| Injection | Generation (any) | Available | 8.2 MW | Firm, ≤ 0 % curtailment a year | 2029 (2029)variant: 36kv | 17 Nov 2026 |
| Injection | Generation (any) | Available | 20 MW | Flexible, ≤ 5 % curtailment a year | 2029 (2029)variant: 36kv | 17 Nov 2026 |
| Injection | Generation (any) | Available | 20 MW | Flexible, ≤ 10 % curtailment a year | 2029 (2029)variant: 36kv | 17 Nov 2026 |
| Injection | Generation (any) | Available | 20 MW | Flexible, ≤ 20 % curtailment a year | 2029 (2029)variant: 36kv | 17 Nov 2026 |
| Injection | Generation (any) | Available | 20 MW | Firm, ≤ 0 % curtailment a year | 2033 (2033)variant: 36kv | 17 Nov 2026 |
| Injection | Generation (any) | Available | 20 MW | Flexible, ≤ 5 % curtailment a year | 2033 (2033)variant: 36kv | 17 Nov 2026 |
| Injection | Generation (any) | Available | 20 MW | Flexible, ≤ 10 % curtailment a year | 2033 (2033)variant: 36kv | 17 Nov 2026 |
| Injection | Generation (any) | Available | 20 MW | Flexible, ≤ 20 % curtailment a year | 2033 (2033)variant: 36kv | 17 Nov 2026 |
| Injection | Solar PV | Available | 20 MW | Firm, ≤ 0 % curtailment a year | 2029 (2029)variant: 36kv | 17 Nov 2026 |
| Injection | Solar PV | Available | 20 MW | Flexible, ≤ 5 % curtailment a year | 2029 (2029)variant: 36kv | 17 Nov 2026 |
| Injection | Solar PV | Available | 20 MW | Flexible, ≤ 10 % curtailment a year | 2029 (2029)variant: 36kv | 17 Nov 2026 |
| Injection | Solar PV | Available | 20 MW | Flexible, ≤ 20 % curtailment a year | 2029 (2029)variant: 36kv | 17 Nov 2026 |
| Injection | Solar PV | Available | 20 MW | Firm, ≤ 0 % curtailment a year | 2033 (2033)variant: 36kv | 17 Nov 2026 |
| Injection | Solar PV | Available | 20 MW | Flexible, ≤ 5 % curtailment a year | 2033 (2033)variant: 36kv | 17 Nov 2026 |
| Injection | Solar PV | Available | 20 MW | Flexible, ≤ 10 % curtailment a year | 2033 (2033)variant: 36kv | 17 Nov 2026 |
| Injection | Solar PV | Available | 20 MW | Flexible, ≤ 20 % curtailment a year | 2033 (2033)variant: 36kv | 17 Nov 2026 |
| Injection | Onshore wind | Available | 20 MW | Firm, ≤ 0 % curtailment a year | 2029 (2029)variant: 36kv | 17 Nov 2026 |
| Injection | Onshore wind | Available | 20 MW | Flexible, ≤ 5 % curtailment a year | 2029 (2029)variant: 36kv | 17 Nov 2026 |
| Injection | Onshore wind | Available | 20 MW | Flexible, ≤ 10 % curtailment a year | 2029 (2029)variant: 36kv | 17 Nov 2026 |
| Injection | Onshore wind | Available | 20 MW | Flexible, ≤ 20 % curtailment a year | 2029 (2029)variant: 36kv | 17 Nov 2026 |
| Injection | Onshore wind | Available | 20 MW | Firm, ≤ 0 % curtailment a year | 2033 (2033)variant: 36kv | 17 Nov 2026 |
| Injection | Onshore wind | Available | 20 MW | Flexible, ≤ 5 % curtailment a year | 2033 (2033)variant: 36kv | 17 Nov 2026 |
| Injection | Onshore wind | Available | 20 MW | Flexible, ≤ 10 % curtailment a year | 2033 (2033)variant: 36kv | 17 Nov 2026 |
| Injection | Onshore wind | Available | 20 MW | Flexible, ≤ 20 % curtailment a year | 2033 (2033)variant: 36kv | 17 Nov 2026 |
| Offtake | Load (any) | Available | 5.5 MW | Firm, ≤ 0 % curtailment a year | 2029 (2029)variant: 36kv | 17 Nov 2026 |
| Offtake | Load (any) | Available | 10.3 MW | Flexible, ≤ 5 % curtailment a year | 2029 (2029)variant: 36kv | 17 Nov 2026 |
| Offtake | Load (any) | Available | 18.5 MW | Flexible, ≤ 10 % curtailment a year | 2029 (2029)variant: 36kv | 17 Nov 2026 |
| Offtake | Load (any) | Available | 20 MW | Flexible, ≤ 20 % curtailment a year | 2029 (2029)variant: 36kv | 17 Nov 2026 |
| Offtake | Load (any) | Available | 16.2 MW | Firm, ≤ 0 % curtailment a year | 2033 (2033)variant: 36kv | 17 Nov 2026 |
| Offtake | Load (any) | Available | 20 MW | Flexible, ≤ 5 % curtailment a year | 2033 (2033)variant: 36kv | 17 Nov 2026 |
| Offtake | Load (any) | Available | 20 MW | Flexible, ≤ 10 % curtailment a year | 2033 (2033)variant: 36kv | 17 Nov 2026 |
| Offtake | Load (any) | Available | 20 MW | Flexible, ≤ 20 % curtailment a year | 2033 (2033)variant: 36kv | 17 Nov 2026 |
| Bidirectional | Battery | Available | 4.8 MW | Firm, ≤ 0 % curtailment a year | 2029 (2029)variant: 36kv | 17 Nov 2026 |
| Bidirectional | Battery | Available | 8.4 MW | Flexible, ≤ 5 % curtailment a year | 2029 (2029)variant: 36kv | 17 Nov 2026 |
| Bidirectional | Battery | Available | 14.9 MW | Flexible, ≤ 10 % curtailment a year | 2029 (2029)variant: 36kv | 17 Nov 2026 |
| Bidirectional | Battery | Available | 20 MW | Flexible, ≤ 20 % curtailment a year | 2029 (2029)variant: 36kv | 17 Nov 2026 |
| Bidirectional | Battery | Available | 4.8 MW | Firm, ≤ 0 % curtailment a year | 2033 (2033)variant: 36kv | 17 Nov 2026 |
| Bidirectional | Battery | Available | 20 MW | Flexible, ≤ 5 % curtailment a year | 2033 (2033)variant: 36kv | 17 Nov 2026 |
| Bidirectional | Battery | Available | 20 MW | Flexible, ≤ 10 % curtailment a year | 2033 (2033)variant: 36kv | 17 Nov 2026 |
| Bidirectional | Battery | Available | 20 MW | Flexible, ≤ 20 % curtailment a year | 2033 (2033)variant: 36kv | 17 Nov 2026 |