Substation / 6.6 kV / primary

GREEN ST T12 & T13

SP Electricity North West / United Kingdom

Latest published values

6 served · 0 withheld

Each row is what the operator’s latest published dataset reports for one combination of direction, technology, measure, firmness and horizon. Hosting-capacity figures are indicative and reflect what operators publish. They are not a connection offer; only the operator can confirm capacity for a specific request.

Latest published capacity values, one row per series
DirectionTechnologyMeasureValueFirmnessHorizonSource date
InjectionGeneration (any)Available31.27978 MWConditionalNow (snapshot)variant: inverter_based14 Aug 2026
InjectionGeneration (any)Available9.193618 MWConditionalNow (snapshot)variant: synchronous_lv14 Aug 2026
InjectionGeneration (any)Available6.707916 MWConditionalNow (snapshot)variant: synchronous_hv14 Aug 2026
OfftakeLoad (any)Available7.71995 MWConditionalNow (snapshot)14 Aug 2026
OfftakeLoad (any)Available0 MWFirmNow (snapshot)14 Aug 2026
BidirectionalBatteryAvailable7.71995 MWConditionalNow (snapshot)14 Aug 2026

SP Electricity North West, Heatmap Tool (CC BY 4.0) (last updated 2026-08-14)

What each value means

Methodology, both clocks, provenance and rights

Injection · Generation (any) · Available

31.27978 MW

Granted

The operator's latest published dataset reports 31.279780346 MW under methodology gb_enwl_heatmap_tool_2026.

Firmness
Conditional
Horizon
Now (snapshot) · variant: inverter_based
Methodology
gb_enwl_heatmap_tool_2026ENWL Heatmap Tool: primary and BSP headroombasis operator calculated · network state unknown · comparability class gb_enwl_heatmapNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
14 Aug 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-10-02 08:21 UTC
Source health
Healthy
Provenance
gb_enwl_heatmap_toolrecord primary:GREEN ST T12 & T13 · payload sha256 0121d69efe4e…Operator’s publication (opens the operator’s site)
Licence
CC BY 4.0Attribution: SP Electricity North West, Heatmap Tool (CC BY 4.0) (last updated 2026-08-14)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
Generation Headroom N-0 -(MW) / Inverter Based

Injection · Generation (any) · Available

9.193618 MW

Granted

The operator's latest published dataset reports 9.19361787 MW under methodology gb_enwl_heatmap_tool_2026.

Firmness
Conditional
Horizon
Now (snapshot) · variant: synchronous_lv
Methodology
gb_enwl_heatmap_tool_2026ENWL Heatmap Tool: primary and BSP headroombasis operator calculated · network state unknown · comparability class gb_enwl_heatmapNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
14 Aug 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-10-02 08:21 UTC
Source health
Healthy
Provenance
gb_enwl_heatmap_toolrecord primary:GREEN ST T12 & T13 · payload sha256 0121d69efe4e…Operator’s publication (opens the operator’s site)
Licence
CC BY 4.0Attribution: SP Electricity North West, Heatmap Tool (CC BY 4.0) (last updated 2026-08-14)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
Generation Headroom N-0 -(MW) / Synchronous - LV

Injection · Generation (any) · Available

6.707916 MW

Granted

The operator's latest published dataset reports 6.707916182 MW under methodology gb_enwl_heatmap_tool_2026.

Firmness
Conditional
Horizon
Now (snapshot) · variant: synchronous_hv
Methodology
gb_enwl_heatmap_tool_2026ENWL Heatmap Tool: primary and BSP headroombasis operator calculated · network state unknown · comparability class gb_enwl_heatmapNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
14 Aug 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-10-02 08:21 UTC
Source health
Healthy
Provenance
gb_enwl_heatmap_toolrecord primary:GREEN ST T12 & T13 · payload sha256 0121d69efe4e…Operator’s publication (opens the operator’s site)
Licence
CC BY 4.0Attribution: SP Electricity North West, Heatmap Tool (CC BY 4.0) (last updated 2026-08-14)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
Generation Headroom N-0 -(MW) / Synchronous - HV

Offtake · Load (any) · Available

7.71995 MW

Granted

The operator's latest published dataset reports 7.719950207 MW under methodology gb_enwl_heatmap_tool_2026.

Firmness
Conditional
Horizon
Now (snapshot)
Methodology
gb_enwl_heatmap_tool_2026ENWL Heatmap Tool: primary and BSP headroombasis operator calculated · network state unknown · comparability class gb_enwl_heatmapNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
14 Aug 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-10-02 08:21 UTC
Source health
Healthy
Provenance
gb_enwl_heatmap_toolrecord primary:GREEN ST T12 & T13 · payload sha256 0121d69efe4e…Operator’s publication (opens the operator’s site)
Licence
CC BY 4.0Attribution: SP Electricity North West, Heatmap Tool (CC BY 4.0) (last updated 2026-08-14)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
Demand Headroom (MW) / N-0

Offtake · Load (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology gb_enwl_heatmap_tool_2026.

Firmness
Firm
Horizon
Now (snapshot)
Methodology
gb_enwl_heatmap_tool_2026ENWL Heatmap Tool: primary and BSP headroombasis operator calculated · network state unknown · comparability class gb_enwl_heatmapNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
14 Aug 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-10-02 08:21 UTC
Source health
Healthy
Provenance
gb_enwl_heatmap_toolrecord primary:GREEN ST T12 & T13 · payload sha256 0121d69efe4e…Operator’s publication (opens the operator’s site)
Licence
CC BY 4.0Attribution: SP Electricity North West, Heatmap Tool (CC BY 4.0) (last updated 2026-08-14)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
Demand Headroom (MW) / Firm

Bidirectional · Battery · Available

7.71995 MW

Granted

The operator's latest published dataset reports 7.719950207 MW under methodology gb_enwl_heatmap_tool_2026.

Firmness
Conditional
Horizon
Now (snapshot)
Methodology
gb_enwl_heatmap_tool_2026ENWL Heatmap Tool: primary and BSP headroombasis operator calculated · network state unknown · comparability class gb_enwl_heatmapNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
14 Aug 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-10-02 08:21 UTC
Source health
Healthy
Provenance
gb_enwl_heatmap_toolrecord primary:GREEN ST T12 & T13 · payload sha256 0121d69efe4e…Operator’s publication (opens the operator’s site)
Licence
CC BY 4.0Attribution: SP Electricity North West, Heatmap Tool (CC BY 4.0) (last updated 2026-08-14)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
Battery Storage Headroom N-0 -(MW)

History

Served series only

Offtake · Load (any) · Available

current 0 MW

26 Sep 2026: 0 MW
26 Sep 2026range 0 to 0 MW2 Oct 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current0 MW

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Load (any) · Available

current 7.71995 MW

26 Sep 2026: 7.71995 MW
26 Sep 2026range 7.71995 to 7.71995 MW2 Oct 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current7.71995 MW

Time axis: when we observed each value, not the operator’s effective date.

Injection · Generation (any) · Available

current 31.27978 MW

26 Sep 2026: 31.27978 MW
26 Sep 2026range 31.27978 to 31.27978 MW2 Oct 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current31.27978 MW

Time axis: when we observed each value, not the operator’s effective date.

Injection · Generation (any) · Available

current 9.193618 MW

26 Sep 2026: 9.193618 MW
26 Sep 2026range 9.193618 to 9.193618 MW2 Oct 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current9.193618 MW

Time axis: when we observed each value, not the operator’s effective date.

Injection · Generation (any) · Available

current 6.707916 MW

26 Sep 2026: 6.707916 MW
26 Sep 2026range 6.707916 to 6.707916 MW2 Oct 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current6.707916 MW

Time axis: when we observed each value, not the operator’s effective date.

Bidirectional · Battery · Available

current 7.71995 MW

26 Sep 2026: 7.71995 MW
26 Sep 2026range 7.71995 to 7.71995 MW2 Oct 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current7.71995 MW

Time axis: when we observed each value, not the operator’s effective date.

Through the API

curl "https://api.gridcapacityapi.com/v1/substations/sub_06gdq6jnj9v4fbz7j7chbzhy0m/capacity" \  -H "Authorization: Bearer gc_live_..."
GREEN ST T12 & T13 6.6 kV substation: grid capacity (SP Electricity North West) · GridCapacity API