Skip to content

Busbar / 20 kV

MARZAGAN

Edistribución Redes Digitales, S.L.U. / Telde, Palmas, Las, Spain

Latest published values

3 served · 0 withheld

Each row is what the operator’s latest published dataset reports for one combination of direction, technology, measure, firmness and horizon. Hosting-capacity figures are indicative and reflect what operators publish. They are not a connection offer; only the operator can confirm capacity for a specific request.

Latest published capacity values, one row per series
DirectionTechnologyMeasureValueFirmnessHorizonSource date
OfftakeLoad (any)Allocated35.41 MWFirmNow (snapshot)11 Nov 2026
OfftakeLoad (any)Available5.37 MWFirmNow (snapshot)11 Nov 2026
OfftakeLoad (any)Requested0 MWFirmNow (snapshot)11 Nov 2026

Origen de los datos: Comisión Nacional de los Mercados y la Competencia (CNMC) (last updated 2026-11-11)

What each value means

Methodology, both clocks, provenance and rights

Offtake · Load (any) · Allocated

35.41 MW

Granted

The operator's latest published dataset reports 35.41 MW under methodology es_cnmc_dem_rdd_2026.

Firmness
Firm
Horizon
Now (snapshot)
Methodology
es_cnmc_dem_rdd_2026Firm demand access capacity at the distribution networks (each DSO's figures in CNMC's map)basis operator calculated · network state unknown · comparability class es_rdd_demand_firm_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
11 Nov 2026
Retrieved / confirmed
2026-11-11 14:22 UTClast confirmed unchanged 2026-11-22 21:06 UTC
Source health
Healthy
Provenance
es_cnmc_demand_capacityrecord rdd:R1-299:MARZAGAN:20 · payload sha256 3990c4bacb7b…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Origen de los datos: Comisión Nacional de los Mercados y la Competencia (CNMC) (last updated 2026-11-11)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
CAP_OCUPADA

Offtake · Load (any) · Available

5.37 MW

Granted

The operator's latest published dataset reports 5.37 MW under methodology es_cnmc_dem_rdd_2026.

Firmness
Firm
Horizon
Now (snapshot)
Methodology
es_cnmc_dem_rdd_2026Firm demand access capacity at the distribution networks (each DSO's figures in CNMC's map)basis operator calculated · network state unknown · comparability class es_rdd_demand_firm_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
11 Nov 2026
Retrieved / confirmed
2026-11-11 14:22 UTClast confirmed unchanged 2026-11-22 21:06 UTC
Source health
Healthy
Provenance
es_cnmc_demand_capacityrecord rdd:R1-299:MARZAGAN:20 · payload sha256 3990c4bacb7b…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Origen de los datos: Comisión Nacional de los Mercados y la Competencia (CNMC) (last updated 2026-11-11)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
CAP_DISPONIBLE

Offtake · Load (any) · Requested

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology es_cnmc_dem_rdd_2026.

Firmness
Firm
Horizon
Now (snapshot)
Methodology
es_cnmc_dem_rdd_2026Firm demand access capacity at the distribution networks (each DSO's figures in CNMC's map)basis operator calculated · network state unknown · comparability class es_rdd_demand_firm_access_cir1_2024Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
11 Nov 2026
Retrieved / confirmed
2026-11-11 14:22 UTClast confirmed unchanged 2026-11-22 21:06 UTC
Source health
Healthy
Provenance
es_cnmc_demand_capacityrecord rdd:R1-299:MARZAGAN:20 · payload sha256 3990c4bacb7b…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Origen de los datos: Comisión Nacional de los Mercados y la Competencia (CNMC) (last updated 2026-11-11)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
CAP_ADMITIDA_NO_EVALUADA

History

Served series only

Offtake · Load (any) · Available

current 5.37 MW

26 Sep 2026: 6.32 MW11 Nov 2026: 5.37 MW
26 Sep 2026range 5.37 to 6.32 MW24 Nov 2026
2 published values, as a table
Observed fromUntilValue
26 Sep 202611 Nov 20266.32 MW
11 Nov 2026current5.37 MW

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Load (any) · Allocated

current 35.41 MW

26 Sep 2026: 34.46 MW11 Nov 2026: 35.41 MW
26 Sep 2026range 34.46 to 35.41 MW24 Nov 2026
2 published values, as a table
Observed fromUntilValue
26 Sep 202611 Nov 202634.46 MW
11 Nov 2026current35.41 MW

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Load (any) · Requested

current 0 MW

26 Sep 2026: 0 MW14 Oct 2026: 0.95 MW11 Nov 2026: 0 MW
26 Sep 2026range 0 to 0.95 MW24 Nov 2026
3 published values, as a table
Observed fromUntilValue
26 Sep 202614 Oct 20260 MW
14 Oct 202611 Nov 20260.95 MW
11 Nov 2026current0 MW

Time axis: when we observed each value, not the operator’s effective date.

Through the API

curl "https://api.gridcapacityapi.com/v1/grid-assets/bus_06gdrjdt0nvyq5gesxsmq6evjc/capacity" \  -H "Authorization: Bearer gc_live_..."