| Injection | Generation (any) | Available | 5.5 MW | Firm, ≤ 0 % curtailment a year | 2027 (2027)variant: 70kv | 26 Sep 2026 |
| Injection | Generation (any) | Available | 9 MW | Flexible, ≤ 5 % curtailment a year | 2027 (2027)variant: 70kv | 26 Sep 2026 |
| Injection | Generation (any) | Available | 12 MW | Flexible, ≤ 10 % curtailment a year | 2027 (2027)variant: 70kv | 26 Sep 2026 |
| Injection | Generation (any) | Available | 23.7 MW | Flexible, ≤ 20 % curtailment a year | 2027 (2027)variant: 70kv | 26 Sep 2026 |
| Injection | Generation (any) | Available | 5.5 MW | Firm, ≤ 0 % curtailment a year | 2031 (2031)variant: 70kv | 26 Sep 2026 |
| Injection | Generation (any) | Available | 9 MW | Flexible, ≤ 5 % curtailment a year | 2031 (2031)variant: 70kv | 26 Sep 2026 |
| Injection | Generation (any) | Available | 12 MW | Flexible, ≤ 10 % curtailment a year | 2031 (2031)variant: 70kv | 26 Sep 2026 |
| Injection | Generation (any) | Available | 23.7 MW | Flexible, ≤ 20 % curtailment a year | 2031 (2031)variant: 70kv | 26 Sep 2026 |
| Injection | Solar PV | Available | 12.1 MW | Firm, ≤ 0 % curtailment a year | 2027 (2027)variant: 70kv | 26 Sep 2026 |
| Injection | Solar PV | Available | 50 MW | Flexible, ≤ 5 % curtailment a year | 2027 (2027)variant: 70kv | 26 Sep 2026 |
| Injection | Solar PV | Available | 50 MW | Flexible, ≤ 10 % curtailment a year | 2027 (2027)variant: 70kv | 26 Sep 2026 |
| Injection | Solar PV | Available | 50 MW | Flexible, ≤ 20 % curtailment a year | 2027 (2027)variant: 70kv | 26 Sep 2026 |
| Injection | Solar PV | Available | 12.1 MW | Firm, ≤ 0 % curtailment a year | 2031 (2031)variant: 70kv | 26 Sep 2026 |
| Injection | Solar PV | Available | 50 MW | Flexible, ≤ 5 % curtailment a year | 2031 (2031)variant: 70kv | 26 Sep 2026 |
| Injection | Solar PV | Available | 50 MW | Flexible, ≤ 10 % curtailment a year | 2031 (2031)variant: 70kv | 26 Sep 2026 |
| Injection | Solar PV | Available | 50 MW | Flexible, ≤ 20 % curtailment a year | 2031 (2031)variant: 70kv | 26 Sep 2026 |
| Injection | Onshore wind | Available | 6.6 MW | Firm, ≤ 0 % curtailment a year | 2027 (2027)variant: 70kv | 26 Sep 2026 |
| Injection | Onshore wind | Available | 13.7 MW | Flexible, ≤ 5 % curtailment a year | 2027 (2027)variant: 70kv | 26 Sep 2026 |
| Injection | Onshore wind | Available | 19 MW | Flexible, ≤ 10 % curtailment a year | 2027 (2027)variant: 70kv | 26 Sep 2026 |
| Injection | Onshore wind | Available | 36.6 MW | Flexible, ≤ 20 % curtailment a year | 2027 (2027)variant: 70kv | 26 Sep 2026 |
| Injection | Onshore wind | Available | 8 MW | Firm, ≤ 0 % curtailment a year | 2031 (2031)variant: 70kv | 26 Sep 2026 |
| Injection | Onshore wind | Available | 13.7 MW | Flexible, ≤ 5 % curtailment a year | 2031 (2031)variant: 70kv | 26 Sep 2026 |
| Injection | Onshore wind | Available | 19 MW | Flexible, ≤ 10 % curtailment a year | 2031 (2031)variant: 70kv | 26 Sep 2026 |
| Injection | Onshore wind | Available | 36.6 MW | Flexible, ≤ 20 % curtailment a year | 2031 (2031)variant: 70kv | 26 Sep 2026 |
| Offtake | Load (any) | Available | 1.9 MW | Firm, ≤ 0 % curtailment a year | 2027 (2027)variant: 70kv | 26 Sep 2026 |
| Offtake | Load (any) | Available | 11.9 MW | Flexible, ≤ 5 % curtailment a year | 2027 (2027)variant: 70kv | 26 Sep 2026 |
| Offtake | Load (any) | Available | 19 MW | Flexible, ≤ 10 % curtailment a year | 2027 (2027)variant: 70kv | 26 Sep 2026 |
| Offtake | Load (any) | Available | 33 MW | Flexible, ≤ 20 % curtailment a year | 2027 (2027)variant: 70kv | 26 Sep 2026 |
| Offtake | Load (any) | Available | 1.9 MW | Firm, ≤ 0 % curtailment a year | 2031 (2031)variant: 70kv | 26 Sep 2026 |
| Offtake | Load (any) | Available | 11.9 MW | Flexible, ≤ 5 % curtailment a year | 2031 (2031)variant: 70kv | 26 Sep 2026 |
| Offtake | Load (any) | Available | 19.8 MW | Flexible, ≤ 10 % curtailment a year | 2031 (2031)variant: 70kv | 26 Sep 2026 |
| Offtake | Load (any) | Available | 39.9 MW | Flexible, ≤ 20 % curtailment a year | 2031 (2031)variant: 70kv | 26 Sep 2026 |
| Bidirectional | Battery | Available | 1.1 MW | Firm, ≤ 0 % curtailment a year | 2027 (2027)variant: 70kv | 26 Sep 2026 |
| Bidirectional | Battery | Available | 9 MW | Flexible, ≤ 5 % curtailment a year | 2027 (2027)variant: 70kv | 26 Sep 2026 |
| Bidirectional | Battery | Available | 12 MW | Flexible, ≤ 10 % curtailment a year | 2027 (2027)variant: 70kv | 26 Sep 2026 |
| Bidirectional | Battery | Available | 23.7 MW | Flexible, ≤ 20 % curtailment a year | 2027 (2027)variant: 70kv | 26 Sep 2026 |
| Bidirectional | Battery | Available | 1.1 MW | Firm, ≤ 0 % curtailment a year | 2031 (2031)variant: 70kv | 26 Sep 2026 |
| Bidirectional | Battery | Available | 9 MW | Flexible, ≤ 5 % curtailment a year | 2031 (2031)variant: 70kv | 26 Sep 2026 |
| Bidirectional | Battery | Available | 12 MW | Flexible, ≤ 10 % curtailment a year | 2031 (2031)variant: 70kv | 26 Sep 2026 |
| Bidirectional | Battery | Available | 23.7 MW | Flexible, ≤ 20 % curtailment a year | 2031 (2031)variant: 70kv | 26 Sep 2026 |