Skip to content

Substation / 6.6 kV / primary

CASTLETON

SP Electricity North West / United Kingdom

Latest published values

6 served · 0 withheld

Each row is what the operator’s latest published dataset reports for one combination of direction, technology, measure, firmness and horizon. Hosting-capacity figures are indicative and reflect what operators publish. They are not a connection offer; only the operator can confirm capacity for a specific request.

Latest published capacity values, one row per series
DirectionTechnologyMeasureValueFirmnessHorizonSource date
InjectionGeneration (any)Available20.696508 MWConditionalNow (snapshot)variant: inverter_based14 Aug 2026
InjectionGeneration (any)Available3.356681 MWConditionalNow (snapshot)variant: synchronous_lv14 Aug 2026
InjectionGeneration (any)Available2.449127 MWConditionalNow (snapshot)variant: synchronous_hv14 Aug 2026
OfftakeLoad (any)Available10.982655 MWConditionalNow (snapshot)14 Aug 2026
OfftakeLoad (any)Available6.345655 MWFirmNow (snapshot)14 Aug 2026
BidirectionalBatteryAvailable10.982655 MWConditionalNow (snapshot)14 Aug 2026

SP Electricity North West, Heatmap Tool (CC BY 4.0) (last updated 2026-08-14)

What each value means

Methodology, both clocks, provenance and rights

Injection · Generation (any) · Available

20.696508 MW

Granted

The operator's latest published dataset reports 20.696507624 MW under methodology gb_enwl_heatmap_tool_2026.

Firmness
Conditional
Horizon
Now (snapshot) · variant: inverter_based
Methodology
gb_enwl_heatmap_tool_2026ENWL Heatmap Tool: primary and BSP headroombasis operator calculated · network state unknown · comparability class gb_enwl_heatmapNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
14 Aug 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-10-02 08:21 UTC
Source health
Healthy
Provenance
gb_enwl_heatmap_toolrecord primary:CASTLETON · payload sha256 dc4811254f38…Operator’s publication (opens the operator’s site)
Licence
CC BY 4.0Attribution: SP Electricity North West, Heatmap Tool (CC BY 4.0) (last updated 2026-08-14)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
Generation Headroom N-0 -(MW) / Inverter Based

Injection · Generation (any) · Available

3.356681 MW

Granted

The operator's latest published dataset reports 3.356681292 MW under methodology gb_enwl_heatmap_tool_2026.

Firmness
Conditional
Horizon
Now (snapshot) · variant: synchronous_lv
Methodology
gb_enwl_heatmap_tool_2026ENWL Heatmap Tool: primary and BSP headroombasis operator calculated · network state unknown · comparability class gb_enwl_heatmapNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
14 Aug 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-10-02 08:21 UTC
Source health
Healthy
Provenance
gb_enwl_heatmap_toolrecord primary:CASTLETON · payload sha256 dc4811254f38…Operator’s publication (opens the operator’s site)
Licence
CC BY 4.0Attribution: SP Electricity North West, Heatmap Tool (CC BY 4.0) (last updated 2026-08-14)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
Generation Headroom N-0 -(MW) / Synchronous - LV

Injection · Generation (any) · Available

2.449127 MW

Granted

The operator's latest published dataset reports 2.449126892 MW under methodology gb_enwl_heatmap_tool_2026.

Firmness
Conditional
Horizon
Now (snapshot) · variant: synchronous_hv
Methodology
gb_enwl_heatmap_tool_2026ENWL Heatmap Tool: primary and BSP headroombasis operator calculated · network state unknown · comparability class gb_enwl_heatmapNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
14 Aug 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-10-02 08:21 UTC
Source health
Healthy
Provenance
gb_enwl_heatmap_toolrecord primary:CASTLETON · payload sha256 dc4811254f38…Operator’s publication (opens the operator’s site)
Licence
CC BY 4.0Attribution: SP Electricity North West, Heatmap Tool (CC BY 4.0) (last updated 2026-08-14)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
Generation Headroom N-0 -(MW) / Synchronous - HV

Offtake · Load (any) · Available

10.982655 MW

Granted

The operator's latest published dataset reports 10.982655192 MW under methodology gb_enwl_heatmap_tool_2026.

Firmness
Conditional
Horizon
Now (snapshot)
Methodology
gb_enwl_heatmap_tool_2026ENWL Heatmap Tool: primary and BSP headroombasis operator calculated · network state unknown · comparability class gb_enwl_heatmapNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
14 Aug 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-10-02 08:21 UTC
Source health
Healthy
Provenance
gb_enwl_heatmap_toolrecord primary:CASTLETON · payload sha256 dc4811254f38…Operator’s publication (opens the operator’s site)
Licence
CC BY 4.0Attribution: SP Electricity North West, Heatmap Tool (CC BY 4.0) (last updated 2026-08-14)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
Demand Headroom (MW) / N-0

Offtake · Load (any) · Available

6.345655 MW

Granted

The operator's latest published dataset reports 6.345655192 MW under methodology gb_enwl_heatmap_tool_2026.

Firmness
Firm
Horizon
Now (snapshot)
Methodology
gb_enwl_heatmap_tool_2026ENWL Heatmap Tool: primary and BSP headroombasis operator calculated · network state unknown · comparability class gb_enwl_heatmapNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
14 Aug 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-10-02 08:21 UTC
Source health
Healthy
Provenance
gb_enwl_heatmap_toolrecord primary:CASTLETON · payload sha256 dc4811254f38…Operator’s publication (opens the operator’s site)
Licence
CC BY 4.0Attribution: SP Electricity North West, Heatmap Tool (CC BY 4.0) (last updated 2026-08-14)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
Demand Headroom (MW) / Firm

Bidirectional · Battery · Available

10.982655 MW

Granted

The operator's latest published dataset reports 10.982655192 MW under methodology gb_enwl_heatmap_tool_2026.

Firmness
Conditional
Horizon
Now (snapshot)
Methodology
gb_enwl_heatmap_tool_2026ENWL Heatmap Tool: primary and BSP headroombasis operator calculated · network state unknown · comparability class gb_enwl_heatmapNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
14 Aug 2026
Retrieved / confirmed
2026-09-26 02:45 UTClast confirmed unchanged 2026-10-02 08:21 UTC
Source health
Healthy
Provenance
gb_enwl_heatmap_toolrecord primary:CASTLETON · payload sha256 dc4811254f38…Operator’s publication (opens the operator’s site)
Licence
CC BY 4.0Attribution: SP Electricity North West, Heatmap Tool (CC BY 4.0) (last updated 2026-08-14)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
Battery Storage Headroom N-0 -(MW)

History

Served series only

Offtake · Load (any) · Available

current 6.345655 MW

26 Sep 2026: 6.345655 MW
26 Sep 2026range 6.345655 to 6.345655 MW2 Oct 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current6.345655 MW

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Load (any) · Available

current 10.982655 MW

26 Sep 2026: 10.982655 MW
26 Sep 2026range 10.982655 to 10.982655 MW2 Oct 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current10.982655 MW

Time axis: when we observed each value, not the operator’s effective date.

Injection · Generation (any) · Available

current 20.696508 MW

26 Sep 2026: 20.696508 MW
26 Sep 2026range 20.696508 to 20.696508 MW2 Oct 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current20.696508 MW

Time axis: when we observed each value, not the operator’s effective date.

Injection · Generation (any) · Available

current 3.356681 MW

26 Sep 2026: 3.356681 MW
26 Sep 2026range 3.356681 to 3.356681 MW2 Oct 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current3.356681 MW

Time axis: when we observed each value, not the operator’s effective date.

Injection · Generation (any) · Available

current 2.449127 MW

26 Sep 2026: 2.449127 MW
26 Sep 2026range 2.449127 to 2.449127 MW2 Oct 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current2.449127 MW

Time axis: when we observed each value, not the operator’s effective date.

Bidirectional · Battery · Available

current 10.982655 MW

26 Sep 2026: 10.982655 MW
26 Sep 2026range 10.982655 to 10.982655 MW2 Oct 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current10.982655 MW

Time axis: when we observed each value, not the operator’s effective date.

Through the API

curl "https://api.gridcapacityapi.com/v1/substations/sub_06gdq6jnj9v4fbz7j686jgwnq8/capacity" \  -H "Authorization: Bearer gc_live_..."
CASTLETON 6.6 kV substation: grid capacity (SP Electricity North West) · GridCapacity API