Substation / 11 kV / primary

HUTTON END

SP Electricity North West / United Kingdom

Latest published values

6 served · 0 withheld

Each row is what the operator’s latest published dataset reports for one combination of direction, technology, measure, firmness and horizon. Hosting-capacity figures are indicative and reflect what operators publish. They are not a connection offer; only the operator can confirm capacity for a specific request.

Latest published capacity values, one row per series
DirectionTechnologyMeasureValueFirmnessHorizonSource date
InjectionGeneration (any)Available26.30385 MWConditionalNow (snapshot)variant: inverter_based14 Aug 2026
InjectionGeneration (any)Available22.887045 MWConditionalNow (snapshot)variant: synchronous_lv14 Aug 2026
InjectionGeneration (any)Available16.44937 MWConditionalNow (snapshot)variant: synchronous_hv14 Aug 2026
OfftakeLoad (any)Available12.245138 MWConditionalNow (snapshot)14 Aug 2026
OfftakeLoad (any)Available10.279547 MWFirmNow (snapshot)14 Aug 2026
BidirectionalBatteryAvailable12.245138 MWConditionalNow (snapshot)14 Aug 2026

SP Electricity North West, Heatmap Tool (CC BY 4.0) (last updated 2026-08-14)

What each value means

Methodology, both clocks, provenance and rights

Injection · Generation (any) · Available

26.30385 MW

Granted

The operator's latest published dataset reports 26.303850097 MW under methodology gb_enwl_heatmap_tool_2026.

Firmness
Conditional
Horizon
Now (snapshot) · variant: inverter_based
Methodology
gb_enwl_heatmap_tool_2026ENWL Heatmap Tool: primary and BSP headroombasis operator calculated · network state unknown · comparability class gb_enwl_heatmapNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
14 Aug 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-10-02 08:21 UTC
Source health
Healthy
Provenance
gb_enwl_heatmap_toolrecord primary:HUTTON END · payload sha256 46968c486fcc…Operator’s publication (opens the operator’s site)
Licence
CC BY 4.0Attribution: SP Electricity North West, Heatmap Tool (CC BY 4.0) (last updated 2026-08-14)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
Generation Headroom N-0 -(MW) / Inverter Based

Injection · Generation (any) · Available

22.887045 MW

Granted

The operator's latest published dataset reports 22.887044534 MW under methodology gb_enwl_heatmap_tool_2026.

Firmness
Conditional
Horizon
Now (snapshot) · variant: synchronous_lv
Methodology
gb_enwl_heatmap_tool_2026ENWL Heatmap Tool: primary and BSP headroombasis operator calculated · network state unknown · comparability class gb_enwl_heatmapNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
14 Aug 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-10-02 08:21 UTC
Source health
Healthy
Provenance
gb_enwl_heatmap_toolrecord primary:HUTTON END · payload sha256 46968c486fcc…Operator’s publication (opens the operator’s site)
Licence
CC BY 4.0Attribution: SP Electricity North West, Heatmap Tool (CC BY 4.0) (last updated 2026-08-14)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
Generation Headroom N-0 -(MW) / Synchronous - LV

Injection · Generation (any) · Available

16.44937 MW

Granted

The operator's latest published dataset reports 16.449369544 MW under methodology gb_enwl_heatmap_tool_2026.

Firmness
Conditional
Horizon
Now (snapshot) · variant: synchronous_hv
Methodology
gb_enwl_heatmap_tool_2026ENWL Heatmap Tool: primary and BSP headroombasis operator calculated · network state unknown · comparability class gb_enwl_heatmapNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
14 Aug 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-10-02 08:21 UTC
Source health
Healthy
Provenance
gb_enwl_heatmap_toolrecord primary:HUTTON END · payload sha256 46968c486fcc…Operator’s publication (opens the operator’s site)
Licence
CC BY 4.0Attribution: SP Electricity North West, Heatmap Tool (CC BY 4.0) (last updated 2026-08-14)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
Generation Headroom N-0 -(MW) / Synchronous - HV

Offtake · Load (any) · Available

12.245138 MW

Granted

The operator's latest published dataset reports 12.245137568 MW under methodology gb_enwl_heatmap_tool_2026.

Firmness
Conditional
Horizon
Now (snapshot)
Methodology
gb_enwl_heatmap_tool_2026ENWL Heatmap Tool: primary and BSP headroombasis operator calculated · network state unknown · comparability class gb_enwl_heatmapNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
14 Aug 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-10-02 08:21 UTC
Source health
Healthy
Provenance
gb_enwl_heatmap_toolrecord primary:HUTTON END · payload sha256 46968c486fcc…Operator’s publication (opens the operator’s site)
Licence
CC BY 4.0Attribution: SP Electricity North West, Heatmap Tool (CC BY 4.0) (last updated 2026-08-14)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
Demand Headroom (MW) / N-0

Offtake · Load (any) · Available

10.279547 MW

Granted

The operator's latest published dataset reports 10.279546702 MW under methodology gb_enwl_heatmap_tool_2026.

Firmness
Firm
Horizon
Now (snapshot)
Methodology
gb_enwl_heatmap_tool_2026ENWL Heatmap Tool: primary and BSP headroombasis operator calculated · network state unknown · comparability class gb_enwl_heatmapNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
14 Aug 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-10-02 08:21 UTC
Source health
Healthy
Provenance
gb_enwl_heatmap_toolrecord primary:HUTTON END · payload sha256 46968c486fcc…Operator’s publication (opens the operator’s site)
Licence
CC BY 4.0Attribution: SP Electricity North West, Heatmap Tool (CC BY 4.0) (last updated 2026-08-14)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
Demand Headroom (MW) / Firm

Bidirectional · Battery · Available

12.245138 MW

Granted

The operator's latest published dataset reports 12.245137568 MW under methodology gb_enwl_heatmap_tool_2026.

Firmness
Conditional
Horizon
Now (snapshot)
Methodology
gb_enwl_heatmap_tool_2026ENWL Heatmap Tool: primary and BSP headroombasis operator calculated · network state unknown · comparability class gb_enwl_heatmapNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
14 Aug 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-10-02 08:21 UTC
Source health
Healthy
Provenance
gb_enwl_heatmap_toolrecord primary:HUTTON END · payload sha256 46968c486fcc…Operator’s publication (opens the operator’s site)
Licence
CC BY 4.0Attribution: SP Electricity North West, Heatmap Tool (CC BY 4.0) (last updated 2026-08-14)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
Battery Storage Headroom N-0 -(MW)

History

Served series only

Offtake · Load (any) · Available

current 10.279547 MW

26 Sep 2026: 10.279547 MW
26 Sep 2026range 10.279547 to 10.279547 MW2 Oct 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current10.279547 MW

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Load (any) · Available

current 12.245138 MW

26 Sep 2026: 12.245138 MW
26 Sep 2026range 12.245138 to 12.245138 MW2 Oct 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current12.245138 MW

Time axis: when we observed each value, not the operator’s effective date.

Injection · Generation (any) · Available

current 26.30385 MW

26 Sep 2026: 26.30385 MW
26 Sep 2026range 26.30385 to 26.30385 MW2 Oct 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current26.30385 MW

Time axis: when we observed each value, not the operator’s effective date.

Injection · Generation (any) · Available

current 22.887045 MW

26 Sep 2026: 22.887045 MW
26 Sep 2026range 22.887045 to 22.887045 MW2 Oct 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current22.887045 MW

Time axis: when we observed each value, not the operator’s effective date.

Injection · Generation (any) · Available

current 16.44937 MW

26 Sep 2026: 16.44937 MW
26 Sep 2026range 16.44937 to 16.44937 MW2 Oct 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current16.44937 MW

Time axis: when we observed each value, not the operator’s effective date.

Bidirectional · Battery · Available

current 12.245138 MW

26 Sep 2026: 12.245138 MW
26 Sep 2026range 12.245138 to 12.245138 MW2 Oct 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current12.245138 MW

Time axis: when we observed each value, not the operator’s effective date.

Through the API

curl "https://api.gridcapacityapi.com/v1/substations/sub_06gdq6jnj9v4fbz7j7ypp7m1ag/capacity" \  -H "Authorization: Bearer gc_live_..."