| Injection | Generation (any) | Available | 48.4 MW | Firm, ≤ 0 % curtailment a year | 2029 (2029)variant: 70kv | 17 Nov 2026 |
| Injection | Generation (any) | Available | 44 MW | Firm, ≤ 0 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Injection | Generation (any) | Available | 175 MW | Flexible, ≤ 5 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Injection | Generation (any) | Available | 50 MW | Flexible, ≤ 5 % curtailment a year | 2029 (2029)variant: 70kv | 17 Nov 2026 |
| Injection | Generation (any) | Available | 175 MW | Flexible, ≤ 10 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Injection | Generation (any) | Available | 50 MW | Flexible, ≤ 10 % curtailment a year | 2029 (2029)variant: 70kv | 17 Nov 2026 |
| Injection | Generation (any) | Available | 175 MW | Flexible, ≤ 20 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Injection | Generation (any) | Available | 50 MW | Flexible, ≤ 20 % curtailment a year | 2029 (2029)variant: 70kv | 17 Nov 2026 |
| Injection | Generation (any) | Available | 96.6 MW | Firm, ≤ 0 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |
| Injection | Generation (any) | Available | 48.4 MW | Firm, ≤ 0 % curtailment a year | 2033 (2033)variant: 70kv | 17 Nov 2026 |
| Injection | Generation (any) | Available | 175 MW | Flexible, ≤ 5 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |
| Injection | Generation (any) | Available | 50 MW | Flexible, ≤ 5 % curtailment a year | 2033 (2033)variant: 70kv | 17 Nov 2026 |
| Injection | Generation (any) | Available | 175 MW | Flexible, ≤ 10 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |
| Injection | Generation (any) | Available | 50 MW | Flexible, ≤ 10 % curtailment a year | 2033 (2033)variant: 70kv | 17 Nov 2026 |
| Injection | Generation (any) | Available | 175 MW | Flexible, ≤ 20 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |
| Injection | Generation (any) | Available | 50 MW | Flexible, ≤ 20 % curtailment a year | 2033 (2033)variant: 70kv | 17 Nov 2026 |
| Injection | Solar PV | Available | 175 MW | Firm, ≤ 0 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Injection | Solar PV | Available | 50 MW | Firm, ≤ 0 % curtailment a year | 2029 (2029)variant: 70kv | 17 Nov 2026 |
| Injection | Solar PV | Available | 175 MW | Flexible, ≤ 5 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Injection | Solar PV | Available | 50 MW | Flexible, ≤ 5 % curtailment a year | 2029 (2029)variant: 70kv | 17 Nov 2026 |
| Injection | Solar PV | Available | 175 MW | Flexible, ≤ 10 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Injection | Solar PV | Available | 50 MW | Flexible, ≤ 10 % curtailment a year | 2029 (2029)variant: 70kv | 17 Nov 2026 |
| Injection | Solar PV | Available | 175 MW | Flexible, ≤ 20 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Injection | Solar PV | Available | 50 MW | Flexible, ≤ 20 % curtailment a year | 2029 (2029)variant: 70kv | 17 Nov 2026 |
| Injection | Solar PV | Available | 175 MW | Firm, ≤ 0 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |
| Injection | Solar PV | Available | 50 MW | Firm, ≤ 0 % curtailment a year | 2033 (2033)variant: 70kv | 17 Nov 2026 |
| Injection | Solar PV | Available | 175 MW | Flexible, ≤ 5 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |
| Injection | Solar PV | Available | 50 MW | Flexible, ≤ 5 % curtailment a year | 2033 (2033)variant: 70kv | 17 Nov 2026 |
| Injection | Solar PV | Available | 175 MW | Flexible, ≤ 10 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |
| Injection | Solar PV | Available | 50 MW | Flexible, ≤ 10 % curtailment a year | 2033 (2033)variant: 70kv | 17 Nov 2026 |
| Injection | Solar PV | Available | 175 MW | Flexible, ≤ 20 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |
| Injection | Solar PV | Available | 50 MW | Flexible, ≤ 20 % curtailment a year | 2033 (2033)variant: 70kv | 17 Nov 2026 |
| Injection | Onshore wind | Available | 175 MW | Firm, ≤ 0 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Injection | Onshore wind | Available | 50 MW | Firm, ≤ 0 % curtailment a year | 2029 (2029)variant: 70kv | 17 Nov 2026 |
| Injection | Onshore wind | Available | 175 MW | Flexible, ≤ 5 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Injection | Onshore wind | Available | 50 MW | Flexible, ≤ 5 % curtailment a year | 2029 (2029)variant: 70kv | 17 Nov 2026 |
| Injection | Onshore wind | Available | 175 MW | Flexible, ≤ 10 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Injection | Onshore wind | Available | 50 MW | Flexible, ≤ 10 % curtailment a year | 2029 (2029)variant: 70kv | 17 Nov 2026 |
| Injection | Onshore wind | Available | 175 MW | Flexible, ≤ 20 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Injection | Onshore wind | Available | 50 MW | Flexible, ≤ 20 % curtailment a year | 2029 (2029)variant: 70kv | 17 Nov 2026 |
| Injection | Onshore wind | Available | 175 MW | Firm, ≤ 0 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |
| Injection | Onshore wind | Available | 50 MW | Firm, ≤ 0 % curtailment a year | 2033 (2033)variant: 70kv | 17 Nov 2026 |
| Injection | Onshore wind | Available | 175 MW | Flexible, ≤ 5 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |
| Injection | Onshore wind | Available | 50 MW | Flexible, ≤ 5 % curtailment a year | 2033 (2033)variant: 70kv | 17 Nov 2026 |
| Injection | Onshore wind | Available | 175 MW | Flexible, ≤ 10 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |
| Injection | Onshore wind | Available | 50 MW | Flexible, ≤ 10 % curtailment a year | 2033 (2033)variant: 70kv | 17 Nov 2026 |
| Injection | Onshore wind | Available | 175 MW | Flexible, ≤ 20 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |
| Injection | Onshore wind | Available | 50 MW | Flexible, ≤ 20 % curtailment a year | 2033 (2033)variant: 70kv | 17 Nov 2026 |
| Offtake | Load (any) | Available | 8.7 MW | Firm, ≤ 0 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Offtake | Load (any) | Available | 0 MW | Firm, ≤ 0 % curtailment a year | 2029 (2029)variant: 70kv | 17 Nov 2026 |
| Offtake | Load (any) | Available | 16.5 MW | Flexible, ≤ 5 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Offtake | Load (any) | Available | 0 MW | Flexible, ≤ 5 % curtailment a year | 2029 (2029)variant: 70kv | 17 Nov 2026 |
| Offtake | Load (any) | Available | 26.3 MW | Flexible, ≤ 10 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Offtake | Load (any) | Available | 0 MW | Flexible, ≤ 10 % curtailment a year | 2029 (2029)variant: 70kv | 17 Nov 2026 |
| Offtake | Load (any) | Available | 47.6 MW | Flexible, ≤ 20 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Offtake | Load (any) | Available | 0 MW | Flexible, ≤ 20 % curtailment a year | 2029 (2029)variant: 70kv | 17 Nov 2026 |
| Offtake | Load (any) | Available | 15 MW | Firm, ≤ 0 % curtailment a year | 2033 (2033)variant: 70kv | 17 Nov 2026 |
| Offtake | Load (any) | Available | 13.3 MW | Firm, ≤ 0 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |
| Offtake | Load (any) | Available | 28.3 MW | Flexible, ≤ 5 % curtailment a year | 2033 (2033)variant: 70kv | 17 Nov 2026 |
| Offtake | Load (any) | Available | 25 MW | Flexible, ≤ 5 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |
| Offtake | Load (any) | Available | 43.2 MW | Flexible, ≤ 10 % curtailment a year | 2033 (2033)variant: 70kv | 17 Nov 2026 |
| Offtake | Load (any) | Available | 38.4 MW | Flexible, ≤ 10 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |
| Offtake | Load (any) | Available | 134.3 MW | Flexible, ≤ 20 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |
| Offtake | Load (any) | Available | 50 MW | Flexible, ≤ 20 % curtailment a year | 2033 (2033)variant: 70kv | 17 Nov 2026 |
| Bidirectional | Battery | Available | 6.9 MW | Firm, ≤ 0 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Bidirectional | Battery | Available | 0 MW | Firm, ≤ 0 % curtailment a year | 2029 (2029)variant: 70kv | 17 Nov 2026 |
| Bidirectional | Battery | Available | 13.7 MW | Flexible, ≤ 5 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Bidirectional | Battery | Available | 0 MW | Flexible, ≤ 5 % curtailment a year | 2029 (2029)variant: 70kv | 17 Nov 2026 |
| Bidirectional | Battery | Available | 21.4 MW | Flexible, ≤ 10 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Bidirectional | Battery | Available | 0 MW | Flexible, ≤ 10 % curtailment a year | 2029 (2029)variant: 70kv | 17 Nov 2026 |
| Bidirectional | Battery | Available | 41.8 MW | Flexible, ≤ 20 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Bidirectional | Battery | Available | 0 MW | Flexible, ≤ 20 % curtailment a year | 2029 (2029)variant: 70kv | 17 Nov 2026 |
| Bidirectional | Battery | Available | 13.2 MW | Firm, ≤ 0 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |
| Bidirectional | Battery | Available | 0 MW | Firm, ≤ 0 % curtailment a year | 2033 (2033)variant: 70kv | 17 Nov 2026 |
| Bidirectional | Battery | Available | 19.4 MW | Flexible, ≤ 5 % curtailment a year | 2033 (2033)variant: 70kv | 17 Nov 2026 |
| Bidirectional | Battery | Available | 18.7 MW | Flexible, ≤ 5 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |
| Bidirectional | Battery | Available | 27.3 MW | Flexible, ≤ 10 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |
| Bidirectional | Battery | Available | 26.3 MW | Flexible, ≤ 10 % curtailment a year | 2033 (2033)variant: 70kv | 17 Nov 2026 |
| Bidirectional | Battery | Available | 70.3 MW | Flexible, ≤ 20 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |
| Bidirectional | Battery | Available | 46.2 MW | Flexible, ≤ 20 % curtailment a year | 2033 (2033)variant: 70kv | 17 Nov 2026 |