| Injection | Generation (any) | Available | 2.3 MW | Firm, ≤ 0 % curtailment a year | 2027 (2027)variant: 36kv | 26 Sep 2026 |
| Injection | Generation (any) | Available | 20 MW | Flexible, ≤ 5 % curtailment a year | 2027 (2027)variant: 36kv | 26 Sep 2026 |
| Injection | Generation (any) | Available | 20 MW | Flexible, ≤ 10 % curtailment a year | 2027 (2027)variant: 36kv | 26 Sep 2026 |
| Injection | Generation (any) | Available | 20 MW | Flexible, ≤ 20 % curtailment a year | 2027 (2027)variant: 36kv | 26 Sep 2026 |
| Injection | Generation (any) | Available | 2.3 MW | Firm, ≤ 0 % curtailment a year | 2031 (2031)variant: 36kv | 26 Sep 2026 |
| Injection | Generation (any) | Available | 20 MW | Flexible, ≤ 5 % curtailment a year | 2031 (2031)variant: 36kv | 26 Sep 2026 |
| Injection | Generation (any) | Available | 20 MW | Flexible, ≤ 10 % curtailment a year | 2031 (2031)variant: 36kv | 26 Sep 2026 |
| Injection | Generation (any) | Available | 20 MW | Flexible, ≤ 20 % curtailment a year | 2031 (2031)variant: 36kv | 26 Sep 2026 |
| Injection | Solar PV | Available | 13 MW | Firm, ≤ 0 % curtailment a year | 2027 (2027)variant: 36kv | 26 Sep 2026 |
| Injection | Solar PV | Available | 20 MW | Flexible, ≤ 5 % curtailment a year | 2027 (2027)variant: 36kv | 26 Sep 2026 |
| Injection | Solar PV | Available | 20 MW | Flexible, ≤ 10 % curtailment a year | 2027 (2027)variant: 36kv | 26 Sep 2026 |
| Injection | Solar PV | Available | 20 MW | Flexible, ≤ 20 % curtailment a year | 2027 (2027)variant: 36kv | 26 Sep 2026 |
| Injection | Solar PV | Available | 13 MW | Firm, ≤ 0 % curtailment a year | 2031 (2031)variant: 36kv | 26 Sep 2026 |
| Injection | Solar PV | Available | 20 MW | Flexible, ≤ 5 % curtailment a year | 2031 (2031)variant: 36kv | 26 Sep 2026 |
| Injection | Solar PV | Available | 20 MW | Flexible, ≤ 10 % curtailment a year | 2031 (2031)variant: 36kv | 26 Sep 2026 |
| Injection | Solar PV | Available | 20 MW | Flexible, ≤ 20 % curtailment a year | 2031 (2031)variant: 36kv | 26 Sep 2026 |
| Injection | Onshore wind | Available | 4.1 MW | Firm, ≤ 0 % curtailment a year | 2027 (2027)variant: 36kv | 26 Sep 2026 |
| Injection | Onshore wind | Available | 20 MW | Flexible, ≤ 5 % curtailment a year | 2027 (2027)variant: 36kv | 26 Sep 2026 |
| Injection | Onshore wind | Available | 20 MW | Flexible, ≤ 10 % curtailment a year | 2027 (2027)variant: 36kv | 26 Sep 2026 |
| Injection | Onshore wind | Available | 20 MW | Flexible, ≤ 20 % curtailment a year | 2027 (2027)variant: 36kv | 26 Sep 2026 |
| Injection | Onshore wind | Available | 4.1 MW | Firm, ≤ 0 % curtailment a year | 2031 (2031)variant: 36kv | 26 Sep 2026 |
| Injection | Onshore wind | Available | 20 MW | Flexible, ≤ 5 % curtailment a year | 2031 (2031)variant: 36kv | 26 Sep 2026 |
| Injection | Onshore wind | Available | 20 MW | Flexible, ≤ 10 % curtailment a year | 2031 (2031)variant: 36kv | 26 Sep 2026 |
| Injection | Onshore wind | Available | 20 MW | Flexible, ≤ 20 % curtailment a year | 2031 (2031)variant: 36kv | 26 Sep 2026 |
| Offtake | Load (any) | Available | 0.5 MW | Firm, ≤ 0 % curtailment a year | 2027 (2027)variant: 36kv | 26 Sep 2026 |
| Offtake | Load (any) | Available | 4 MW | Flexible, ≤ 5 % curtailment a year | 2027 (2027)variant: 36kv | 26 Sep 2026 |
| Offtake | Load (any) | Available | 4.8 MW | Flexible, ≤ 10 % curtailment a year | 2027 (2027)variant: 36kv | 26 Sep 2026 |
| Offtake | Load (any) | Available | 6.6 MW | Flexible, ≤ 20 % curtailment a year | 2027 (2027)variant: 36kv | 26 Sep 2026 |
| Offtake | Load (any) | Available | 0.5 MW | Firm, ≤ 0 % curtailment a year | 2031 (2031)variant: 36kv | 26 Sep 2026 |
| Offtake | Load (any) | Available | 5.5 MW | Flexible, ≤ 5 % curtailment a year | 2031 (2031)variant: 36kv | 26 Sep 2026 |
| Offtake | Load (any) | Available | 10.1 MW | Flexible, ≤ 10 % curtailment a year | 2031 (2031)variant: 36kv | 26 Sep 2026 |
| Offtake | Load (any) | Available | 20 MW | Flexible, ≤ 20 % curtailment a year | 2031 (2031)variant: 36kv | 26 Sep 2026 |
| Bidirectional | Battery | Available | 0.5 MW | Firm, ≤ 0 % curtailment a year | 2027 (2027)variant: 36kv | 26 Sep 2026 |
| Bidirectional | Battery | Available | 3.7 MW | Flexible, ≤ 5 % curtailment a year | 2027 (2027)variant: 36kv | 26 Sep 2026 |
| Bidirectional | Battery | Available | 4.7 MW | Flexible, ≤ 10 % curtailment a year | 2027 (2027)variant: 36kv | 26 Sep 2026 |
| Bidirectional | Battery | Available | 6.1 MW | Flexible, ≤ 20 % curtailment a year | 2027 (2027)variant: 36kv | 26 Sep 2026 |
| Bidirectional | Battery | Available | 0.5 MW | Firm, ≤ 0 % curtailment a year | 2031 (2031)variant: 36kv | 26 Sep 2026 |
| Bidirectional | Battery | Available | 3.9 MW | Flexible, ≤ 5 % curtailment a year | 2031 (2031)variant: 36kv | 26 Sep 2026 |
| Bidirectional | Battery | Available | 7.8 MW | Flexible, ≤ 10 % curtailment a year | 2031 (2031)variant: 36kv | 26 Sep 2026 |
| Bidirectional | Battery | Available | 19.1 MW | Flexible, ≤ 20 % curtailment a year | 2031 (2031)variant: 36kv | 26 Sep 2026 |