026: 0.70937 MVA
26 Sep 2026range 0.70937 to 0.70937 MVA2 Oct 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current0.70937 MVA

Time axis: when we observed each value, not the operator’s effective date.

Injection · Generation (any) · Allocated

current 0.275 MVA

26 Sep 2026: 0.275 MVA
26 Sep 2026range 0.275 to 0.275 MVA2 Oct 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current0.275 MVA

Time axis: when we observed each value, not the operator’s effective date.

Injection · Generation (any) · Requested

current 5.8 MVA

26 Sep 2026: 5.8 MVA
26 Sep 2026range 5.8 to 5.8 MVA2 Oct 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current5.8 MVA

Time axis: when we observed each value, not the operator’s effective date.

Injection · Generation (any) · Available

current 0 MVA

26 Sep 2026: 0 MVA
26 Sep 2026range 0 to 0 MVA2 Oct 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current0 MVA

Time axis: when we observed each value, not the operator’s effective date.

Injection · Generation (any) · Available

current 0 MVA

26 Sep 2026: 0 MVA
26 Sep 2026range 0 to 0 MVA2 Oct 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current0 MVA

Time axis: when we observed each value, not the operator’s effective date.

Injection · Generation (any) · Available

current 0 MVA

26 Sep 2026: 0 MVA
26 Sep 2026range 0 to 0 MVA2 Oct 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current0 MVA

Time axis: when we observed each value, not the operator’s effective date.

Injection · Generation (any) · Available

current 0 MVA

26 Sep 2026: 0 MVA
26 Sep 2026range 0 to 0 MVA2 Oct 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current0 MVA

Time axis: when we observed each value, not the operator’s effective date.

Injection · Generation (any) · Connected · RARI

current 0.70937 MVA

26 Sep 2026: 0.70937 MVA
26 Sep 2026range 0.70937 to 0.70937 MVA2 Oct 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current0.70937 MVA

Time axis: when we observed each value, not the operator’s effective date.

Injection · Generation (any) · Allocated · RARI

current 0.275 MVA

26 Sep 2026: 0.275 MVA
26 Sep 2026range 0.275 to 0.275 MVA2 Oct 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current0.275 MVA

Time axis: when we observed each value, not the operator’s effective date.

Injection · Generation (any) · Requested · RARI

current 5.8 MVA

26 Sep 2026: 5.8 MVA
26 Sep 2026range 5.8 to 5.8 MVA2 Oct 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current5.8 MVA

Time axis: when we observed each value, not the operator’s effective date.

Injection · Generation (any) · Available · RARI

current 0 MVA

26 Sep 2026: 0 MVA
26 Sep 2026range 0 to 0 MVA2 Oct 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current0 MVA

Time axis: when we observed each value, not the operator’s effective date.

Injection · Generation (any) · Available · RARI

current 0 MVA

26 Sep 2026: 0 MVA
26 Sep 2026range 0 to 0 MVA2 Oct 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current0 MVA

Time axis: when we observed each value, not the operator’s effective date.

The first 12 of 22 served series with a history. The history route returns every one of them.

Through the API

curl "https://api.gridcapacityapi.com/v1/substations/sub_06gdq7j331rjh7adq2s2gszksw/capacity" \  -H "Authorization: Bearer gc_live_..."
ROUSSAS substation: grid capacity (E-REDES, Distribuição de Eletricidade) · GridCapacity API