| Injection | Generation (any) | Available | 28.6 MW | Firm, ≤ 0 % curtailment a year | 2029 (2029)variant: 70kv | 17 Nov 2026 |
| Injection | Generation (any) | Available | 50 MW | Flexible, ≤ 5 % curtailment a year | 2029 (2029)variant: 70kv | 17 Nov 2026 |
| Injection | Generation (any) | Available | 50 MW | Flexible, ≤ 10 % curtailment a year | 2029 (2029)variant: 70kv | 17 Nov 2026 |
| Injection | Generation (any) | Available | 50 MW | Flexible, ≤ 20 % curtailment a year | 2029 (2029)variant: 70kv | 17 Nov 2026 |
| Injection | Generation (any) | Available | 47.2 MW | Firm, ≤ 0 % curtailment a year | 2033 (2033)variant: 70kv | 17 Nov 2026 |
| Injection | Generation (any) | Available | 50 MW | Flexible, ≤ 5 % curtailment a year | 2033 (2033)variant: 70kv | 17 Nov 2026 |
| Injection | Generation (any) | Available | 50 MW | Flexible, ≤ 10 % curtailment a year | 2033 (2033)variant: 70kv | 17 Nov 2026 |
| Injection | Generation (any) | Available | 50 MW | Flexible, ≤ 20 % curtailment a year | 2033 (2033)variant: 70kv | 17 Nov 2026 |
| Injection | Solar PV | Available | 50 MW | Firm, ≤ 0 % curtailment a year | 2029 (2029)variant: 70kv | 17 Nov 2026 |
| Injection | Solar PV | Available | 50 MW | Flexible, ≤ 5 % curtailment a year | 2029 (2029)variant: 70kv | 17 Nov 2026 |
| Injection | Solar PV | Available | 50 MW | Flexible, ≤ 10 % curtailment a year | 2029 (2029)variant: 70kv | 17 Nov 2026 |
| Injection | Solar PV | Available | 50 MW | Flexible, ≤ 20 % curtailment a year | 2029 (2029)variant: 70kv | 17 Nov 2026 |
| Injection | Solar PV | Available | 50 MW | Firm, ≤ 0 % curtailment a year | 2033 (2033)variant: 70kv | 17 Nov 2026 |
| Injection | Solar PV | Available | 50 MW | Flexible, ≤ 5 % curtailment a year | 2033 (2033)variant: 70kv | 17 Nov 2026 |
| Injection | Solar PV | Available | 50 MW | Flexible, ≤ 10 % curtailment a year | 2033 (2033)variant: 70kv | 17 Nov 2026 |
| Injection | Solar PV | Available | 50 MW | Flexible, ≤ 20 % curtailment a year | 2033 (2033)variant: 70kv | 17 Nov 2026 |
| Injection | Onshore wind | Available | 35.5 MW | Firm, ≤ 0 % curtailment a year | 2029 (2029)variant: 70kv | 17 Nov 2026 |
| Injection | Onshore wind | Available | 50 MW | Flexible, ≤ 5 % curtailment a year | 2029 (2029)variant: 70kv | 17 Nov 2026 |
| Injection | Onshore wind | Available | 50 MW | Flexible, ≤ 10 % curtailment a year | 2029 (2029)variant: 70kv | 17 Nov 2026 |
| Injection | Onshore wind | Available | 50 MW | Flexible, ≤ 20 % curtailment a year | 2029 (2029)variant: 70kv | 17 Nov 2026 |
| Injection | Onshore wind | Available | 49 MW | Firm, ≤ 0 % curtailment a year | 2033 (2033)variant: 70kv | 17 Nov 2026 |
| Injection | Onshore wind | Available | 50 MW | Flexible, ≤ 5 % curtailment a year | 2033 (2033)variant: 70kv | 17 Nov 2026 |
| Injection | Onshore wind | Available | 50 MW | Flexible, ≤ 10 % curtailment a year | 2033 (2033)variant: 70kv | 17 Nov 2026 |
| Injection | Onshore wind | Available | 50 MW | Flexible, ≤ 20 % curtailment a year | 2033 (2033)variant: 70kv | 17 Nov 2026 |
| Offtake | Load (any) | Available | 3.2 MW | Firm, ≤ 0 % curtailment a year | 2029 (2029)variant: 70kv | 17 Nov 2026 |
| Offtake | Load (any) | Available | 4.5 MW | Flexible, ≤ 5 % curtailment a year | 2029 (2029)variant: 70kv | 17 Nov 2026 |
| Offtake | Load (any) | Available | 7.3 MW | Flexible, ≤ 10 % curtailment a year | 2029 (2029)variant: 70kv | 17 Nov 2026 |
| Offtake | Load (any) | Available | 39.4 MW | Flexible, ≤ 20 % curtailment a year | 2029 (2029)variant: 70kv | 17 Nov 2026 |
| Offtake | Load (any) | Available | 3.2 MW | Firm, ≤ 0 % curtailment a year | 2033 (2033)variant: 70kv | 17 Nov 2026 |
| Offtake | Load (any) | Available | 4.5 MW | Flexible, ≤ 5 % curtailment a year | 2033 (2033)variant: 70kv | 17 Nov 2026 |
| Offtake | Load (any) | Available | 7.3 MW | Flexible, ≤ 10 % curtailment a year | 2033 (2033)variant: 70kv | 17 Nov 2026 |
| Offtake | Load (any) | Available | 39.4 MW | Flexible, ≤ 20 % curtailment a year | 2033 (2033)variant: 70kv | 17 Nov 2026 |
| Bidirectional | Battery | Available | 3 MW | Firm, ≤ 0 % curtailment a year | 2029 (2029)variant: 70kv | 17 Nov 2026 |
| Bidirectional | Battery | Available | 3.5 MW | Flexible, ≤ 5 % curtailment a year | 2029 (2029)variant: 70kv | 17 Nov 2026 |
| Bidirectional | Battery | Available | 3.9 MW | Flexible, ≤ 10 % curtailment a year | 2029 (2029)variant: 70kv | 17 Nov 2026 |
| Bidirectional | Battery | Available | 5 MW | Flexible, ≤ 20 % curtailment a year | 2029 (2029)variant: 70kv | 17 Nov 2026 |
| Bidirectional | Battery | Available | 3 MW | Firm, ≤ 0 % curtailment a year | 2033 (2033)variant: 70kv | 17 Nov 2026 |
| Bidirectional | Battery | Available | 3.5 MW | Flexible, ≤ 5 % curtailment a year | 2033 (2033)variant: 70kv | 17 Nov 2026 |
| Bidirectional | Battery | Available | 3.9 MW | Flexible, ≤ 10 % curtailment a year | 2033 (2033)variant: 70kv | 17 Nov 2026 |
| Bidirectional | Battery | Available | 5 MW | Flexible, ≤ 20 % curtailment a year | 2033 (2033)variant: 70kv | 17 Nov 2026 |