Skip to content

Substation / 150 kV

PITEM

Elia Transmission Belgium / Belgium

Latest published values

20 served · 0 withheld

Each row is what the operator’s latest published dataset reports for one combination of direction, technology, measure, firmness and horizon. Hosting-capacity figures are indicative and reflect what operators publish. They are not a connection offer; only the operator can confirm capacity for a specific request.

Latest published capacity values, one row per series
DirectionTechnologyMeasureValueFirmnessHorizonSource date
InjectionGeneration (any)Available11.1 MWFirm, ≤ 0 % curtailment a year2031 (2031)variant: 150kv26 Sep 2026
InjectionGeneration (any)Available26.6 MWFlexible, ≤ 5 % curtailment a year2031 (2031)variant: 150kv26 Sep 2026
InjectionGeneration (any)Available36.7 MWFlexible, ≤ 10 % curtailment a year2031 (2031)variant: 150kv26 Sep 2026
InjectionGeneration (any)Available62.1 MWFlexible, ≤ 20 % curtailment a year2031 (2031)variant: 150kv26 Sep 2026
InjectionSolar PVAvailable38.8 MWFirm, ≤ 0 % curtailment a year2031 (2031)variant: 150kv26 Sep 2026
InjectionSolar PVAvailable82.2 MWFlexible, ≤ 5 % curtailment a year2031 (2031)variant: 150kv26 Sep 2026
InjectionSolar PVAvailable107.3 MWFlexible, ≤ 10 % curtailment a year2031 (2031)variant: 150kv26 Sep 2026
InjectionSolar PVAvailable175 MWFlexible, ≤ 20 % curtailment a year2031 (2031)variant: 150kv26 Sep 2026
InjectionOnshore windAvailable12.1 MWFirm, ≤ 0 % curtailment a year2031 (2031)variant: 150kv26 Sep 2026
InjectionOnshore windAvailable33.1 MWFlexible, ≤ 5 % curtailment a year2031 (2031)variant: 150kv26 Sep 2026
InjectionOnshore windAvailable43 MWFlexible, ≤ 10 % curtailment a year2031 (2031)variant: 150kv26 Sep 2026
InjectionOnshore windAvailable66 MWFlexible, ≤ 20 % curtailment a year2031 (2031)variant: 150kv26 Sep 2026
OfftakeLoad (any)Available4.8 MWFirm, ≤ 0 % curtailment a year2031 (2031)variant: 150kv26 Sep 2026
OfftakeLoad (any)Available33.2 MWFlexible, ≤ 5 % curtailment a year2031 (2031)variant: 150kv26 Sep 2026
OfftakeLoad (any)Available83.8 MWFlexible, ≤ 10 % curtailment a year2031 (2031)variant: 150kv26 Sep 2026
OfftakeLoad (any)Available175 MWFlexible, ≤ 20 % curtailment a year2031 (2031)variant: 150kv26 Sep 2026
BidirectionalBatteryAvailable4.8 MWFirm, ≤ 0 % curtailment a year2031 (2031)variant: 150kv26 Sep 2026
BidirectionalBatteryAvailable26.6 MWFlexible, ≤ 5 % curtailment a year2031 (2031)variant: 150kv26 Sep 2026
BidirectionalBatteryAvailable36.7 MWFlexible, ≤ 10 % curtailment a year2031 (2031)variant: 150kv26 Sep 2026
BidirectionalBatteryAvailable62.1 MWFlexible, ≤ 20 % curtailment a year2031 (2031)variant: 150kv26 Sep 2026

Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map

What each value means

Methodology, both clocks, provenance and rights

Injection · Generation (any) · Available

11.1 MW

Granted

The operator's latest published dataset reports 11.1 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2031 (2031) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/PITEM150 · payload sha256 0003345cbda9…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
PITEM150
Operator note: flexibilityLevel
0%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Injection · Generation (any) · Available

26.6 MW

Granted

The operator's latest published dataset reports 26.6 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2031 (2031) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/PITEM150 · payload sha256 0003345cbda9…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
PITEM150
Operator note: flexibilityLevel
5%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Injection · Generation (any) · Available

36.7 MW

Granted

The operator's latest published dataset reports 36.7 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2031 (2031) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/PITEM150 · payload sha256 0003345cbda9…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
PITEM150
Operator note: flexibilityLevel
10%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Injection · Generation (any) · Available

62.1 MW

Granted

The operator's latest published dataset reports 62.1 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2031 (2031) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/PITEM150 · payload sha256 0003345cbda9…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
PITEM150
Operator note: flexibilityLevel
20%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Injection · Solar PV · Available

38.8 MW

Granted

The operator's latest published dataset reports 38.8 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2031 (2031) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/PITEM150 · payload sha256 0003345cbda9…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
PITEM150
Operator note: flexibilityLevel
0%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Injection · Solar PV · Available

82.2 MW

Granted

The operator's latest published dataset reports 82.2 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2031 (2031) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/PITEM150 · payload sha256 0003345cbda9…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
PITEM150
Operator note: flexibilityLevel
5%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Injection · Solar PV · Available

107.3 MW

Granted

The operator's latest published dataset reports 107.3 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2031 (2031) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/PITEM150 · payload sha256 0003345cbda9…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
PITEM150
Operator note: flexibilityLevel
10%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Injection · Solar PV · Available

175 MW

Granted

The operator's latest published dataset reports 175 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2031 (2031) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/PITEM150 · payload sha256 0003345cbda9…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
PITEM150
Operator note: flexibilityLevel
20%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Injection · Onshore wind · Available

12.1 MW

Granted

The operator's latest published dataset reports 12.1 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2031 (2031) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/PITEM150 · payload sha256 0003345cbda9…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
PITEM150
Operator note: flexibilityLevel
0%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Injection · Onshore wind · Available

33.1 MW

Granted

The operator's latest published dataset reports 33.1 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2031 (2031) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/PITEM150 · payload sha256 0003345cbda9…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
PITEM150
Operator note: flexibilityLevel
5%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Injection · Onshore wind · Available

43 MW

Granted

The operator's latest published dataset reports 43 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2031 (2031) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/PITEM150 · payload sha256 0003345cbda9…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
PITEM150
Operator note: flexibilityLevel
10%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Injection · Onshore wind · Available

66 MW

Granted

The operator's latest published dataset reports 66 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2031 (2031) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/PITEM150 · payload sha256 0003345cbda9…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
PITEM150
Operator note: flexibilityLevel
20%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Offtake · Load (any) · Available

4.8 MW

Granted

The operator's latest published dataset reports 4.8 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2031 (2031) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/PITEM150 · payload sha256 0003345cbda9…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
PITEM150
Operator note: flexibilityLevel
0%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Offtake · Load (any) · Available

33.2 MW

Granted

The operator's latest published dataset reports 33.2 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2031 (2031) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/PITEM150 · payload sha256 0003345cbda9…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
PITEM150
Operator note: flexibilityLevel
5%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Offtake · Load (any) · Available

83.8 MW

Granted

The operator's latest published dataset reports 83.8 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2031 (2031) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/PITEM150 · payload sha256 0003345cbda9…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
PITEM150
Operator note: flexibilityLevel
10%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Offtake · Load (any) · Available

175 MW

Granted

The operator's latest published dataset reports 175 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2031 (2031) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/PITEM150 · payload sha256 0003345cbda9…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
PITEM150
Operator note: flexibilityLevel
20%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Bidirectional · Battery · Available

4.8 MW

Granted

The operator's latest published dataset reports 4.8 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2031 (2031) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/PITEM150 · payload sha256 0003345cbda9…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
PITEM150
Operator note: flexibilityLevel
0%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Bidirectional · Battery · Available

26.6 MW

Granted

The operator's latest published dataset reports 26.6 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2031 (2031) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/PITEM150 · payload sha256 0003345cbda9…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
PITEM150
Operator note: flexibilityLevel
5%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Bidirectional · Battery · Available

36.7 MW

Granted

The operator's latest published dataset reports 36.7 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2031 (2031) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/PITEM150 · payload sha256 0003345cbda9…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
PITEM150
Operator note: flexibilityLevel
10%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Bidirectional · Battery · Available

62.1 MW

Granted

The operator's latest published dataset reports 62.1 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2031 (2031) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/PITEM150 · payload sha256 0003345cbda9…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
PITEM150
Operator note: flexibilityLevel
20%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

History

Served series only

Bidirectional · Battery · Available · 2031

current 4.8 MW

26 Sep 2026: 4.8 MW
26 Sep 2026range 4.8 to 4.8 MW2 Oct 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current4.8 MW

Time axis: when we observed each value, not the operator’s effective date.

Bidirectional · Battery · Available · 2031

current 26.6 MW

26 Sep 2026: 26.6 MW
26 Sep 2026range 26.6 to 26.6 MW2 Oct 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current26.6 MW

Time axis: when we observed each value, not the operator’s effective date.

Bidirectional · Battery · Available · 2031

current 36.7 MW

26 Sep 2026: 36.7 MW
26 Sep 2026range 36.7 to 36.7 MW2 Oct 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current36.7 MW

Time axis: when we observed each value, not the operator’s effective date.

Bidirectional · Battery · Available · 2031

current 62.1 MW

26 Sep 2026: 62.1 MW
26 Sep 2026range 62.1 to 62.1 MW2 Oct 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current62.1 MW

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Load (any) · Available · 2031

current 4.8 MW

26 Sep 2026: 4.8 MW
26 Sep 2026range 4.8 to 4.8 MW2 Oct 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current4.8 MW

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Load (any) · Available · 2031

current 33.2 MW

26 Sep 2026: 33.2 MW
26 Sep 2026range 33.2 to 33.2 MW2 Oct 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current33.2 MW

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Load (any) · Available · 2031

current 83.8 MW

26 Sep 2026: 83.8 MW
26 Sep 2026range 83.8 to 83.8 MW2 Oct 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current83.8 MW

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Load (any) · Available · 2031

current 175 MW

26 Sep 2026: 175 MW
26 Sep 2026range 175 to 175 MW2 Oct 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current175 MW

Time axis: when we observed each value, not the operator’s effective date.

Injection · Generation (any) · Available · 2031

current 11.1 MW

26 Sep 2026: 11.1 MW
26 Sep 2026range 11.1 to 11.1 MW2 Oct 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current11.1 MW

Time axis: when we observed each value, not the operator’s effective date.

Injection · Generation (any) · Available · 2031

current 26.6 MW

26 Sep 2026: 26.6 MW
26 Sep 2026range 26.6 to 26.6 MW2 Oct 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current26.6 MW

Time axis: when we observed each value, not the operator’s effective date.

Injection · Generation (any) · Available · 2031

current 36.7 MW

26 Sep 2026: 36.7 MW
26 Sep 2026range 36.7 to 36.7 MW2 Oct 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current36.7 MW

Time axis: when we observed each value, not the operator’s effective date.

Injection · Generation (any) · Available · 2031

current 62.1 MW

26 Sep 2026: 62.1 MW
26 Sep 2026range 62.1 to 62.1 MW2 Oct 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current62.1 MW

Time axis: when we observed each value, not the operator’s effective date.

The first 12 of 20 served series with a history. The history route returns every one of them.

Through the API

curl "https://api.gridcapacityapi.com/v1/substations/sub_06gdrm9me5sg3bp3dk1h8922fr/capacity" \  -H "Authorization: Bearer gc_live_..."
PITEM 150 kV substation: grid capacity (Elia Transmission Belgium) · GridCapacity API