| Injection | Generation (any) | Available | 172.5 MW | Firm, ≤ 0 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Injection | Generation (any) | Available | 19 MW | Firm, ≤ 0 % curtailment a year | 2029 (2029)variant: 70kv | 17 Nov 2026 |
| Injection | Generation (any) | Available | 175 MW | Flexible, ≤ 5 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Injection | Generation (any) | Available | 35.4 MW | Flexible, ≤ 5 % curtailment a year | 2029 (2029)variant: 70kv | 17 Nov 2026 |
| Injection | Generation (any) | Available | 175 MW | Flexible, ≤ 10 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Injection | Generation (any) | Available | 50 MW | Flexible, ≤ 10 % curtailment a year | 2029 (2029)variant: 70kv | 17 Nov 2026 |
| Injection | Generation (any) | Available | 175 MW | Flexible, ≤ 20 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Injection | Generation (any) | Available | 50 MW | Flexible, ≤ 20 % curtailment a year | 2029 (2029)variant: 70kv | 17 Nov 2026 |
| Injection | Generation (any) | Available | 175 MW | Firm, ≤ 0 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |
| Injection | Generation (any) | Available | 42.2 MW | Firm, ≤ 0 % curtailment a year | 2033 (2033)variant: 70kv | 17 Nov 2026 |
| Injection | Generation (any) | Available | 175 MW | Flexible, ≤ 5 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |
| Injection | Generation (any) | Available | 50 MW | Flexible, ≤ 5 % curtailment a year | 2033 (2033)variant: 70kv | 17 Nov 2026 |
| Injection | Generation (any) | Available | 175 MW | Flexible, ≤ 10 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |
| Injection | Generation (any) | Available | 50 MW | Flexible, ≤ 10 % curtailment a year | 2033 (2033)variant: 70kv | 17 Nov 2026 |
| Injection | Generation (any) | Available | 175 MW | Flexible, ≤ 20 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |
| Injection | Generation (any) | Available | 50 MW | Flexible, ≤ 20 % curtailment a year | 2033 (2033)variant: 70kv | 17 Nov 2026 |
| Injection | Solar PV | Available | 175 MW | Firm, ≤ 0 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Injection | Solar PV | Available | 50 MW | Firm, ≤ 0 % curtailment a year | 2029 (2029)variant: 70kv | 17 Nov 2026 |
| Injection | Solar PV | Available | 175 MW | Flexible, ≤ 5 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Injection | Solar PV | Available | 50 MW | Flexible, ≤ 5 % curtailment a year | 2029 (2029)variant: 70kv | 17 Nov 2026 |
| Injection | Solar PV | Available | 175 MW | Flexible, ≤ 10 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Injection | Solar PV | Available | 50 MW | Flexible, ≤ 10 % curtailment a year | 2029 (2029)variant: 70kv | 17 Nov 2026 |
| Injection | Solar PV | Available | 175 MW | Flexible, ≤ 20 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Injection | Solar PV | Available | 50 MW | Flexible, ≤ 20 % curtailment a year | 2029 (2029)variant: 70kv | 17 Nov 2026 |
| Injection | Solar PV | Available | 175 MW | Firm, ≤ 0 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |
| Injection | Solar PV | Available | 50 MW | Firm, ≤ 0 % curtailment a year | 2033 (2033)variant: 70kv | 17 Nov 2026 |
| Injection | Solar PV | Available | 175 MW | Flexible, ≤ 5 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |
| Injection | Solar PV | Available | 50 MW | Flexible, ≤ 5 % curtailment a year | 2033 (2033)variant: 70kv | 17 Nov 2026 |
| Injection | Solar PV | Available | 175 MW | Flexible, ≤ 10 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |
| Injection | Solar PV | Available | 50 MW | Flexible, ≤ 10 % curtailment a year | 2033 (2033)variant: 70kv | 17 Nov 2026 |
| Injection | Solar PV | Available | 175 MW | Flexible, ≤ 20 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |
| Injection | Solar PV | Available | 50 MW | Flexible, ≤ 20 % curtailment a year | 2033 (2033)variant: 70kv | 17 Nov 2026 |
| Injection | Onshore wind | Available | 175 MW | Firm, ≤ 0 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Injection | Onshore wind | Available | 50 MW | Firm, ≤ 0 % curtailment a year | 2029 (2029)variant: 70kv | 17 Nov 2026 |
| Injection | Onshore wind | Available | 175 MW | Flexible, ≤ 5 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Injection | Onshore wind | Available | 50 MW | Flexible, ≤ 5 % curtailment a year | 2029 (2029)variant: 70kv | 17 Nov 2026 |
| Injection | Onshore wind | Available | 175 MW | Flexible, ≤ 10 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Injection | Onshore wind | Available | 50 MW | Flexible, ≤ 10 % curtailment a year | 2029 (2029)variant: 70kv | 17 Nov 2026 |
| Injection | Onshore wind | Available | 175 MW | Flexible, ≤ 20 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Injection | Onshore wind | Available | 50 MW | Flexible, ≤ 20 % curtailment a year | 2029 (2029)variant: 70kv | 17 Nov 2026 |
| Injection | Onshore wind | Available | 175 MW | Firm, ≤ 0 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |
| Injection | Onshore wind | Available | 50 MW | Firm, ≤ 0 % curtailment a year | 2033 (2033)variant: 70kv | 17 Nov 2026 |
| Injection | Onshore wind | Available | 175 MW | Flexible, ≤ 5 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |
| Injection | Onshore wind | Available | 50 MW | Flexible, ≤ 5 % curtailment a year | 2033 (2033)variant: 70kv | 17 Nov 2026 |
| Injection | Onshore wind | Available | 175 MW | Flexible, ≤ 10 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |
| Injection | Onshore wind | Available | 50 MW | Flexible, ≤ 10 % curtailment a year | 2033 (2033)variant: 70kv | 17 Nov 2026 |
| Injection | Onshore wind | Available | 175 MW | Flexible, ≤ 20 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |
| Injection | Onshore wind | Available | 50 MW | Flexible, ≤ 20 % curtailment a year | 2033 (2033)variant: 70kv | 17 Nov 2026 |
| Offtake | Load (any) | Available | 6.1 MW | Firm, ≤ 0 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Offtake | Load (any) | Available | 0 MW | Firm, ≤ 0 % curtailment a year | 2029 (2029)variant: 70kv | 17 Nov 2026 |
| Offtake | Load (any) | Available | 15.2 MW | Flexible, ≤ 5 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Offtake | Load (any) | Available | 13.4 MW | Flexible, ≤ 5 % curtailment a year | 2029 (2029)variant: 70kv | 17 Nov 2026 |
| Offtake | Load (any) | Available | 48.5 MW | Flexible, ≤ 10 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Offtake | Load (any) | Available | 21 MW | Flexible, ≤ 10 % curtailment a year | 2029 (2029)variant: 70kv | 17 Nov 2026 |
| Offtake | Load (any) | Available | 121 MW | Flexible, ≤ 20 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Offtake | Load (any) | Available | 30.4 MW | Flexible, ≤ 20 % curtailment a year | 2029 (2029)variant: 70kv | 17 Nov 2026 |
| Offtake | Load (any) | Available | 10.8 MW | Firm, ≤ 0 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |
| Offtake | Load (any) | Available | 10.7 MW | Firm, ≤ 0 % curtailment a year | 2033 (2033)variant: 70kv | 17 Nov 2026 |
| Offtake | Load (any) | Available | 147.3 MW | Flexible, ≤ 5 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |
| Offtake | Load (any) | Available | 34.1 MW | Flexible, ≤ 5 % curtailment a year | 2033 (2033)variant: 70kv | 17 Nov 2026 |
| Offtake | Load (any) | Available | 175 MW | Flexible, ≤ 10 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |
| Offtake | Load (any) | Available | 39.5 MW | Flexible, ≤ 10 % curtailment a year | 2033 (2033)variant: 70kv | 17 Nov 2026 |
| Offtake | Load (any) | Available | 175 MW | Flexible, ≤ 20 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |
| Offtake | Load (any) | Available | 47.5 MW | Flexible, ≤ 20 % curtailment a year | 2033 (2033)variant: 70kv | 17 Nov 2026 |
| Bidirectional | Battery | Available | 5.4 MW | Firm, ≤ 0 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Bidirectional | Battery | Available | 0 MW | Firm, ≤ 0 % curtailment a year | 2029 (2029)variant: 70kv | 17 Nov 2026 |
| Bidirectional | Battery | Available | 9.6 MW | Flexible, ≤ 5 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Bidirectional | Battery | Available | 8.1 MW | Flexible, ≤ 5 % curtailment a year | 2029 (2029)variant: 70kv | 17 Nov 2026 |
| Bidirectional | Battery | Available | 18.6 MW | Flexible, ≤ 10 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Bidirectional | Battery | Available | 15.8 MW | Flexible, ≤ 10 % curtailment a year | 2029 (2029)variant: 70kv | 17 Nov 2026 |
| Bidirectional | Battery | Available | 96.8 MW | Flexible, ≤ 20 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Bidirectional | Battery | Available | 30 MW | Flexible, ≤ 20 % curtailment a year | 2029 (2029)variant: 70kv | 17 Nov 2026 |
| Bidirectional | Battery | Available | 6.4 MW | Firm, ≤ 0 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |
| Bidirectional | Battery | Available | 0.2 MW | Firm, ≤ 0 % curtailment a year | 2033 (2033)variant: 70kv | 17 Nov 2026 |
| Bidirectional | Battery | Available | 68 MW | Flexible, ≤ 5 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |
| Bidirectional | Battery | Available | 16.9 MW | Flexible, ≤ 5 % curtailment a year | 2033 (2033)variant: 70kv | 17 Nov 2026 |
| Bidirectional | Battery | Available | 121.7 MW | Flexible, ≤ 10 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |
| Bidirectional | Battery | Available | 24.3 MW | Flexible, ≤ 10 % curtailment a year | 2033 (2033)variant: 70kv | 17 Nov 2026 |
| Bidirectional | Battery | Available | 154.4 MW | Flexible, ≤ 20 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |
| Bidirectional | Battery | Available | 33.6 MW | Flexible, ≤ 20 % curtailment a year | 2033 (2033)variant: 70kv | 17 Nov 2026 |