Substation / 150 kV

MONTI

Elia Transmission Belgium / Belgium

Latest published values

40 served · 0 withheld

Each row is what the operator’s latest published dataset reports for one combination of direction, technology, measure, firmness and horizon. Hosting-capacity figures are indicative and reflect what operators publish. They are not a connection offer; only the operator can confirm capacity for a specific request.

Latest published capacity values, one row per series
DirectionTechnologyMeasureValueFirmnessHorizonSource date
InjectionGeneration (any)Available4.9 MWFirm, ≤ 0 % curtailment a year2027 (2027)variant: 150kv26 Sep 2026
InjectionGeneration (any)Available10.5 MWFlexible, ≤ 5 % curtailment a year2027 (2027)variant: 150kv26 Sep 2026
InjectionGeneration (any)Available25.2 MWFlexible, ≤ 10 % curtailment a year2027 (2027)variant: 150kv26 Sep 2026
InjectionGeneration (any)Available104.4 MWFlexible, ≤ 20 % curtailment a year2027 (2027)variant: 150kv26 Sep 2026
InjectionGeneration (any)Available4.9 MWFirm, ≤ 0 % curtailment a year2031 (2031)variant: 150kv26 Sep 2026
InjectionGeneration (any)Available10.5 MWFlexible, ≤ 5 % curtailment a year2031 (2031)variant: 150kv26 Sep 2026
InjectionGeneration (any)Available25.2 MWFlexible, ≤ 10 % curtailment a year2031 (2031)variant: 150kv26 Sep 2026
InjectionGeneration (any)Available104.4 MWFlexible, ≤ 20 % curtailment a year2031 (2031)variant: 150kv26 Sep 2026
InjectionSolar PVAvailable7.3 MWFirm, ≤ 0 % curtailment a year2027 (2027)variant: 150kv26 Sep 2026
InjectionSolar PVAvailable13.6 MWFlexible, ≤ 5 % curtailment a year2027 (2027)variant: 150kv26 Sep 2026
InjectionSolar PVAvailable16.4 MWFlexible, ≤ 10 % curtailment a year2027 (2027)variant: 150kv26 Sep 2026
InjectionSolar PVAvailable26 MWFlexible, ≤ 20 % curtailment a year2027 (2027)variant: 150kv26 Sep 2026
InjectionSolar PVAvailable7.3 MWFirm, ≤ 0 % curtailment a year2031 (2031)variant: 150kv26 Sep 2026
InjectionSolar PVAvailable13.6 MWFlexible, ≤ 5 % curtailment a year2031 (2031)variant: 150kv26 Sep 2026
InjectionSolar PVAvailable16.4 MWFlexible, ≤ 10 % curtailment a year2031 (2031)variant: 150kv26 Sep 2026
InjectionSolar PVAvailable26 MWFlexible, ≤ 20 % curtailment a year2031 (2031)variant: 150kv26 Sep 2026
InjectionOnshore windAvailable7.5 MWFirm, ≤ 0 % curtailment a year2027 (2027)variant: 150kv26 Sep 2026
InjectionOnshore windAvailable19.9 MWFlexible, ≤ 5 % curtailment a year2027 (2027)variant: 150kv26 Sep 2026
InjectionOnshore windAvailable55 MWFlexible, ≤ 10 % curtailment a year2027 (2027)variant: 150kv26 Sep 2026
InjectionOnshore windAvailable145.2 MWFlexible, ≤ 20 % curtailment a year2027 (2027)variant: 150kv26 Sep 2026
InjectionOnshore windAvailable7.5 MWFirm, ≤ 0 % curtailment a year2031 (2031)variant: 150kv26 Sep 2026
InjectionOnshore windAvailable19.9 MWFlexible, ≤ 5 % curtailment a year2031 (2031)variant: 150kv26 Sep 2026
InjectionOnshore windAvailable55 MWFlexible, ≤ 10 % curtailment a year2031 (2031)variant: 150kv26 Sep 2026
InjectionOnshore windAvailable145.2 MWFlexible, ≤ 20 % curtailment a year2031 (2031)variant: 150kv26 Sep 2026
OfftakeLoad (any)Available4.6 MWFirm, ≤ 0 % curtailment a year2027 (2027)variant: 150kv26 Sep 2026
OfftakeLoad (any)Available11.9 MWFlexible, ≤ 5 % curtailment a year2027 (2027)variant: 150kv26 Sep 2026
OfftakeLoad (any)Available16.3 MWFlexible, ≤ 10 % curtailment a year2027 (2027)variant: 150kv26 Sep 2026
OfftakeLoad (any)Available23.3 MWFlexible, ≤ 20 % curtailment a year2027 (2027)variant: 150kv26 Sep 2026
OfftakeLoad (any)Available4.6 MWFirm, ≤ 0 % curtailment a year2031 (2031)variant: 150kv26 Sep 2026
OfftakeLoad (any)Available13.9 MWFlexible, ≤ 5 % curtailment a year2031 (2031)variant: 150kv26 Sep 2026
OfftakeLoad (any)Available18.1 MWFlexible, ≤ 10 % curtailment a year2031 (2031)variant: 150kv26 Sep 2026
OfftakeLoad (any)Available25.9 MWFlexible, ≤ 20 % curtailment a year2031 (2031)variant: 150kv26 Sep 2026
BidirectionalBatteryAvailable4.5 MWFirm, ≤ 0 % curtailment a year2027 (2027)variant: 150kv26 Sep 2026
BidirectionalBatteryAvailable10.5 MWFlexible, ≤ 5 % curtailment a year2027 (2027)variant: 150kv26 Sep 2026
BidirectionalBatteryAvailable16.2 MWFlexible, ≤ 10 % curtailment a year2027 (2027)variant: 150kv26 Sep 2026
BidirectionalBatteryAvailable21.7 MWFlexible, ≤ 20 % curtailment a year2027 (2027)variant: 150kv26 Sep 2026
BidirectionalBatteryAvailable4.5 MWFirm, ≤ 0 % curtailment a year2031 (2031)variant: 150kv26 Sep 2026
BidirectionalBatteryAvailable10.5 MWFlexible, ≤ 5 % curtailment a year2031 (2031)variant: 150kv26 Sep 2026
BidirectionalBatteryAvailable17.6 MWFlexible, ≤ 10 % curtailment a year2031 (2031)variant: 150kv26 Sep 2026
BidirectionalBatteryAvailable24.9 MWFlexible, ≤ 20 % curtailment a year2031 (2031)variant: 150kv26 Sep 2026

Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map

What each value means

Methodology, both clocks, provenance and rights

Injection · Generation (any) · Available

4.9 MW

Granted

The operator's latest published dataset reports 4.9 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2027 (2027) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2027/MONTI150 · payload sha256 3fda4b31c694…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
MONTI150
Operator note: flexibilityLevel
0%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Injection · Generation (any) · Available

10.5 MW

Granted

The operator's latest published dataset reports 10.5 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2027 (2027) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2027/MONTI150 · payload sha256 3fda4b31c694…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
MONTI150
Operator note: flexibilityLevel
5%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Injection · Generation (any) · Available

25.2 MW

Granted

The operator's latest published dataset reports 25.2 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2027 (2027) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2027/MONTI150 · payload sha256 3fda4b31c694…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
MONTI150
Operator note: flexibilityLevel
10%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Injection · Generation (any) · Available

104.4 MW

Granted

The operator's latest published dataset reports 104.4 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2027 (2027) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2027/MONTI150 · payload sha256 3fda4b31c694…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
MONTI150
Operator note: flexibilityLevel
20%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Injection · Generation (any) · Available

4.9 MW

Granted

The operator's latest published dataset reports 4.9 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2031 (2031) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/MONTI150 · payload sha256 0d5d46f8828f…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
MONTI150
Operator note: flexibilityLevel
0%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Injection · Generation (any) · Available

10.5 MW

Granted

The operator's latest published dataset reports 10.5 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2031 (2031) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/MONTI150 · payload sha256 0d5d46f8828f…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
MONTI150
Operator note: flexibilityLevel
5%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Injection · Generation (any) · Available

25.2 MW

Granted

The operator's latest published dataset reports 25.2 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2031 (2031) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/MONTI150 · payload sha256 0d5d46f8828f…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
MONTI150
Operator note: flexibilityLevel
10%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Injection · Generation (any) · Available

104.4 MW

Granted

The operator's latest published dataset reports 104.4 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2031 (2031) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/MONTI150 · payload sha256 0d5d46f8828f…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
MONTI150
Operator note: flexibilityLevel
20%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Injection · Solar PV · Available

7.3 MW

Granted

The operator's latest published dataset reports 7.3 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2027 (2027) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2027/MONTI150 · payload sha256 3fda4b31c694…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
MONTI150
Operator note: flexibilityLevel
0%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Injection · Solar PV · Available

13.6 MW

Granted

The operator's latest published dataset reports 13.6 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2027 (2027) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2027/MONTI150 · payload sha256 3fda4b31c694…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
MONTI150
Operator note: flexibilityLevel
5%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Injection · Solar PV · Available

16.4 MW

Granted

The operator's latest published dataset reports 16.4 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2027 (2027) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2027/MONTI150 · payload sha256 3fda4b31c694…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
MONTI150
Operator note: flexibilityLevel
10%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Injection · Solar PV · Available

26 MW

Granted

The operator's latest published dataset reports 26 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2027 (2027) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2027/MONTI150 · payload sha256 3fda4b31c694…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
MONTI150
Operator note: flexibilityLevel
20%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Injection · Solar PV · Available

7.3 MW

Granted

The operator's latest published dataset reports 7.3 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2031 (2031) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/MONTI150 · payload sha256 0d5d46f8828f…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
MONTI150
Operator note: flexibilityLevel
0%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Injection · Solar PV · Available

13.6 MW

Granted

The operator's latest published dataset reports 13.6 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2031 (2031) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/MONTI150 · payload sha256 0d5d46f8828f…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
MONTI150
Operator note: flexibilityLevel
5%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Injection · Solar PV · Available

16.4 MW

Granted

The operator's latest published dataset reports 16.4 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2031 (2031) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/MONTI150 · payload sha256 0d5d46f8828f…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
MONTI150
Operator note: flexibilityLevel
10%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Injection · Solar PV · Available

26 MW

Granted

The operator's latest published dataset reports 26 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2031 (2031) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/MONTI150 · payload sha256 0d5d46f8828f…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
MONTI150
Operator note: flexibilityLevel
20%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Injection · Onshore wind · Available

7.5 MW

Granted

The operator's latest published dataset reports 7.5 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2027 (2027) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2027/MONTI150 · payload sha256 3fda4b31c694…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
MONTI150
Operator note: flexibilityLevel
0%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Injection · Onshore wind · Available

19.9 MW

Granted

The operator's latest published dataset reports 19.9 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2027 (2027) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2027/MONTI150 · payload sha256 3fda4b31c694…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
MONTI150
Operator note: flexibilityLevel
5%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Injection · Onshore wind · Available

55 MW

Granted

The operator's latest published dataset reports 55 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2027 (2027) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2027/MONTI150 · payload sha256 3fda4b31c694…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
MONTI150
Operator note: flexibilityLevel
10%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Injection · Onshore wind · Available

145.2 MW

Granted

The operator's latest published dataset reports 145.2 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2027 (2027) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2027/MONTI150 · payload sha256 3fda4b31c694…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
MONTI150
Operator note: flexibilityLevel
20%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Injection · Onshore wind · Available

7.5 MW

Granted

The operator's latest published dataset reports 7.5 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2031 (2031) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/MONTI150 · payload sha256 0d5d46f8828f…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
MONTI150
Operator note: flexibilityLevel
0%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Injection · Onshore wind · Available

19.9 MW

Granted

The operator's latest published dataset reports 19.9 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2031 (2031) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/MONTI150 · payload sha256 0d5d46f8828f…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
MONTI150
Operator note: flexibilityLevel
5%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Injection · Onshore wind · Available

55 MW

Granted

The operator's latest published dataset reports 55 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2031 (2031) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/MONTI150 · payload sha256 0d5d46f8828f…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
MONTI150
Operator note: flexibilityLevel
10%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Injection · Onshore wind · Available

145.2 MW

Granted

The operator's latest published dataset reports 145.2 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2031 (2031) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/MONTI150 · payload sha256 0d5d46f8828f…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
MONTI150
Operator note: flexibilityLevel
20%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Offtake · Load (any) · Available

4.6 MW

Granted

The operator's latest published dataset reports 4.6 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2027 (2027) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2027/MONTI150 · payload sha256 3fda4b31c694…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
MONTI150
Operator note: flexibilityLevel
0%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Offtake · Load (any) · Available

11.9 MW

Granted

The operator's latest published dataset reports 11.9 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2027 (2027) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2027/MONTI150 · payload sha256 3fda4b31c694…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
MONTI150
Operator note: flexibilityLevel
5%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Offtake · Load (any) · Available

16.3 MW

Granted

The operator's latest published dataset reports 16.3 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2027 (2027) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2027/MONTI150 · payload sha256 3fda4b31c694…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
MONTI150
Operator note: flexibilityLevel
10%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Offtake · Load (any) · Available

23.3 MW

Granted

The operator's latest published dataset reports 23.3 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2027 (2027) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2027/MONTI150 · payload sha256 3fda4b31c694…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
MONTI150
Operator note: flexibilityLevel
20%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Offtake · Load (any) · Available

4.6 MW

Granted

The operator's latest published dataset reports 4.6 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2031 (2031) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/MONTI150 · payload sha256 0d5d46f8828f…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
MONTI150
Operator note: flexibilityLevel
0%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Offtake · Load (any) · Available

13.9 MW

Granted

The operator's latest published dataset reports 13.9 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2031 (2031) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/MONTI150 · payload sha256 0d5d46f8828f…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
MONTI150
Operator note: flexibilityLevel
5%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Offtake · Load (any) · Available

18.1 MW

Granted

The operator's latest published dataset reports 18.1 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2031 (2031) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/MONTI150 · payload sha256 0d5d46f8828f…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
MONTI150
Operator note: flexibilityLevel
10%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Offtake · Load (any) · Available

25.9 MW

Granted

The operator's latest published dataset reports 25.9 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2031 (2031) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/MONTI150 · payload sha256 0d5d46f8828f…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
MONTI150
Operator note: flexibilityLevel
20%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Bidirectional · Battery · Available

4.5 MW

Granted

The operator's latest published dataset reports 4.5 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2027 (2027) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2027/MONTI150 · payload sha256 3fda4b31c694…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
MONTI150
Operator note: flexibilityLevel
0%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Bidirectional · Battery · Available

10.5 MW

Granted

The operator's latest published dataset reports 10.5 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2027 (2027) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2027/MONTI150 · payload sha256 3fda4b31c694…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
MONTI150
Operator note: flexibilityLevel
5%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Bidirectional · Battery · Available

16.2 MW

Granted

The operator's latest published dataset reports 16.2 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2027 (2027) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2027/MONTI150 · payload sha256 3fda4b31c694…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
MONTI150
Operator note: flexibilityLevel
10%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Bidirectional · Battery · Available

21.7 MW

Granted

The operator's latest published dataset reports 21.7 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2027 (2027) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2027/MONTI150 · payload sha256 3fda4b31c694…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
MONTI150
Operator note: flexibilityLevel
20%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Bidirectional · Battery · Available

4.5 MW

Granted

The operator's latest published dataset reports 4.5 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2031 (2031) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/MONTI150 · payload sha256 0d5d46f8828f…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
MONTI150
Operator note: flexibilityLevel
0%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Bidirectional · Battery · Available

10.5 MW

Granted

The operator's latest published dataset reports 10.5 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2031 (2031) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/MONTI150 · payload sha256 0d5d46f8828f…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
MONTI150
Operator note: flexibilityLevel
5%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Bidirectional · Battery · Available

17.6 MW

Granted

The operator's latest published dataset reports 17.6 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2031 (2031) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/MONTI150 · payload sha256 0d5d46f8828f…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
MONTI150
Operator note: flexibilityLevel
10%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Bidirectional · Battery · Available

24.9 MW

Granted

The operator's latest published dataset reports 24.9 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2031 (2031) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/MONTI150 · payload sha256 0d5d46f8828f…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
MONTI150
Operator note: flexibilityLevel
20%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

History

Served series only

Bidirectional · Battery · Available · 2027

current 4.5 MW

26 Sep 2026: 4.5 MW
26 Sep 2026range 4.5 to 4.5 MW2 Oct 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current4.5 MW

Time axis: when we observed each value, not the operator’s effective date.

Bidirectional · Battery · Available · 2027

current 10.5 MW

26 Sep 2026: 10.5 MW
26 Sep 2026range 10.5 to 10.5 MW2 Oct 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current10.5 MW

Time axis: when we observed each value, not the operator’s effective date.

Bidirectional · Battery · Available · 2027

current 16.2 MW

26 Sep 2026: 16.2 MW
26 Sep 2026range 16.2 to 16.2 MW2 Oct 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current16.2 MW

Time axis: when we observed each value, not the operator’s effective date.

Bidirectional · Battery · Available · 2027

current 21.7 MW

26 Sep 2026: 21.7 MW
26 Sep 2026range 21.7 to 21.7 MW2 Oct 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current21.7 MW

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Load (any) · Available · 2027

current 4.6 MW

26 Sep 2026: 4.6 MW
26 Sep 2026range 4.6 to 4.6 MW2 Oct 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current4.6 MW

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Load (any) · Available · 2027

current 11.9 MW

26 Sep 2026: 11.9 MW
26 Sep 2026range 11.9 to 11.9 MW2 Oct 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current11.9 MW

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Load (any) · Available · 2027

current 16.3 MW

26 Sep 2026: 16.3 MW
26 Sep 2026range 16.3 to 16.3 MW2 Oct 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current16.3 MW

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Load (any) · Available · 2027

current 23.3 MW

26 Sep 2026: 23.3 MW
26 Sep 2026range 23.3 to 23.3 MW2 Oct 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current23.3 MW

Time axis: when we observed each value, not the operator’s effective date.

Injection · Generation (any) · Available · 2027

current 4.9 MW

26 Sep 2026: 4.9 MW
26 Sep 2026range 4.9 to 4.9 MW2 Oct 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current4.9 MW

Time axis: when we observed each value, not the operator’s effective date.

Injection · Generation (any) · Available · 2027

current 10.5 MW

26 Sep 2026: 10.5 MW
26 Sep 2026range 10.5 to 10.5 MW2 Oct 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current10.5 MW

Time axis: when we observed each value, not the operator’s effective date.

Injection · Generation (any) · Available · 2027

current 25.2 MW

26 Sep 2026: 25.2 MW
26 Sep 2026range 25.2 to 25.2 MW2 Oct 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current25.2 MW

Time axis: when we observed each value, not the operator’s effective date.

Injection · Generation (any) · Available · 2027

current 104.4 MW

26 Sep 2026: 104.4 MW
26 Sep 2026range 104.4 to 104.4 MW2 Oct 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current104.4 MW

Time axis: when we observed each value, not the operator’s effective date.

The first 12 of 40 served series with a history. The history route returns every one of them.

Through the API

curl "https://api.gridcapacityapi.com/v1/substations/sub_06gdrm9mchsy17qr65ey5fvsdm/capacity" \  -H "Authorization: Bearer gc_live_..."
MONTI 150 kV substation: grid capacity (Elia Transmission Belgium) · GridCapacity API