Substation / 36 kV

TORHO

Elia Transmission Belgium / Belgium

Latest published values

40 served · 0 withheld

Each row is what the operator’s latest published dataset reports for one combination of direction, technology, measure, firmness and horizon. Hosting-capacity figures are indicative and reflect what operators publish. They are not a connection offer; only the operator can confirm capacity for a specific request.

Latest published capacity values, one row per series
DirectionTechnologyMeasureValueFirmnessHorizonSource date
InjectionGeneration (any)Available1.3 MWFirm, ≤ 0 % curtailment a year2029 (2029)variant: 36kv17 Nov 2026
InjectionGeneration (any)Available20 MWFlexible, ≤ 5 % curtailment a year2029 (2029)variant: 36kv17 Nov 2026
InjectionGeneration (any)Available20 MWFlexible, ≤ 10 % curtailment a year2029 (2029)variant: 36kv17 Nov 2026
InjectionGeneration (any)Available20 MWFlexible, ≤ 20 % curtailment a year2029 (2029)variant: 36kv17 Nov 2026
InjectionGeneration (any)Available1.3 MWFirm, ≤ 0 % curtailment a year2033 (2033)variant: 36kv17 Nov 2026
InjectionGeneration (any)Available20 MWFlexible, ≤ 5 % curtailment a year2033 (2033)variant: 36kv17 Nov 2026
InjectionGeneration (any)Available20 MWFlexible, ≤ 10 % curtailment a year2033 (2033)variant: 36kv17 Nov 2026
InjectionGeneration (any)Available20 MWFlexible, ≤ 20 % curtailment a year2033 (2033)variant: 36kv17 Nov 2026
InjectionSolar PVAvailable0 MWFirm, ≤ 0 % curtailment a year2029 (2029)variant: 36kv17 Nov 2026
InjectionSolar PVAvailable3.1 MWFlexible, ≤ 5 % curtailment a year2029 (2029)variant: 36kv17 Nov 2026
InjectionSolar PVAvailable7.1 MWFlexible, ≤ 10 % curtailment a year2029 (2029)variant: 36kv17 Nov 2026
InjectionSolar PVAvailable20 MWFlexible, ≤ 20 % curtailment a year2029 (2029)variant: 36kv17 Nov 2026
InjectionSolar PVAvailable1.9 MWFirm, ≤ 0 % curtailment a year2033 (2033)variant: 36kv17 Nov 2026
InjectionSolar PVAvailable3.1 MWFlexible, ≤ 5 % curtailment a year2033 (2033)variant: 36kv17 Nov 2026
InjectionSolar PVAvailable7.1 MWFlexible, ≤ 10 % curtailment a year2033 (2033)variant: 36kv17 Nov 2026
InjectionSolar PVAvailable20 MWFlexible, ≤ 20 % curtailment a year2033 (2033)variant: 36kv17 Nov 2026
InjectionOnshore windAvailable0 MWFirm, ≤ 0 % curtailment a year2029 (2029)variant: 36kv17 Nov 2026
InjectionOnshore windAvailable20 MWFlexible, ≤ 5 % curtailment a year2029 (2029)variant: 36kv17 Nov 2026
InjectionOnshore windAvailable20 MWFlexible, ≤ 10 % curtailment a year2029 (2029)variant: 36kv17 Nov 2026
InjectionOnshore windAvailable20 MWFlexible, ≤ 20 % curtailment a year2029 (2029)variant: 36kv17 Nov 2026
InjectionOnshore windAvailable10 MWFirm, ≤ 0 % curtailment a year2033 (2033)variant: 36kv17 Nov 2026
InjectionOnshore windAvailable20 MWFlexible, ≤ 5 % curtailment a year2033 (2033)variant: 36kv17 Nov 2026
InjectionOnshore windAvailable20 MWFlexible, ≤ 10 % curtailment a year2033 (2033)variant: 36kv17 Nov 2026
InjectionOnshore windAvailable20 MWFlexible, ≤ 20 % curtailment a year2033 (2033)variant: 36kv17 Nov 2026
OfftakeLoad (any)Available3.5 MWFirm, ≤ 0 % curtailment a year2029 (2029)variant: 36kv17 Nov 2026
OfftakeLoad (any)Available10.6 MWFlexible, ≤ 5 % curtailment a year2029 (2029)variant: 36kv17 Nov 2026
OfftakeLoad (any)Available15.9 MWFlexible, ≤ 10 % curtailment a year2029 (2029)variant: 36kv17 Nov 2026
OfftakeLoad (any)Available20 MWFlexible, ≤ 20 % curtailment a year2029 (2029)variant: 36kv17 Nov 2026
OfftakeLoad (any)Available6.9 MWFirm, ≤ 0 % curtailment a year2033 (2033)variant: 36kv17 Nov 2026
OfftakeLoad (any)Available20 MWFlexible, ≤ 5 % curtailment a year2033 (2033)variant: 36kv17 Nov 2026
OfftakeLoad (any)Available20 MWFlexible, ≤ 10 % curtailment a year2033 (2033)variant: 36kv17 Nov 2026
OfftakeLoad (any)Available20 MWFlexible, ≤ 20 % curtailment a year2033 (2033)variant: 36kv17 Nov 2026
BidirectionalBatteryAvailable0 MWFirm, ≤ 0 % curtailment a year2029 (2029)variant: 36kv17 Nov 2026
BidirectionalBatteryAvailable5.1 MWFlexible, ≤ 5 % curtailment a year2029 (2029)variant: 36kv17 Nov 2026
BidirectionalBatteryAvailable6.2 MWFlexible, ≤ 10 % curtailment a year2029 (2029)variant: 36kv17 Nov 2026
BidirectionalBatteryAvailable10.8 MWFlexible, ≤ 20 % curtailment a year2029 (2029)variant: 36kv17 Nov 2026
BidirectionalBatteryAvailable0 MWFirm, ≤ 0 % curtailment a year2033 (2033)variant: 36kv17 Nov 2026
BidirectionalBatteryAvailable20 MWFlexible, ≤ 5 % curtailment a year2033 (2033)variant: 36kv17 Nov 2026
BidirectionalBatteryAvailable20 MWFlexible, ≤ 10 % curtailment a year2033 (2033)variant: 36kv17 Nov 2026
BidirectionalBatteryAvailable20 MWFlexible, ≤ 20 % curtailment a year2033 (2033)variant: 36kv17 Nov 2026

Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map

What each value means

Methodology, both clocks, provenance and rights

Injection · Generation (any) · Available

1.3 MW

Granted

The operator's latest published dataset reports 1.3 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2029 (2029) · variant: 36kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/TORHO 36 · payload sha256 1deb1708ff4a…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
TORHO 36
Operator note: flexibilityLevel
0%_flex
Operator note: variant
36kv
Operator note: voltage kv
36

Injection · Generation (any) · Available

20 MW

Granted

The operator's latest published dataset reports 20 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2029 (2029) · variant: 36kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/TORHO 36 · payload sha256 1deb1708ff4a…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
TORHO 36
Operator note: flexibilityLevel
5%_flex
Operator note: variant
36kv
Operator note: voltage kv
36

Injection · Generation (any) · Available

20 MW

Granted

The operator's latest published dataset reports 20 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2029 (2029) · variant: 36kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/TORHO 36 · payload sha256 1deb1708ff4a…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
TORHO 36
Operator note: flexibilityLevel
10%_flex
Operator note: variant
36kv
Operator note: voltage kv
36

Injection · Generation (any) · Available

20 MW

Granted

The operator's latest published dataset reports 20 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2029 (2029) · variant: 36kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/TORHO 36 · payload sha256 1deb1708ff4a…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
TORHO 36
Operator note: flexibilityLevel
20%_flex
Operator note: variant
36kv
Operator note: voltage kv
36

Injection · Generation (any) · Available

1.3 MW

Granted

The operator's latest published dataset reports 1.3 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2033 (2033) · variant: 36kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/TORHO 36 · payload sha256 6a1975b565ba…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
TORHO 36
Operator note: flexibilityLevel
0%_flex
Operator note: variant
36kv
Operator note: voltage kv
36

Injection · Generation (any) · Available

20 MW

Granted

The operator's latest published dataset reports 20 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2033 (2033) · variant: 36kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/TORHO 36 · payload sha256 6a1975b565ba…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
TORHO 36
Operator note: flexibilityLevel
5%_flex
Operator note: variant
36kv
Operator note: voltage kv
36

Injection · Generation (any) · Available

20 MW

Granted

The operator's latest published dataset reports 20 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2033 (2033) · variant: 36kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/TORHO 36 · payload sha256 6a1975b565ba…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
TORHO 36
Operator note: flexibilityLevel
10%_flex
Operator note: variant
36kv
Operator note: voltage kv
36

Injection · Generation (any) · Available

20 MW

Granted

The operator's latest published dataset reports 20 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2033 (2033) · variant: 36kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/TORHO 36 · payload sha256 6a1975b565ba…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
TORHO 36
Operator note: flexibilityLevel
20%_flex
Operator note: variant
36kv
Operator note: voltage kv
36

Injection · Solar PV · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2029 (2029) · variant: 36kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/TORHO 36 · payload sha256 1deb1708ff4a…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
TORHO 36
Operator note: flexibilityLevel
0%_flex
Operator note: variant
36kv
Operator note: voltage kv
36

Injection · Solar PV · Available

3.1 MW

Granted

The operator's latest published dataset reports 3.1 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2029 (2029) · variant: 36kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/TORHO 36 · payload sha256 1deb1708ff4a…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
TORHO 36
Operator note: flexibilityLevel
5%_flex
Operator note: variant
36kv
Operator note: voltage kv
36

Injection · Solar PV · Available

7.1 MW

Granted

The operator's latest published dataset reports 7.1 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2029 (2029) · variant: 36kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/TORHO 36 · payload sha256 1deb1708ff4a…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
TORHO 36
Operator note: flexibilityLevel
10%_flex
Operator note: variant
36kv
Operator note: voltage kv
36

Injection · Solar PV · Available

20 MW

Granted

The operator's latest published dataset reports 20 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2029 (2029) · variant: 36kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/TORHO 36 · payload sha256 1deb1708ff4a…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
TORHO 36
Operator note: flexibilityLevel
20%_flex
Operator note: variant
36kv
Operator note: voltage kv
36

Injection · Solar PV · Available

1.9 MW

Granted

The operator's latest published dataset reports 1.9 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2033 (2033) · variant: 36kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/TORHO 36 · payload sha256 6a1975b565ba…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
TORHO 36
Operator note: flexibilityLevel
0%_flex
Operator note: variant
36kv
Operator note: voltage kv
36

Injection · Solar PV · Available

3.1 MW

Granted

The operator's latest published dataset reports 3.1 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2033 (2033) · variant: 36kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/TORHO 36 · payload sha256 6a1975b565ba…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
TORHO 36
Operator note: flexibilityLevel
5%_flex
Operator note: variant
36kv
Operator note: voltage kv
36

Injection · Solar PV · Available

7.1 MW

Granted

The operator's latest published dataset reports 7.1 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2033 (2033) · variant: 36kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/TORHO 36 · payload sha256 6a1975b565ba…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
TORHO 36
Operator note: flexibilityLevel
10%_flex
Operator note: variant
36kv
Operator note: voltage kv
36

Injection · Solar PV · Available

20 MW

Granted

The operator's latest published dataset reports 20 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2033 (2033) · variant: 36kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/TORHO 36 · payload sha256 6a1975b565ba…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
TORHO 36
Operator note: flexibilityLevel
20%_flex
Operator note: variant
36kv
Operator note: voltage kv
36

Injection · Onshore wind · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2029 (2029) · variant: 36kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/TORHO 36 · payload sha256 1deb1708ff4a…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
TORHO 36
Operator note: flexibilityLevel
0%_flex
Operator note: variant
36kv
Operator note: voltage kv
36

Injection · Onshore wind · Available

20 MW

Granted

The operator's latest published dataset reports 20 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2029 (2029) · variant: 36kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/TORHO 36 · payload sha256 1deb1708ff4a…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
TORHO 36
Operator note: flexibilityLevel
5%_flex
Operator note: variant
36kv
Operator note: voltage kv
36

Injection · Onshore wind · Available

20 MW

Granted

The operator's latest published dataset reports 20 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2029 (2029) · variant: 36kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/TORHO 36 · payload sha256 1deb1708ff4a…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
TORHO 36
Operator note: flexibilityLevel
10%_flex
Operator note: variant
36kv
Operator note: voltage kv
36

Injection · Onshore wind · Available

20 MW

Granted

The operator's latest published dataset reports 20 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2029 (2029) · variant: 36kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/TORHO 36 · payload sha256 1deb1708ff4a…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
TORHO 36
Operator note: flexibilityLevel
20%_flex
Operator note: variant
36kv
Operator note: voltage kv
36

Injection · Onshore wind · Available

10 MW

Granted

The operator's latest published dataset reports 10 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2033 (2033) · variant: 36kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/TORHO 36 · payload sha256 6a1975b565ba…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
TORHO 36
Operator note: flexibilityLevel
0%_flex
Operator note: variant
36kv
Operator note: voltage kv
36

Injection · Onshore wind · Available

20 MW

Granted

The operator's latest published dataset reports 20 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2033 (2033) · variant: 36kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/TORHO 36 · payload sha256 6a1975b565ba…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
TORHO 36
Operator note: flexibilityLevel
5%_flex
Operator note: variant
36kv
Operator note: voltage kv
36

Injection · Onshore wind · Available

20 MW

Granted

The operator's latest published dataset reports 20 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2033 (2033) · variant: 36kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/TORHO 36 · payload sha256 6a1975b565ba…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
TORHO 36
Operator note: flexibilityLevel
10%_flex
Operator note: variant
36kv
Operator note: voltage kv
36

Injection · Onshore wind · Available

20 MW

Granted

The operator's latest published dataset reports 20 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2033 (2033) · variant: 36kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/TORHO 36 · payload sha256 6a1975b565ba…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
TORHO 36
Operator note: flexibilityLevel
20%_flex
Operator note: variant
36kv
Operator note: voltage kv
36

Offtake · Load (any) · Available

3.5 MW

Granted

The operator's latest published dataset reports 3.5 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2029 (2029) · variant: 36kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/TORHO 36 · payload sha256 1deb1708ff4a…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
TORHO 36
Operator note: flexibilityLevel
0%_flex
Operator note: variant
36kv
Operator note: voltage kv
36

Offtake · Load (any) · Available

10.6 MW

Granted

The operator's latest published dataset reports 10.6 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2029 (2029) · variant: 36kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/TORHO 36 · payload sha256 1deb1708ff4a…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
TORHO 36
Operator note: flexibilityLevel
5%_flex
Operator note: variant
36kv
Operator note: voltage kv
36

Offtake · Load (any) · Available

15.9 MW

Granted

The operator's latest published dataset reports 15.9 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2029 (2029) · variant: 36kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/TORHO 36 · payload sha256 1deb1708ff4a…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
TORHO 36
Operator note: flexibilityLevel
10%_flex
Operator note: variant
36kv
Operator note: voltage kv
36

Offtake · Load (any) · Available

20 MW

Granted

The operator's latest published dataset reports 20 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2029 (2029) · variant: 36kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/TORHO 36 · payload sha256 1deb1708ff4a…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
TORHO 36
Operator note: flexibilityLevel
20%_flex
Operator note: variant
36kv
Operator note: voltage kv
36

Offtake · Load (any) · Available

6.9 MW

Granted

The operator's latest published dataset reports 6.9 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2033 (2033) · variant: 36kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/TORHO 36 · payload sha256 6a1975b565ba…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
TORHO 36
Operator note: flexibilityLevel
0%_flex
Operator note: variant
36kv
Operator note: voltage kv
36

Offtake · Load (any) · Available

20 MW

Granted

The operator's latest published dataset reports 20 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2033 (2033) · variant: 36kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/TORHO 36 · payload sha256 6a1975b565ba…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
TORHO 36
Operator note: flexibilityLevel
5%_flex
Operator note: variant
36kv
Operator note: voltage kv
36

Offtake · Load (any) · Available

20 MW

Granted

The operator's latest published dataset reports 20 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2033 (2033) · variant: 36kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/TORHO 36 · payload sha256 6a1975b565ba…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
TORHO 36
Operator note: flexibilityLevel
10%_flex
Operator note: variant
36kv
Operator note: voltage kv
36

Offtake · Load (any) · Available

20 MW

Granted

The operator's latest published dataset reports 20 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2033 (2033) · variant: 36kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/TORHO 36 · payload sha256 6a1975b565ba…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
TORHO 36
Operator note: flexibilityLevel
20%_flex
Operator note: variant
36kv
Operator note: voltage kv
36

Bidirectional · Battery · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2029 (2029) · variant: 36kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/TORHO 36 · payload sha256 1deb1708ff4a…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
TORHO 36
Operator note: flexibilityLevel
0%_flex
Operator note: variant
36kv
Operator note: voltage kv
36

Bidirectional · Battery · Available

5.1 MW

Granted

The operator's latest published dataset reports 5.1 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2029 (2029) · variant: 36kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/TORHO 36 · payload sha256 1deb1708ff4a…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
TORHO 36
Operator note: flexibilityLevel
5%_flex
Operator note: variant
36kv
Operator note: voltage kv
36

Bidirectional · Battery · Available

6.2 MW

Granted

The operator's latest published dataset reports 6.2 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2029 (2029) · variant: 36kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/TORHO 36 · payload sha256 1deb1708ff4a…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
TORHO 36
Operator note: flexibilityLevel
10%_flex
Operator note: variant
36kv
Operator note: voltage kv
36

Bidirectional · Battery · Available

10.8 MW

Granted

The operator's latest published dataset reports 10.8 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2029 (2029) · variant: 36kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/TORHO 36 · payload sha256 1deb1708ff4a…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
TORHO 36
Operator note: flexibilityLevel
20%_flex
Operator note: variant
36kv
Operator note: voltage kv
36

Bidirectional · Battery · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2033 (2033) · variant: 36kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/TORHO 36 · payload sha256 6a1975b565ba…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
TORHO 36
Operator note: flexibilityLevel
0%_flex
Operator note: variant
36kv
Operator note: voltage kv
36

Bidirectional · Battery · Available

20 MW

Granted

The operator's latest published dataset reports 20 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2033 (2033) · variant: 36kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/TORHO 36 · payload sha256 6a1975b565ba…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
TORHO 36
Operator note: flexibilityLevel
5%_flex
Operator note: variant
36kv
Operator note: voltage kv
36

Bidirectional · Battery · Available

20 MW

Granted

The operator's latest published dataset reports 20 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2033 (2033) · variant: 36kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/TORHO 36 · payload sha256 6a1975b565ba…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
TORHO 36
Operator note: flexibilityLevel
10%_flex
Operator note: variant
36kv
Operator note: voltage kv
36

Bidirectional · Battery · Available

20 MW

Granted

The operator's latest published dataset reports 20 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2033 (2033) · variant: 36kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/TORHO 36 · payload sha256 6a1975b565ba…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
TORHO 36
Operator note: flexibilityLevel
20%_flex
Operator note: variant
36kv
Operator note: voltage kv
36

History

Served series only

Bidirectional · Battery · Available · 2027

last, until 17 Nov 2026: 0 MW

26 Sep 2026: 0 MW
26 Sep 2026range 0 to 0 MW24 Nov 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 202617 Nov 20260 MW

Time axis: when we observed each value, not the operator’s effective date.

Bidirectional · Battery · Available · 2027

last, until 17 Nov 2026: 0 MW

26 Sep 2026: 0 MW
26 Sep 2026range 0 to 0 MW24 Nov 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 202617 Nov 20260 MW

Time axis: when we observed each value, not the operator’s effective date.

Bidirectional · Battery · Available · 2027

last, until 17 Nov 2026: 17.6 MW

26 Sep 2026: 17.6 MW
26 Sep 2026range 17.6 to 17.6 MW24 Nov 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 202617 Nov 202617.6 MW

Time axis: when we observed each value, not the operator’s effective date.

Bidirectional · Battery · Available · 2027

last, until 17 Nov 2026: 20 MW

26 Sep 2026: 20 MW
26 Sep 2026range 20 to 20 MW24 Nov 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 202617 Nov 202620 MW

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Load (any) · Available · 2027

last, until 17 Nov 2026: 0.4 MW

26 Sep 2026: 0.4 MW
26 Sep 2026range 0.4 to 0.4 MW24 Nov 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 202617 Nov 20260.4 MW

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Load (any) · Available · 2027

last, until 17 Nov 2026: 15.2 MW

26 Sep 2026: 15.3 MW17 Oct 2026: 15.2 MW
26 Sep 2026range 15.2 to 15.3 MW24 Nov 2026
2 published values, as a table
Observed fromUntilValue
26 Sep 202617 Oct 202615.3 MW
17 Oct 202617 Nov 202615.2 MW

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Load (any) · Available · 2027

last, until 17 Nov 2026: 19 MW

26 Sep 2026: 19.2 MW17 Oct 2026: 19 MW
26 Sep 2026range 19 to 19.2 MW24 Nov 2026
2 published values, as a table
Observed fromUntilValue
26 Sep 202617 Oct 202619.2 MW
17 Oct 202617 Nov 202619 MW

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Load (any) · Available · 2027

last, until 17 Nov 2026: 20 MW

26 Sep 2026: 20 MW
26 Sep 2026range 20 to 20 MW24 Nov 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 202617 Nov 202620 MW

Time axis: when we observed each value, not the operator’s effective date.

Injection · Generation (any) · Available · 2027

last, until 17 Nov 2026: 0 MW

26 Sep 2026: 0 MW
26 Sep 2026range 0 to 0 MW24 Nov 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 202617 Nov 20260 MW

Time axis: when we observed each value, not the operator’s effective date.

Injection · Generation (any) · Available · 2027

last, until 17 Nov 2026: 0 MW

26 Sep 2026: 0 MW
26 Sep 2026range 0 to 0 MW24 Nov 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 202617 Nov 20260 MW

Time axis: when we observed each value, not the operator’s effective date.

Injection · Generation (any) · Available · 2027

last, until 17 Nov 2026: 20 MW

26 Sep 2026: 20 MW
26 Sep 2026range 20 to 20 MW24 Nov 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 202617 Nov 202620 MW

Time axis: when we observed each value, not the operator’s effective date.

Injection · Generation (any) · Available · 2027

last, until 17 Nov 2026: 20 MW

26 Sep 2026: 20 MW
26 Sep 2026range 20 to 20 MW24 Nov 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 202617 Nov 202620 MW

Time axis: when we observed each value, not the operator’s effective date.

The first 12 of 80 served series with a history. The history route returns every one of them.

Through the API