Substation / 6.6 kV / primary

GREENHILL

SP Electricity North West / United Kingdom

Latest published values

6 served · 0 withheld

Each row is what the operator’s latest published dataset reports for one combination of direction, technology, measure, firmness and horizon. Hosting-capacity figures are indicative and reflect what operators publish. They are not a connection offer; only the operator can confirm capacity for a specific request.

Latest published capacity values, one row per series
DirectionTechnologyMeasureValueFirmnessHorizonSource date
InjectionGeneration (any)Available61.848828 MWConditionalNow (snapshot)variant: inverter_based14 Aug 2026
InjectionGeneration (any)Available10.158835 MWConditionalNow (snapshot)variant: synchronous_lv14 Aug 2026
InjectionGeneration (any)Available7.412165 MWConditionalNow (snapshot)variant: synchronous_hv14 Aug 2026
OfftakeLoad (any)Available11.585927 MWConditionalNow (snapshot)14 Aug 2026
OfftakeLoad (any)Available11.585927 MWFirmNow (snapshot)14 Aug 2026
BidirectionalBatteryAvailable11.585927 MWConditionalNow (snapshot)14 Aug 2026

SP Electricity North West, Heatmap Tool (CC BY 4.0) (last updated 2026-08-14)

What each value means

Methodology, both clocks, provenance and rights

Injection · Generation (any) · Available

61.848828 MW

Granted

The operator's latest published dataset reports 61.848827678 MW under methodology gb_enwl_heatmap_tool_2026.

Firmness
Conditional
Horizon
Now (snapshot) · variant: inverter_based
Methodology
gb_enwl_heatmap_tool_2026ENWL Heatmap Tool: primary and BSP headroombasis operator calculated · network state unknown · comparability class gb_enwl_heatmapNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
14 Aug 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-10-02 08:21 UTC
Source health
Healthy
Provenance
gb_enwl_heatmap_toolrecord primary:GREENHILL · payload sha256 0dace4a0be79…Operator’s publication (opens the operator’s site)
Licence
CC BY 4.0Attribution: SP Electricity North West, Heatmap Tool (CC BY 4.0) (last updated 2026-08-14)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
Generation Headroom N-0 -(MW) / Inverter Based

Injection · Generation (any) · Available

10.158835 MW

Granted

The operator's latest published dataset reports 10.158835261 MW under methodology gb_enwl_heatmap_tool_2026.

Firmness
Conditional
Horizon
Now (snapshot) · variant: synchronous_lv
Methodology
gb_enwl_heatmap_tool_2026ENWL Heatmap Tool: primary and BSP headroombasis operator calculated · network state unknown · comparability class gb_enwl_heatmapNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
14 Aug 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-10-02 08:21 UTC
Source health
Healthy
Provenance
gb_enwl_heatmap_toolrecord primary:GREENHILL · payload sha256 0dace4a0be79…Operator’s publication (opens the operator’s site)
Licence
CC BY 4.0Attribution: SP Electricity North West, Heatmap Tool (CC BY 4.0) (last updated 2026-08-14)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
Generation Headroom N-0 -(MW) / Synchronous - LV

Injection · Generation (any) · Available

7.412165 MW

Granted

The operator's latest published dataset reports 7.412165308 MW under methodology gb_enwl_heatmap_tool_2026.

Firmness
Conditional
Horizon
Now (snapshot) · variant: synchronous_hv
Methodology
gb_enwl_heatmap_tool_2026ENWL Heatmap Tool: primary and BSP headroombasis operator calculated · network state unknown · comparability class gb_enwl_heatmapNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
14 Aug 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-10-02 08:21 UTC
Source health
Healthy
Provenance
gb_enwl_heatmap_toolrecord primary:GREENHILL · payload sha256 0dace4a0be79…Operator’s publication (opens the operator’s site)
Licence
CC BY 4.0Attribution: SP Electricity North West, Heatmap Tool (CC BY 4.0) (last updated 2026-08-14)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
Generation Headroom N-0 -(MW) / Synchronous - HV

Offtake · Load (any) · Available

11.585927 MW

Granted

The operator's latest published dataset reports 11.585927114 MW under methodology gb_enwl_heatmap_tool_2026.

Firmness
Conditional
Horizon
Now (snapshot)
Methodology
gb_enwl_heatmap_tool_2026ENWL Heatmap Tool: primary and BSP headroombasis operator calculated · network state unknown · comparability class gb_enwl_heatmapNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
14 Aug 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-10-02 08:21 UTC
Source health
Healthy
Provenance
gb_enwl_heatmap_toolrecord primary:GREENHILL · payload sha256 0dace4a0be79…Operator’s publication (opens the operator’s site)
Licence
CC BY 4.0Attribution: SP Electricity North West, Heatmap Tool (CC BY 4.0) (last updated 2026-08-14)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
Demand Headroom (MW) / N-0

Offtake · Load (any) · Available

11.585927 MW

Granted

The operator's latest published dataset reports 11.585927114 MW under methodology gb_enwl_heatmap_tool_2026.

Firmness
Firm
Horizon
Now (snapshot)
Methodology
gb_enwl_heatmap_tool_2026ENWL Heatmap Tool: primary and BSP headroombasis operator calculated · network state unknown · comparability class gb_enwl_heatmapNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
14 Aug 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-10-02 08:21 UTC
Source health
Healthy
Provenance
gb_enwl_heatmap_toolrecord primary:GREENHILL · payload sha256 0dace4a0be79…Operator’s publication (opens the operator’s site)
Licence
CC BY 4.0Attribution: SP Electricity North West, Heatmap Tool (CC BY 4.0) (last updated 2026-08-14)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
Demand Headroom (MW) / Firm

Bidirectional · Battery · Available

11.585927 MW

Granted

The operator's latest published dataset reports 11.585927114 MW under methodology gb_enwl_heatmap_tool_2026.

Firmness
Conditional
Horizon
Now (snapshot)
Methodology
gb_enwl_heatmap_tool_2026ENWL Heatmap Tool: primary and BSP headroombasis operator calculated · network state unknown · comparability class gb_enwl_heatmapNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
14 Aug 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-10-02 08:21 UTC
Source health
Healthy
Provenance
gb_enwl_heatmap_toolrecord primary:GREENHILL · payload sha256 0dace4a0be79…Operator’s publication (opens the operator’s site)
Licence
CC BY 4.0Attribution: SP Electricity North West, Heatmap Tool (CC BY 4.0) (last updated 2026-08-14)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
Battery Storage Headroom N-0 -(MW)

History

Served series only

Offtake · Load (any) · Available

current 11.585927 MW

26 Sep 2026: 11.585927 MW
26 Sep 2026range 11.585927 to 11.585927 MW2 Oct 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current11.585927 MW

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Load (any) · Available

current 11.585927 MW

26 Sep 2026: 11.585927 MW
26 Sep 2026range 11.585927 to 11.585927 MW2 Oct 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current11.585927 MW

Time axis: when we observed each value, not the operator’s effective date.

Injection · Generation (any) · Available

current 61.848828 MW

26 Sep 2026: 61.848828 MW
26 Sep 2026range 61.848828 to 61.848828 MW2 Oct 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current61.848828 MW

Time axis: when we observed each value, not the operator’s effective date.

Injection · Generation (any) · Available

current 10.158835 MW

26 Sep 2026: 10.158835 MW
26 Sep 2026range 10.158835 to 10.158835 MW2 Oct 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current10.158835 MW

Time axis: when we observed each value, not the operator’s effective date.

Injection · Generation (any) · Available

current 7.412165 MW

26 Sep 2026: 7.412165 MW
26 Sep 2026range 7.412165 to 7.412165 MW2 Oct 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current7.412165 MW

Time axis: when we observed each value, not the operator’s effective date.

Bidirectional · Battery · Available

current 11.585927 MW

26 Sep 2026: 11.585927 MW
26 Sep 2026range 11.585927 to 11.585927 MW2 Oct 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current11.585927 MW

Time axis: when we observed each value, not the operator’s effective date.

Through the API

curl "https://api.gridcapacityapi.com/v1/substations/sub_06gdq6jnj9v4fbz7j7dh1whz38/capacity" \  -H "Authorization: Bearer gc_live_..."