Substation / 70 kV

OPGLA

Elia Transmission Belgium / Belgium

Latest published values

40 served · 0 withheld

Each row is what the operator’s latest published dataset reports for one combination of direction, technology, measure, firmness and horizon. Hosting-capacity figures are indicative and reflect what operators publish. They are not a connection offer; only the operator can confirm capacity for a specific request.

Latest published capacity values, one row per series
DirectionTechnologyMeasureValueFirmnessHorizonSource date
InjectionGeneration (any)Available41.5 MWFirm, ≤ 0 % curtailment a year2029 (2029)variant: 70kv17 Nov 2026
InjectionGeneration (any)Available50 MWFlexible, ≤ 5 % curtailment a year2029 (2029)variant: 70kv17 Nov 2026
InjectionGeneration (any)Available50 MWFlexible, ≤ 10 % curtailment a year2029 (2029)variant: 70kv17 Nov 2026
InjectionGeneration (any)Available50 MWFlexible, ≤ 20 % curtailment a year2029 (2029)variant: 70kv17 Nov 2026
InjectionGeneration (any)Available50 MWFirm, ≤ 0 % curtailment a year2033 (2033)variant: 70kv17 Nov 2026
InjectionGeneration (any)Available50 MWFlexible, ≤ 5 % curtailment a year2033 (2033)variant: 70kv17 Nov 2026
InjectionGeneration (any)Available50 MWFlexible, ≤ 10 % curtailment a year2033 (2033)variant: 70kv17 Nov 2026
InjectionGeneration (any)Available50 MWFlexible, ≤ 20 % curtailment a year2033 (2033)variant: 70kv17 Nov 2026
InjectionSolar PVAvailable50 MWFirm, ≤ 0 % curtailment a year2029 (2029)variant: 70kv17 Nov 2026
InjectionSolar PVAvailable50 MWFlexible, ≤ 5 % curtailment a year2029 (2029)variant: 70kv17 Nov 2026
InjectionSolar PVAvailable50 MWFlexible, ≤ 10 % curtailment a year2029 (2029)variant: 70kv17 Nov 2026
InjectionSolar PVAvailable50 MWFlexible, ≤ 20 % curtailment a year2029 (2029)variant: 70kv17 Nov 2026
InjectionSolar PVAvailable50 MWFirm, ≤ 0 % curtailment a year2033 (2033)variant: 70kv17 Nov 2026
InjectionSolar PVAvailable50 MWFlexible, ≤ 5 % curtailment a year2033 (2033)variant: 70kv17 Nov 2026
InjectionSolar PVAvailable50 MWFlexible, ≤ 10 % curtailment a year2033 (2033)variant: 70kv17 Nov 2026
InjectionSolar PVAvailable50 MWFlexible, ≤ 20 % curtailment a year2033 (2033)variant: 70kv17 Nov 2026
InjectionOnshore windAvailable50 MWFirm, ≤ 0 % curtailment a year2029 (2029)variant: 70kv17 Nov 2026
InjectionOnshore windAvailable50 MWFlexible, ≤ 5 % curtailment a year2029 (2029)variant: 70kv17 Nov 2026
InjectionOnshore windAvailable50 MWFlexible, ≤ 10 % curtailment a year2029 (2029)variant: 70kv17 Nov 2026
InjectionOnshore windAvailable50 MWFlexible, ≤ 20 % curtailment a year2029 (2029)variant: 70kv17 Nov 2026
InjectionOnshore windAvailable50 MWFirm, ≤ 0 % curtailment a year2033 (2033)variant: 70kv17 Nov 2026
InjectionOnshore windAvailable50 MWFlexible, ≤ 5 % curtailment a year2033 (2033)variant: 70kv17 Nov 2026
InjectionOnshore windAvailable50 MWFlexible, ≤ 10 % curtailment a year2033 (2033)variant: 70kv17 Nov 2026
InjectionOnshore windAvailable50 MWFlexible, ≤ 20 % curtailment a year2033 (2033)variant: 70kv17 Nov 2026
OfftakeLoad (any)Available0 MWFirm, ≤ 0 % curtailment a year2029 (2029)variant: 70kv17 Nov 2026
OfftakeLoad (any)Available0 MWFlexible, ≤ 5 % curtailment a year2029 (2029)variant: 70kv17 Nov 2026
OfftakeLoad (any)Available0 MWFlexible, ≤ 10 % curtailment a year2029 (2029)variant: 70kv17 Nov 2026
OfftakeLoad (any)Available26 MWFlexible, ≤ 20 % curtailment a year2029 (2029)variant: 70kv17 Nov 2026
OfftakeLoad (any)Available0 MWFirm, ≤ 0 % curtailment a year2033 (2033)variant: 70kv17 Nov 2026
OfftakeLoad (any)Available26.7 MWFlexible, ≤ 5 % curtailment a year2033 (2033)variant: 70kv17 Nov 2026
OfftakeLoad (any)Available39.5 MWFlexible, ≤ 10 % curtailment a year2033 (2033)variant: 70kv17 Nov 2026
OfftakeLoad (any)Available50 MWFlexible, ≤ 20 % curtailment a year2033 (2033)variant: 70kv17 Nov 2026
BidirectionalBatteryAvailable0 MWFirm, ≤ 0 % curtailment a year2029 (2029)variant: 70kv17 Nov 2026
BidirectionalBatteryAvailable0 MWFlexible, ≤ 5 % curtailment a year2029 (2029)variant: 70kv17 Nov 2026
BidirectionalBatteryAvailable0 MWFlexible, ≤ 10 % curtailment a year2029 (2029)variant: 70kv17 Nov 2026
BidirectionalBatteryAvailable19.2 MWFlexible, ≤ 20 % curtailment a year2029 (2029)variant: 70kv17 Nov 2026
BidirectionalBatteryAvailable0 MWFirm, ≤ 0 % curtailment a year2033 (2033)variant: 70kv17 Nov 2026
BidirectionalBatteryAvailable20.2 MWFlexible, ≤ 5 % curtailment a year2033 (2033)variant: 70kv17 Nov 2026
BidirectionalBatteryAvailable26.1 MWFlexible, ≤ 10 % curtailment a year2033 (2033)variant: 70kv17 Nov 2026
BidirectionalBatteryAvailable46.6 MWFlexible, ≤ 20 % curtailment a year2033 (2033)variant: 70kv17 Nov 2026

Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map

What each value means

Methodology, both clocks, provenance and rights

Injection · Generation (any) · Available

41.5 MW

Granted

The operator's latest published dataset reports 41.5 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2029 (2029) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/OPGLA 70 · payload sha256 665cc185ba3a…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
OPGLA 70
Operator note: flexibilityLevel
0%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

Injection · Generation (any) · Available

50 MW

Granted

The operator's latest published dataset reports 50 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2029 (2029) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/OPGLA 70 · payload sha256 665cc185ba3a…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
OPGLA 70
Operator note: flexibilityLevel
5%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

Injection · Generation (any) · Available

50 MW

Granted

The operator's latest published dataset reports 50 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2029 (2029) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/OPGLA 70 · payload sha256 665cc185ba3a…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
OPGLA 70
Operator note: flexibilityLevel
10%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

Injection · Generation (any) · Available

50 MW

Granted

The operator's latest published dataset reports 50 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2029 (2029) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/OPGLA 70 · payload sha256 665cc185ba3a…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
OPGLA 70
Operator note: flexibilityLevel
20%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

Injection · Generation (any) · Available

50 MW

Granted

The operator's latest published dataset reports 50 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2033 (2033) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/OPGLA 70 · payload sha256 b1326c96c662…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
OPGLA 70
Operator note: flexibilityLevel
0%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

Injection · Generation (any) · Available

50 MW

Granted

The operator's latest published dataset reports 50 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2033 (2033) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/OPGLA 70 · payload sha256 b1326c96c662…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
OPGLA 70
Operator note: flexibilityLevel
5%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

Injection · Generation (any) · Available

50 MW

Granted

The operator's latest published dataset reports 50 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2033 (2033) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/OPGLA 70 · payload sha256 b1326c96c662…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
OPGLA 70
Operator note: flexibilityLevel
10%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

Injection · Generation (any) · Available

50 MW

Granted

The operator's latest published dataset reports 50 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2033 (2033) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/OPGLA 70 · payload sha256 b1326c96c662…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
OPGLA 70
Operator note: flexibilityLevel
20%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

Injection · Solar PV · Available

50 MW

Granted

The operator's latest published dataset reports 50 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2029 (2029) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/OPGLA 70 · payload sha256 665cc185ba3a…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
OPGLA 70
Operator note: flexibilityLevel
0%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

Injection · Solar PV · Available

50 MW

Granted

The operator's latest published dataset reports 50 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2029 (2029) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/OPGLA 70 · payload sha256 665cc185ba3a…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
OPGLA 70
Operator note: flexibilityLevel
5%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

Injection · Solar PV · Available

50 MW

Granted

The operator's latest published dataset reports 50 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2029 (2029) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/OPGLA 70 · payload sha256 665cc185ba3a…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
OPGLA 70
Operator note: flexibilityLevel
10%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

Injection · Solar PV · Available

50 MW

Granted

The operator's latest published dataset reports 50 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2029 (2029) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/OPGLA 70 · payload sha256 665cc185ba3a…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
OPGLA 70
Operator note: flexibilityLevel
20%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

Injection · Solar PV · Available

50 MW

Granted

The operator's latest published dataset reports 50 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2033 (2033) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/OPGLA 70 · payload sha256 b1326c96c662…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
OPGLA 70
Operator note: flexibilityLevel
0%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

Injection · Solar PV · Available

50 MW

Granted

The operator's latest published dataset reports 50 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2033 (2033) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/OPGLA 70 · payload sha256 b1326c96c662…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
OPGLA 70
Operator note: flexibilityLevel
5%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

Injection · Solar PV · Available

50 MW

Granted

The operator's latest published dataset reports 50 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2033 (2033) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/OPGLA 70 · payload sha256 b1326c96c662…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
OPGLA 70
Operator note: flexibilityLevel
10%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

Injection · Solar PV · Available

50 MW

Granted

The operator's latest published dataset reports 50 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2033 (2033) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/OPGLA 70 · payload sha256 b1326c96c662…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
OPGLA 70
Operator note: flexibilityLevel
20%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

Injection · Onshore wind · Available

50 MW

Granted

The operator's latest published dataset reports 50 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2029 (2029) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/OPGLA 70 · payload sha256 665cc185ba3a…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
OPGLA 70
Operator note: flexibilityLevel
0%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

Injection · Onshore wind · Available

50 MW

Granted

The operator's latest published dataset reports 50 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2029 (2029) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/OPGLA 70 · payload sha256 665cc185ba3a…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
OPGLA 70
Operator note: flexibilityLevel
5%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

Injection · Onshore wind · Available

50 MW

Granted

The operator's latest published dataset reports 50 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2029 (2029) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/OPGLA 70 · payload sha256 665cc185ba3a…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
OPGLA 70
Operator note: flexibilityLevel
10%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

Injection · Onshore wind · Available

50 MW

Granted

The operator's latest published dataset reports 50 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2029 (2029) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/OPGLA 70 · payload sha256 665cc185ba3a…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
OPGLA 70
Operator note: flexibilityLevel
20%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

Injection · Onshore wind · Available

50 MW

Granted

The operator's latest published dataset reports 50 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2033 (2033) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/OPGLA 70 · payload sha256 b1326c96c662…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
OPGLA 70
Operator note: flexibilityLevel
0%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

Injection · Onshore wind · Available

50 MW

Granted

The operator's latest published dataset reports 50 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2033 (2033) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/OPGLA 70 · payload sha256 b1326c96c662…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
OPGLA 70
Operator note: flexibilityLevel
5%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

Injection · Onshore wind · Available

50 MW

Granted

The operator's latest published dataset reports 50 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2033 (2033) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/OPGLA 70 · payload sha256 b1326c96c662…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
OPGLA 70
Operator note: flexibilityLevel
10%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

Injection · Onshore wind · Available

50 MW

Granted

The operator's latest published dataset reports 50 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2033 (2033) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/OPGLA 70 · payload sha256 b1326c96c662…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
OPGLA 70
Operator note: flexibilityLevel
20%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

Offtake · Load (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2029 (2029) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/OPGLA 70 · payload sha256 665cc185ba3a…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
OPGLA 70
Operator note: flexibilityLevel
0%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

Offtake · Load (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2029 (2029) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/OPGLA 70 · payload sha256 665cc185ba3a…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
OPGLA 70
Operator note: flexibilityLevel
5%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

Offtake · Load (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2029 (2029) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/OPGLA 70 · payload sha256 665cc185ba3a…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
OPGLA 70
Operator note: flexibilityLevel
10%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

Offtake · Load (any) · Available

26 MW

Granted

The operator's latest published dataset reports 26 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2029 (2029) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/OPGLA 70 · payload sha256 665cc185ba3a…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
OPGLA 70
Operator note: flexibilityLevel
20%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

Offtake · Load (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2033 (2033) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/OPGLA 70 · payload sha256 b1326c96c662…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
OPGLA 70
Operator note: flexibilityLevel
0%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

Offtake · Load (any) · Available

26.7 MW

Granted

The operator's latest published dataset reports 26.7 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2033 (2033) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/OPGLA 70 · payload sha256 b1326c96c662…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
OPGLA 70
Operator note: flexibilityLevel
5%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

Offtake · Load (any) · Available

39.5 MW

Granted

The operator's latest published dataset reports 39.5 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2033 (2033) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/OPGLA 70 · payload sha256 b1326c96c662…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
OPGLA 70
Operator note: flexibilityLevel
10%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

Offtake · Load (any) · Available

50 MW

Granted

The operator's latest published dataset reports 50 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2033 (2033) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/OPGLA 70 · payload sha256 b1326c96c662…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
OPGLA 70
Operator note: flexibilityLevel
20%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

Bidirectional · Battery · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2029 (2029) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/OPGLA 70 · payload sha256 665cc185ba3a…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
OPGLA 70
Operator note: flexibilityLevel
0%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

Bidirectional · Battery · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2029 (2029) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/OPGLA 70 · payload sha256 665cc185ba3a…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
OPGLA 70
Operator note: flexibilityLevel
5%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

Bidirectional · Battery · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2029 (2029) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/OPGLA 70 · payload sha256 665cc185ba3a…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
OPGLA 70
Operator note: flexibilityLevel
10%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

Bidirectional · Battery · Available

19.2 MW

Granted

The operator's latest published dataset reports 19.2 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2029 (2029) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/OPGLA 70 · payload sha256 665cc185ba3a…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
OPGLA 70
Operator note: flexibilityLevel
20%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

Bidirectional · Battery · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2033 (2033) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/OPGLA 70 · payload sha256 b1326c96c662…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
OPGLA 70
Operator note: flexibilityLevel
0%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

Bidirectional · Battery · Available

20.2 MW

Granted

The operator's latest published dataset reports 20.2 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2033 (2033) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/OPGLA 70 · payload sha256 b1326c96c662…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
OPGLA 70
Operator note: flexibilityLevel
5%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

Bidirectional · Battery · Available

26.1 MW

Granted

The operator's latest published dataset reports 26.1 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2033 (2033) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/OPGLA 70 · payload sha256 b1326c96c662…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
OPGLA 70
Operator note: flexibilityLevel
10%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

Bidirectional · Battery · Available

46.6 MW

Granted

The operator's latest published dataset reports 46.6 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2033 (2033) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/OPGLA 70 · payload sha256 b1326c96c662…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
OPGLA 70
Operator note: flexibilityLevel
20%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

History

Served series only

Bidirectional · Battery · Available · 2027

last, until 17 Nov 2026: 2.7 MW

26 Sep 2026: 2.7 MW
26 Sep 2026range 2.7 to 2.7 MW24 Nov 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 202617 Nov 20262.7 MW

Time axis: when we observed each value, not the operator’s effective date.

Bidirectional · Battery · Available · 2027

last, until 17 Nov 2026: 13.9 MW

26 Sep 2026: 13.8 MW17 Oct 2026: 13.9 MW
26 Sep 2026range 13.8 to 13.9 MW24 Nov 2026
2 published values, as a table
Observed fromUntilValue
26 Sep 202617 Oct 202613.8 MW
17 Oct 202617 Nov 202613.9 MW

Time axis: when we observed each value, not the operator’s effective date.

Bidirectional · Battery · Available · 2027

last, until 17 Nov 2026: 20 MW

26 Sep 2026: 19.8 MW17 Oct 2026: 20 MW
26 Sep 2026range 19.8 to 20 MW24 Nov 2026
2 published values, as a table
Observed fromUntilValue
26 Sep 202617 Oct 202619.8 MW
17 Oct 202617 Nov 202620 MW

Time axis: when we observed each value, not the operator’s effective date.

Bidirectional · Battery · Available · 2027

last, until 17 Nov 2026: 42.2 MW

26 Sep 2026: 42.2 MW
26 Sep 2026range 42.2 to 42.2 MW24 Nov 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 202617 Nov 202642.2 MW

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Load (any) · Available · 2027

last, until 17 Nov 2026: 2.7 MW

26 Sep 2026: 2.7 MW
26 Sep 2026range 2.7 to 2.7 MW24 Nov 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 202617 Nov 20262.7 MW

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Load (any) · Available · 2027

last, until 17 Nov 2026: 16.6 MW

26 Sep 2026: 16.8 MW17 Oct 2026: 16.6 MW
26 Sep 2026range 16.6 to 16.8 MW24 Nov 2026
2 published values, as a table
Observed fromUntilValue
26 Sep 202617 Oct 202616.8 MW
17 Oct 202617 Nov 202616.6 MW

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Load (any) · Available · 2027

last, until 17 Nov 2026: 25.8 MW

26 Sep 2026: 26.7 MW17 Oct 2026: 25.8 MW
26 Sep 2026range 25.8 to 26.7 MW24 Nov 2026
2 published values, as a table
Observed fromUntilValue
26 Sep 202617 Oct 202626.7 MW
17 Oct 202617 Nov 202625.8 MW

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Load (any) · Available · 2027

last, until 17 Nov 2026: 49.3 MW

26 Sep 2026: 50 MW17 Oct 2026: 49.3 MW
26 Sep 2026range 49.3 to 50 MW24 Nov 2026
2 published values, as a table
Observed fromUntilValue
26 Sep 202617 Oct 202650 MW
17 Oct 202617 Nov 202649.3 MW

Time axis: when we observed each value, not the operator’s effective date.

Injection · Generation (any) · Available · 2027

last, until 17 Nov 2026: 8.7 MW

26 Sep 2026: 8.7 MW
26 Sep 2026range 8.7 to 8.7 MW24 Nov 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 202617 Nov 20268.7 MW

Time axis: when we observed each value, not the operator’s effective date.

Injection · Generation (any) · Available · 2027

last, until 17 Nov 2026: 37.2 MW

26 Sep 2026: 31.1 MW17 Oct 2026: 37.2 MW
26 Sep 2026range 31.1 to 37.2 MW24 Nov 2026
2 published values, as a table
Observed fromUntilValue
26 Sep 202617 Oct 202631.1 MW
17 Oct 202617 Nov 202637.2 MW

Time axis: when we observed each value, not the operator’s effective date.

Injection · Generation (any) · Available · 2027

last, until 17 Nov 2026: 50 MW

26 Sep 2026: 50 MW
26 Sep 2026range 50 to 50 MW24 Nov 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 202617 Nov 202650 MW

Time axis: when we observed each value, not the operator’s effective date.

Injection · Generation (any) · Available · 2027

last, until 17 Nov 2026: 50 MW

26 Sep 2026: 50 MW
26 Sep 2026range 50 to 50 MW24 Nov 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 202617 Nov 202650 MW

Time axis: when we observed each value, not the operator’s effective date.

The first 12 of 80 served series with a history. The history route returns every one of them.

Through the API

curl "https://api.gridcapacityapi.com/v1/substations/sub_06gdrm9mddsd1536g4pd5bc0y4/capacity" \  -H "Authorization: Bearer gc_live_..."