Substation / 220 kV

SERAI

Elia Transmission Belgium / Belgium

Latest published values

40 served · 0 withheld

Each row is what the operator’s latest published dataset reports for one combination of direction, technology, measure, firmness and horizon. Hosting-capacity figures are indicative and reflect what operators publish. They are not a connection offer; only the operator can confirm capacity for a specific request.

Latest published capacity values, one row per series
DirectionTechnologyMeasureValueFirmnessHorizonSource date
InjectionGeneration (any)Available18.9 MWFirm, ≤ 0 % curtailment a year2029 (2029)variant: 220kv17 Nov 2026
InjectionGeneration (any)Available51.3 MWFlexible, ≤ 5 % curtailment a year2029 (2029)variant: 220kv17 Nov 2026
InjectionGeneration (any)Available170.7 MWFlexible, ≤ 10 % curtailment a year2029 (2029)variant: 220kv17 Nov 2026
InjectionGeneration (any)Available175 MWFlexible, ≤ 20 % curtailment a year2029 (2029)variant: 220kv17 Nov 2026
InjectionGeneration (any)Available18.9 MWFirm, ≤ 0 % curtailment a year2033 (2033)variant: 220kv17 Nov 2026
InjectionGeneration (any)Available51.3 MWFlexible, ≤ 5 % curtailment a year2033 (2033)variant: 220kv17 Nov 2026
InjectionGeneration (any)Available170.7 MWFlexible, ≤ 10 % curtailment a year2033 (2033)variant: 220kv17 Nov 2026
InjectionGeneration (any)Available175 MWFlexible, ≤ 20 % curtailment a year2033 (2033)variant: 220kv17 Nov 2026
InjectionSolar PVAvailable65.3 MWFirm, ≤ 0 % curtailment a year2029 (2029)variant: 220kv17 Nov 2026
InjectionSolar PVAvailable175 MWFlexible, ≤ 5 % curtailment a year2029 (2029)variant: 220kv17 Nov 2026
InjectionSolar PVAvailable175 MWFlexible, ≤ 10 % curtailment a year2029 (2029)variant: 220kv17 Nov 2026
InjectionSolar PVAvailable175 MWFlexible, ≤ 20 % curtailment a year2029 (2029)variant: 220kv17 Nov 2026
InjectionSolar PVAvailable175 MWFirm, ≤ 0 % curtailment a year2033 (2033)variant: 220kv17 Nov 2026
InjectionSolar PVAvailable175 MWFlexible, ≤ 5 % curtailment a year2033 (2033)variant: 220kv17 Nov 2026
InjectionSolar PVAvailable175 MWFlexible, ≤ 10 % curtailment a year2033 (2033)variant: 220kv17 Nov 2026
InjectionSolar PVAvailable175 MWFlexible, ≤ 20 % curtailment a year2033 (2033)variant: 220kv17 Nov 2026
InjectionOnshore windAvailable175 MWFirm, ≤ 0 % curtailment a year2029 (2029)variant: 220kv17 Nov 2026
InjectionOnshore windAvailable175 MWFlexible, ≤ 5 % curtailment a year2029 (2029)variant: 220kv17 Nov 2026
InjectionOnshore windAvailable175 MWFlexible, ≤ 10 % curtailment a year2029 (2029)variant: 220kv17 Nov 2026
InjectionOnshore windAvailable175 MWFlexible, ≤ 20 % curtailment a year2029 (2029)variant: 220kv17 Nov 2026
InjectionOnshore windAvailable175 MWFirm, ≤ 0 % curtailment a year2033 (2033)variant: 220kv17 Nov 2026
InjectionOnshore windAvailable175 MWFlexible, ≤ 5 % curtailment a year2033 (2033)variant: 220kv17 Nov 2026
InjectionOnshore windAvailable175 MWFlexible, ≤ 10 % curtailment a year2033 (2033)variant: 220kv17 Nov 2026
InjectionOnshore windAvailable175 MWFlexible, ≤ 20 % curtailment a year2033 (2033)variant: 220kv17 Nov 2026
OfftakeLoad (any)Available22.9 MWFirm, ≤ 0 % curtailment a year2029 (2029)variant: 220kv17 Nov 2026
OfftakeLoad (any)Available42.6 MWFlexible, ≤ 5 % curtailment a year2029 (2029)variant: 220kv17 Nov 2026
OfftakeLoad (any)Available102 MWFlexible, ≤ 10 % curtailment a year2029 (2029)variant: 220kv17 Nov 2026
OfftakeLoad (any)Available175 MWFlexible, ≤ 20 % curtailment a year2029 (2029)variant: 220kv17 Nov 2026
OfftakeLoad (any)Available175 MWFirm, ≤ 0 % curtailment a year2033 (2033)variant: 220kv17 Nov 2026
OfftakeLoad (any)Available175 MWFlexible, ≤ 5 % curtailment a year2033 (2033)variant: 220kv17 Nov 2026
OfftakeLoad (any)Available175 MWFlexible, ≤ 10 % curtailment a year2033 (2033)variant: 220kv17 Nov 2026
OfftakeLoad (any)Available175 MWFlexible, ≤ 20 % curtailment a year2033 (2033)variant: 220kv17 Nov 2026
BidirectionalBatteryAvailable18.9 MWFirm, ≤ 0 % curtailment a year2029 (2029)variant: 220kv17 Nov 2026
BidirectionalBatteryAvailable36.7 MWFlexible, ≤ 5 % curtailment a year2029 (2029)variant: 220kv17 Nov 2026
BidirectionalBatteryAvailable74.4 MWFlexible, ≤ 10 % curtailment a year2029 (2029)variant: 220kv17 Nov 2026
BidirectionalBatteryAvailable175 MWFlexible, ≤ 20 % curtailment a year2029 (2029)variant: 220kv17 Nov 2026
BidirectionalBatteryAvailable18.9 MWFirm, ≤ 0 % curtailment a year2033 (2033)variant: 220kv17 Nov 2026
BidirectionalBatteryAvailable51.3 MWFlexible, ≤ 5 % curtailment a year2033 (2033)variant: 220kv17 Nov 2026
BidirectionalBatteryAvailable170.7 MWFlexible, ≤ 10 % curtailment a year2033 (2033)variant: 220kv17 Nov 2026
BidirectionalBatteryAvailable175 MWFlexible, ≤ 20 % curtailment a year2033 (2033)variant: 220kv17 Nov 2026

Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map

What each value means

Methodology, both clocks, provenance and rights

Injection · Generation (any) · Available

18.9 MW

Granted

The operator's latest published dataset reports 18.9 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2029 (2029) · variant: 220kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/SERAI220 · payload sha256 d6071fc5b23c…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
SERAI220
Operator note: flexibilityLevel
0%_flex
Operator note: variant
220kv
Operator note: voltage kv
220

Injection · Generation (any) · Available

51.3 MW

Granted

The operator's latest published dataset reports 51.3 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2029 (2029) · variant: 220kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/SERAI220 · payload sha256 d6071fc5b23c…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
SERAI220
Operator note: flexibilityLevel
5%_flex
Operator note: variant
220kv
Operator note: voltage kv
220

Injection · Generation (any) · Available

170.7 MW

Granted

The operator's latest published dataset reports 170.7 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2029 (2029) · variant: 220kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/SERAI220 · payload sha256 d6071fc5b23c…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
SERAI220
Operator note: flexibilityLevel
10%_flex
Operator note: variant
220kv
Operator note: voltage kv
220

Injection · Generation (any) · Available

175 MW

Granted

The operator's latest published dataset reports 175 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2029 (2029) · variant: 220kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/SERAI220 · payload sha256 d6071fc5b23c…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
SERAI220
Operator note: flexibilityLevel
20%_flex
Operator note: variant
220kv
Operator note: voltage kv
220

Injection · Generation (any) · Available

18.9 MW

Granted

The operator's latest published dataset reports 18.9 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2033 (2033) · variant: 220kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/SERAI220 · payload sha256 e61bd29f26f7…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
SERAI220
Operator note: flexibilityLevel
0%_flex
Operator note: variant
220kv
Operator note: voltage kv
220

Injection · Generation (any) · Available

51.3 MW

Granted

The operator's latest published dataset reports 51.3 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2033 (2033) · variant: 220kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/SERAI220 · payload sha256 e61bd29f26f7…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
SERAI220
Operator note: flexibilityLevel
5%_flex
Operator note: variant
220kv
Operator note: voltage kv
220

Injection · Generation (any) · Available

170.7 MW

Granted

The operator's latest published dataset reports 170.7 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2033 (2033) · variant: 220kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/SERAI220 · payload sha256 e61bd29f26f7…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
SERAI220
Operator note: flexibilityLevel
10%_flex
Operator note: variant
220kv
Operator note: voltage kv
220

Injection · Generation (any) · Available

175 MW

Granted

The operator's latest published dataset reports 175 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2033 (2033) · variant: 220kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/SERAI220 · payload sha256 e61bd29f26f7…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
SERAI220
Operator note: flexibilityLevel
20%_flex
Operator note: variant
220kv
Operator note: voltage kv
220

Injection · Solar PV · Available

65.3 MW

Granted

The operator's latest published dataset reports 65.3 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2029 (2029) · variant: 220kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/SERAI220 · payload sha256 d6071fc5b23c…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
SERAI220
Operator note: flexibilityLevel
0%_flex
Operator note: variant
220kv
Operator note: voltage kv
220

Injection · Solar PV · Available

175 MW

Granted

The operator's latest published dataset reports 175 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2029 (2029) · variant: 220kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/SERAI220 · payload sha256 d6071fc5b23c…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
SERAI220
Operator note: flexibilityLevel
5%_flex
Operator note: variant
220kv
Operator note: voltage kv
220

Injection · Solar PV · Available

175 MW

Granted

The operator's latest published dataset reports 175 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2029 (2029) · variant: 220kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/SERAI220 · payload sha256 d6071fc5b23c…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
SERAI220
Operator note: flexibilityLevel
10%_flex
Operator note: variant
220kv
Operator note: voltage kv
220

Injection · Solar PV · Available

175 MW

Granted

The operator's latest published dataset reports 175 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2029 (2029) · variant: 220kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/SERAI220 · payload sha256 d6071fc5b23c…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
SERAI220
Operator note: flexibilityLevel
20%_flex
Operator note: variant
220kv
Operator note: voltage kv
220

Injection · Solar PV · Available

175 MW

Granted

The operator's latest published dataset reports 175 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2033 (2033) · variant: 220kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/SERAI220 · payload sha256 e61bd29f26f7…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
SERAI220
Operator note: flexibilityLevel
0%_flex
Operator note: variant
220kv
Operator note: voltage kv
220

Injection · Solar PV · Available

175 MW

Granted

The operator's latest published dataset reports 175 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2033 (2033) · variant: 220kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/SERAI220 · payload sha256 e61bd29f26f7…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
SERAI220
Operator note: flexibilityLevel
5%_flex
Operator note: variant
220kv
Operator note: voltage kv
220

Injection · Solar PV · Available

175 MW

Granted

The operator's latest published dataset reports 175 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2033 (2033) · variant: 220kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/SERAI220 · payload sha256 e61bd29f26f7…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
SERAI220
Operator note: flexibilityLevel
10%_flex
Operator note: variant
220kv
Operator note: voltage kv
220

Injection · Solar PV · Available

175 MW

Granted

The operator's latest published dataset reports 175 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2033 (2033) · variant: 220kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/SERAI220 · payload sha256 e61bd29f26f7…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
SERAI220
Operator note: flexibilityLevel
20%_flex
Operator note: variant
220kv
Operator note: voltage kv
220

Injection · Onshore wind · Available

175 MW

Granted

The operator's latest published dataset reports 175 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2029 (2029) · variant: 220kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/SERAI220 · payload sha256 d6071fc5b23c…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
SERAI220
Operator note: flexibilityLevel
0%_flex
Operator note: variant
220kv
Operator note: voltage kv
220

Injection · Onshore wind · Available

175 MW

Granted

The operator's latest published dataset reports 175 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2029 (2029) · variant: 220kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/SERAI220 · payload sha256 d6071fc5b23c…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
SERAI220
Operator note: flexibilityLevel
5%_flex
Operator note: variant
220kv
Operator note: voltage kv
220

Injection · Onshore wind · Available

175 MW

Granted

The operator's latest published dataset reports 175 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2029 (2029) · variant: 220kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/SERAI220 · payload sha256 d6071fc5b23c…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
SERAI220
Operator note: flexibilityLevel
10%_flex
Operator note: variant
220kv
Operator note: voltage kv
220

Injection · Onshore wind · Available

175 MW

Granted

The operator's latest published dataset reports 175 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2029 (2029) · variant: 220kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/SERAI220 · payload sha256 d6071fc5b23c…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
SERAI220
Operator note: flexibilityLevel
20%_flex
Operator note: variant
220kv
Operator note: voltage kv
220

Injection · Onshore wind · Available

175 MW

Granted

The operator's latest published dataset reports 175 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2033 (2033) · variant: 220kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/SERAI220 · payload sha256 e61bd29f26f7…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
SERAI220
Operator note: flexibilityLevel
0%_flex
Operator note: variant
220kv
Operator note: voltage kv
220

Injection · Onshore wind · Available

175 MW

Granted

The operator's latest published dataset reports 175 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2033 (2033) · variant: 220kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/SERAI220 · payload sha256 e61bd29f26f7…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
SERAI220
Operator note: flexibilityLevel
5%_flex
Operator note: variant
220kv
Operator note: voltage kv
220

Injection · Onshore wind · Available

175 MW

Granted

The operator's latest published dataset reports 175 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2033 (2033) · variant: 220kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/SERAI220 · payload sha256 e61bd29f26f7…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
SERAI220
Operator note: flexibilityLevel
10%_flex
Operator note: variant
220kv
Operator note: voltage kv
220

Injection · Onshore wind · Available

175 MW

Granted

The operator's latest published dataset reports 175 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2033 (2033) · variant: 220kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/SERAI220 · payload sha256 e61bd29f26f7…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
SERAI220
Operator note: flexibilityLevel
20%_flex
Operator note: variant
220kv
Operator note: voltage kv
220

Offtake · Load (any) · Available

22.9 MW

Granted

The operator's latest published dataset reports 22.9 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2029 (2029) · variant: 220kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/SERAI220 · payload sha256 d6071fc5b23c…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
SERAI220
Operator note: flexibilityLevel
0%_flex
Operator note: variant
220kv
Operator note: voltage kv
220

Offtake · Load (any) · Available

42.6 MW

Granted

The operator's latest published dataset reports 42.6 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2029 (2029) · variant: 220kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/SERAI220 · payload sha256 d6071fc5b23c…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
SERAI220
Operator note: flexibilityLevel
5%_flex
Operator note: variant
220kv
Operator note: voltage kv
220

Offtake · Load (any) · Available

102 MW

Granted

The operator's latest published dataset reports 102 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2029 (2029) · variant: 220kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/SERAI220 · payload sha256 d6071fc5b23c…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
SERAI220
Operator note: flexibilityLevel
10%_flex
Operator note: variant
220kv
Operator note: voltage kv
220

Offtake · Load (any) · Available

175 MW

Granted

The operator's latest published dataset reports 175 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2029 (2029) · variant: 220kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/SERAI220 · payload sha256 d6071fc5b23c…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
SERAI220
Operator note: flexibilityLevel
20%_flex
Operator note: variant
220kv
Operator note: voltage kv
220

Offtake · Load (any) · Available

175 MW

Granted

The operator's latest published dataset reports 175 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2033 (2033) · variant: 220kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/SERAI220 · payload sha256 e61bd29f26f7…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
SERAI220
Operator note: flexibilityLevel
0%_flex
Operator note: variant
220kv
Operator note: voltage kv
220

Offtake · Load (any) · Available

175 MW

Granted

The operator's latest published dataset reports 175 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2033 (2033) · variant: 220kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/SERAI220 · payload sha256 e61bd29f26f7…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
SERAI220
Operator note: flexibilityLevel
5%_flex
Operator note: variant
220kv
Operator note: voltage kv
220

Offtake · Load (any) · Available

175 MW

Granted

The operator's latest published dataset reports 175 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2033 (2033) · variant: 220kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/SERAI220 · payload sha256 e61bd29f26f7…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
SERAI220
Operator note: flexibilityLevel
10%_flex
Operator note: variant
220kv
Operator note: voltage kv
220

Offtake · Load (any) · Available

175 MW

Granted

The operator's latest published dataset reports 175 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2033 (2033) · variant: 220kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/SERAI220 · payload sha256 e61bd29f26f7…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
SERAI220
Operator note: flexibilityLevel
20%_flex
Operator note: variant
220kv
Operator note: voltage kv
220

Bidirectional · Battery · Available

18.9 MW

Granted

The operator's latest published dataset reports 18.9 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2029 (2029) · variant: 220kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/SERAI220 · payload sha256 d6071fc5b23c…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
SERAI220
Operator note: flexibilityLevel
0%_flex
Operator note: variant
220kv
Operator note: voltage kv
220

Bidirectional · Battery · Available

36.7 MW

Granted

The operator's latest published dataset reports 36.7 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2029 (2029) · variant: 220kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/SERAI220 · payload sha256 d6071fc5b23c…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
SERAI220
Operator note: flexibilityLevel
5%_flex
Operator note: variant
220kv
Operator note: voltage kv
220

Bidirectional · Battery · Available

74.4 MW

Granted

The operator's latest published dataset reports 74.4 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2029 (2029) · variant: 220kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/SERAI220 · payload sha256 d6071fc5b23c…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
SERAI220
Operator note: flexibilityLevel
10%_flex
Operator note: variant
220kv
Operator note: voltage kv
220

Bidirectional · Battery · Available

175 MW

Granted

The operator's latest published dataset reports 175 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2029 (2029) · variant: 220kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/SERAI220 · payload sha256 d6071fc5b23c…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
SERAI220
Operator note: flexibilityLevel
20%_flex
Operator note: variant
220kv
Operator note: voltage kv
220

Bidirectional · Battery · Available

18.9 MW

Granted

The operator's latest published dataset reports 18.9 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2033 (2033) · variant: 220kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/SERAI220 · payload sha256 e61bd29f26f7…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
SERAI220
Operator note: flexibilityLevel
0%_flex
Operator note: variant
220kv
Operator note: voltage kv
220

Bidirectional · Battery · Available

51.3 MW

Granted

The operator's latest published dataset reports 51.3 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2033 (2033) · variant: 220kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/SERAI220 · payload sha256 e61bd29f26f7…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
SERAI220
Operator note: flexibilityLevel
5%_flex
Operator note: variant
220kv
Operator note: voltage kv
220

Bidirectional · Battery · Available

170.7 MW

Granted

The operator's latest published dataset reports 170.7 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2033 (2033) · variant: 220kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/SERAI220 · payload sha256 e61bd29f26f7…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
SERAI220
Operator note: flexibilityLevel
10%_flex
Operator note: variant
220kv
Operator note: voltage kv
220

Bidirectional · Battery · Available

175 MW

Granted

The operator's latest published dataset reports 175 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2033 (2033) · variant: 220kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/SERAI220 · payload sha256 e61bd29f26f7…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
SERAI220
Operator note: flexibilityLevel
20%_flex
Operator note: variant
220kv
Operator note: voltage kv
220

History

Served series only

Bidirectional · Battery · Available · 2027

last, until 17 Nov 2026: 6.6 MW

26 Sep 2026: 6.6 MW
26 Sep 2026range 6.6 to 6.6 MW24 Nov 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 202617 Nov 20266.6 MW

Time axis: when we observed each value, not the operator’s effective date.

Bidirectional · Battery · Available · 2027

last, until 17 Nov 2026: 19.2 MW

26 Sep 2026: 19.5 MW17 Oct 2026: 19.2 MW
26 Sep 2026range 19.2 to 19.5 MW24 Nov 2026
2 published values, as a table
Observed fromUntilValue
26 Sep 202617 Oct 202619.5 MW
17 Oct 202617 Nov 202619.2 MW

Time axis: when we observed each value, not the operator’s effective date.

Bidirectional · Battery · Available · 2027

last, until 17 Nov 2026: 23 MW

26 Sep 2026: 23.1 MW17 Oct 2026: 23 MW
26 Sep 2026range 23 to 23.1 MW24 Nov 2026
2 published values, as a table
Observed fromUntilValue
26 Sep 202617 Oct 202623.1 MW
17 Oct 202617 Nov 202623 MW

Time axis: when we observed each value, not the operator’s effective date.

Bidirectional · Battery · Available · 2027

last, until 17 Nov 2026: 31.3 MW

26 Sep 2026: 31.4 MW17 Oct 2026: 31.3 MW
26 Sep 2026range 31.3 to 31.4 MW24 Nov 2026
2 published values, as a table
Observed fromUntilValue
26 Sep 202617 Oct 202631.4 MW
17 Oct 202617 Nov 202631.3 MW

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Load (any) · Available · 2027

last, until 17 Nov 2026: 6.6 MW

26 Sep 2026: 6.6 MW
26 Sep 2026range 6.6 to 6.6 MW24 Nov 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 202617 Nov 20266.6 MW

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Load (any) · Available · 2027

last, until 17 Nov 2026: 23 MW

26 Sep 2026: 25.8 MW17 Oct 2026: 23 MW
26 Sep 2026range 23 to 25.8 MW24 Nov 2026
2 published values, as a table
Observed fromUntilValue
26 Sep 202617 Oct 202625.8 MW
17 Oct 202617 Nov 202623 MW

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Load (any) · Available · 2027

last, until 17 Nov 2026: 31.7 MW

26 Sep 2026: 35 MW17 Oct 2026: 31.7 MW
26 Sep 2026range 31.7 to 35 MW24 Nov 2026
2 published values, as a table
Observed fromUntilValue
26 Sep 202617 Oct 202635 MW
17 Oct 202617 Nov 202631.7 MW

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Load (any) · Available · 2027

last, until 17 Nov 2026: 62.1 MW

26 Sep 2026: 69.7 MW17 Oct 2026: 62.1 MW
26 Sep 2026range 62.1 to 69.7 MW24 Nov 2026
2 published values, as a table
Observed fromUntilValue
26 Sep 202617 Oct 202669.7 MW
17 Oct 202617 Nov 202662.1 MW

Time axis: when we observed each value, not the operator’s effective date.

Injection · Generation (any) · Available · 2027

last, until 17 Nov 2026: 11.1 MW

26 Sep 2026: 11 MW17 Oct 2026: 11.1 MW
26 Sep 2026range 11 to 11.1 MW24 Nov 2026
2 published values, as a table
Observed fromUntilValue
26 Sep 202617 Oct 202611 MW
17 Oct 202617 Nov 202611.1 MW

Time axis: when we observed each value, not the operator’s effective date.

Injection · Generation (any) · Available · 2027

last, until 17 Nov 2026: 36.8 MW

26 Sep 2026: 33.2 MW17 Oct 2026: 36.8 MW
26 Sep 2026range 33.2 to 36.8 MW24 Nov 2026
2 published values, as a table
Observed fromUntilValue
26 Sep 202617 Oct 202633.2 MW
17 Oct 202617 Nov 202636.8 MW

Time axis: when we observed each value, not the operator’s effective date.

Injection · Generation (any) · Available · 2027

last, until 17 Nov 2026: 89.1 MW

26 Sep 2026: 79.2 MW17 Oct 2026: 89.1 MW
26 Sep 2026range 79.2 to 89.1 MW24 Nov 2026
2 published values, as a table
Observed fromUntilValue
26 Sep 202617 Oct 202679.2 MW
17 Oct 202617 Nov 202689.1 MW

Time axis: when we observed each value, not the operator’s effective date.

Injection · Generation (any) · Available · 2027

last, until 17 Nov 2026: 175 MW

26 Sep 2026: 175 MW
26 Sep 2026range 175 to 175 MW24 Nov 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 202617 Nov 2026175 MW

Time axis: when we observed each value, not the operator’s effective date.

The first 12 of 80 served series with a history. The history route returns every one of them.

Through the API

curl "https://api.gridcapacityapi.com/v1/substations/sub_06gdrm9mg5rqdaf3wfjh0x3hr0/capacity" \  -H "Authorization: Bearer gc_live_..."