Substation / 380 kV

RIMIE

Elia Transmission Belgium / Belgium

Latest published values

120 served · 0 withheld

Each row is what the operator’s latest published dataset reports for one combination of direction, technology, measure, firmness and horizon. Hosting-capacity figures are indicative and reflect what operators publish. They are not a connection offer; only the operator can confirm capacity for a specific request.

Latest published capacity values, one row per series
DirectionTechnologyMeasureValueFirmnessHorizonSource date
InjectionGeneration (any)Available93.3 MWFirm, ≤ 0 % curtailment a year2029 (2029)variant: 380kv17 Nov 2026
InjectionGeneration (any)Available20.3 MWFirm, ≤ 0 % curtailment a year2029 (2029)variant: 220kv17 Nov 2026
InjectionGeneration (any)Available19.3 MWFirm, ≤ 0 % curtailment a year2029 (2029)variant: 70kv17 Nov 2026
InjectionGeneration (any)Available300 MWFlexible, ≤ 5 % curtailment a year2029 (2029)variant: 380kv17 Nov 2026
InjectionGeneration (any)Available53.8 MWFlexible, ≤ 5 % curtailment a year2029 (2029)variant: 220kv17 Nov 2026
InjectionGeneration (any)Available50 MWFlexible, ≤ 5 % curtailment a year2029 (2029)variant: 70kv17 Nov 2026
InjectionGeneration (any)Available300 MWFlexible, ≤ 10 % curtailment a year2029 (2029)variant: 380kv17 Nov 2026
InjectionGeneration (any)Available153 MWFlexible, ≤ 10 % curtailment a year2029 (2029)variant: 220kv17 Nov 2026
InjectionGeneration (any)Available50 MWFlexible, ≤ 10 % curtailment a year2029 (2029)variant: 70kv17 Nov 2026
InjectionGeneration (any)Available300 MWFlexible, ≤ 20 % curtailment a year2029 (2029)variant: 380kv17 Nov 2026
InjectionGeneration (any)Available175 MWFlexible, ≤ 20 % curtailment a year2029 (2029)variant: 220kv17 Nov 2026
InjectionGeneration (any)Available50 MWFlexible, ≤ 20 % curtailment a year2029 (2029)variant: 70kv17 Nov 2026
InjectionGeneration (any)Available294.7 MWFirm, ≤ 0 % curtailment a year2033 (2033)variant: 380kv17 Nov 2026
InjectionGeneration (any)Available20.3 MWFirm, ≤ 0 % curtailment a year2033 (2033)variant: 220kv17 Nov 2026
InjectionGeneration (any)Available19.3 MWFirm, ≤ 0 % curtailment a year2033 (2033)variant: 70kv17 Nov 2026
InjectionGeneration (any)Available300 MWFlexible, ≤ 5 % curtailment a year2033 (2033)variant: 380kv17 Nov 2026
InjectionGeneration (any)Available53.8 MWFlexible, ≤ 5 % curtailment a year2033 (2033)variant: 220kv17 Nov 2026
InjectionGeneration (any)Available50 MWFlexible, ≤ 5 % curtailment a year2033 (2033)variant: 70kv17 Nov 2026
InjectionGeneration (any)Available300 MWFlexible, ≤ 10 % curtailment a year2033 (2033)variant: 380kv17 Nov 2026
InjectionGeneration (any)Available153 MWFlexible, ≤ 10 % curtailment a year2033 (2033)variant: 220kv17 Nov 2026
InjectionGeneration (any)Available50 MWFlexible, ≤ 10 % curtailment a year2033 (2033)variant: 70kv17 Nov 2026
InjectionGeneration (any)Available300 MWFlexible, ≤ 20 % curtailment a year2033 (2033)variant: 380kv17 Nov 2026
InjectionGeneration (any)Available175 MWFlexible, ≤ 20 % curtailment a year2033 (2033)variant: 220kv17 Nov 2026
InjectionGeneration (any)Available50 MWFlexible, ≤ 20 % curtailment a year2033 (2033)variant: 70kv17 Nov 2026
InjectionSolar PVAvailable300 MWFirm, ≤ 0 % curtailment a year2029 (2029)variant: 380kv17 Nov 2026
InjectionSolar PVAvailable69.4 MWFirm, ≤ 0 % curtailment a year2029 (2029)variant: 220kv17 Nov 2026
InjectionSolar PVAvailable50 MWFirm, ≤ 0 % curtailment a year2029 (2029)variant: 70kv17 Nov 2026
InjectionSolar PVAvailable300 MWFlexible, ≤ 5 % curtailment a year2029 (2029)variant: 380kv17 Nov 2026
InjectionSolar PVAvailable175 MWFlexible, ≤ 5 % curtailment a year2029 (2029)variant: 220kv17 Nov 2026
InjectionSolar PVAvailable50 MWFlexible, ≤ 5 % curtailment a year2029 (2029)variant: 70kv17 Nov 2026
InjectionSolar PVAvailable300 MWFlexible, ≤ 10 % curtailment a year2029 (2029)variant: 380kv17 Nov 2026
InjectionSolar PVAvailable175 MWFlexible, ≤ 10 % curtailment a year2029 (2029)variant: 220kv17 Nov 2026
InjectionSolar PVAvailable50 MWFlexible, ≤ 10 % curtailment a year2029 (2029)variant: 70kv17 Nov 2026
InjectionSolar PVAvailable300 MWFlexible, ≤ 20 % curtailment a year2029 (2029)variant: 380kv17 Nov 2026
InjectionSolar PVAvailable175 MWFlexible, ≤ 20 % curtailment a year2029 (2029)variant: 220kv17 Nov 2026
InjectionSolar PVAvailable50 MWFlexible, ≤ 20 % curtailment a year2029 (2029)variant: 70kv17 Nov 2026
InjectionSolar PVAvailable300 MWFirm, ≤ 0 % curtailment a year2033 (2033)variant: 380kv17 Nov 2026
InjectionSolar PVAvailable175 MWFirm, ≤ 0 % curtailment a year2033 (2033)variant: 220kv17 Nov 2026
InjectionSolar PVAvailable50 MWFirm, ≤ 0 % curtailment a year2033 (2033)variant: 70kv17 Nov 2026
InjectionSolar PVAvailable300 MWFlexible, ≤ 5 % curtailment a year2033 (2033)variant: 380kv17 Nov 2026
InjectionSolar PVAvailable175 MWFlexible, ≤ 5 % curtailment a year2033 (2033)variant: 220kv17 Nov 2026
InjectionSolar PVAvailable50 MWFlexible, ≤ 5 % curtailment a year2033 (2033)variant: 70kv17 Nov 2026
InjectionSolar PVAvailable300 MWFlexible, ≤ 10 % curtailment a year2033 (2033)variant: 380kv17 Nov 2026
InjectionSolar PVAvailable175 MWFlexible, ≤ 10 % curtailment a year2033 (2033)variant: 220kv17 Nov 2026
InjectionSolar PVAvailable50 MWFlexible, ≤ 10 % curtailment a year2033 (2033)variant: 70kv17 Nov 2026
InjectionSolar PVAvailable300 MWFlexible, ≤ 20 % curtailment a year2033 (2033)variant: 380kv17 Nov 2026
InjectionSolar PVAvailable175 MWFlexible, ≤ 20 % curtailment a year2033 (2033)variant: 220kv17 Nov 2026
InjectionSolar PVAvailable50 MWFlexible, ≤ 20 % curtailment a year2033 (2033)variant: 70kv17 Nov 2026
InjectionOnshore windAvailable300 MWFirm, ≤ 0 % curtailment a year2029 (2029)variant: 380kv17 Nov 2026
InjectionOnshore windAvailable175 MWFirm, ≤ 0 % curtailment a year2029 (2029)variant: 220kv17 Nov 2026
InjectionOnshore windAvailable50 MWFirm, ≤ 0 % curtailment a year2029 (2029)variant: 70kv17 Nov 2026
InjectionOnshore windAvailable300 MWFlexible, ≤ 5 % curtailment a year2029 (2029)variant: 380kv17 Nov 2026
InjectionOnshore windAvailable175 MWFlexible, ≤ 5 % curtailment a year2029 (2029)variant: 220kv17 Nov 2026
InjectionOnshore windAvailable50 MWFlexible, ≤ 5 % curtailment a year2029 (2029)variant: 70kv17 Nov 2026
InjectionOnshore windAvailable300 MWFlexible, ≤ 10 % curtailment a year2029 (2029)variant: 380kv17 Nov 2026
InjectionOnshore windAvailable175 MWFlexible, ≤ 10 % curtailment a year2029 (2029)variant: 220kv17 Nov 2026
InjectionOnshore windAvailable50 MWFlexible, ≤ 10 % curtailment a year2029 (2029)variant: 70kv17 Nov 2026
InjectionOnshore windAvailable300 MWFlexible, ≤ 20 % curtailment a year2029 (2029)variant: 380kv17 Nov 2026
InjectionOnshore windAvailable175 MWFlexible, ≤ 20 % curtailment a year2029 (2029)variant: 220kv17 Nov 2026
InjectionOnshore windAvailable50 MWFlexible, ≤ 20 % curtailment a year2029 (2029)variant: 70kv17 Nov 2026
InjectionOnshore windAvailable300 MWFirm, ≤ 0 % curtailment a year2033 (2033)variant: 380kv17 Nov 2026
InjectionOnshore windAvailable175 MWFirm, ≤ 0 % curtailment a year2033 (2033)variant: 220kv17 Nov 2026
InjectionOnshore windAvailable50 MWFirm, ≤ 0 % curtailment a year2033 (2033)variant: 70kv17 Nov 2026
InjectionOnshore windAvailable300 MWFlexible, ≤ 5 % curtailment a year2033 (2033)variant: 380kv17 Nov 2026
InjectionOnshore windAvailable175 MWFlexible, ≤ 5 % curtailment a year2033 (2033)variant: 220kv17 Nov 2026
InjectionOnshore windAvailable50 MWFlexible, ≤ 5 % curtailment a year2033 (2033)variant: 70kv17 Nov 2026
InjectionOnshore windAvailable300 MWFlexible, ≤ 10 % curtailment a year2033 (2033)variant: 380kv17 Nov 2026
InjectionOnshore windAvailable175 MWFlexible, ≤ 10 % curtailment a year2033 (2033)variant: 220kv17 Nov 2026
InjectionOnshore windAvailable50 MWFlexible, ≤ 10 % curtailment a year2033 (2033)variant: 70kv17 Nov 2026
InjectionOnshore windAvailable300 MWFlexible, ≤ 20 % curtailment a year2033 (2033)variant: 380kv17 Nov 2026
InjectionOnshore windAvailable175 MWFlexible, ≤ 20 % curtailment a year2033 (2033)variant: 220kv17 Nov 2026
InjectionOnshore windAvailable50 MWFlexible, ≤ 20 % curtailment a year2033 (2033)variant: 70kv17 Nov 2026
OfftakeLoad (any)Available176.7 MWFirm, ≤ 0 % curtailment a year2029 (2029)variant: 380kv17 Nov 2026
OfftakeLoad (any)Available22.2 MWFirm, ≤ 0 % curtailment a year2029 (2029)variant: 220kv17 Nov 2026
OfftakeLoad (any)Available0 MWFirm, ≤ 0 % curtailment a year2029 (2029)variant: 70kv17 Nov 2026
OfftakeLoad (any)Available300 MWFlexible, ≤ 5 % curtailment a year2029 (2029)variant: 380kv17 Nov 2026
OfftakeLoad (any)Available50.2 MWFlexible, ≤ 5 % curtailment a year2029 (2029)variant: 220kv17 Nov 2026
OfftakeLoad (any)Available48.4 MWFlexible, ≤ 5 % curtailment a year2029 (2029)variant: 70kv17 Nov 2026
OfftakeLoad (any)Available300 MWFlexible, ≤ 10 % curtailment a year2029 (2029)variant: 380kv17 Nov 2026
OfftakeLoad (any)Available120.3 MWFlexible, ≤ 10 % curtailment a year2029 (2029)variant: 220kv17 Nov 2026
OfftakeLoad (any)Available50 MWFlexible, ≤ 10 % curtailment a year2029 (2029)variant: 70kv17 Nov 2026
OfftakeLoad (any)Available300 MWFlexible, ≤ 20 % curtailment a year2029 (2029)variant: 380kv17 Nov 2026
OfftakeLoad (any)Available175 MWFlexible, ≤ 20 % curtailment a year2029 (2029)variant: 220kv17 Nov 2026
OfftakeLoad (any)Available50 MWFlexible, ≤ 20 % curtailment a year2029 (2029)variant: 70kv17 Nov 2026
OfftakeLoad (any)Available300 MWFirm, ≤ 0 % curtailment a year2033 (2033)variant: 380kv17 Nov 2026
OfftakeLoad (any)Available175 MWFirm, ≤ 0 % curtailment a year2033 (2033)variant: 220kv17 Nov 2026
OfftakeLoad (any)Available0 MWFirm, ≤ 0 % curtailment a year2033 (2033)variant: 70kv17 Nov 2026
OfftakeLoad (any)Available300 MWFlexible, ≤ 5 % curtailment a year2033 (2033)variant: 380kv17 Nov 2026
OfftakeLoad (any)Available175 MWFlexible, ≤ 5 % curtailment a year2033 (2033)variant: 220kv17 Nov 2026
OfftakeLoad (any)Available50 MWFlexible, ≤ 5 % curtailment a year2033 (2033)variant: 70kv17 Nov 2026
OfftakeLoad (any)Available300 MWFlexible, ≤ 10 % curtailment a year2033 (2033)variant: 380kv17 Nov 2026
OfftakeLoad (any)Available175 MWFlexible, ≤ 10 % curtailment a year2033 (2033)variant: 220kv17 Nov 2026
OfftakeLoad (any)Available50 MWFlexible, ≤ 10 % curtailment a year2033 (2033)variant: 70kv17 Nov 2026
OfftakeLoad (any)Available300 MWFlexible, ≤ 20 % curtailment a year2033 (2033)variant: 380kv17 Nov 2026
OfftakeLoad (any)Available175 MWFlexible, ≤ 20 % curtailment a year2033 (2033)variant: 220kv17 Nov 2026
OfftakeLoad (any)Available50 MWFlexible, ≤ 20 % curtailment a year2033 (2033)variant: 70kv17 Nov 2026
BidirectionalBatteryAvailable93.3 MWFirm, ≤ 0 % curtailment a year2029 (2029)variant: 380kv17 Nov 2026
BidirectionalBatteryAvailable20.3 MWFirm, ≤ 0 % curtailment a year2029 (2029)variant: 220kv17 Nov 2026
BidirectionalBatteryAvailable0 MWFirm, ≤ 0 % curtailment a year2029 (2029)variant: 70kv17 Nov 2026
BidirectionalBatteryAvailable300 MWFlexible, ≤ 5 % curtailment a year2029 (2029)variant: 380kv17 Nov 2026
BidirectionalBatteryAvailable39.6 MWFlexible, ≤ 5 % curtailment a year2029 (2029)variant: 220kv17 Nov 2026
BidirectionalBatteryAvailable33.1 MWFlexible, ≤ 5 % curtailment a year2029 (2029)variant: 70kv17 Nov 2026
BidirectionalBatteryAvailable300 MWFlexible, ≤ 10 % curtailment a year2029 (2029)variant: 380kv17 Nov 2026
BidirectionalBatteryAvailable81.3 MWFlexible, ≤ 10 % curtailment a year2029 (2029)variant: 220kv17 Nov 2026
BidirectionalBatteryAvailable50 MWFlexible, ≤ 10 % curtailment a year2029 (2029)variant: 70kv17 Nov 2026
BidirectionalBatteryAvailable300 MWFlexible, ≤ 20 % curtailment a year2029 (2029)variant: 380kv17 Nov 2026
BidirectionalBatteryAvailable175 MWFlexible, ≤ 20 % curtailment a year2029 (2029)variant: 220kv17 Nov 2026
BidirectionalBatteryAvailable50 MWFlexible, ≤ 20 % curtailment a year2029 (2029)variant: 70kv17 Nov 2026
BidirectionalBatteryAvailable294.7 MWFirm, ≤ 0 % curtailment a year2033 (2033)variant: 380kv17 Nov 2026
BidirectionalBatteryAvailable20.3 MWFirm, ≤ 0 % curtailment a year2033 (2033)variant: 220kv17 Nov 2026
BidirectionalBatteryAvailable0 MWFirm, ≤ 0 % curtailment a year2033 (2033)variant: 70kv17 Nov 2026
BidirectionalBatteryAvailable300 MWFlexible, ≤ 5 % curtailment a year2033 (2033)variant: 380kv17 Nov 2026
BidirectionalBatteryAvailable53.8 MWFlexible, ≤ 5 % curtailment a year2033 (2033)variant: 220kv17 Nov 2026
BidirectionalBatteryAvailable50 MWFlexible, ≤ 5 % curtailment a year2033 (2033)variant: 70kv17 Nov 2026
BidirectionalBatteryAvailable300 MWFlexible, ≤ 10 % curtailment a year2033 (2033)variant: 380kv17 Nov 2026
BidirectionalBatteryAvailable153 MWFlexible, ≤ 10 % curtailment a year2033 (2033)variant: 220kv17 Nov 2026
BidirectionalBatteryAvailable50 MWFlexible, ≤ 10 % curtailment a year2033 (2033)variant: 70kv17 Nov 2026
BidirectionalBatteryAvailable300 MWFlexible, ≤ 20 % curtailment a year2033 (2033)variant: 380kv17 Nov 2026
BidirectionalBatteryAvailable175 MWFlexible, ≤ 20 % curtailment a year2033 (2033)variant: 220kv17 Nov 2026
BidirectionalBatteryAvailable50 MWFlexible, ≤ 20 % curtailment a year2033 (2033)variant: 70kv17 Nov 2026

Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map

What each value means

Methodology, both clocks, provenance and rights

Injection · Generation (any) · Available

93.3 MW

Granted

The operator's latest published dataset reports 93.3 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2029 (2029) · variant: 380kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/RIMIE380 · payload sha256 e60f9b7cf659…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
RIMIE380
Operator note: flexibilityLevel
0%_flex
Operator note: variant
380kv
Operator note: voltage kv
380

Injection · Generation (any) · Available

20.3 MW

Granted

The operator's latest published dataset reports 20.3 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2029 (2029) · variant: 220kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/RIMIE220 · payload sha256 fc23dbfe730e…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
RIMIE220
Operator note: flexibilityLevel
0%_flex
Operator note: variant
220kv
Operator note: voltage kv
220

Injection · Generation (any) · Available

19.3 MW

Granted

The operator's latest published dataset reports 19.3 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2029 (2029) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/RIMIE 70 · payload sha256 ca6ac2eae672…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
RIMIE 70
Operator note: flexibilityLevel
0%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

Injection · Generation (any) · Available

300 MW

Granted

The operator's latest published dataset reports 300 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2029 (2029) · variant: 380kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/RIMIE380 · payload sha256 e60f9b7cf659…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at published maximum mw
300
Operator note: at voltage level cap
true
Operator note: code
RIMIE380
Operator note: flexibilityLevel
5%_flex
Operator note: variant
380kv
Operator note: voltage kv
380

Injection · Generation (any) · Available

53.8 MW

Granted

The operator's latest published dataset reports 53.8 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2029 (2029) · variant: 220kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/RIMIE220 · payload sha256 fc23dbfe730e…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
RIMIE220
Operator note: flexibilityLevel
5%_flex
Operator note: variant
220kv
Operator note: voltage kv
220

Injection · Generation (any) · Available

50 MW

Granted

The operator's latest published dataset reports 50 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2029 (2029) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/RIMIE 70 · payload sha256 ca6ac2eae672…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
RIMIE 70
Operator note: flexibilityLevel
5%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

Injection · Generation (any) · Available

300 MW

Granted

The operator's latest published dataset reports 300 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2029 (2029) · variant: 380kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/RIMIE380 · payload sha256 e60f9b7cf659…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at published maximum mw
300
Operator note: at voltage level cap
true
Operator note: code
RIMIE380
Operator note: flexibilityLevel
10%_flex
Operator note: variant
380kv
Operator note: voltage kv
380

Injection · Generation (any) · Available

153 MW

Granted

The operator's latest published dataset reports 153 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2029 (2029) · variant: 220kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/RIMIE220 · payload sha256 fc23dbfe730e…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
RIMIE220
Operator note: flexibilityLevel
10%_flex
Operator note: variant
220kv
Operator note: voltage kv
220

Injection · Generation (any) · Available

50 MW

Granted

The operator's latest published dataset reports 50 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2029 (2029) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/RIMIE 70 · payload sha256 ca6ac2eae672…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
RIMIE 70
Operator note: flexibilityLevel
10%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

Injection · Generation (any) · Available

300 MW

Granted

The operator's latest published dataset reports 300 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2029 (2029) · variant: 380kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/RIMIE380 · payload sha256 e60f9b7cf659…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at published maximum mw
300
Operator note: at voltage level cap
true
Operator note: code
RIMIE380
Operator note: flexibilityLevel
20%_flex
Operator note: variant
380kv
Operator note: voltage kv
380

Injection · Generation (any) · Available

175 MW

Granted

The operator's latest published dataset reports 175 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2029 (2029) · variant: 220kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/RIMIE220 · payload sha256 fc23dbfe730e…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
RIMIE220
Operator note: flexibilityLevel
20%_flex
Operator note: variant
220kv
Operator note: voltage kv
220

Injection · Generation (any) · Available

50 MW

Granted

The operator's latest published dataset reports 50 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2029 (2029) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/RIMIE 70 · payload sha256 ca6ac2eae672…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
RIMIE 70
Operator note: flexibilityLevel
20%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

Injection · Generation (any) · Available

294.7 MW

Granted

The operator's latest published dataset reports 294.7 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2033 (2033) · variant: 380kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/RIMIE380 · payload sha256 b369a409376b…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
RIMIE380
Operator note: flexibilityLevel
0%_flex
Operator note: variant
380kv
Operator note: voltage kv
380

Injection · Generation (any) · Available

20.3 MW

Granted

The operator's latest published dataset reports 20.3 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2033 (2033) · variant: 220kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/RIMIE220 · payload sha256 0d316d7cef0a…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
RIMIE220
Operator note: flexibilityLevel
0%_flex
Operator note: variant
220kv
Operator note: voltage kv
220

Injection · Generation (any) · Available

19.3 MW

Granted

The operator's latest published dataset reports 19.3 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2033 (2033) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/RIMIE 70 · payload sha256 336e6bb58c86…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
RIMIE 70
Operator note: flexibilityLevel
0%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

Injection · Generation (any) · Available

300 MW

Granted

The operator's latest published dataset reports 300 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2033 (2033) · variant: 380kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/RIMIE380 · payload sha256 b369a409376b…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at published maximum mw
300
Operator note: at voltage level cap
true
Operator note: code
RIMIE380
Operator note: flexibilityLevel
5%_flex
Operator note: variant
380kv
Operator note: voltage kv
380

Injection · Generation (any) · Available

53.8 MW

Granted

The operator's latest published dataset reports 53.8 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2033 (2033) · variant: 220kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/RIMIE220 · payload sha256 0d316d7cef0a…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
RIMIE220
Operator note: flexibilityLevel
5%_flex
Operator note: variant
220kv
Operator note: voltage kv
220

Injection · Generation (any) · Available

50 MW

Granted

The operator's latest published dataset reports 50 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2033 (2033) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/RIMIE 70 · payload sha256 336e6bb58c86…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
RIMIE 70
Operator note: flexibilityLevel
5%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

Injection · Generation (any) · Available

300 MW

Granted

The operator's latest published dataset reports 300 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2033 (2033) · variant: 380kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/RIMIE380 · payload sha256 b369a409376b…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at published maximum mw
300
Operator note: at voltage level cap
true
Operator note: code
RIMIE380
Operator note: flexibilityLevel
10%_flex
Operator note: variant
380kv
Operator note: voltage kv
380

Injection · Generation (any) · Available

153 MW

Granted

The operator's latest published dataset reports 153 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2033 (2033) · variant: 220kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/RIMIE220 · payload sha256 0d316d7cef0a…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
RIMIE220
Operator note: flexibilityLevel
10%_flex
Operator note: variant
220kv
Operator note: voltage kv
220

Injection · Generation (any) · Available

50 MW

Granted

The operator's latest published dataset reports 50 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2033 (2033) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/RIMIE 70 · payload sha256 336e6bb58c86…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
RIMIE 70
Operator note: flexibilityLevel
10%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

Injection · Generation (any) · Available

300 MW

Granted

The operator's latest published dataset reports 300 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2033 (2033) · variant: 380kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/RIMIE380 · payload sha256 b369a409376b…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at published maximum mw
300
Operator note: at voltage level cap
true
Operator note: code
RIMIE380
Operator note: flexibilityLevel
20%_flex
Operator note: variant
380kv
Operator note: voltage kv
380

Injection · Generation (any) · Available

175 MW

Granted

The operator's latest published dataset reports 175 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2033 (2033) · variant: 220kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/RIMIE220 · payload sha256 0d316d7cef0a…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
RIMIE220
Operator note: flexibilityLevel
20%_flex
Operator note: variant
220kv
Operator note: voltage kv
220

Injection · Generation (any) · Available

50 MW

Granted

The operator's latest published dataset reports 50 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2033 (2033) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/RIMIE 70 · payload sha256 336e6bb58c86…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
RIMIE 70
Operator note: flexibilityLevel
20%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

Injection · Solar PV · Available

300 MW

Granted

The operator's latest published dataset reports 300 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2029 (2029) · variant: 380kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/RIMIE380 · payload sha256 e60f9b7cf659…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at published maximum mw
300
Operator note: at voltage level cap
true
Operator note: code
RIMIE380
Operator note: flexibilityLevel
0%_flex
Operator note: variant
380kv
Operator note: voltage kv
380

Injection · Solar PV · Available

69.4 MW

Granted

The operator's latest published dataset reports 69.4 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2029 (2029) · variant: 220kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/RIMIE220 · payload sha256 fc23dbfe730e…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
RIMIE220
Operator note: flexibilityLevel
0%_flex
Operator note: variant
220kv
Operator note: voltage kv
220

Injection · Solar PV · Available

50 MW

Granted

The operator's latest published dataset reports 50 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2029 (2029) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/RIMIE 70 · payload sha256 ca6ac2eae672…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
RIMIE 70
Operator note: flexibilityLevel
0%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

Injection · Solar PV · Available

300 MW

Granted

The operator's latest published dataset reports 300 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2029 (2029) · variant: 380kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/RIMIE380 · payload sha256 e60f9b7cf659…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at published maximum mw
300
Operator note: at voltage level cap
true
Operator note: code
RIMIE380
Operator note: flexibilityLevel
5%_flex
Operator note: variant
380kv
Operator note: voltage kv
380

Injection · Solar PV · Available

175 MW

Granted

The operator's latest published dataset reports 175 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2029 (2029) · variant: 220kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/RIMIE220 · payload sha256 fc23dbfe730e…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
RIMIE220
Operator note: flexibilityLevel
5%_flex
Operator note: variant
220kv
Operator note: voltage kv
220

Injection · Solar PV · Available

50 MW

Granted

The operator's latest published dataset reports 50 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2029 (2029) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/RIMIE 70 · payload sha256 ca6ac2eae672…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
RIMIE 70
Operator note: flexibilityLevel
5%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

Injection · Solar PV · Available

300 MW

Granted

The operator's latest published dataset reports 300 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2029 (2029) · variant: 380kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/RIMIE380 · payload sha256 e60f9b7cf659…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at published maximum mw
300
Operator note: at voltage level cap
true
Operator note: code
RIMIE380
Operator note: flexibilityLevel
10%_flex
Operator note: variant
380kv
Operator note: voltage kv
380

Injection · Solar PV · Available

175 MW

Granted

The operator's latest published dataset reports 175 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2029 (2029) · variant: 220kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/RIMIE220 · payload sha256 fc23dbfe730e…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
RIMIE220
Operator note: flexibilityLevel
10%_flex
Operator note: variant
220kv
Operator note: voltage kv
220

Injection · Solar PV · Available

50 MW

Granted

The operator's latest published dataset reports 50 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2029 (2029) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/RIMIE 70 · payload sha256 ca6ac2eae672…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
RIMIE 70
Operator note: flexibilityLevel
10%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

Injection · Solar PV · Available

300 MW

Granted

The operator's latest published dataset reports 300 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2029 (2029) · variant: 380kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/RIMIE380 · payload sha256 e60f9b7cf659…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at published maximum mw
300
Operator note: at voltage level cap
true
Operator note: code
RIMIE380
Operator note: flexibilityLevel
20%_flex
Operator note: variant
380kv
Operator note: voltage kv
380

Injection · Solar PV · Available

175 MW

Granted

The operator's latest published dataset reports 175 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2029 (2029) · variant: 220kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/RIMIE220 · payload sha256 fc23dbfe730e…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
RIMIE220
Operator note: flexibilityLevel
20%_flex
Operator note: variant
220kv
Operator note: voltage kv
220

Injection · Solar PV · Available

50 MW

Granted

The operator's latest published dataset reports 50 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2029 (2029) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/RIMIE 70 · payload sha256 ca6ac2eae672…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
RIMIE 70
Operator note: flexibilityLevel
20%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

Injection · Solar PV · Available

300 MW

Granted

The operator's latest published dataset reports 300 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2033 (2033) · variant: 380kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/RIMIE380 · payload sha256 b369a409376b…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at published maximum mw
300
Operator note: at voltage level cap
true
Operator note: code
RIMIE380
Operator note: flexibilityLevel
0%_flex
Operator note: variant
380kv
Operator note: voltage kv
380

Injection · Solar PV · Available

175 MW

Granted

The operator's latest published dataset reports 175 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2033 (2033) · variant: 220kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/RIMIE220 · payload sha256 0d316d7cef0a…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
RIMIE220
Operator note: flexibilityLevel
0%_flex
Operator note: variant
220kv
Operator note: voltage kv
220

Injection · Solar PV · Available

50 MW

Granted

The operator's latest published dataset reports 50 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2033 (2033) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/RIMIE 70 · payload sha256 336e6bb58c86…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
RIMIE 70
Operator note: flexibilityLevel
0%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

Injection · Solar PV · Available

300 MW

Granted

The operator's latest published dataset reports 300 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2033 (2033) · variant: 380kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/RIMIE380 · payload sha256 b369a409376b…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at published maximum mw
300
Operator note: at voltage level cap
true
Operator note: code
RIMIE380
Operator note: flexibilityLevel
5%_flex
Operator note: variant
380kv
Operator note: voltage kv
380

Injection · Solar PV · Available

175 MW

Granted

The operator's latest published dataset reports 175 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2033 (2033) · variant: 220kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/RIMIE220 · payload sha256 0d316d7cef0a…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
RIMIE220
Operator note: flexibilityLevel
5%_flex
Operator note: variant
220kv
Operator note: voltage kv
220

Injection · Solar PV · Available

50 MW

Granted

The operator's latest published dataset reports 50 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2033 (2033) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/RIMIE 70 · payload sha256 336e6bb58c86…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
RIMIE 70
Operator note: flexibilityLevel
5%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

Injection · Solar PV · Available

300 MW

Granted

The operator's latest published dataset reports 300 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2033 (2033) · variant: 380kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/RIMIE380 · payload sha256 b369a409376b…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at published maximum mw
300
Operator note: at voltage level cap
true
Operator note: code
RIMIE380
Operator note: flexibilityLevel
10%_flex
Operator note: variant
380kv
Operator note: voltage kv
380

Injection · Solar PV · Available

175 MW

Granted

The operator's latest published dataset reports 175 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2033 (2033) · variant: 220kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/RIMIE220 · payload sha256 0d316d7cef0a…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
RIMIE220
Operator note: flexibilityLevel
10%_flex
Operator note: variant
220kv
Operator note: voltage kv
220

Injection · Solar PV · Available

50 MW

Granted

The operator's latest published dataset reports 50 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2033 (2033) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/RIMIE 70 · payload sha256 336e6bb58c86…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
RIMIE 70
Operator note: flexibilityLevel
10%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

Injection · Solar PV · Available

300 MW

Granted

The operator's latest published dataset reports 300 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2033 (2033) · variant: 380kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/RIMIE380 · payload sha256 b369a409376b…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at published maximum mw
300
Operator note: at voltage level cap
true
Operator note: code
RIMIE380
Operator note: flexibilityLevel
20%_flex
Operator note: variant
380kv
Operator note: voltage kv
380

Injection · Solar PV · Available

175 MW

Granted

The operator's latest published dataset reports 175 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2033 (2033) · variant: 220kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/RIMIE220 · payload sha256 0d316d7cef0a…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
RIMIE220
Operator note: flexibilityLevel
20%_flex
Operator note: variant
220kv
Operator note: voltage kv
220

Injection · Solar PV · Available

50 MW

Granted

The operator's latest published dataset reports 50 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2033 (2033) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/RIMIE 70 · payload sha256 336e6bb58c86…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
RIMIE 70
Operator note: flexibilityLevel
20%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

Injection · Onshore wind · Available

300 MW

Granted

The operator's latest published dataset reports 300 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2029 (2029) · variant: 380kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/RIMIE380 · payload sha256 e60f9b7cf659…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at published maximum mw
300
Operator note: at voltage level cap
true
Operator note: code
RIMIE380
Operator note: flexibilityLevel
0%_flex
Operator note: variant
380kv
Operator note: voltage kv
380

Injection · Onshore wind · Available

175 MW

Granted

The operator's latest published dataset reports 175 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2029 (2029) · variant: 220kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/RIMIE220 · payload sha256 fc23dbfe730e…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
RIMIE220
Operator note: flexibilityLevel
0%_flex
Operator note: variant
220kv
Operator note: voltage kv
220

Injection · Onshore wind · Available

50 MW

Granted

The operator's latest published dataset reports 50 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2029 (2029) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/RIMIE 70 · payload sha256 ca6ac2eae672…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
RIMIE 70
Operator note: flexibilityLevel
0%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

Injection · Onshore wind · Available

300 MW

Granted

The operator's latest published dataset reports 300 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2029 (2029) · variant: 380kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/RIMIE380 · payload sha256 e60f9b7cf659…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at published maximum mw
300
Operator note: at voltage level cap
true
Operator note: code
RIMIE380
Operator note: flexibilityLevel
5%_flex
Operator note: variant
380kv
Operator note: voltage kv
380

Injection · Onshore wind · Available

175 MW

Granted

The operator's latest published dataset reports 175 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2029 (2029) · variant: 220kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/RIMIE220 · payload sha256 fc23dbfe730e…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
RIMIE220
Operator note: flexibilityLevel
5%_flex
Operator note: variant
220kv
Operator note: voltage kv
220

Injection · Onshore wind · Available

50 MW

Granted

The operator's latest published dataset reports 50 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2029 (2029) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/RIMIE 70 · payload sha256 ca6ac2eae672…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
RIMIE 70
Operator note: flexibilityLevel
5%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

Injection · Onshore wind · Available

300 MW

Granted

The operator's latest published dataset reports 300 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2029 (2029) · variant: 380kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/RIMIE380 · payload sha256 e60f9b7cf659…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at published maximum mw
300
Operator note: at voltage level cap
true
Operator note: code
RIMIE380
Operator note: flexibilityLevel
10%_flex
Operator note: variant
380kv
Operator note: voltage kv
380

Injection · Onshore wind · Available

175 MW

Granted

The operator's latest published dataset reports 175 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2029 (2029) · variant: 220kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/RIMIE220 · payload sha256 fc23dbfe730e…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
RIMIE220
Operator note: flexibilityLevel
10%_flex
Operator note: variant
220kv
Operator note: voltage kv
220

Injection · Onshore wind · Available

50 MW

Granted

The operator's latest published dataset reports 50 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2029 (2029) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/RIMIE 70 · payload sha256 ca6ac2eae672…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
RIMIE 70
Operator note: flexibilityLevel
10%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

Injection · Onshore wind · Available

300 MW

Granted

The operator's latest published dataset reports 300 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2029 (2029) · variant: 380kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/RIMIE380 · payload sha256 e60f9b7cf659…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at published maximum mw
300
Operator note: at voltage level cap
true
Operator note: code
RIMIE380
Operator note: flexibilityLevel
20%_flex
Operator note: variant
380kv
Operator note: voltage kv
380

Injection · Onshore wind · Available

175 MW

Granted

The operator's latest published dataset reports 175 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2029 (2029) · variant: 220kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/RIMIE220 · payload sha256 fc23dbfe730e…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
RIMIE220
Operator note: flexibilityLevel
20%_flex
Operator note: variant
220kv
Operator note: voltage kv
220

Injection · Onshore wind · Available

50 MW

Granted

The operator's latest published dataset reports 50 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2029 (2029) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/RIMIE 70 · payload sha256 ca6ac2eae672…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
RIMIE 70
Operator note: flexibilityLevel
20%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

Injection · Onshore wind · Available

300 MW

Granted

The operator's latest published dataset reports 300 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2033 (2033) · variant: 380kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/RIMIE380 · payload sha256 b369a409376b…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at published maximum mw
300
Operator note: at voltage level cap
true
Operator note: code
RIMIE380
Operator note: flexibilityLevel
0%_flex
Operator note: variant
380kv
Operator note: voltage kv
380

Injection · Onshore wind · Available

175 MW

Granted

The operator's latest published dataset reports 175 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2033 (2033) · variant: 220kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/RIMIE220 · payload sha256 0d316d7cef0a…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
RIMIE220
Operator note: flexibilityLevel
0%_flex
Operator note: variant
220kv
Operator note: voltage kv
220

Injection · Onshore wind · Available

50 MW

Granted

The operator's latest published dataset reports 50 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2033 (2033) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/RIMIE 70 · payload sha256 336e6bb58c86…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
RIMIE 70
Operator note: flexibilityLevel
0%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

Injection · Onshore wind · Available

300 MW

Granted

The operator's latest published dataset reports 300 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2033 (2033) · variant: 380kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/RIMIE380 · payload sha256 b369a409376b…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at published maximum mw
300
Operator note: at voltage level cap
true
Operator note: code
RIMIE380
Operator note: flexibilityLevel
5%_flex
Operator note: variant
380kv
Operator note: voltage kv
380

Injection · Onshore wind · Available

175 MW

Granted

The operator's latest published dataset reports 175 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2033 (2033) · variant: 220kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/RIMIE220 · payload sha256 0d316d7cef0a…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
RIMIE220
Operator note: flexibilityLevel
5%_flex
Operator note: variant
220kv
Operator note: voltage kv
220

Injection · Onshore wind · Available

50 MW

Granted

The operator's latest published dataset reports 50 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2033 (2033) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/RIMIE 70 · payload sha256 336e6bb58c86…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
RIMIE 70
Operator note: flexibilityLevel
5%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

Injection · Onshore wind · Available

300 MW

Granted

The operator's latest published dataset reports 300 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2033 (2033) · variant: 380kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/RIMIE380 · payload sha256 b369a409376b…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at published maximum mw
300
Operator note: at voltage level cap
true
Operator note: code
RIMIE380
Operator note: flexibilityLevel
10%_flex
Operator note: variant
380kv
Operator note: voltage kv
380

Injection · Onshore wind · Available

175 MW

Granted

The operator's latest published dataset reports 175 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2033 (2033) · variant: 220kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/RIMIE220 · payload sha256 0d316d7cef0a…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
RIMIE220
Operator note: flexibilityLevel
10%_flex
Operator note: variant
220kv
Operator note: voltage kv
220

Injection · Onshore wind · Available

50 MW

Granted

The operator's latest published dataset reports 50 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2033 (2033) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/RIMIE 70 · payload sha256 336e6bb58c86…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
RIMIE 70
Operator note: flexibilityLevel
10%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

Injection · Onshore wind · Available

300 MW

Granted

The operator's latest published dataset reports 300 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2033 (2033) · variant: 380kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/RIMIE380 · payload sha256 b369a409376b…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at published maximum mw
300
Operator note: at voltage level cap
true
Operator note: code
RIMIE380
Operator note: flexibilityLevel
20%_flex
Operator note: variant
380kv
Operator note: voltage kv
380

Injection · Onshore wind · Available

175 MW

Granted

The operator's latest published dataset reports 175 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2033 (2033) · variant: 220kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/RIMIE220 · payload sha256 0d316d7cef0a…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
RIMIE220
Operator note: flexibilityLevel
20%_flex
Operator note: variant
220kv
Operator note: voltage kv
220

Injection · Onshore wind · Available

50 MW

Granted

The operator's latest published dataset reports 50 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2033 (2033) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/RIMIE 70 · payload sha256 336e6bb58c86…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
RIMIE 70
Operator note: flexibilityLevel
20%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

Offtake · Load (any) · Available

176.7 MW

Granted

The operator's latest published dataset reports 176.7 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2029 (2029) · variant: 380kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/RIMIE380 · payload sha256 e60f9b7cf659…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
RIMIE380
Operator note: flexibilityLevel
0%_flex
Operator note: variant
380kv
Operator note: voltage kv
380

Offtake · Load (any) · Available

22.2 MW

Granted

The operator's latest published dataset reports 22.2 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2029 (2029) · variant: 220kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/RIMIE220 · payload sha256 fc23dbfe730e…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
RIMIE220
Operator note: flexibilityLevel
0%_flex
Operator note: variant
220kv
Operator note: voltage kv
220

Offtake · Load (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2029 (2029) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/RIMIE 70 · payload sha256 ca6ac2eae672…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
RIMIE 70
Operator note: flexibilityLevel
0%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

Offtake · Load (any) · Available

300 MW

Granted

The operator's latest published dataset reports 300 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2029 (2029) · variant: 380kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/RIMIE380 · payload sha256 e60f9b7cf659…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at published maximum mw
300
Operator note: at voltage level cap
true
Operator note: code
RIMIE380
Operator note: flexibilityLevel
5%_flex
Operator note: variant
380kv
Operator note: voltage kv
380

Offtake · Load (any) · Available

50.2 MW

Granted

The operator's latest published dataset reports 50.2 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2029 (2029) · variant: 220kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/RIMIE220 · payload sha256 fc23dbfe730e…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
RIMIE220
Operator note: flexibilityLevel
5%_flex
Operator note: variant
220kv
Operator note: voltage kv
220

Offtake · Load (any) · Available

48.4 MW

Granted

The operator's latest published dataset reports 48.4 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2029 (2029) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/RIMIE 70 · payload sha256 ca6ac2eae672…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
RIMIE 70
Operator note: flexibilityLevel
5%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

Offtake · Load (any) · Available

300 MW

Granted

The operator's latest published dataset reports 300 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2029 (2029) · variant: 380kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/RIMIE380 · payload sha256 e60f9b7cf659…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at published maximum mw
300
Operator note: at voltage level cap
true
Operator note: code
RIMIE380
Operator note: flexibilityLevel
10%_flex
Operator note: variant
380kv
Operator note: voltage kv
380

Offtake · Load (any) · Available

120.3 MW

Granted

The operator's latest published dataset reports 120.3 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2029 (2029) · variant: 220kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/RIMIE220 · payload sha256 fc23dbfe730e…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
RIMIE220
Operator note: flexibilityLevel
10%_flex
Operator note: variant
220kv
Operator note: voltage kv
220

Offtake · Load (any) · Available

50 MW

Granted

The operator's latest published dataset reports 50 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2029 (2029) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/RIMIE 70 · payload sha256 ca6ac2eae672…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
RIMIE 70
Operator note: flexibilityLevel
10%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

Offtake · Load (any) · Available

300 MW

Granted

The operator's latest published dataset reports 300 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2029 (2029) · variant: 380kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/RIMIE380 · payload sha256 e60f9b7cf659…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at published maximum mw
300
Operator note: at voltage level cap
true
Operator note: code
RIMIE380
Operator note: flexibilityLevel
20%_flex
Operator note: variant
380kv
Operator note: voltage kv
380

Offtake · Load (any) · Available

175 MW

Granted

The operator's latest published dataset reports 175 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2029 (2029) · variant: 220kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/RIMIE220 · payload sha256 fc23dbfe730e…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
RIMIE220
Operator note: flexibilityLevel
20%_flex
Operator note: variant
220kv
Operator note: voltage kv
220

Offtake · Load (any) · Available

50 MW

Granted

The operator's latest published dataset reports 50 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2029 (2029) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/RIMIE 70 · payload sha256 ca6ac2eae672…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
RIMIE 70
Operator note: flexibilityLevel
20%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

Offtake · Load (any) · Available

300 MW

Granted

The operator's latest published dataset reports 300 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2033 (2033) · variant: 380kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/RIMIE380 · payload sha256 b369a409376b…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at published maximum mw
300
Operator note: at voltage level cap
true
Operator note: code
RIMIE380
Operator note: flexibilityLevel
0%_flex
Operator note: variant
380kv
Operator note: voltage kv
380

Offtake · Load (any) · Available

175 MW

Granted

The operator's latest published dataset reports 175 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2033 (2033) · variant: 220kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/RIMIE220 · payload sha256 0d316d7cef0a…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
RIMIE220
Operator note: flexibilityLevel
0%_flex
Operator note: variant
220kv
Operator note: voltage kv
220

Offtake · Load (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2033 (2033) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/RIMIE 70 · payload sha256 336e6bb58c86…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
RIMIE 70
Operator note: flexibilityLevel
0%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

Offtake · Load (any) · Available

300 MW

Granted

The operator's latest published dataset reports 300 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2033 (2033) · variant: 380kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/RIMIE380 · payload sha256 b369a409376b…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at published maximum mw
300
Operator note: at voltage level cap
true
Operator note: code
RIMIE380
Operator note: flexibilityLevel
5%_flex
Operator note: variant
380kv
Operator note: voltage kv
380

Offtake · Load (any) · Available

175 MW

Granted

The operator's latest published dataset reports 175 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2033 (2033) · variant: 220kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/RIMIE220 · payload sha256 0d316d7cef0a…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
RIMIE220
Operator note: flexibilityLevel
5%_flex
Operator note: variant
220kv
Operator note: voltage kv
220

Offtake · Load (any) · Available

50 MW

Granted

The operator's latest published dataset reports 50 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2033 (2033) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/RIMIE 70 · payload sha256 336e6bb58c86…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
RIMIE 70
Operator note: flexibilityLevel
5%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

Offtake · Load (any) · Available

300 MW

Granted

The operator's latest published dataset reports 300 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2033 (2033) · variant: 380kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/RIMIE380 · payload sha256 b369a409376b…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at published maximum mw
300
Operator note: at voltage level cap
true
Operator note: code
RIMIE380
Operator note: flexibilityLevel
10%_flex
Operator note: variant
380kv
Operator note: voltage kv
380

Offtake · Load (any) · Available

175 MW

Granted

The operator's latest published dataset reports 175 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2033 (2033) · variant: 220kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/RIMIE220 · payload sha256 0d316d7cef0a…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
RIMIE220
Operator note: flexibilityLevel
10%_flex
Operator note: variant
220kv
Operator note: voltage kv
220

Offtake · Load (any) · Available

50 MW

Granted

The operator's latest published dataset reports 50 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2033 (2033) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/RIMIE 70 · payload sha256 336e6bb58c86…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
RIMIE 70
Operator note: flexibilityLevel
10%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

Offtake · Load (any) · Available

300 MW

Granted

The operator's latest published dataset reports 300 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2033 (2033) · variant: 380kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/RIMIE380 · payload sha256 b369a409376b…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at published maximum mw
300
Operator note: at voltage level cap
true
Operator note: code
RIMIE380
Operator note: flexibilityLevel
20%_flex
Operator note: variant
380kv
Operator note: voltage kv
380

Offtake · Load (any) · Available

175 MW

Granted

The operator's latest published dataset reports 175 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2033 (2033) · variant: 220kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/RIMIE220 · payload sha256 0d316d7cef0a…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
RIMIE220
Operator note: flexibilityLevel
20%_flex
Operator note: variant
220kv
Operator note: voltage kv
220

Offtake · Load (any) · Available

50 MW

Granted

The operator's latest published dataset reports 50 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2033 (2033) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/RIMIE 70 · payload sha256 336e6bb58c86…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
RIMIE 70
Operator note: flexibilityLevel
20%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

Bidirectional · Battery · Available

93.3 MW

Granted

The operator's latest published dataset reports 93.3 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2029 (2029) · variant: 380kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/RIMIE380 · payload sha256 e60f9b7cf659…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
RIMIE380
Operator note: flexibilityLevel
0%_flex
Operator note: variant
380kv
Operator note: voltage kv
380

Bidirectional · Battery · Available

20.3 MW

Granted

The operator's latest published dataset reports 20.3 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2029 (2029) · variant: 220kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/RIMIE220 · payload sha256 fc23dbfe730e…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
RIMIE220
Operator note: flexibilityLevel
0%_flex
Operator note: variant
220kv
Operator note: voltage kv
220

Bidirectional · Battery · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2029 (2029) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/RIMIE 70 · payload sha256 ca6ac2eae672…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
RIMIE 70
Operator note: flexibilityLevel
0%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

Bidirectional · Battery · Available

300 MW

Granted

The operator's latest published dataset reports 300 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2029 (2029) · variant: 380kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/RIMIE380 · payload sha256 e60f9b7cf659…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at published maximum mw
300
Operator note: at voltage level cap
true
Operator note: code
RIMIE380
Operator note: flexibilityLevel
5%_flex
Operator note: variant
380kv
Operator note: voltage kv
380

Bidirectional · Battery · Available

39.6 MW

Granted

The operator's latest published dataset reports 39.6 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2029 (2029) · variant: 220kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/RIMIE220 · payload sha256 fc23dbfe730e…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
RIMIE220
Operator note: flexibilityLevel
5%_flex
Operator note: variant
220kv
Operator note: voltage kv
220

Bidirectional · Battery · Available

33.1 MW

Granted

The operator's latest published dataset reports 33.1 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2029 (2029) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/RIMIE 70 · payload sha256 ca6ac2eae672…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
RIMIE 70
Operator note: flexibilityLevel
5%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

Bidirectional · Battery · Available

300 MW

Granted

The operator's latest published dataset reports 300 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2029 (2029) · variant: 380kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/RIMIE380 · payload sha256 e60f9b7cf659…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at published maximum mw
300
Operator note: at voltage level cap
true
Operator note: code
RIMIE380
Operator note: flexibilityLevel
10%_flex
Operator note: variant
380kv
Operator note: voltage kv
380

Bidirectional · Battery · Available

81.3 MW

Granted

The operator's latest published dataset reports 81.3 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2029 (2029) · variant: 220kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/RIMIE220 · payload sha256 fc23dbfe730e…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
RIMIE220
Operator note: flexibilityLevel
10%_flex
Operator note: variant
220kv
Operator note: voltage kv
220

Bidirectional · Battery · Available

50 MW

Granted

The operator's latest published dataset reports 50 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2029 (2029) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/RIMIE 70 · payload sha256 ca6ac2eae672…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
RIMIE 70
Operator note: flexibilityLevel
10%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

Bidirectional · Battery · Available

300 MW

Granted

The operator's latest published dataset reports 300 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2029 (2029) · variant: 380kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/RIMIE380 · payload sha256 e60f9b7cf659…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at published maximum mw
300
Operator note: at voltage level cap
true
Operator note: code
RIMIE380
Operator note: flexibilityLevel
20%_flex
Operator note: variant
380kv
Operator note: voltage kv
380

Bidirectional · Battery · Available

175 MW

Granted

The operator's latest published dataset reports 175 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2029 (2029) · variant: 220kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/RIMIE220 · payload sha256 fc23dbfe730e…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
RIMIE220
Operator note: flexibilityLevel
20%_flex
Operator note: variant
220kv
Operator note: voltage kv
220

Bidirectional · Battery · Available

50 MW

Granted

The operator's latest published dataset reports 50 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2029 (2029) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/RIMIE 70 · payload sha256 ca6ac2eae672…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
RIMIE 70
Operator note: flexibilityLevel
20%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

Bidirectional · Battery · Available

294.7 MW

Granted

The operator's latest published dataset reports 294.7 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2033 (2033) · variant: 380kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/RIMIE380 · payload sha256 b369a409376b…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
RIMIE380
Operator note: flexibilityLevel
0%_flex
Operator note: variant
380kv
Operator note: voltage kv
380

Bidirectional · Battery · Available

20.3 MW

Granted

The operator's latest published dataset reports 20.3 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2033 (2033) · variant: 220kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/RIMIE220 · payload sha256 0d316d7cef0a…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
RIMIE220
Operator note: flexibilityLevel
0%_flex
Operator note: variant
220kv
Operator note: voltage kv
220

Bidirectional · Battery · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2033 (2033) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/RIMIE 70 · payload sha256 336e6bb58c86…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
RIMIE 70
Operator note: flexibilityLevel
0%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

Bidirectional · Battery · Available

300 MW

Granted

The operator's latest published dataset reports 300 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2033 (2033) · variant: 380kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/RIMIE380 · payload sha256 b369a409376b…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at published maximum mw
300
Operator note: at voltage level cap
true
Operator note: code
RIMIE380
Operator note: flexibilityLevel
5%_flex
Operator note: variant
380kv
Operator note: voltage kv
380

Bidirectional · Battery · Available

53.8 MW

Granted

The operator's latest published dataset reports 53.8 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2033 (2033) · variant: 220kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/RIMIE220 · payload sha256 0d316d7cef0a…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
RIMIE220
Operator note: flexibilityLevel
5%_flex
Operator note: variant
220kv
Operator note: voltage kv
220

Bidirectional · Battery · Available

50 MW

Granted

The operator's latest published dataset reports 50 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2033 (2033) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/RIMIE 70 · payload sha256 336e6bb58c86…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
RIMIE 70
Operator note: flexibilityLevel
5%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

Bidirectional · Battery · Available

300 MW

Granted

The operator's latest published dataset reports 300 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2033 (2033) · variant: 380kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/RIMIE380 · payload sha256 b369a409376b…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at published maximum mw
300
Operator note: at voltage level cap
true
Operator note: code
RIMIE380
Operator note: flexibilityLevel
10%_flex
Operator note: variant
380kv
Operator note: voltage kv
380

Bidirectional · Battery · Available

153 MW

Granted

The operator's latest published dataset reports 153 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2033 (2033) · variant: 220kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/RIMIE220 · payload sha256 0d316d7cef0a…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
RIMIE220
Operator note: flexibilityLevel
10%_flex
Operator note: variant
220kv
Operator note: voltage kv
220

Bidirectional · Battery · Available

50 MW

Granted

The operator's latest published dataset reports 50 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2033 (2033) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/RIMIE 70 · payload sha256 336e6bb58c86…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
RIMIE 70
Operator note: flexibilityLevel
10%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

Bidirectional · Battery · Available

300 MW

Granted

The operator's latest published dataset reports 300 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2033 (2033) · variant: 380kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/RIMIE380 · payload sha256 b369a409376b…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at published maximum mw
300
Operator note: at voltage level cap
true
Operator note: code
RIMIE380
Operator note: flexibilityLevel
20%_flex
Operator note: variant
380kv
Operator note: voltage kv
380

Bidirectional · Battery · Available

175 MW

Granted

The operator's latest published dataset reports 175 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2033 (2033) · variant: 220kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/RIMIE220 · payload sha256 0d316d7cef0a…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
RIMIE220
Operator note: flexibilityLevel
20%_flex
Operator note: variant
220kv
Operator note: voltage kv
220

Bidirectional · Battery · Available

50 MW

Granted

The operator's latest published dataset reports 50 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2033 (2033) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/RIMIE 70 · payload sha256 336e6bb58c86…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
RIMIE 70
Operator note: flexibilityLevel
20%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

History

Served series only

Bidirectional · Battery · Available · 2027

last, until 17 Nov 2026: 5.2 MW

26 Sep 2026: 5.2 MW
26 Sep 2026range 5.2 to 5.2 MW24 Nov 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 202617 Nov 20265.2 MW

Time axis: when we observed each value, not the operator’s effective date.

Bidirectional · Battery · Available · 2027

last, until 17 Nov 2026: 14.3 MW

26 Sep 2026: 14.1 MW17 Oct 2026: 14.3 MW
26 Sep 2026range 14.1 to 14.3 MW24 Nov 2026
2 published values, as a table
Observed fromUntilValue
26 Sep 202617 Oct 202614.1 MW
17 Oct 202617 Nov 202614.3 MW

Time axis: when we observed each value, not the operator’s effective date.

Bidirectional · Battery · Available · 2027

last, until 17 Nov 2026: 23.9 MW

26 Sep 2026: 24.2 MW17 Oct 2026: 23.9 MW
26 Sep 2026range 23.9 to 24.2 MW24 Nov 2026
2 published values, as a table
Observed fromUntilValue
26 Sep 202617 Oct 202624.2 MW
17 Oct 202617 Nov 202623.9 MW

Time axis: when we observed each value, not the operator’s effective date.

Bidirectional · Battery · Available · 2027

last, until 17 Nov 2026: 38.5 MW

26 Sep 2026: 38.5 MW
26 Sep 2026range 38.5 to 38.5 MW24 Nov 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 202617 Nov 202638.5 MW

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Load (any) · Available · 2027

last, until 17 Nov 2026: 7 MW

26 Sep 2026: 7 MW
26 Sep 2026range 7 to 7 MW24 Nov 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 202617 Nov 20267 MW

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Load (any) · Available · 2027

last, until 17 Nov 2026: 21.5 MW

26 Sep 2026: 20.9 MW17 Oct 2026: 21.5 MW
26 Sep 2026range 20.9 to 21.5 MW24 Nov 2026
2 published values, as a table
Observed fromUntilValue
26 Sep 202617 Oct 202620.9 MW
17 Oct 202617 Nov 202621.5 MW

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Load (any) · Available · 2027

last, until 17 Nov 2026: 39.1 MW

26 Sep 2026: 38.1 MW17 Oct 2026: 39.1 MW
26 Sep 2026range 38.1 to 39.1 MW24 Nov 2026
2 published values, as a table
Observed fromUntilValue
26 Sep 202617 Oct 202638.1 MW
17 Oct 202617 Nov 202639.1 MW

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Load (any) · Available · 2027

last, until 17 Nov 2026: 50 MW

26 Sep 2026: 50 MW
26 Sep 2026range 50 to 50 MW24 Nov 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 202617 Nov 202650 MW

Time axis: when we observed each value, not the operator’s effective date.

Injection · Generation (any) · Available · 2027

last, until 17 Nov 2026: 5.2 MW

26 Sep 2026: 5.2 MW
26 Sep 2026range 5.2 to 5.2 MW24 Nov 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 202617 Nov 20265.2 MW

Time axis: when we observed each value, not the operator’s effective date.

Injection · Generation (any) · Available · 2027

last, until 17 Nov 2026: 14.3 MW

26 Sep 2026: 14.1 MW17 Oct 2026: 14.3 MW
26 Sep 2026range 14.1 to 14.3 MW24 Nov 2026
2 published values, as a table
Observed fromUntilValue
26 Sep 202617 Oct 202614.1 MW
17 Oct 202617 Nov 202614.3 MW

Time axis: when we observed each value, not the operator’s effective date.

Injection · Generation (any) · Available · 2027

last, until 17 Nov 2026: 23.9 MW

26 Sep 2026: 24.2 MW17 Oct 2026: 23.9 MW
26 Sep 2026range 23.9 to 24.2 MW24 Nov 2026
2 published values, as a table
Observed fromUntilValue
26 Sep 202617 Oct 202624.2 MW
17 Oct 202617 Nov 202623.9 MW

Time axis: when we observed each value, not the operator’s effective date.

Injection · Generation (any) · Available · 2027

last, until 17 Nov 2026: 50 MW

26 Sep 2026: 50 MW
26 Sep 2026range 50 to 50 MW24 Nov 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 202617 Nov 202650 MW

Time axis: when we observed each value, not the operator’s effective date.

The first 12 of 240 served series with a history. The history route returns every one of them.

Through the API

curl "https://api.gridcapacityapi.com/v1/substations/sub_06gdrm9mf1vms2kvp43pqm67kc/capacity" \  -H "Authorization: Bearer gc_live_..."