| Injection | Generation (any) | Available | 8.7 MW | Firm, ≤ 0 % curtailment a year | 2027 (2027)variant: 150kv | 26 Sep 2026 |
| Injection | Generation (any) | Available | 13.4 MW | Flexible, ≤ 5 % curtailment a year | 2027 (2027)variant: 150kv | 26 Sep 2026 |
| Injection | Generation (any) | Available | 20.2 MW | Flexible, ≤ 10 % curtailment a year | 2027 (2027)variant: 150kv | 26 Sep 2026 |
| Injection | Generation (any) | Available | 28.2 MW | Flexible, ≤ 20 % curtailment a year | 2027 (2027)variant: 150kv | 26 Sep 2026 |
| Injection | Generation (any) | Available | 8.9 MW | Firm, ≤ 0 % curtailment a year | 2031 (2031)variant: 150kv | 26 Sep 2026 |
| Injection | Generation (any) | Available | 15.5 MW | Flexible, ≤ 5 % curtailment a year | 2031 (2031)variant: 150kv | 26 Sep 2026 |
| Injection | Generation (any) | Available | 24.2 MW | Flexible, ≤ 10 % curtailment a year | 2031 (2031)variant: 150kv | 26 Sep 2026 |
| Injection | Generation (any) | Available | 31.2 MW | Flexible, ≤ 20 % curtailment a year | 2031 (2031)variant: 150kv | 26 Sep 2026 |
| Injection | Solar PV | Available | 18.3 MW | Firm, ≤ 0 % curtailment a year | 2027 (2027)variant: 150kv | 26 Sep 2026 |
| Injection | Solar PV | Available | 40.7 MW | Flexible, ≤ 5 % curtailment a year | 2027 (2027)variant: 150kv | 26 Sep 2026 |
| Injection | Solar PV | Available | 48.9 MW | Flexible, ≤ 10 % curtailment a year | 2027 (2027)variant: 150kv | 26 Sep 2026 |
| Injection | Solar PV | Available | 66.6 MW | Flexible, ≤ 20 % curtailment a year | 2027 (2027)variant: 150kv | 26 Sep 2026 |
| Injection | Solar PV | Available | 18.3 MW | Firm, ≤ 0 % curtailment a year | 2031 (2031)variant: 150kv | 26 Sep 2026 |
| Injection | Solar PV | Available | 44.8 MW | Flexible, ≤ 5 % curtailment a year | 2031 (2031)variant: 150kv | 26 Sep 2026 |
| Injection | Solar PV | Available | 54 MW | Flexible, ≤ 10 % curtailment a year | 2031 (2031)variant: 150kv | 26 Sep 2026 |
| Injection | Solar PV | Available | 76.3 MW | Flexible, ≤ 20 % curtailment a year | 2031 (2031)variant: 150kv | 26 Sep 2026 |
| Injection | Onshore wind | Available | 10.3 MW | Firm, ≤ 0 % curtailment a year | 2027 (2027)variant: 150kv | 26 Sep 2026 |
| Injection | Onshore wind | Available | 23.2 MW | Flexible, ≤ 5 % curtailment a year | 2027 (2027)variant: 150kv | 26 Sep 2026 |
| Injection | Onshore wind | Available | 39.8 MW | Flexible, ≤ 10 % curtailment a year | 2027 (2027)variant: 150kv | 26 Sep 2026 |
| Injection | Onshore wind | Available | 59.6 MW | Flexible, ≤ 20 % curtailment a year | 2027 (2027)variant: 150kv | 26 Sep 2026 |
| Injection | Onshore wind | Available | 10.3 MW | Firm, ≤ 0 % curtailment a year | 2031 (2031)variant: 150kv | 26 Sep 2026 |
| Injection | Onshore wind | Available | 24 MW | Flexible, ≤ 5 % curtailment a year | 2031 (2031)variant: 150kv | 26 Sep 2026 |
| Injection | Onshore wind | Available | 41.8 MW | Flexible, ≤ 10 % curtailment a year | 2031 (2031)variant: 150kv | 26 Sep 2026 |
| Injection | Onshore wind | Available | 66.5 MW | Flexible, ≤ 20 % curtailment a year | 2031 (2031)variant: 150kv | 26 Sep 2026 |
| Offtake | Load (any) | Available | 3.3 MW | Firm, ≤ 0 % curtailment a year | 2027 (2027)variant: 150kv | 26 Sep 2026 |
| Offtake | Load (any) | Available | 4 MW | Flexible, ≤ 5 % curtailment a year | 2027 (2027)variant: 150kv | 26 Sep 2026 |
| Offtake | Load (any) | Available | 4.6 MW | Flexible, ≤ 10 % curtailment a year | 2027 (2027)variant: 150kv | 26 Sep 2026 |
| Offtake | Load (any) | Available | 6.5 MW | Flexible, ≤ 20 % curtailment a year | 2027 (2027)variant: 150kv | 26 Sep 2026 |
| Offtake | Load (any) | Available | 3.3 MW | Firm, ≤ 0 % curtailment a year | 2031 (2031)variant: 150kv | 26 Sep 2026 |
| Offtake | Load (any) | Available | 4.3 MW | Flexible, ≤ 5 % curtailment a year | 2031 (2031)variant: 150kv | 26 Sep 2026 |
| Offtake | Load (any) | Available | 5.5 MW | Flexible, ≤ 10 % curtailment a year | 2031 (2031)variant: 150kv | 26 Sep 2026 |
| Offtake | Load (any) | Available | 9.4 MW | Flexible, ≤ 20 % curtailment a year | 2031 (2031)variant: 150kv | 26 Sep 2026 |
| Bidirectional | Battery | Available | 3.3 MW | Firm, ≤ 0 % curtailment a year | 2027 (2027)variant: 150kv | 26 Sep 2026 |
| Bidirectional | Battery | Available | 4 MW | Flexible, ≤ 5 % curtailment a year | 2027 (2027)variant: 150kv | 26 Sep 2026 |
| Bidirectional | Battery | Available | 4.5 MW | Flexible, ≤ 10 % curtailment a year | 2027 (2027)variant: 150kv | 26 Sep 2026 |
| Bidirectional | Battery | Available | 6.2 MW | Flexible, ≤ 20 % curtailment a year | 2027 (2027)variant: 150kv | 26 Sep 2026 |
| Bidirectional | Battery | Available | 3.3 MW | Firm, ≤ 0 % curtailment a year | 2031 (2031)variant: 150kv | 26 Sep 2026 |
| Bidirectional | Battery | Available | 4.1 MW | Flexible, ≤ 5 % curtailment a year | 2031 (2031)variant: 150kv | 26 Sep 2026 |
| Bidirectional | Battery | Available | 5 MW | Flexible, ≤ 10 % curtailment a year | 2031 (2031)variant: 150kv | 26 Sep 2026 |
| Bidirectional | Battery | Available | 7.7 MW | Flexible, ≤ 20 % curtailment a year | 2031 (2031)variant: 150kv | 26 Sep 2026 |