Substation / 36 kV

ROLLE

Elia Transmission Belgium / Belgium

Latest published values

40 served · 0 withheld

Each row is what the operator’s latest published dataset reports for one combination of direction, technology, measure, firmness and horizon. Hosting-capacity figures are indicative and reflect what operators publish. They are not a connection offer; only the operator can confirm capacity for a specific request.

Latest published capacity values, one row per series
DirectionTechnologyMeasureValueFirmnessHorizonSource date
InjectionGeneration (any)Available0 MWFirm, ≤ 0 % curtailment a year2029 (2029)variant: 36kv17 Nov 2026
InjectionGeneration (any)Available4.5 MWFlexible, ≤ 5 % curtailment a year2029 (2029)variant: 36kv17 Nov 2026
InjectionGeneration (any)Available6.2 MWFlexible, ≤ 10 % curtailment a year2029 (2029)variant: 36kv17 Nov 2026
InjectionGeneration (any)Available10.7 MWFlexible, ≤ 20 % curtailment a year2029 (2029)variant: 36kv17 Nov 2026
InjectionGeneration (any)Available0 MWFirm, ≤ 0 % curtailment a year2033 (2033)variant: 36kv17 Nov 2026
InjectionGeneration (any)Available4.5 MWFlexible, ≤ 5 % curtailment a year2033 (2033)variant: 36kv17 Nov 2026
InjectionGeneration (any)Available6.2 MWFlexible, ≤ 10 % curtailment a year2033 (2033)variant: 36kv17 Nov 2026
InjectionGeneration (any)Available10.7 MWFlexible, ≤ 20 % curtailment a year2033 (2033)variant: 36kv17 Nov 2026
InjectionSolar PVAvailable11.7 MWFirm, ≤ 0 % curtailment a year2029 (2029)variant: 36kv17 Nov 2026
InjectionSolar PVAvailable20 MWFlexible, ≤ 5 % curtailment a year2029 (2029)variant: 36kv17 Nov 2026
InjectionSolar PVAvailable20 MWFlexible, ≤ 10 % curtailment a year2029 (2029)variant: 36kv17 Nov 2026
InjectionSolar PVAvailable20 MWFlexible, ≤ 20 % curtailment a year2029 (2029)variant: 36kv17 Nov 2026
InjectionSolar PVAvailable13.8 MWFirm, ≤ 0 % curtailment a year2033 (2033)variant: 36kv17 Nov 2026
InjectionSolar PVAvailable20 MWFlexible, ≤ 5 % curtailment a year2033 (2033)variant: 36kv17 Nov 2026
InjectionSolar PVAvailable20 MWFlexible, ≤ 10 % curtailment a year2033 (2033)variant: 36kv17 Nov 2026
InjectionSolar PVAvailable20 MWFlexible, ≤ 20 % curtailment a year2033 (2033)variant: 36kv17 Nov 2026
InjectionOnshore windAvailable9.8 MWFirm, ≤ 0 % curtailment a year2029 (2029)variant: 36kv17 Nov 2026
InjectionOnshore windAvailable20 MWFlexible, ≤ 5 % curtailment a year2029 (2029)variant: 36kv17 Nov 2026
InjectionOnshore windAvailable20 MWFlexible, ≤ 10 % curtailment a year2029 (2029)variant: 36kv17 Nov 2026
InjectionOnshore windAvailable20 MWFlexible, ≤ 20 % curtailment a year2029 (2029)variant: 36kv17 Nov 2026
InjectionOnshore windAvailable9.8 MWFirm, ≤ 0 % curtailment a year2033 (2033)variant: 36kv17 Nov 2026
InjectionOnshore windAvailable20 MWFlexible, ≤ 5 % curtailment a year2033 (2033)variant: 36kv17 Nov 2026
InjectionOnshore windAvailable20 MWFlexible, ≤ 10 % curtailment a year2033 (2033)variant: 36kv17 Nov 2026
InjectionOnshore windAvailable20 MWFlexible, ≤ 20 % curtailment a year2033 (2033)variant: 36kv17 Nov 2026
OfftakeLoad (any)Available13.9 MWFirm, ≤ 0 % curtailment a year2029 (2029)variant: 36kv17 Nov 2026
OfftakeLoad (any)Available20 MWFlexible, ≤ 5 % curtailment a year2029 (2029)variant: 36kv17 Nov 2026
OfftakeLoad (any)Available20 MWFlexible, ≤ 10 % curtailment a year2029 (2029)variant: 36kv17 Nov 2026
OfftakeLoad (any)Available20 MWFlexible, ≤ 20 % curtailment a year2029 (2029)variant: 36kv17 Nov 2026
OfftakeLoad (any)Available20 MWFirm, ≤ 0 % curtailment a year2033 (2033)variant: 36kv17 Nov 2026
OfftakeLoad (any)Available20 MWFlexible, ≤ 5 % curtailment a year2033 (2033)variant: 36kv17 Nov 2026
OfftakeLoad (any)Available20 MWFlexible, ≤ 10 % curtailment a year2033 (2033)variant: 36kv17 Nov 2026
OfftakeLoad (any)Available20 MWFlexible, ≤ 20 % curtailment a year2033 (2033)variant: 36kv17 Nov 2026
BidirectionalBatteryAvailable0 MWFirm, ≤ 0 % curtailment a year2029 (2029)variant: 36kv17 Nov 2026
BidirectionalBatteryAvailable4.5 MWFlexible, ≤ 5 % curtailment a year2029 (2029)variant: 36kv17 Nov 2026
BidirectionalBatteryAvailable6.2 MWFlexible, ≤ 10 % curtailment a year2029 (2029)variant: 36kv17 Nov 2026
BidirectionalBatteryAvailable10.7 MWFlexible, ≤ 20 % curtailment a year2029 (2029)variant: 36kv17 Nov 2026
BidirectionalBatteryAvailable0 MWFirm, ≤ 0 % curtailment a year2033 (2033)variant: 36kv17 Nov 2026
BidirectionalBatteryAvailable4.5 MWFlexible, ≤ 5 % curtailment a year2033 (2033)variant: 36kv17 Nov 2026
BidirectionalBatteryAvailable6.2 MWFlexible, ≤ 10 % curtailment a year2033 (2033)variant: 36kv17 Nov 2026
BidirectionalBatteryAvailable10.7 MWFlexible, ≤ 20 % curtailment a year2033 (2033)variant: 36kv17 Nov 2026

Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map

What each value means

Methodology, both clocks, provenance and rights

Injection · Generation (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2029 (2029) · variant: 36kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/ROLLE 36 · payload sha256 28b490a6cd72…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
ROLLE 36
Operator note: flexibilityLevel
0%_flex
Operator note: variant
36kv
Operator note: voltage kv
36

Injection · Generation (any) · Available

4.5 MW

Granted

The operator's latest published dataset reports 4.5 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2029 (2029) · variant: 36kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/ROLLE 36 · payload sha256 28b490a6cd72…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
ROLLE 36
Operator note: flexibilityLevel
5%_flex
Operator note: variant
36kv
Operator note: voltage kv
36

Injection · Generation (any) · Available

6.2 MW

Granted

The operator's latest published dataset reports 6.2 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2029 (2029) · variant: 36kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/ROLLE 36 · payload sha256 28b490a6cd72…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
ROLLE 36
Operator note: flexibilityLevel
10%_flex
Operator note: variant
36kv
Operator note: voltage kv
36

Injection · Generation (any) · Available

10.7 MW

Granted

The operator's latest published dataset reports 10.7 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2029 (2029) · variant: 36kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/ROLLE 36 · payload sha256 28b490a6cd72…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
ROLLE 36
Operator note: flexibilityLevel
20%_flex
Operator note: variant
36kv
Operator note: voltage kv
36

Injection · Generation (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2033 (2033) · variant: 36kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/ROLLE 36 · payload sha256 29f56dc6af62…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
ROLLE 36
Operator note: flexibilityLevel
0%_flex
Operator note: variant
36kv
Operator note: voltage kv
36

Injection · Generation (any) · Available

4.5 MW

Granted

The operator's latest published dataset reports 4.5 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2033 (2033) · variant: 36kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/ROLLE 36 · payload sha256 29f56dc6af62…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
ROLLE 36
Operator note: flexibilityLevel
5%_flex
Operator note: variant
36kv
Operator note: voltage kv
36

Injection · Generation (any) · Available

6.2 MW

Granted

The operator's latest published dataset reports 6.2 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2033 (2033) · variant: 36kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/ROLLE 36 · payload sha256 29f56dc6af62…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
ROLLE 36
Operator note: flexibilityLevel
10%_flex
Operator note: variant
36kv
Operator note: voltage kv
36

Injection · Generation (any) · Available

10.7 MW

Granted

The operator's latest published dataset reports 10.7 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2033 (2033) · variant: 36kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/ROLLE 36 · payload sha256 29f56dc6af62…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
ROLLE 36
Operator note: flexibilityLevel
20%_flex
Operator note: variant
36kv
Operator note: voltage kv
36

Injection · Solar PV · Available

11.7 MW

Granted

The operator's latest published dataset reports 11.7 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2029 (2029) · variant: 36kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/ROLLE 36 · payload sha256 28b490a6cd72…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
ROLLE 36
Operator note: flexibilityLevel
0%_flex
Operator note: variant
36kv
Operator note: voltage kv
36

Injection · Solar PV · Available

20 MW

Granted

The operator's latest published dataset reports 20 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2029 (2029) · variant: 36kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/ROLLE 36 · payload sha256 28b490a6cd72…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
ROLLE 36
Operator note: flexibilityLevel
5%_flex
Operator note: variant
36kv
Operator note: voltage kv
36

Injection · Solar PV · Available

20 MW

Granted

The operator's latest published dataset reports 20 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2029 (2029) · variant: 36kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/ROLLE 36 · payload sha256 28b490a6cd72…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
ROLLE 36
Operator note: flexibilityLevel
10%_flex
Operator note: variant
36kv
Operator note: voltage kv
36

Injection · Solar PV · Available

20 MW

Granted

The operator's latest published dataset reports 20 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2029 (2029) · variant: 36kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/ROLLE 36 · payload sha256 28b490a6cd72…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
ROLLE 36
Operator note: flexibilityLevel
20%_flex
Operator note: variant
36kv
Operator note: voltage kv
36

Injection · Solar PV · Available

13.8 MW

Granted

The operator's latest published dataset reports 13.8 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2033 (2033) · variant: 36kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/ROLLE 36 · payload sha256 29f56dc6af62…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
ROLLE 36
Operator note: flexibilityLevel
0%_flex
Operator note: variant
36kv
Operator note: voltage kv
36

Injection · Solar PV · Available

20 MW

Granted

The operator's latest published dataset reports 20 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2033 (2033) · variant: 36kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/ROLLE 36 · payload sha256 29f56dc6af62…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
ROLLE 36
Operator note: flexibilityLevel
5%_flex
Operator note: variant
36kv
Operator note: voltage kv
36

Injection · Solar PV · Available

20 MW

Granted

The operator's latest published dataset reports 20 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2033 (2033) · variant: 36kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/ROLLE 36 · payload sha256 29f56dc6af62…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
ROLLE 36
Operator note: flexibilityLevel
10%_flex
Operator note: variant
36kv
Operator note: voltage kv
36

Injection · Solar PV · Available

20 MW

Granted

The operator's latest published dataset reports 20 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2033 (2033) · variant: 36kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/ROLLE 36 · payload sha256 29f56dc6af62…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
ROLLE 36
Operator note: flexibilityLevel
20%_flex
Operator note: variant
36kv
Operator note: voltage kv
36

Injection · Onshore wind · Available

9.8 MW

Granted

The operator's latest published dataset reports 9.8 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2029 (2029) · variant: 36kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/ROLLE 36 · payload sha256 28b490a6cd72…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
ROLLE 36
Operator note: flexibilityLevel
0%_flex
Operator note: variant
36kv
Operator note: voltage kv
36

Injection · Onshore wind · Available

20 MW

Granted

The operator's latest published dataset reports 20 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2029 (2029) · variant: 36kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/ROLLE 36 · payload sha256 28b490a6cd72…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
ROLLE 36
Operator note: flexibilityLevel
5%_flex
Operator note: variant
36kv
Operator note: voltage kv
36

Injection · Onshore wind · Available

20 MW

Granted

The operator's latest published dataset reports 20 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2029 (2029) · variant: 36kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/ROLLE 36 · payload sha256 28b490a6cd72…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
ROLLE 36
Operator note: flexibilityLevel
10%_flex
Operator note: variant
36kv
Operator note: voltage kv
36

Injection · Onshore wind · Available

20 MW

Granted

The operator's latest published dataset reports 20 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2029 (2029) · variant: 36kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/ROLLE 36 · payload sha256 28b490a6cd72…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
ROLLE 36
Operator note: flexibilityLevel
20%_flex
Operator note: variant
36kv
Operator note: voltage kv
36

Injection · Onshore wind · Available

9.8 MW

Granted

The operator's latest published dataset reports 9.8 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2033 (2033) · variant: 36kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/ROLLE 36 · payload sha256 29f56dc6af62…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
ROLLE 36
Operator note: flexibilityLevel
0%_flex
Operator note: variant
36kv
Operator note: voltage kv
36

Injection · Onshore wind · Available

20 MW

Granted

The operator's latest published dataset reports 20 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2033 (2033) · variant: 36kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/ROLLE 36 · payload sha256 29f56dc6af62…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
ROLLE 36
Operator note: flexibilityLevel
5%_flex
Operator note: variant
36kv
Operator note: voltage kv
36

Injection · Onshore wind · Available

20 MW

Granted

The operator's latest published dataset reports 20 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2033 (2033) · variant: 36kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/ROLLE 36 · payload sha256 29f56dc6af62…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
ROLLE 36
Operator note: flexibilityLevel
10%_flex
Operator note: variant
36kv
Operator note: voltage kv
36

Injection · Onshore wind · Available

20 MW

Granted

The operator's latest published dataset reports 20 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2033 (2033) · variant: 36kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/ROLLE 36 · payload sha256 29f56dc6af62…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
ROLLE 36
Operator note: flexibilityLevel
20%_flex
Operator note: variant
36kv
Operator note: voltage kv
36

Offtake · Load (any) · Available

13.9 MW

Granted

The operator's latest published dataset reports 13.9 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2029 (2029) · variant: 36kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/ROLLE 36 · payload sha256 28b490a6cd72…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
ROLLE 36
Operator note: flexibilityLevel
0%_flex
Operator note: variant
36kv
Operator note: voltage kv
36

Offtake · Load (any) · Available

20 MW

Granted

The operator's latest published dataset reports 20 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2029 (2029) · variant: 36kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/ROLLE 36 · payload sha256 28b490a6cd72…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
ROLLE 36
Operator note: flexibilityLevel
5%_flex
Operator note: variant
36kv
Operator note: voltage kv
36

Offtake · Load (any) · Available

20 MW

Granted

The operator's latest published dataset reports 20 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2029 (2029) · variant: 36kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/ROLLE 36 · payload sha256 28b490a6cd72…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
ROLLE 36
Operator note: flexibilityLevel
10%_flex
Operator note: variant
36kv
Operator note: voltage kv
36

Offtake · Load (any) · Available

20 MW

Granted

The operator's latest published dataset reports 20 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2029 (2029) · variant: 36kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/ROLLE 36 · payload sha256 28b490a6cd72…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
ROLLE 36
Operator note: flexibilityLevel
20%_flex
Operator note: variant
36kv
Operator note: voltage kv
36

Offtake · Load (any) · Available

20 MW

Granted

The operator's latest published dataset reports 20 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2033 (2033) · variant: 36kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/ROLLE 36 · payload sha256 29f56dc6af62…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
ROLLE 36
Operator note: flexibilityLevel
0%_flex
Operator note: variant
36kv
Operator note: voltage kv
36

Offtake · Load (any) · Available

20 MW

Granted

The operator's latest published dataset reports 20 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2033 (2033) · variant: 36kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/ROLLE 36 · payload sha256 29f56dc6af62…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
ROLLE 36
Operator note: flexibilityLevel
5%_flex
Operator note: variant
36kv
Operator note: voltage kv
36

Offtake · Load (any) · Available

20 MW

Granted

The operator's latest published dataset reports 20 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2033 (2033) · variant: 36kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/ROLLE 36 · payload sha256 29f56dc6af62…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
ROLLE 36
Operator note: flexibilityLevel
10%_flex
Operator note: variant
36kv
Operator note: voltage kv
36

Offtake · Load (any) · Available

20 MW

Granted

The operator's latest published dataset reports 20 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2033 (2033) · variant: 36kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/ROLLE 36 · payload sha256 29f56dc6af62…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
ROLLE 36
Operator note: flexibilityLevel
20%_flex
Operator note: variant
36kv
Operator note: voltage kv
36

Bidirectional · Battery · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2029 (2029) · variant: 36kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/ROLLE 36 · payload sha256 28b490a6cd72…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
ROLLE 36
Operator note: flexibilityLevel
0%_flex
Operator note: variant
36kv
Operator note: voltage kv
36

Bidirectional · Battery · Available

4.5 MW

Granted

The operator's latest published dataset reports 4.5 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2029 (2029) · variant: 36kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/ROLLE 36 · payload sha256 28b490a6cd72…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
ROLLE 36
Operator note: flexibilityLevel
5%_flex
Operator note: variant
36kv
Operator note: voltage kv
36

Bidirectional · Battery · Available

6.2 MW

Granted

The operator's latest published dataset reports 6.2 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2029 (2029) · variant: 36kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/ROLLE 36 · payload sha256 28b490a6cd72…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
ROLLE 36
Operator note: flexibilityLevel
10%_flex
Operator note: variant
36kv
Operator note: voltage kv
36

Bidirectional · Battery · Available

10.7 MW

Granted

The operator's latest published dataset reports 10.7 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2029 (2029) · variant: 36kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/ROLLE 36 · payload sha256 28b490a6cd72…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
ROLLE 36
Operator note: flexibilityLevel
20%_flex
Operator note: variant
36kv
Operator note: voltage kv
36

Bidirectional · Battery · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2033 (2033) · variant: 36kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/ROLLE 36 · payload sha256 29f56dc6af62…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
ROLLE 36
Operator note: flexibilityLevel
0%_flex
Operator note: variant
36kv
Operator note: voltage kv
36

Bidirectional · Battery · Available

4.5 MW

Granted

The operator's latest published dataset reports 4.5 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2033 (2033) · variant: 36kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/ROLLE 36 · payload sha256 29f56dc6af62…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
ROLLE 36
Operator note: flexibilityLevel
5%_flex
Operator note: variant
36kv
Operator note: voltage kv
36

Bidirectional · Battery · Available

6.2 MW

Granted

The operator's latest published dataset reports 6.2 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2033 (2033) · variant: 36kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/ROLLE 36 · payload sha256 29f56dc6af62…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
ROLLE 36
Operator note: flexibilityLevel
10%_flex
Operator note: variant
36kv
Operator note: voltage kv
36

Bidirectional · Battery · Available

10.7 MW

Granted

The operator's latest published dataset reports 10.7 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2033 (2033) · variant: 36kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/ROLLE 36 · payload sha256 29f56dc6af62…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
ROLLE 36
Operator note: flexibilityLevel
20%_flex
Operator note: variant
36kv
Operator note: voltage kv
36

History

Served series only

Bidirectional · Battery · Available · 2029

current 0 MW

17 Nov 2026: 0 MW
17 Nov 2026range 0 to 0 MW24 Nov 2026
1 published value, as a table
Observed fromUntilValue
17 Nov 2026current0 MW

Time axis: when we observed each value, not the operator’s effective date.

Bidirectional · Battery · Available · 2029

current 4.5 MW

17 Nov 2026: 4.5 MW
17 Nov 2026range 4.5 to 4.5 MW24 Nov 2026
1 published value, as a table
Observed fromUntilValue
17 Nov 2026current4.5 MW

Time axis: when we observed each value, not the operator’s effective date.

Bidirectional · Battery · Available · 2029

current 6.2 MW

17 Nov 2026: 6.2 MW
17 Nov 2026range 6.2 to 6.2 MW24 Nov 2026
1 published value, as a table
Observed fromUntilValue
17 Nov 2026current6.2 MW

Time axis: when we observed each value, not the operator’s effective date.

Bidirectional · Battery · Available · 2029

current 10.7 MW

17 Nov 2026: 10.7 MW
17 Nov 2026range 10.7 to 10.7 MW24 Nov 2026
1 published value, as a table
Observed fromUntilValue
17 Nov 2026current10.7 MW

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Load (any) · Available · 2029

current 13.9 MW

17 Nov 2026: 13.9 MW
17 Nov 2026range 13.9 to 13.9 MW24 Nov 2026
1 published value, as a table
Observed fromUntilValue
17 Nov 2026current13.9 MW

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Load (any) · Available · 2029

current 20 MW

17 Nov 2026: 20 MW
17 Nov 2026range 20 to 20 MW24 Nov 2026
1 published value, as a table
Observed fromUntilValue
17 Nov 2026current20 MW

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Load (any) · Available · 2029

current 20 MW

17 Nov 2026: 20 MW
17 Nov 2026range 20 to 20 MW24 Nov 2026
1 published value, as a table
Observed fromUntilValue
17 Nov 2026current20 MW

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Load (any) · Available · 2029

current 20 MW

17 Nov 2026: 20 MW
17 Nov 2026range 20 to 20 MW24 Nov 2026
1 published value, as a table
Observed fromUntilValue
17 Nov 2026current20 MW

Time axis: when we observed each value, not the operator’s effective date.

Injection · Generation (any) · Available · 2029

current 0 MW

17 Nov 2026: 0 MW
17 Nov 2026range 0 to 0 MW24 Nov 2026
1 published value, as a table
Observed fromUntilValue
17 Nov 2026current0 MW

Time axis: when we observed each value, not the operator’s effective date.

Injection · Generation (any) · Available · 2029

current 4.5 MW

17 Nov 2026: 4.5 MW
17 Nov 2026range 4.5 to 4.5 MW24 Nov 2026
1 published value, as a table
Observed fromUntilValue
17 Nov 2026current4.5 MW

Time axis: when we observed each value, not the operator’s effective date.

Injection · Generation (any) · Available · 2029

current 6.2 MW

17 Nov 2026: 6.2 MW
17 Nov 2026range 6.2 to 6.2 MW24 Nov 2026
1 published value, as a table
Observed fromUntilValue
17 Nov 2026current6.2 MW

Time axis: when we observed each value, not the operator’s effective date.

Injection · Generation (any) · Available · 2029

current 10.7 MW

17 Nov 2026: 10.7 MW
17 Nov 2026range 10.7 to 10.7 MW24 Nov 2026
1 published value, as a table
Observed fromUntilValue
17 Nov 2026current10.7 MW

Time axis: when we observed each value, not the operator’s effective date.

The first 12 of 40 served series with a history. The history route returns every one of them.

Through the API

curl "https://api.gridcapacityapi.com/v1/substations/sub_06gyf8fn31tk59a7x2xazq9rdm/capacity" \  -H "Authorization: Bearer gc_live_..."