FALLOWFIELD

SP Electricity North West / United Kingdom

Latest published values

6 served · 0 withheld

Each row is what the operator’s latest published dataset reports for one combination of direction, technology, measure, firmness and horizon. Hosting-capacity figures are indicative and reflect what operators publish. They are not a connection offer; only the operator can confirm capacity for a specific request.

Latest published capacity values, one row per series
DirectionTechnologyMeasureValueFirmnessHorizonSource date
InjectionGeneration (any)Available11.052 MWConditionalNow (snapshot)variant: inverter_based14 Aug 2026
InjectionGeneration (any)Available1.957494 MWConditionalNow (snapshot)variant: synchronous_lv14 Aug 2026
InjectionGeneration (any)Available1.434426 MWConditionalNow (snapshot)variant: synchronous_hv14 Aug 2026
OfftakeLoad (any)Available6.069476 MWConditionalNow (snapshot)14 Aug 2026
OfftakeLoad (any)Available1.432476 MWFirmNow (snapshot)14 Aug 2026
BidirectionalBatteryAvailable6.069476 MWConditionalNow (snapshot)14 Aug 2026

SP Electricity North West, Heatmap Tool (CC BY 4.0) (last updated 2026-08-14)

What each value means

Methodology, both clocks, provenance and rights

Injection · Generation (any) · Available

11.052 MW

Granted

The operator's latest published dataset reports 11.052 MW under methodology gb_enwl_heatmap_tool_2026.

Firmness
Conditional
Horizon
Now (snapshot) · variant: inverter_based
Methodology
gb_enwl_heatmap_tool_2026ENWL Heatmap Tool: primary and BSP headroombasis operator calculated · network state unknown · comparability class gb_enwl_heatmapNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
14 Aug 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-10-02 08:21 UTC
Source health
Healthy
Provenance
gb_enwl_heatmap_toolrecord primary:FALLOWFIELD · payload sha256 1b1d85cd8197…Operator’s publication (opens the operator’s site)
Licence
CC BY 4.0Attribution: SP Electricity North West, Heatmap Tool (CC BY 4.0) (last updated 2026-08-14)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
Generation Headroom N-0 -(MW) / Inverter Based

Injection · Generation (any) · Available

1.957494 MW

Granted

The operator's latest published dataset reports 1.957494407 MW under methodology gb_enwl_heatmap_tool_2026.

Firmness
Conditional
Horizon
Now (snapshot) · variant: synchronous_lv
Methodology
gb_enwl_heatmap_tool_2026ENWL Heatmap Tool: primary and BSP headroombasis operator calculated · network state unknown · comparability class gb_enwl_heatmapNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
14 Aug 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-10-02 08:21 UTC
Source health
Healthy
Provenance
gb_enwl_heatmap_toolrecord primary:FALLOWFIELD · payload sha256 1b1d85cd8197…Operator’s publication (opens the operator’s site)
Licence
CC BY 4.0Attribution: SP Electricity North West, Heatmap Tool (CC BY 4.0) (last updated 2026-08-14)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
Generation Headroom N-0 -(MW) / Synchronous - LV

Injection · Generation (any) · Available

1.434426 MW

Granted

The operator's latest published dataset reports 1.43442623 MW under methodology gb_enwl_heatmap_tool_2026.

Firmness
Conditional
Horizon
Now (snapshot) · variant: synchronous_hv
Methodology
gb_enwl_heatmap_tool_2026ENWL Heatmap Tool: primary and BSP headroombasis operator calculated · network state unknown · comparability class gb_enwl_heatmapNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
14 Aug 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-10-02 08:21 UTC
Source health
Healthy
Provenance
gb_enwl_heatmap_toolrecord primary:FALLOWFIELD · payload sha256 1b1d85cd8197…Operator’s publication (opens the operator’s site)
Licence
CC BY 4.0Attribution: SP Electricity North West, Heatmap Tool (CC BY 4.0) (last updated 2026-08-14)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
Generation Headroom N-0 -(MW) / Synchronous - HV

Offtake · Load (any) · Available

6.069476 MW

Granted

The operator's latest published dataset reports 6.069476165 MW under methodology gb_enwl_heatmap_tool_2026.

Firmness
Conditional
Horizon
Now (snapshot)
Methodology
gb_enwl_heatmap_tool_2026ENWL Heatmap Tool: primary and BSP headroombasis operator calculated · network state unknown · comparability class gb_enwl_heatmapNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
14 Aug 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-10-02 08:21 UTC
Source health
Healthy
Provenance
gb_enwl_heatmap_toolrecord primary:FALLOWFIELD · payload sha256 1b1d85cd8197…Operator’s publication (opens the operator’s site)
Licence
CC BY 4.0Attribution: SP Electricity North West, Heatmap Tool (CC BY 4.0) (last updated 2026-08-14)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
Demand Headroom (MW) / N-0

Offtake · Load (any) · Available

1.432476 MW

Granted

The operator's latest published dataset reports 1.432476165 MW under methodology gb_enwl_heatmap_tool_2026.

Firmness
Firm
Horizon
Now (snapshot)
Methodology
gb_enwl_heatmap_tool_2026ENWL Heatmap Tool: primary and BSP headroombasis operator calculated · network state unknown · comparability class gb_enwl_heatmapNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
14 Aug 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-10-02 08:21 UTC
Source health
Healthy
Provenance
gb_enwl_heatmap_toolrecord primary:FALLOWFIELD · payload sha256 1b1d85cd8197…Operator’s publication (opens the operator’s site)
Licence
CC BY 4.0Attribution: SP Electricity North West, Heatmap Tool (CC BY 4.0) (last updated 2026-08-14)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
Demand Headroom (MW) / Firm

Bidirectional · Battery · Available

6.069476 MW

Granted

The operator's latest published dataset reports 6.069476165 MW under methodology gb_enwl_heatmap_tool_2026.

Firmness
Conditional
Horizon
Now (snapshot)
Methodology
gb_enwl_heatmap_tool_2026ENWL Heatmap Tool: primary and BSP headroombasis operator calculated · network state unknown · comparability class gb_enwl_heatmapNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
14 Aug 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-10-02 08:21 UTC
Source health
Healthy
Provenance
gb_enwl_heatmap_toolrecord primary:FALLOWFIELD · payload sha256 1b1d85cd8197…Operator’s publication (opens the operator’s site)
Licence
CC BY 4.0Attribution: SP Electricity North West, Heatmap Tool (CC BY 4.0) (last updated 2026-08-14)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
Battery Storage Headroom N-0 -(MW)

History

Served series only

Offtake · Load (any) · Available

current 1.432476 MW

26 Sep 2026: 1.432476 MW
26 Sep 2026range 1.432476 to 1.432476 MW2 Oct 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current1.432476 MW

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Load (any) · Available

current 6.069476 MW

26 Sep 2026: 6.069476 MW
26 Sep 2026range 6.069476 to 6.069476 MW2 Oct 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current6.069476 MW

Time axis: when we observed each value, not the operator’s effective date.

Injection · Generation (any) · Available

current 11.052 MW

26 Sep 2026: 11.052 MW
26 Sep 2026range 11.052 to 11.052 MW2 Oct 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current11.052 MW

Time axis: when we observed each value, not the operator’s effective date.

Injection · Generation (any) · Available

current 1.957494 MW

26 Sep 2026: 1.957494 MW
26 Sep 2026range 1.957494 to 1.957494 MW2 Oct 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current1.957494 MW

Time axis: when we observed each value, not the operator’s effective date.

Injection · Generation (any) · Available

current 1.434426 MW

26 Sep 2026: 1.434426 MW
26 Sep 2026range 1.434426 to 1.434426 MW2 Oct 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current1.434426 MW

Time axis: when we observed each value, not the operator’s effective date.

Bidirectional · Battery · Available

current 6.069476 MW

26 Sep 2026: 6.069476 MW
26 Sep 2026range 6.069476 to 6.069476 MW2 Oct 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current6.069476 MW

Time axis: when we observed each value, not the operator’s effective date.

Through the API

curl "https://api.gridcapacityapi.com/v1/substations/sub_06gdq6jnj9v4fbz7j71ya9vjpc/capacity" \  -H "Authorization: Bearer gc_live_..."