| Injection | Generation (any) | Available | 1.2 MW | Firm, ≤ 0 % curtailment a year | 2027 (2027)variant: 70kv | 26 Sep 2026 |
| Injection | Generation (any) | Available | 9.6 MW | Flexible, ≤ 5 % curtailment a year | 2027 (2027)variant: 70kv | 26 Sep 2026 |
| Injection | Generation (any) | Available | 11.3 MW | Flexible, ≤ 10 % curtailment a year | 2027 (2027)variant: 70kv | 26 Sep 2026 |
| Injection | Generation (any) | Available | 14.7 MW | Flexible, ≤ 20 % curtailment a year | 2027 (2027)variant: 70kv | 26 Sep 2026 |
| Injection | Generation (any) | Available | 1.2 MW | Firm, ≤ 0 % curtailment a year | 2031 (2031)variant: 70kv | 26 Sep 2026 |
| Injection | Generation (any) | Available | 9.6 MW | Flexible, ≤ 5 % curtailment a year | 2031 (2031)variant: 70kv | 26 Sep 2026 |
| Injection | Generation (any) | Available | 11.3 MW | Flexible, ≤ 10 % curtailment a year | 2031 (2031)variant: 70kv | 26 Sep 2026 |
| Injection | Generation (any) | Available | 14.7 MW | Flexible, ≤ 20 % curtailment a year | 2031 (2031)variant: 70kv | 26 Sep 2026 |
| Injection | Solar PV | Available | 2 MW | Firm, ≤ 0 % curtailment a year | 2027 (2027)variant: 70kv | 26 Sep 2026 |
| Injection | Solar PV | Available | 49.3 MW | Flexible, ≤ 5 % curtailment a year | 2027 (2027)variant: 70kv | 26 Sep 2026 |
| Injection | Solar PV | Available | 50 MW | Flexible, ≤ 10 % curtailment a year | 2027 (2027)variant: 70kv | 26 Sep 2026 |
| Injection | Solar PV | Available | 50 MW | Flexible, ≤ 20 % curtailment a year | 2027 (2027)variant: 70kv | 26 Sep 2026 |
| Injection | Solar PV | Available | 2.1 MW | Firm, ≤ 0 % curtailment a year | 2031 (2031)variant: 70kv | 26 Sep 2026 |
| Injection | Solar PV | Available | 49.3 MW | Flexible, ≤ 5 % curtailment a year | 2031 (2031)variant: 70kv | 26 Sep 2026 |
| Injection | Solar PV | Available | 50 MW | Flexible, ≤ 10 % curtailment a year | 2031 (2031)variant: 70kv | 26 Sep 2026 |
| Injection | Solar PV | Available | 50 MW | Flexible, ≤ 20 % curtailment a year | 2031 (2031)variant: 70kv | 26 Sep 2026 |
| Injection | Onshore wind | Available | 1.7 MW | Firm, ≤ 0 % curtailment a year | 2027 (2027)variant: 70kv | 26 Sep 2026 |
| Injection | Onshore wind | Available | 12.8 MW | Flexible, ≤ 5 % curtailment a year | 2027 (2027)variant: 70kv | 26 Sep 2026 |
| Injection | Onshore wind | Available | 15.5 MW | Flexible, ≤ 10 % curtailment a year | 2027 (2027)variant: 70kv | 26 Sep 2026 |
| Injection | Onshore wind | Available | 23.5 MW | Flexible, ≤ 20 % curtailment a year | 2027 (2027)variant: 70kv | 26 Sep 2026 |
| Injection | Onshore wind | Available | 1.7 MW | Firm, ≤ 0 % curtailment a year | 2031 (2031)variant: 70kv | 26 Sep 2026 |
| Injection | Onshore wind | Available | 12.8 MW | Flexible, ≤ 5 % curtailment a year | 2031 (2031)variant: 70kv | 26 Sep 2026 |
| Injection | Onshore wind | Available | 15.5 MW | Flexible, ≤ 10 % curtailment a year | 2031 (2031)variant: 70kv | 26 Sep 2026 |
| Injection | Onshore wind | Available | 23.5 MW | Flexible, ≤ 20 % curtailment a year | 2031 (2031)variant: 70kv | 26 Sep 2026 |
| Offtake | Load (any) | Available | 1.2 MW | Firm, ≤ 0 % curtailment a year | 2027 (2027)variant: 70kv | 26 Sep 2026 |
| Offtake | Load (any) | Available | 2 MW | Flexible, ≤ 5 % curtailment a year | 2027 (2027)variant: 70kv | 26 Sep 2026 |
| Offtake | Load (any) | Available | 2.5 MW | Flexible, ≤ 10 % curtailment a year | 2027 (2027)variant: 70kv | 26 Sep 2026 |
| Offtake | Load (any) | Available | 3.5 MW | Flexible, ≤ 20 % curtailment a year | 2027 (2027)variant: 70kv | 26 Sep 2026 |
| Offtake | Load (any) | Available | 1.2 MW | Firm, ≤ 0 % curtailment a year | 2031 (2031)variant: 70kv | 26 Sep 2026 |
| Offtake | Load (any) | Available | 2 MW | Flexible, ≤ 5 % curtailment a year | 2031 (2031)variant: 70kv | 26 Sep 2026 |
| Offtake | Load (any) | Available | 2.5 MW | Flexible, ≤ 10 % curtailment a year | 2031 (2031)variant: 70kv | 26 Sep 2026 |
| Offtake | Load (any) | Available | 3.5 MW | Flexible, ≤ 20 % curtailment a year | 2031 (2031)variant: 70kv | 26 Sep 2026 |
| Bidirectional | Battery | Available | 1.2 MW | Firm, ≤ 0 % curtailment a year | 2027 (2027)variant: 70kv | 26 Sep 2026 |
| Bidirectional | Battery | Available | 2 MW | Flexible, ≤ 5 % curtailment a year | 2027 (2027)variant: 70kv | 26 Sep 2026 |
| Bidirectional | Battery | Available | 2.6 MW | Flexible, ≤ 10 % curtailment a year | 2027 (2027)variant: 70kv | 26 Sep 2026 |
| Bidirectional | Battery | Available | 3.6 MW | Flexible, ≤ 20 % curtailment a year | 2027 (2027)variant: 70kv | 26 Sep 2026 |
| Bidirectional | Battery | Available | 1.2 MW | Firm, ≤ 0 % curtailment a year | 2031 (2031)variant: 70kv | 26 Sep 2026 |
| Bidirectional | Battery | Available | 2 MW | Flexible, ≤ 5 % curtailment a year | 2031 (2031)variant: 70kv | 26 Sep 2026 |
| Bidirectional | Battery | Available | 2.6 MW | Flexible, ≤ 10 % curtailment a year | 2031 (2031)variant: 70kv | 26 Sep 2026 |
| Bidirectional | Battery | Available | 3.6 MW | Flexible, ≤ 20 % curtailment a year | 2031 (2031)variant: 70kv | 26 Sep 2026 |