Substation / 150 kV

SCHEL

Elia Transmission Belgium / Belgium

Latest published values

80 served · 0 withheld

Each row is what the operator’s latest published dataset reports for one combination of direction, technology, measure, firmness and horizon. Hosting-capacity figures are indicative and reflect what operators publish. They are not a connection offer; only the operator can confirm capacity for a specific request.

Latest published capacity values, one row per series
DirectionTechnologyMeasureValueFirmnessHorizonSource date
InjectionGeneration (any)Available6.7 MWFirm, ≤ 0 % curtailment a year2027 (2027)variant: 150kv26 Sep 2026
InjectionGeneration (any)Available5.3 MWFirm, ≤ 0 % curtailment a year2027 (2027)variant: 70kv26 Sep 2026
InjectionGeneration (any)Available22.2 MWFlexible, ≤ 5 % curtailment a year2027 (2027)variant: 70kv26 Sep 2026
InjectionGeneration (any)Available18.7 MWFlexible, ≤ 5 % curtailment a year2027 (2027)variant: 150kv26 Sep 2026
InjectionGeneration (any)Available24.2 MWFlexible, ≤ 10 % curtailment a year2027 (2027)variant: 70kv26 Sep 2026
InjectionGeneration (any)Available20.5 MWFlexible, ≤ 10 % curtailment a year2027 (2027)variant: 150kv26 Sep 2026
InjectionGeneration (any)Available29 MWFlexible, ≤ 20 % curtailment a year2027 (2027)variant: 70kv26 Sep 2026
InjectionGeneration (any)Available24.9 MWFlexible, ≤ 20 % curtailment a year2027 (2027)variant: 150kv26 Sep 2026
InjectionGeneration (any)Available6.7 MWFirm, ≤ 0 % curtailment a year2031 (2031)variant: 150kv26 Sep 2026
InjectionGeneration (any)Available5.3 MWFirm, ≤ 0 % curtailment a year2031 (2031)variant: 70kv26 Sep 2026
InjectionGeneration (any)Available22.6 MWFlexible, ≤ 5 % curtailment a year2031 (2031)variant: 70kv26 Sep 2026
InjectionGeneration (any)Available19.2 MWFlexible, ≤ 5 % curtailment a year2031 (2031)variant: 150kv26 Sep 2026
InjectionGeneration (any)Available25.3 MWFlexible, ≤ 10 % curtailment a year2031 (2031)variant: 70kv26 Sep 2026
InjectionGeneration (any)Available21.5 MWFlexible, ≤ 10 % curtailment a year2031 (2031)variant: 150kv26 Sep 2026
InjectionGeneration (any)Available31.2 MWFlexible, ≤ 20 % curtailment a year2031 (2031)variant: 70kv26 Sep 2026
InjectionGeneration (any)Available26.8 MWFlexible, ≤ 20 % curtailment a year2031 (2031)variant: 150kv26 Sep 2026
InjectionSolar PVAvailable27.8 MWFirm, ≤ 0 % curtailment a year2027 (2027)variant: 150kv26 Sep 2026
InjectionSolar PVAvailable24.1 MWFirm, ≤ 0 % curtailment a year2027 (2027)variant: 70kv26 Sep 2026
InjectionSolar PVAvailable63.3 MWFlexible, ≤ 5 % curtailment a year2027 (2027)variant: 150kv26 Sep 2026
InjectionSolar PVAvailable50 MWFlexible, ≤ 5 % curtailment a year2027 (2027)variant: 70kv26 Sep 2026
InjectionSolar PVAvailable80.3 MWFlexible, ≤ 10 % curtailment a year2027 (2027)variant: 150kv26 Sep 2026
InjectionSolar PVAvailable50 MWFlexible, ≤ 10 % curtailment a year2027 (2027)variant: 70kv26 Sep 2026
InjectionSolar PVAvailable107.8 MWFlexible, ≤ 20 % curtailment a year2027 (2027)variant: 150kv26 Sep 2026
InjectionSolar PVAvailable50 MWFlexible, ≤ 20 % curtailment a year2027 (2027)variant: 70kv26 Sep 2026
InjectionSolar PVAvailable27.9 MWFirm, ≤ 0 % curtailment a year2031 (2031)variant: 150kv26 Sep 2026
InjectionSolar PVAvailable24.1 MWFirm, ≤ 0 % curtailment a year2031 (2031)variant: 70kv26 Sep 2026
InjectionSolar PVAvailable65 MWFlexible, ≤ 5 % curtailment a year2031 (2031)variant: 150kv26 Sep 2026
InjectionSolar PVAvailable50 MWFlexible, ≤ 5 % curtailment a year2031 (2031)variant: 70kv26 Sep 2026
InjectionSolar PVAvailable84.4 MWFlexible, ≤ 10 % curtailment a year2031 (2031)variant: 150kv26 Sep 2026
InjectionSolar PVAvailable50 MWFlexible, ≤ 10 % curtailment a year2031 (2031)variant: 70kv26 Sep 2026
InjectionSolar PVAvailable118.5 MWFlexible, ≤ 20 % curtailment a year2031 (2031)variant: 150kv26 Sep 2026
InjectionSolar PVAvailable50 MWFlexible, ≤ 20 % curtailment a year2031 (2031)variant: 70kv26 Sep 2026
InjectionOnshore windAvailable9.8 MWFirm, ≤ 0 % curtailment a year2027 (2027)variant: 150kv26 Sep 2026
InjectionOnshore windAvailable8.1 MWFirm, ≤ 0 % curtailment a year2027 (2027)variant: 70kv26 Sep 2026
InjectionOnshore windAvailable35.8 MWFlexible, ≤ 5 % curtailment a year2027 (2027)variant: 70kv26 Sep 2026
InjectionOnshore windAvailable30.9 MWFlexible, ≤ 5 % curtailment a year2027 (2027)variant: 150kv26 Sep 2026
InjectionOnshore windAvailable43.2 MWFlexible, ≤ 10 % curtailment a year2027 (2027)variant: 70kv26 Sep 2026
InjectionOnshore windAvailable36.8 MWFlexible, ≤ 10 % curtailment a year2027 (2027)variant: 150kv26 Sep 2026
InjectionOnshore windAvailable50 MWFlexible, ≤ 20 % curtailment a year2027 (2027)variant: 70kv26 Sep 2026
InjectionOnshore windAvailable49.5 MWFlexible, ≤ 20 % curtailment a year2027 (2027)variant: 150kv26 Sep 2026
InjectionOnshore windAvailable9.8 MWFirm, ≤ 0 % curtailment a year2031 (2031)variant: 150kv26 Sep 2026
InjectionOnshore windAvailable8.1 MWFirm, ≤ 0 % curtailment a year2031 (2031)variant: 70kv26 Sep 2026
InjectionOnshore windAvailable36.5 MWFlexible, ≤ 5 % curtailment a year2031 (2031)variant: 70kv26 Sep 2026
InjectionOnshore windAvailable34.4 MWFlexible, ≤ 5 % curtailment a year2031 (2031)variant: 150kv26 Sep 2026
InjectionOnshore windAvailable49.8 MWFlexible, ≤ 10 % curtailment a year2031 (2031)variant: 70kv26 Sep 2026
InjectionOnshore windAvailable45.8 MWFlexible, ≤ 10 % curtailment a year2031 (2031)variant: 150kv26 Sep 2026
InjectionOnshore windAvailable69.5 MWFlexible, ≤ 20 % curtailment a year2031 (2031)variant: 150kv26 Sep 2026
InjectionOnshore windAvailable50 MWFlexible, ≤ 20 % curtailment a year2031 (2031)variant: 70kv26 Sep 2026
OfftakeLoad (any)Available6.3 MWFirm, ≤ 0 % curtailment a year2027 (2027)variant: 150kv26 Sep 2026
OfftakeLoad (any)Available2.8 MWFirm, ≤ 0 % curtailment a year2027 (2027)variant: 70kv26 Sep 2026
OfftakeLoad (any)Available10.9 MWFlexible, ≤ 5 % curtailment a year2027 (2027)variant: 70kv26 Sep 2026
OfftakeLoad (any)Available10.4 MWFlexible, ≤ 5 % curtailment a year2027 (2027)variant: 150kv26 Sep 2026
OfftakeLoad (any)Available14.3 MWFlexible, ≤ 10 % curtailment a year2027 (2027)variant: 70kv26 Sep 2026
OfftakeLoad (any)Available13.2 MWFlexible, ≤ 10 % curtailment a year2027 (2027)variant: 150kv26 Sep 2026
OfftakeLoad (any)Available24.3 MWFlexible, ≤ 20 % curtailment a year2027 (2027)variant: 70kv26 Sep 2026
OfftakeLoad (any)Available21.1 MWFlexible, ≤ 20 % curtailment a year2027 (2027)variant: 150kv26 Sep 2026
OfftakeLoad (any)Available6.3 MWFirm, ≤ 0 % curtailment a year2031 (2031)variant: 150kv26 Sep 2026
OfftakeLoad (any)Available2.8 MWFirm, ≤ 0 % curtailment a year2031 (2031)variant: 70kv26 Sep 2026
OfftakeLoad (any)Available10.9 MWFlexible, ≤ 5 % curtailment a year2031 (2031)variant: 70kv26 Sep 2026
OfftakeLoad (any)Available10.4 MWFlexible, ≤ 5 % curtailment a year2031 (2031)variant: 150kv26 Sep 2026
OfftakeLoad (any)Available14.3 MWFlexible, ≤ 10 % curtailment a year2031 (2031)variant: 70kv26 Sep 2026
OfftakeLoad (any)Available13.2 MWFlexible, ≤ 10 % curtailment a year2031 (2031)variant: 150kv26 Sep 2026
OfftakeLoad (any)Available24.3 MWFlexible, ≤ 20 % curtailment a year2031 (2031)variant: 70kv26 Sep 2026
OfftakeLoad (any)Available21.1 MWFlexible, ≤ 20 % curtailment a year2031 (2031)variant: 150kv26 Sep 2026
BidirectionalBatteryAvailable6.3 MWFirm, ≤ 0 % curtailment a year2027 (2027)variant: 150kv26 Sep 2026
BidirectionalBatteryAvailable2.8 MWFirm, ≤ 0 % curtailment a year2027 (2027)variant: 70kv26 Sep 2026
BidirectionalBatteryAvailable10.2 MWFlexible, ≤ 5 % curtailment a year2027 (2027)variant: 70kv26 Sep 2026
BidirectionalBatteryAvailable9.7 MWFlexible, ≤ 5 % curtailment a year2027 (2027)variant: 150kv26 Sep 2026
BidirectionalBatteryAvailable13.6 MWFlexible, ≤ 10 % curtailment a year2027 (2027)variant: 70kv26 Sep 2026
BidirectionalBatteryAvailable12.5 MWFlexible, ≤ 10 % curtailment a year2027 (2027)variant: 150kv26 Sep 2026
BidirectionalBatteryAvailable22.3 MWFlexible, ≤ 20 % curtailment a year2027 (2027)variant: 70kv26 Sep 2026
BidirectionalBatteryAvailable19.5 MWFlexible, ≤ 20 % curtailment a year2027 (2027)variant: 150kv26 Sep 2026
BidirectionalBatteryAvailable6.3 MWFirm, ≤ 0 % curtailment a year2031 (2031)variant: 150kv26 Sep 2026
BidirectionalBatteryAvailable3.3 MWFirm, ≤ 0 % curtailment a year2031 (2031)variant: 70kv26 Sep 2026
BidirectionalBatteryAvailable10.2 MWFlexible, ≤ 5 % curtailment a year2031 (2031)variant: 70kv26 Sep 2026
BidirectionalBatteryAvailable9.7 MWFlexible, ≤ 5 % curtailment a year2031 (2031)variant: 150kv26 Sep 2026
BidirectionalBatteryAvailable13.6 MWFlexible, ≤ 10 % curtailment a year2031 (2031)variant: 70kv26 Sep 2026
BidirectionalBatteryAvailable12.5 MWFlexible, ≤ 10 % curtailment a year2031 (2031)variant: 150kv26 Sep 2026
BidirectionalBatteryAvailable22.3 MWFlexible, ≤ 20 % curtailment a year2031 (2031)variant: 70kv26 Sep 2026
BidirectionalBatteryAvailable19.5 MWFlexible, ≤ 20 % curtailment a year2031 (2031)variant: 150kv26 Sep 2026

Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map

What each value means

Methodology, both clocks, provenance and rights

Injection · Generation (any) · Available

6.7 MW

Granted

The operator's latest published dataset reports 6.7 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2027 (2027) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2027/SCHEL150 · payload sha256 67231de922bf…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
SCHEL150
Operator note: flexibilityLevel
0%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Injection · Generation (any) · Available

5.3 MW

Granted

The operator's latest published dataset reports 5.3 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2027 (2027) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2027/SCHEL 70 · payload sha256 5ff7cbe1e49b…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
SCHEL 70
Operator note: flexibilityLevel
0%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

Injection · Generation (any) · Available

22.2 MW

Granted

The operator's latest published dataset reports 22.2 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2027 (2027) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2027/SCHEL 70 · payload sha256 5ff7cbe1e49b…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
SCHEL 70
Operator note: flexibilityLevel
5%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

Injection · Generation (any) · Available

18.7 MW

Granted

The operator's latest published dataset reports 18.7 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2027 (2027) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2027/SCHEL150 · payload sha256 67231de922bf…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
SCHEL150
Operator note: flexibilityLevel
5%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Injection · Generation (any) · Available

24.2 MW

Granted

The operator's latest published dataset reports 24.2 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2027 (2027) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2027/SCHEL 70 · payload sha256 5ff7cbe1e49b…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
SCHEL 70
Operator note: flexibilityLevel
10%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

Injection · Generation (any) · Available

20.5 MW

Granted

The operator's latest published dataset reports 20.5 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2027 (2027) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2027/SCHEL150 · payload sha256 67231de922bf…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
SCHEL150
Operator note: flexibilityLevel
10%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Injection · Generation (any) · Available

29 MW

Granted

The operator's latest published dataset reports 29 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2027 (2027) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2027/SCHEL 70 · payload sha256 5ff7cbe1e49b…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
SCHEL 70
Operator note: flexibilityLevel
20%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

Injection · Generation (any) · Available

24.9 MW

Granted

The operator's latest published dataset reports 24.9 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2027 (2027) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2027/SCHEL150 · payload sha256 67231de922bf…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
SCHEL150
Operator note: flexibilityLevel
20%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Injection · Generation (any) · Available

6.7 MW

Granted

The operator's latest published dataset reports 6.7 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2031 (2031) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/SCHEL150 · payload sha256 66b3357eb361…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
SCHEL150
Operator note: flexibilityLevel
0%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Injection · Generation (any) · Available

5.3 MW

Granted

The operator's latest published dataset reports 5.3 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2031 (2031) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/SCHEL 70 · payload sha256 aa5425d684dd…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
SCHEL 70
Operator note: flexibilityLevel
0%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

Injection · Generation (any) · Available

22.6 MW

Granted

The operator's latest published dataset reports 22.6 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2031 (2031) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/SCHEL 70 · payload sha256 aa5425d684dd…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
SCHEL 70
Operator note: flexibilityLevel
5%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

Injection · Generation (any) · Available

19.2 MW

Granted

The operator's latest published dataset reports 19.2 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2031 (2031) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/SCHEL150 · payload sha256 66b3357eb361…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
SCHEL150
Operator note: flexibilityLevel
5%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Injection · Generation (any) · Available

25.3 MW

Granted

The operator's latest published dataset reports 25.3 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2031 (2031) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/SCHEL 70 · payload sha256 aa5425d684dd…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
SCHEL 70
Operator note: flexibilityLevel
10%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

Injection · Generation (any) · Available

21.5 MW

Granted

The operator's latest published dataset reports 21.5 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2031 (2031) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/SCHEL150 · payload sha256 66b3357eb361…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
SCHEL150
Operator note: flexibilityLevel
10%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Injection · Generation (any) · Available

31.2 MW

Granted

The operator's latest published dataset reports 31.2 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2031 (2031) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/SCHEL 70 · payload sha256 aa5425d684dd…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
SCHEL 70
Operator note: flexibilityLevel
20%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

Injection · Generation (any) · Available

26.8 MW

Granted

The operator's latest published dataset reports 26.8 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2031 (2031) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/SCHEL150 · payload sha256 66b3357eb361…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
SCHEL150
Operator note: flexibilityLevel
20%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Injection · Solar PV · Available

27.8 MW

Granted

The operator's latest published dataset reports 27.8 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2027 (2027) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2027/SCHEL150 · payload sha256 67231de922bf…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
SCHEL150
Operator note: flexibilityLevel
0%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Injection · Solar PV · Available

24.1 MW

Granted

The operator's latest published dataset reports 24.1 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2027 (2027) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2027/SCHEL 70 · payload sha256 5ff7cbe1e49b…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
SCHEL 70
Operator note: flexibilityLevel
0%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

Injection · Solar PV · Available

63.3 MW

Granted

The operator's latest published dataset reports 63.3 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2027 (2027) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2027/SCHEL150 · payload sha256 67231de922bf…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
SCHEL150
Operator note: flexibilityLevel
5%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Injection · Solar PV · Available

50 MW

Granted

The operator's latest published dataset reports 50 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2027 (2027) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2027/SCHEL 70 · payload sha256 5ff7cbe1e49b…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
SCHEL 70
Operator note: flexibilityLevel
5%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

Injection · Solar PV · Available

80.3 MW

Granted

The operator's latest published dataset reports 80.3 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2027 (2027) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2027/SCHEL150 · payload sha256 67231de922bf…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
SCHEL150
Operator note: flexibilityLevel
10%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Injection · Solar PV · Available

50 MW

Granted

The operator's latest published dataset reports 50 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2027 (2027) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2027/SCHEL 70 · payload sha256 5ff7cbe1e49b…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
SCHEL 70
Operator note: flexibilityLevel
10%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

Injection · Solar PV · Available

107.8 MW

Granted

The operator's latest published dataset reports 107.8 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2027 (2027) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2027/SCHEL150 · payload sha256 67231de922bf…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
SCHEL150
Operator note: flexibilityLevel
20%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Injection · Solar PV · Available

50 MW

Granted

The operator's latest published dataset reports 50 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2027 (2027) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2027/SCHEL 70 · payload sha256 5ff7cbe1e49b…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
SCHEL 70
Operator note: flexibilityLevel
20%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

Injection · Solar PV · Available

27.9 MW

Granted

The operator's latest published dataset reports 27.9 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2031 (2031) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/SCHEL150 · payload sha256 66b3357eb361…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
SCHEL150
Operator note: flexibilityLevel
0%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Injection · Solar PV · Available

24.1 MW

Granted

The operator's latest published dataset reports 24.1 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2031 (2031) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/SCHEL 70 · payload sha256 aa5425d684dd…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
SCHEL 70
Operator note: flexibilityLevel
0%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

Injection · Solar PV · Available

65 MW

Granted

The operator's latest published dataset reports 65 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2031 (2031) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/SCHEL150 · payload sha256 66b3357eb361…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
SCHEL150
Operator note: flexibilityLevel
5%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Injection · Solar PV · Available

50 MW

Granted

The operator's latest published dataset reports 50 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2031 (2031) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/SCHEL 70 · payload sha256 aa5425d684dd…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
SCHEL 70
Operator note: flexibilityLevel
5%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

Injection · Solar PV · Available

84.4 MW

Granted

The operator's latest published dataset reports 84.4 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2031 (2031) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/SCHEL150 · payload sha256 66b3357eb361…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
SCHEL150
Operator note: flexibilityLevel
10%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Injection · Solar PV · Available

50 MW

Granted

The operator's latest published dataset reports 50 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2031 (2031) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/SCHEL 70 · payload sha256 aa5425d684dd…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
SCHEL 70
Operator note: flexibilityLevel
10%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

Injection · Solar PV · Available

118.5 MW

Granted

The operator's latest published dataset reports 118.5 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2031 (2031) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/SCHEL150 · payload sha256 66b3357eb361…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
SCHEL150
Operator note: flexibilityLevel
20%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Injection · Solar PV · Available

50 MW

Granted

The operator's latest published dataset reports 50 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2031 (2031) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/SCHEL 70 · payload sha256 aa5425d684dd…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
SCHEL 70
Operator note: flexibilityLevel
20%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

Injection · Onshore wind · Available

9.8 MW

Granted

The operator's latest published dataset reports 9.8 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2027 (2027) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2027/SCHEL150 · payload sha256 67231de922bf…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
SCHEL150
Operator note: flexibilityLevel
0%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Injection · Onshore wind · Available

8.1 MW

Granted

The operator's latest published dataset reports 8.1 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2027 (2027) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2027/SCHEL 70 · payload sha256 5ff7cbe1e49b…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
SCHEL 70
Operator note: flexibilityLevel
0%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

Injection · Onshore wind · Available

35.8 MW

Granted

The operator's latest published dataset reports 35.8 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2027 (2027) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2027/SCHEL 70 · payload sha256 5ff7cbe1e49b…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
SCHEL 70
Operator note: flexibilityLevel
5%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

Injection · Onshore wind · Available

30.9 MW

Granted

The operator's latest published dataset reports 30.9 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2027 (2027) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2027/SCHEL150 · payload sha256 67231de922bf…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
SCHEL150
Operator note: flexibilityLevel
5%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Injection · Onshore wind · Available

43.2 MW

Granted

The operator's latest published dataset reports 43.2 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2027 (2027) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2027/SCHEL 70 · payload sha256 5ff7cbe1e49b…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
SCHEL 70
Operator note: flexibilityLevel
10%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

Injection · Onshore wind · Available

36.8 MW

Granted

The operator's latest published dataset reports 36.8 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2027 (2027) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2027/SCHEL150 · payload sha256 67231de922bf…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
SCHEL150
Operator note: flexibilityLevel
10%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Injection · Onshore wind · Available

50 MW

Granted

The operator's latest published dataset reports 50 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2027 (2027) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2027/SCHEL 70 · payload sha256 5ff7cbe1e49b…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
SCHEL 70
Operator note: flexibilityLevel
20%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

Injection · Onshore wind · Available

49.5 MW

Granted

The operator's latest published dataset reports 49.5 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2027 (2027) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2027/SCHEL150 · payload sha256 67231de922bf…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
SCHEL150
Operator note: flexibilityLevel
20%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Injection · Onshore wind · Available

9.8 MW

Granted

The operator's latest published dataset reports 9.8 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2031 (2031) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/SCHEL150 · payload sha256 66b3357eb361…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
SCHEL150
Operator note: flexibilityLevel
0%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Injection · Onshore wind · Available

8.1 MW

Granted

The operator's latest published dataset reports 8.1 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2031 (2031) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/SCHEL 70 · payload sha256 aa5425d684dd…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
SCHEL 70
Operator note: flexibilityLevel
0%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

Injection · Onshore wind · Available

36.5 MW

Granted

The operator's latest published dataset reports 36.5 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2031 (2031) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/SCHEL 70 · payload sha256 aa5425d684dd…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
SCHEL 70
Operator note: flexibilityLevel
5%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

Injection · Onshore wind · Available

34.4 MW

Granted

The operator's latest published dataset reports 34.4 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2031 (2031) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/SCHEL150 · payload sha256 66b3357eb361…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
SCHEL150
Operator note: flexibilityLevel
5%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Injection · Onshore wind · Available

49.8 MW

Granted

The operator's latest published dataset reports 49.8 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2031 (2031) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/SCHEL 70 · payload sha256 aa5425d684dd…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
SCHEL 70
Operator note: flexibilityLevel
10%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

Injection · Onshore wind · Available

45.8 MW

Granted

The operator's latest published dataset reports 45.8 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2031 (2031) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/SCHEL150 · payload sha256 66b3357eb361…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
SCHEL150
Operator note: flexibilityLevel
10%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Injection · Onshore wind · Available

69.5 MW

Granted

The operator's latest published dataset reports 69.5 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2031 (2031) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/SCHEL150 · payload sha256 66b3357eb361…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
SCHEL150
Operator note: flexibilityLevel
20%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Injection · Onshore wind · Available

50 MW

Granted

The operator's latest published dataset reports 50 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2031 (2031) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/SCHEL 70 · payload sha256 aa5425d684dd…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
SCHEL 70
Operator note: flexibilityLevel
20%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

Offtake · Load (any) · Available

6.3 MW

Granted

The operator's latest published dataset reports 6.3 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2027 (2027) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2027/SCHEL150 · payload sha256 67231de922bf…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
SCHEL150
Operator note: flexibilityLevel
0%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Offtake · Load (any) · Available

2.8 MW

Granted

The operator's latest published dataset reports 2.8 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2027 (2027) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2027/SCHEL 70 · payload sha256 5ff7cbe1e49b…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
SCHEL 70
Operator note: flexibilityLevel
0%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

Offtake · Load (any) · Available

10.9 MW

Granted

The operator's latest published dataset reports 10.9 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2027 (2027) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2027/SCHEL 70 · payload sha256 5ff7cbe1e49b…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
SCHEL 70
Operator note: flexibilityLevel
5%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

Offtake · Load (any) · Available

10.4 MW

Granted

The operator's latest published dataset reports 10.4 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2027 (2027) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2027/SCHEL150 · payload sha256 67231de922bf…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
SCHEL150
Operator note: flexibilityLevel
5%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Offtake · Load (any) · Available

14.3 MW

Granted

The operator's latest published dataset reports 14.3 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2027 (2027) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2027/SCHEL 70 · payload sha256 5ff7cbe1e49b…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
SCHEL 70
Operator note: flexibilityLevel
10%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

Offtake · Load (any) · Available

13.2 MW

Granted

The operator's latest published dataset reports 13.2 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2027 (2027) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2027/SCHEL150 · payload sha256 67231de922bf…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
SCHEL150
Operator note: flexibilityLevel
10%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Offtake · Load (any) · Available

24.3 MW

Granted

The operator's latest published dataset reports 24.3 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2027 (2027) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2027/SCHEL 70 · payload sha256 5ff7cbe1e49b…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
SCHEL 70
Operator note: flexibilityLevel
20%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

Offtake · Load (any) · Available

21.1 MW

Granted

The operator's latest published dataset reports 21.1 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2027 (2027) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2027/SCHEL150 · payload sha256 67231de922bf…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
SCHEL150
Operator note: flexibilityLevel
20%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Offtake · Load (any) · Available

6.3 MW

Granted

The operator's latest published dataset reports 6.3 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2031 (2031) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/SCHEL150 · payload sha256 66b3357eb361…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
SCHEL150
Operator note: flexibilityLevel
0%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Offtake · Load (any) · Available

2.8 MW

Granted

The operator's latest published dataset reports 2.8 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2031 (2031) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/SCHEL 70 · payload sha256 aa5425d684dd…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
SCHEL 70
Operator note: flexibilityLevel
0%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

Offtake · Load (any) · Available

10.9 MW

Granted

The operator's latest published dataset reports 10.9 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2031 (2031) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/SCHEL 70 · payload sha256 aa5425d684dd…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
SCHEL 70
Operator note: flexibilityLevel
5%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

Offtake · Load (any) · Available

10.4 MW

Granted

The operator's latest published dataset reports 10.4 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2031 (2031) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/SCHEL150 · payload sha256 66b3357eb361…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
SCHEL150
Operator note: flexibilityLevel
5%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Offtake · Load (any) · Available

14.3 MW

Granted

The operator's latest published dataset reports 14.3 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2031 (2031) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/SCHEL 70 · payload sha256 aa5425d684dd…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
SCHEL 70
Operator note: flexibilityLevel
10%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

Offtake · Load (any) · Available

13.2 MW

Granted

The operator's latest published dataset reports 13.2 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2031 (2031) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/SCHEL150 · payload sha256 66b3357eb361…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
SCHEL150
Operator note: flexibilityLevel
10%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Offtake · Load (any) · Available

24.3 MW

Granted

The operator's latest published dataset reports 24.3 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2031 (2031) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/SCHEL 70 · payload sha256 aa5425d684dd…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
SCHEL 70
Operator note: flexibilityLevel
20%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

Offtake · Load (any) · Available

21.1 MW

Granted

The operator's latest published dataset reports 21.1 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2031 (2031) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/SCHEL150 · payload sha256 66b3357eb361…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
SCHEL150
Operator note: flexibilityLevel
20%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Bidirectional · Battery · Available

6.3 MW

Granted

The operator's latest published dataset reports 6.3 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2027 (2027) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2027/SCHEL150 · payload sha256 67231de922bf…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
SCHEL150
Operator note: flexibilityLevel
0%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Bidirectional · Battery · Available

2.8 MW

Granted

The operator's latest published dataset reports 2.8 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2027 (2027) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2027/SCHEL 70 · payload sha256 5ff7cbe1e49b…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
SCHEL 70
Operator note: flexibilityLevel
0%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

Bidirectional · Battery · Available

10.2 MW

Granted

The operator's latest published dataset reports 10.2 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2027 (2027) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2027/SCHEL 70 · payload sha256 5ff7cbe1e49b…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
SCHEL 70
Operator note: flexibilityLevel
5%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

Bidirectional · Battery · Available

9.7 MW

Granted

The operator's latest published dataset reports 9.7 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2027 (2027) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2027/SCHEL150 · payload sha256 67231de922bf…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
SCHEL150
Operator note: flexibilityLevel
5%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Bidirectional · Battery · Available

13.6 MW

Granted

The operator's latest published dataset reports 13.6 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2027 (2027) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2027/SCHEL 70 · payload sha256 5ff7cbe1e49b…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
SCHEL 70
Operator note: flexibilityLevel
10%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

Bidirectional · Battery · Available

12.5 MW

Granted

The operator's latest published dataset reports 12.5 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2027 (2027) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2027/SCHEL150 · payload sha256 67231de922bf…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
SCHEL150
Operator note: flexibilityLevel
10%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Bidirectional · Battery · Available

22.3 MW

Granted

The operator's latest published dataset reports 22.3 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2027 (2027) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2027/SCHEL 70 · payload sha256 5ff7cbe1e49b…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
SCHEL 70
Operator note: flexibilityLevel
20%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

Bidirectional · Battery · Available

19.5 MW

Granted

The operator's latest published dataset reports 19.5 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2027 (2027) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2027/SCHEL150 · payload sha256 67231de922bf…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
SCHEL150
Operator note: flexibilityLevel
20%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Bidirectional · Battery · Available

6.3 MW

Granted

The operator's latest published dataset reports 6.3 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2031 (2031) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/SCHEL150 · payload sha256 66b3357eb361…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
SCHEL150
Operator note: flexibilityLevel
0%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Bidirectional · Battery · Available

3.3 MW

Granted

The operator's latest published dataset reports 3.3 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2031 (2031) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/SCHEL 70 · payload sha256 aa5425d684dd…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
SCHEL 70
Operator note: flexibilityLevel
0%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

Bidirectional · Battery · Available

10.2 MW

Granted

The operator's latest published dataset reports 10.2 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2031 (2031) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/SCHEL 70 · payload sha256 aa5425d684dd…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
SCHEL 70
Operator note: flexibilityLevel
5%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

Bidirectional · Battery · Available

9.7 MW

Granted

The operator's latest published dataset reports 9.7 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2031 (2031) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/SCHEL150 · payload sha256 66b3357eb361…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
SCHEL150
Operator note: flexibilityLevel
5%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Bidirectional · Battery · Available

13.6 MW

Granted

The operator's latest published dataset reports 13.6 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2031 (2031) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/SCHEL 70 · payload sha256 aa5425d684dd…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
SCHEL 70
Operator note: flexibilityLevel
10%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

Bidirectional · Battery · Available

12.5 MW

Granted

The operator's latest published dataset reports 12.5 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2031 (2031) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/SCHEL150 · payload sha256 66b3357eb361…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
SCHEL150
Operator note: flexibilityLevel
10%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Bidirectional · Battery · Available

22.3 MW

Granted

The operator's latest published dataset reports 22.3 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2031 (2031) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/SCHEL 70 · payload sha256 aa5425d684dd…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
SCHEL 70
Operator note: flexibilityLevel
20%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

Bidirectional · Battery · Available

19.5 MW

Granted

The operator's latest published dataset reports 19.5 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2031 (2031) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/SCHEL150 · payload sha256 66b3357eb361…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
SCHEL150
Operator note: flexibilityLevel
20%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

History

Served series only

Bidirectional · Battery · Available · 2027

current 2.8 MW

26 Sep 2026: 2.8 MW
26 Sep 2026range 2.8 to 2.8 MW2 Oct 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current2.8 MW

Time axis: when we observed each value, not the operator’s effective date.

Bidirectional · Battery · Available · 2027

current 10.2 MW

26 Sep 2026: 10.2 MW
26 Sep 2026range 10.2 to 10.2 MW2 Oct 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current10.2 MW

Time axis: when we observed each value, not the operator’s effective date.

Bidirectional · Battery · Available · 2027

current 13.6 MW

26 Sep 2026: 13.6 MW
26 Sep 2026range 13.6 to 13.6 MW2 Oct 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current13.6 MW

Time axis: when we observed each value, not the operator’s effective date.

Bidirectional · Battery · Available · 2027

current 22.3 MW

26 Sep 2026: 22.3 MW
26 Sep 2026range 22.3 to 22.3 MW2 Oct 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current22.3 MW

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Load (any) · Available · 2027

current 2.8 MW

26 Sep 2026: 2.8 MW
26 Sep 2026range 2.8 to 2.8 MW2 Oct 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current2.8 MW

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Load (any) · Available · 2027

current 10.9 MW

26 Sep 2026: 10.9 MW
26 Sep 2026range 10.9 to 10.9 MW2 Oct 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current10.9 MW

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Load (any) · Available · 2027

current 14.3 MW

26 Sep 2026: 14.3 MW
26 Sep 2026range 14.3 to 14.3 MW2 Oct 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current14.3 MW

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Load (any) · Available · 2027

current 24.3 MW

26 Sep 2026: 24.3 MW
26 Sep 2026range 24.3 to 24.3 MW2 Oct 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current24.3 MW

Time axis: when we observed each value, not the operator’s effective date.

Injection · Generation (any) · Available · 2027

current 5.3 MW

26 Sep 2026: 5.3 MW
26 Sep 2026range 5.3 to 5.3 MW2 Oct 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current5.3 MW

Time axis: when we observed each value, not the operator’s effective date.

Injection · Generation (any) · Available · 2027

current 22.2 MW

26 Sep 2026: 22.2 MW
26 Sep 2026range 22.2 to 22.2 MW2 Oct 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current22.2 MW

Time axis: when we observed each value, not the operator’s effective date.

Injection · Generation (any) · Available · 2027

current 24.2 MW

26 Sep 2026: 24.2 MW
26 Sep 2026range 24.2 to 24.2 MW2 Oct 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current24.2 MW

Time axis: when we observed each value, not the operator’s effective date.

Injection · Generation (any) · Available · 2027

current 29 MW

26 Sep 2026: 29 MW
26 Sep 2026range 29 to 29 MW2 Oct 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current29 MW

Time axis: when we observed each value, not the operator’s effective date.

The first 12 of 80 served series with a history. The history route returns every one of them.

Through the API

curl "https://api.gridcapacityapi.com/v1/substations/sub_06gdrm9mfsvxx32609cmbq9ssg/capacity" \  -H "Authorization: Bearer gc_live_..."
SCHEL 150 kV substation: grid capacity (Elia Transmission Belgium) · GridCapacity API