TERTR

Elia Transmission Belgium / Belgium

Latest published values

40 served · 0 withheld

Each row is what the operator’s latest published dataset reports for one combination of direction, technology, measure, firmness and horizon. Hosting-capacity figures are indicative and reflect what operators publish. They are not a connection offer; only the operator can confirm capacity for a specific request.

Latest published capacity values, one row per series
DirectionTechnologyMeasureValueFirmnessHorizonSource date
InjectionGeneration (any)Available8.5 MWFirm, ≤ 0 % curtailment a year2027 (2027)variant: 30kv26 Sep 2026
InjectionGeneration (any)Available20 MWFlexible, ≤ 5 % curtailment a year2027 (2027)variant: 30kv26 Sep 2026
InjectionGeneration (any)Available20 MWFlexible, ≤ 10 % curtailment a year2027 (2027)variant: 30kv26 Sep 2026
InjectionGeneration (any)Available20 MWFlexible, ≤ 20 % curtailment a year2027 (2027)variant: 30kv26 Sep 2026
InjectionGeneration (any)Available8.5 MWFirm, ≤ 0 % curtailment a year2031 (2031)variant: 30kv26 Sep 2026
InjectionGeneration (any)Available20 MWFlexible, ≤ 5 % curtailment a year2031 (2031)variant: 30kv26 Sep 2026
InjectionGeneration (any)Available20 MWFlexible, ≤ 10 % curtailment a year2031 (2031)variant: 30kv26 Sep 2026
InjectionGeneration (any)Available20 MWFlexible, ≤ 20 % curtailment a year2031 (2031)variant: 30kv26 Sep 2026
InjectionSolar PVAvailable20 MWFirm, ≤ 0 % curtailment a year2027 (2027)variant: 30kv26 Sep 2026
InjectionSolar PVAvailable20 MWFlexible, ≤ 5 % curtailment a year2027 (2027)variant: 30kv26 Sep 2026
InjectionSolar PVAvailable20 MWFlexible, ≤ 10 % curtailment a year2027 (2027)variant: 30kv26 Sep 2026
InjectionSolar PVAvailable20 MWFlexible, ≤ 20 % curtailment a year2027 (2027)variant: 30kv26 Sep 2026
InjectionSolar PVAvailable20 MWFirm, ≤ 0 % curtailment a year2031 (2031)variant: 30kv26 Sep 2026
InjectionSolar PVAvailable20 MWFlexible, ≤ 5 % curtailment a year2031 (2031)variant: 30kv26 Sep 2026
InjectionSolar PVAvailable20 MWFlexible, ≤ 10 % curtailment a year2031 (2031)variant: 30kv26 Sep 2026
InjectionSolar PVAvailable20 MWFlexible, ≤ 20 % curtailment a year2031 (2031)variant: 30kv26 Sep 2026
InjectionOnshore windAvailable17.5 MWFirm, ≤ 0 % curtailment a year2027 (2027)variant: 30kv26 Sep 2026
InjectionOnshore windAvailable20 MWFlexible, ≤ 5 % curtailment a year2027 (2027)variant: 30kv26 Sep 2026
InjectionOnshore windAvailable20 MWFlexible, ≤ 10 % curtailment a year2027 (2027)variant: 30kv26 Sep 2026
InjectionOnshore windAvailable20 MWFlexible, ≤ 20 % curtailment a year2027 (2027)variant: 30kv26 Sep 2026
InjectionOnshore windAvailable17.5 MWFirm, ≤ 0 % curtailment a year2031 (2031)variant: 30kv26 Sep 2026
InjectionOnshore windAvailable20 MWFlexible, ≤ 5 % curtailment a year2031 (2031)variant: 30kv26 Sep 2026
InjectionOnshore windAvailable20 MWFlexible, ≤ 10 % curtailment a year2031 (2031)variant: 30kv26 Sep 2026
InjectionOnshore windAvailable20 MWFlexible, ≤ 20 % curtailment a year2031 (2031)variant: 30kv26 Sep 2026
OfftakeLoad (any)Available1.8 MWFirm, ≤ 0 % curtailment a year2027 (2027)variant: 30kv26 Sep 2026
OfftakeLoad (any)Available9 MWFlexible, ≤ 5 % curtailment a year2027 (2027)variant: 30kv26 Sep 2026
OfftakeLoad (any)Available12.7 MWFlexible, ≤ 10 % curtailment a year2027 (2027)variant: 30kv26 Sep 2026
OfftakeLoad (any)Available20 MWFlexible, ≤ 20 % curtailment a year2027 (2027)variant: 30kv26 Sep 2026
OfftakeLoad (any)Available4.8 MWFirm, ≤ 0 % curtailment a year2031 (2031)variant: 30kv26 Sep 2026
OfftakeLoad (any)Available20 MWFlexible, ≤ 5 % curtailment a year2031 (2031)variant: 30kv26 Sep 2026
OfftakeLoad (any)Available20 MWFlexible, ≤ 10 % curtailment a year2031 (2031)variant: 30kv26 Sep 2026
OfftakeLoad (any)Available20 MWFlexible, ≤ 20 % curtailment a year2031 (2031)variant: 30kv26 Sep 2026
BidirectionalBatteryAvailable1.3 MWFirm, ≤ 0 % curtailment a year2027 (2027)variant: 30kv26 Sep 2026
BidirectionalBatteryAvailable8.6 MWFlexible, ≤ 5 % curtailment a year2027 (2027)variant: 30kv26 Sep 2026
BidirectionalBatteryAvailable12.2 MWFlexible, ≤ 10 % curtailment a year2027 (2027)variant: 30kv26 Sep 2026
BidirectionalBatteryAvailable20 MWFlexible, ≤ 20 % curtailment a year2027 (2027)variant: 30kv26 Sep 2026
BidirectionalBatteryAvailable4.8 MWFirm, ≤ 0 % curtailment a year2031 (2031)variant: 30kv26 Sep 2026
BidirectionalBatteryAvailable20 MWFlexible, ≤ 5 % curtailment a year2031 (2031)variant: 30kv26 Sep 2026
BidirectionalBatteryAvailable20 MWFlexible, ≤ 10 % curtailment a year2031 (2031)variant: 30kv26 Sep 2026
BidirectionalBatteryAvailable20 MWFlexible, ≤ 20 % curtailment a year2031 (2031)variant: 30kv26 Sep 2026

Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map

What each value means

Methodology, both clocks, provenance and rights

Injection · Generation (any) · Available

8.5 MW

Granted

The operator's latest published dataset reports 8.5 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2027 (2027) · variant: 30kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2027/TERTR 30 · payload sha256 33ebf6c6d4da…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
TERTR 30
Operator note: flexibilityLevel
0%_flex
Operator note: variant
30kv
Operator note: voltage kv
30

Injection · Generation (any) · Available

20 MW

Granted

The operator's latest published dataset reports 20 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2027 (2027) · variant: 30kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2027/TERTR 30 · payload sha256 33ebf6c6d4da…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
TERTR 30
Operator note: flexibilityLevel
5%_flex
Operator note: variant
30kv
Operator note: voltage kv
30

Injection · Generation (any) · Available

20 MW

Granted

The operator's latest published dataset reports 20 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2027 (2027) · variant: 30kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2027/TERTR 30 · payload sha256 33ebf6c6d4da…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
TERTR 30
Operator note: flexibilityLevel
10%_flex
Operator note: variant
30kv
Operator note: voltage kv
30

Injection · Generation (any) · Available

20 MW

Granted

The operator's latest published dataset reports 20 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2027 (2027) · variant: 30kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2027/TERTR 30 · payload sha256 33ebf6c6d4da…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
TERTR 30
Operator note: flexibilityLevel
20%_flex
Operator note: variant
30kv
Operator note: voltage kv
30

Injection · Generation (any) · Available

8.5 MW

Granted

The operator's latest published dataset reports 8.5 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2031 (2031) · variant: 30kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/TERTR 30 · payload sha256 013d7f39ff14…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
TERTR 30
Operator note: flexibilityLevel
0%_flex
Operator note: variant
30kv
Operator note: voltage kv
30

Injection · Generation (any) · Available

20 MW

Granted

The operator's latest published dataset reports 20 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2031 (2031) · variant: 30kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/TERTR 30 · payload sha256 013d7f39ff14…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
TERTR 30
Operator note: flexibilityLevel
5%_flex
Operator note: variant
30kv
Operator note: voltage kv
30

Injection · Generation (any) · Available

20 MW

Granted

The operator's latest published dataset reports 20 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2031 (2031) · variant: 30kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/TERTR 30 · payload sha256 013d7f39ff14…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
TERTR 30
Operator note: flexibilityLevel
10%_flex
Operator note: variant
30kv
Operator note: voltage kv
30

Injection · Generation (any) · Available

20 MW

Granted

The operator's latest published dataset reports 20 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2031 (2031) · variant: 30kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/TERTR 30 · payload sha256 013d7f39ff14…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
TERTR 30
Operator note: flexibilityLevel
20%_flex
Operator note: variant
30kv
Operator note: voltage kv
30

Injection · Solar PV · Available

20 MW

Granted

The operator's latest published dataset reports 20 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2027 (2027) · variant: 30kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2027/TERTR 30 · payload sha256 33ebf6c6d4da…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
TERTR 30
Operator note: flexibilityLevel
0%_flex
Operator note: variant
30kv
Operator note: voltage kv
30

Injection · Solar PV · Available

20 MW

Granted

The operator's latest published dataset reports 20 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2027 (2027) · variant: 30kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2027/TERTR 30 · payload sha256 33ebf6c6d4da…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
TERTR 30
Operator note: flexibilityLevel
5%_flex
Operator note: variant
30kv
Operator note: voltage kv
30

Injection · Solar PV · Available

20 MW

Granted

The operator's latest published dataset reports 20 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2027 (2027) · variant: 30kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2027/TERTR 30 · payload sha256 33ebf6c6d4da…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
TERTR 30
Operator note: flexibilityLevel
10%_flex
Operator note: variant
30kv
Operator note: voltage kv
30

Injection · Solar PV · Available

20 MW

Granted

The operator's latest published dataset reports 20 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2027 (2027) · variant: 30kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2027/TERTR 30 · payload sha256 33ebf6c6d4da…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
TERTR 30
Operator note: flexibilityLevel
20%_flex
Operator note: variant
30kv
Operator note: voltage kv
30

Injection · Solar PV · Available

20 MW

Granted

The operator's latest published dataset reports 20 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2031 (2031) · variant: 30kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/TERTR 30 · payload sha256 013d7f39ff14…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
TERTR 30
Operator note: flexibilityLevel
0%_flex
Operator note: variant
30kv
Operator note: voltage kv
30

Injection · Solar PV · Available

20 MW

Granted

The operator's latest published dataset reports 20 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2031 (2031) · variant: 30kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/TERTR 30 · payload sha256 013d7f39ff14…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
TERTR 30
Operator note: flexibilityLevel
5%_flex
Operator note: variant
30kv
Operator note: voltage kv
30

Injection · Solar PV · Available

20 MW

Granted

The operator's latest published dataset reports 20 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2031 (2031) · variant: 30kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/TERTR 30 · payload sha256 013d7f39ff14…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
TERTR 30
Operator note: flexibilityLevel
10%_flex
Operator note: variant
30kv
Operator note: voltage kv
30

Injection · Solar PV · Available

20 MW

Granted

The operator's latest published dataset reports 20 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2031 (2031) · variant: 30kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/TERTR 30 · payload sha256 013d7f39ff14…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
TERTR 30
Operator note: flexibilityLevel
20%_flex
Operator note: variant
30kv
Operator note: voltage kv
30

Injection · Onshore wind · Available

17.5 MW

Granted

The operator's latest published dataset reports 17.5 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2027 (2027) · variant: 30kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2027/TERTR 30 · payload sha256 33ebf6c6d4da…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
TERTR 30
Operator note: flexibilityLevel
0%_flex
Operator note: variant
30kv
Operator note: voltage kv
30

Injection · Onshore wind · Available

20 MW

Granted

The operator's latest published dataset reports 20 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2027 (2027) · variant: 30kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2027/TERTR 30 · payload sha256 33ebf6c6d4da…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
TERTR 30
Operator note: flexibilityLevel
5%_flex
Operator note: variant
30kv
Operator note: voltage kv
30

Injection · Onshore wind · Available

20 MW

Granted

The operator's latest published dataset reports 20 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2027 (2027) · variant: 30kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2027/TERTR 30 · payload sha256 33ebf6c6d4da…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
TERTR 30
Operator note: flexibilityLevel
10%_flex
Operator note: variant
30kv
Operator note: voltage kv
30

Injection · Onshore wind · Available

20 MW

Granted

The operator's latest published dataset reports 20 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2027 (2027) · variant: 30kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2027/TERTR 30 · payload sha256 33ebf6c6d4da…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
TERTR 30
Operator note: flexibilityLevel
20%_flex
Operator note: variant
30kv
Operator note: voltage kv
30

Injection · Onshore wind · Available

17.5 MW

Granted

The operator's latest published dataset reports 17.5 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2031 (2031) · variant: 30kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/TERTR 30 · payload sha256 013d7f39ff14…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
TERTR 30
Operator note: flexibilityLevel
0%_flex
Operator note: variant
30kv
Operator note: voltage kv
30

Injection · Onshore wind · Available

20 MW

Granted

The operator's latest published dataset reports 20 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2031 (2031) · variant: 30kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/TERTR 30 · payload sha256 013d7f39ff14…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
TERTR 30
Operator note: flexibilityLevel
5%_flex
Operator note: variant
30kv
Operator note: voltage kv
30

Injection · Onshore wind · Available

20 MW

Granted

The operator's latest published dataset reports 20 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2031 (2031) · variant: 30kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/TERTR 30 · payload sha256 013d7f39ff14…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
TERTR 30
Operator note: flexibilityLevel
10%_flex
Operator note: variant
30kv
Operator note: voltage kv
30

Injection · Onshore wind · Available

20 MW

Granted

The operator's latest published dataset reports 20 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2031 (2031) · variant: 30kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/TERTR 30 · payload sha256 013d7f39ff14…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
TERTR 30
Operator note: flexibilityLevel
20%_flex
Operator note: variant
30kv
Operator note: voltage kv
30

Offtake · Load (any) · Available

1.8 MW

Granted

The operator's latest published dataset reports 1.8 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2027 (2027) · variant: 30kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2027/TERTR 30 · payload sha256 33ebf6c6d4da…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
TERTR 30
Operator note: flexibilityLevel
0%_flex
Operator note: variant
30kv
Operator note: voltage kv
30

Offtake · Load (any) · Available

9 MW

Granted

The operator's latest published dataset reports 9 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2027 (2027) · variant: 30kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2027/TERTR 30 · payload sha256 33ebf6c6d4da…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
TERTR 30
Operator note: flexibilityLevel
5%_flex
Operator note: variant
30kv
Operator note: voltage kv
30

Offtake · Load (any) · Available

12.7 MW

Granted

The operator's latest published dataset reports 12.7 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2027 (2027) · variant: 30kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2027/TERTR 30 · payload sha256 33ebf6c6d4da…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
TERTR 30
Operator note: flexibilityLevel
10%_flex
Operator note: variant
30kv
Operator note: voltage kv
30

Offtake · Load (any) · Available

20 MW

Granted

The operator's latest published dataset reports 20 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2027 (2027) · variant: 30kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2027/TERTR 30 · payload sha256 33ebf6c6d4da…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
TERTR 30
Operator note: flexibilityLevel
20%_flex
Operator note: variant
30kv
Operator note: voltage kv
30

Offtake · Load (any) · Available

4.8 MW

Granted

The operator's latest published dataset reports 4.8 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2031 (2031) · variant: 30kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/TERTR 30 · payload sha256 013d7f39ff14…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
TERTR 30
Operator note: flexibilityLevel
0%_flex
Operator note: variant
30kv
Operator note: voltage kv
30

Offtake · Load (any) · Available

20 MW

Granted

The operator's latest published dataset reports 20 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2031 (2031) · variant: 30kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/TERTR 30 · payload sha256 013d7f39ff14…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
TERTR 30
Operator note: flexibilityLevel
5%_flex
Operator note: variant
30kv
Operator note: voltage kv
30

Offtake · Load (any) · Available

20 MW

Granted

The operator's latest published dataset reports 20 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2031 (2031) · variant: 30kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/TERTR 30 · payload sha256 013d7f39ff14…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
TERTR 30
Operator note: flexibilityLevel
10%_flex
Operator note: variant
30kv
Operator note: voltage kv
30

Offtake · Load (any) · Available

20 MW

Granted

The operator's latest published dataset reports 20 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2031 (2031) · variant: 30kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/TERTR 30 · payload sha256 013d7f39ff14…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
TERTR 30
Operator note: flexibilityLevel
20%_flex
Operator note: variant
30kv
Operator note: voltage kv
30

Bidirectional · Battery · Available

1.3 MW

Granted

The operator's latest published dataset reports 1.3 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2027 (2027) · variant: 30kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2027/TERTR 30 · payload sha256 33ebf6c6d4da…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
TERTR 30
Operator note: flexibilityLevel
0%_flex
Operator note: variant
30kv
Operator note: voltage kv
30

Bidirectional · Battery · Available

8.6 MW

Granted

The operator's latest published dataset reports 8.6 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2027 (2027) · variant: 30kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2027/TERTR 30 · payload sha256 33ebf6c6d4da…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
TERTR 30
Operator note: flexibilityLevel
5%_flex
Operator note: variant
30kv
Operator note: voltage kv
30

Bidirectional · Battery · Available

12.2 MW

Granted

The operator's latest published dataset reports 12.2 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2027 (2027) · variant: 30kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2027/TERTR 30 · payload sha256 33ebf6c6d4da…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
TERTR 30
Operator note: flexibilityLevel
10%_flex
Operator note: variant
30kv
Operator note: voltage kv
30

Bidirectional · Battery · Available

20 MW

Granted

The operator's latest published dataset reports 20 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2027 (2027) · variant: 30kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2027/TERTR 30 · payload sha256 33ebf6c6d4da…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
TERTR 30
Operator note: flexibilityLevel
20%_flex
Operator note: variant
30kv
Operator note: voltage kv
30

Bidirectional · Battery · Available

4.8 MW

Granted

The operator's latest published dataset reports 4.8 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2031 (2031) · variant: 30kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/TERTR 30 · payload sha256 013d7f39ff14…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
TERTR 30
Operator note: flexibilityLevel
0%_flex
Operator note: variant
30kv
Operator note: voltage kv
30

Bidirectional · Battery · Available

20 MW

Granted

The operator's latest published dataset reports 20 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2031 (2031) · variant: 30kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/TERTR 30 · payload sha256 013d7f39ff14…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
TERTR 30
Operator note: flexibilityLevel
5%_flex
Operator note: variant
30kv
Operator note: voltage kv
30

Bidirectional · Battery · Available

20 MW

Granted

The operator's latest published dataset reports 20 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2031 (2031) · variant: 30kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/TERTR 30 · payload sha256 013d7f39ff14…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
TERTR 30
Operator note: flexibilityLevel
10%_flex
Operator note: variant
30kv
Operator note: voltage kv
30

Bidirectional · Battery · Available

20 MW

Granted

The operator's latest published dataset reports 20 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2031 (2031) · variant: 30kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/TERTR 30 · payload sha256 013d7f39ff14…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
TERTR 30
Operator note: flexibilityLevel
20%_flex
Operator note: variant
30kv
Operator note: voltage kv
30

History

Served series only

Bidirectional · Battery · Available · 2027

current 1.3 MW

26 Sep 2026: 1.3 MW
26 Sep 2026range 1.3 to 1.3 MW2 Oct 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current1.3 MW

Time axis: when we observed each value, not the operator’s effective date.

Bidirectional · Battery · Available · 2027

current 8.6 MW

26 Sep 2026: 8.6 MW
26 Sep 2026range 8.6 to 8.6 MW2 Oct 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current8.6 MW

Time axis: when we observed each value, not the operator’s effective date.

Bidirectional · Battery · Available · 2027

current 12.2 MW

26 Sep 2026: 12.2 MW
26 Sep 2026range 12.2 to 12.2 MW2 Oct 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current12.2 MW

Time axis: when we observed each value, not the operator’s effective date.

Bidirectional · Battery · Available · 2027

current 20 MW

26 Sep 2026: 20 MW
26 Sep 2026range 20 to 20 MW2 Oct 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current20 MW

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Load (any) · Available · 2027

current 1.8 MW

26 Sep 2026: 1.8 MW
26 Sep 2026range 1.8 to 1.8 MW2 Oct 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current1.8 MW

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Load (any) · Available · 2027

current 9 MW

26 Sep 2026: 9 MW
26 Sep 2026range 9 to 9 MW2 Oct 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current9 MW

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Load (any) · Available · 2027

current 12.7 MW

26 Sep 2026: 12.7 MW
26 Sep 2026range 12.7 to 12.7 MW2 Oct 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current12.7 MW

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Load (any) · Available · 2027

current 20 MW

26 Sep 2026: 20 MW
26 Sep 2026range 20 to 20 MW2 Oct 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current20 MW

Time axis: when we observed each value, not the operator’s effective date.

Injection · Generation (any) · Available · 2027

current 8.5 MW

26 Sep 2026: 8.5 MW
26 Sep 2026range 8.5 to 8.5 MW2 Oct 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current8.5 MW

Time axis: when we observed each value, not the operator’s effective date.

Injection · Generation (any) · Available · 2027

current 20 MW

26 Sep 2026: 20 MW
26 Sep 2026range 20 to 20 MW2 Oct 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current20 MW

Time axis: when we observed each value, not the operator’s effective date.

Injection · Generation (any) · Available · 2027

current 20 MW

26 Sep 2026: 20 MW
26 Sep 2026range 20 to 20 MW2 Oct 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current20 MW

Time axis: when we observed each value, not the operator’s effective date.

Injection · Generation (any) · Available · 2027

current 20 MW

26 Sep 2026: 20 MW
26 Sep 2026range 20 to 20 MW2 Oct 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current20 MW

Time axis: when we observed each value, not the operator’s effective date.

The first 12 of 40 served series with a history. The history route returns every one of them.