| Injection | Generation (any) | Available | 11.7 MW | Firm, ≤ 0 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Injection | Generation (any) | Available | 128.8 MW | Flexible, ≤ 5 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Injection | Generation (any) | Available | 175 MW | Flexible, ≤ 10 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Injection | Generation (any) | Available | 175 MW | Flexible, ≤ 20 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Injection | Generation (any) | Available | 175 MW | Firm, ≤ 0 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |
| Injection | Generation (any) | Available | 175 MW | Flexible, ≤ 5 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |
| Injection | Generation (any) | Available | 175 MW | Flexible, ≤ 10 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |
| Injection | Generation (any) | Available | 175 MW | Flexible, ≤ 20 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |
| Injection | Solar PV | Available | 175 MW | Firm, ≤ 0 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Injection | Solar PV | Available | 175 MW | Flexible, ≤ 5 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Injection | Solar PV | Available | 175 MW | Flexible, ≤ 10 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Injection | Solar PV | Available | 175 MW | Flexible, ≤ 20 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Injection | Solar PV | Available | 175 MW | Firm, ≤ 0 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |
| Injection | Solar PV | Available | 175 MW | Flexible, ≤ 5 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |
| Injection | Solar PV | Available | 175 MW | Flexible, ≤ 10 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |
| Injection | Solar PV | Available | 175 MW | Flexible, ≤ 20 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |
| Injection | Onshore wind | Available | 72.5 MW | Firm, ≤ 0 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Injection | Onshore wind | Available | 175 MW | Flexible, ≤ 5 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Injection | Onshore wind | Available | 175 MW | Flexible, ≤ 10 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Injection | Onshore wind | Available | 175 MW | Flexible, ≤ 20 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Injection | Onshore wind | Available | 175 MW | Firm, ≤ 0 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |
| Injection | Onshore wind | Available | 175 MW | Flexible, ≤ 5 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |
| Injection | Onshore wind | Available | 175 MW | Flexible, ≤ 10 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |
| Injection | Onshore wind | Available | 175 MW | Flexible, ≤ 20 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |
| Offtake | Load (any) | Available | 7.9 MW | Firm, ≤ 0 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Offtake | Load (any) | Available | 14.1 MW | Flexible, ≤ 5 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Offtake | Load (any) | Available | 17 MW | Flexible, ≤ 10 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Offtake | Load (any) | Available | 21.5 MW | Flexible, ≤ 20 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Offtake | Load (any) | Available | 22.9 MW | Firm, ≤ 0 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |
| Offtake | Load (any) | Available | 40.2 MW | Flexible, ≤ 5 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |
| Offtake | Load (any) | Available | 55.3 MW | Flexible, ≤ 10 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |
| Offtake | Load (any) | Available | 97.4 MW | Flexible, ≤ 20 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |
| Bidirectional | Battery | Available | 7.7 MW | Firm, ≤ 0 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Bidirectional | Battery | Available | 13.9 MW | Flexible, ≤ 5 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Bidirectional | Battery | Available | 16.7 MW | Flexible, ≤ 10 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Bidirectional | Battery | Available | 20.1 MW | Flexible, ≤ 20 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Bidirectional | Battery | Available | 18.2 MW | Firm, ≤ 0 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |
| Bidirectional | Battery | Available | 28.4 MW | Flexible, ≤ 5 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |
| Bidirectional | Battery | Available | 35.1 MW | Flexible, ≤ 10 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |
| Bidirectional | Battery | Available | 48.5 MW | Flexible, ≤ 20 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |