| Injection | Generation (any) | Available | 19.5 MW | Firm, ≤ 0 % curtailment a year | 2029 (2029)variant: 220kv | 17 Nov 2026 |
| Injection | Generation (any) | Available | 52.6 MW | Flexible, ≤ 5 % curtailment a year | 2029 (2029)variant: 220kv | 17 Nov 2026 |
| Injection | Generation (any) | Available | 159.8 MW | Flexible, ≤ 10 % curtailment a year | 2029 (2029)variant: 220kv | 17 Nov 2026 |
| Injection | Generation (any) | Available | 175 MW | Flexible, ≤ 20 % curtailment a year | 2029 (2029)variant: 220kv | 17 Nov 2026 |
| Injection | Generation (any) | Available | 19.5 MW | Firm, ≤ 0 % curtailment a year | 2033 (2033)variant: 220kv | 17 Nov 2026 |
| Injection | Generation (any) | Available | 52.6 MW | Flexible, ≤ 5 % curtailment a year | 2033 (2033)variant: 220kv | 17 Nov 2026 |
| Injection | Generation (any) | Available | 159.8 MW | Flexible, ≤ 10 % curtailment a year | 2033 (2033)variant: 220kv | 17 Nov 2026 |
| Injection | Generation (any) | Available | 175 MW | Flexible, ≤ 20 % curtailment a year | 2033 (2033)variant: 220kv | 17 Nov 2026 |
| Injection | Solar PV | Available | 67 MW | Firm, ≤ 0 % curtailment a year | 2029 (2029)variant: 220kv | 17 Nov 2026 |
| Injection | Solar PV | Available | 175 MW | Flexible, ≤ 5 % curtailment a year | 2029 (2029)variant: 220kv | 17 Nov 2026 |
| Injection | Solar PV | Available | 175 MW | Flexible, ≤ 10 % curtailment a year | 2029 (2029)variant: 220kv | 17 Nov 2026 |
| Injection | Solar PV | Available | 175 MW | Flexible, ≤ 20 % curtailment a year | 2029 (2029)variant: 220kv | 17 Nov 2026 |
| Injection | Solar PV | Available | 175 MW | Firm, ≤ 0 % curtailment a year | 2033 (2033)variant: 220kv | 17 Nov 2026 |
| Injection | Solar PV | Available | 175 MW | Flexible, ≤ 5 % curtailment a year | 2033 (2033)variant: 220kv | 17 Nov 2026 |
| Injection | Solar PV | Available | 175 MW | Flexible, ≤ 10 % curtailment a year | 2033 (2033)variant: 220kv | 17 Nov 2026 |
| Injection | Solar PV | Available | 175 MW | Flexible, ≤ 20 % curtailment a year | 2033 (2033)variant: 220kv | 17 Nov 2026 |
| Injection | Onshore wind | Available | 175 MW | Firm, ≤ 0 % curtailment a year | 2029 (2029)variant: 220kv | 17 Nov 2026 |
| Injection | Onshore wind | Available | 175 MW | Flexible, ≤ 5 % curtailment a year | 2029 (2029)variant: 220kv | 17 Nov 2026 |
| Injection | Onshore wind | Available | 175 MW | Flexible, ≤ 10 % curtailment a year | 2029 (2029)variant: 220kv | 17 Nov 2026 |
| Injection | Onshore wind | Available | 175 MW | Flexible, ≤ 20 % curtailment a year | 2029 (2029)variant: 220kv | 17 Nov 2026 |
| Injection | Onshore wind | Available | 175 MW | Firm, ≤ 0 % curtailment a year | 2033 (2033)variant: 220kv | 17 Nov 2026 |
| Injection | Onshore wind | Available | 175 MW | Flexible, ≤ 5 % curtailment a year | 2033 (2033)variant: 220kv | 17 Nov 2026 |
| Injection | Onshore wind | Available | 175 MW | Flexible, ≤ 10 % curtailment a year | 2033 (2033)variant: 220kv | 17 Nov 2026 |
| Injection | Onshore wind | Available | 175 MW | Flexible, ≤ 20 % curtailment a year | 2033 (2033)variant: 220kv | 17 Nov 2026 |
| Offtake | Load (any) | Available | 23.3 MW | Firm, ≤ 0 % curtailment a year | 2029 (2029)variant: 220kv | 17 Nov 2026 |
| Offtake | Load (any) | Available | 48.6 MW | Flexible, ≤ 5 % curtailment a year | 2029 (2029)variant: 220kv | 17 Nov 2026 |
| Offtake | Load (any) | Available | 116.8 MW | Flexible, ≤ 10 % curtailment a year | 2029 (2029)variant: 220kv | 17 Nov 2026 |
| Offtake | Load (any) | Available | 175 MW | Flexible, ≤ 20 % curtailment a year | 2029 (2029)variant: 220kv | 17 Nov 2026 |
| Offtake | Load (any) | Available | 175 MW | Firm, ≤ 0 % curtailment a year | 2033 (2033)variant: 220kv | 17 Nov 2026 |
| Offtake | Load (any) | Available | 175 MW | Flexible, ≤ 5 % curtailment a year | 2033 (2033)variant: 220kv | 17 Nov 2026 |
| Offtake | Load (any) | Available | 175 MW | Flexible, ≤ 10 % curtailment a year | 2033 (2033)variant: 220kv | 17 Nov 2026 |
| Offtake | Load (any) | Available | 175 MW | Flexible, ≤ 20 % curtailment a year | 2033 (2033)variant: 220kv | 17 Nov 2026 |
| Bidirectional | Battery | Available | 19.5 MW | Firm, ≤ 0 % curtailment a year | 2029 (2029)variant: 220kv | 17 Nov 2026 |
| Bidirectional | Battery | Available | 38.1 MW | Flexible, ≤ 5 % curtailment a year | 2029 (2029)variant: 220kv | 17 Nov 2026 |
| Bidirectional | Battery | Available | 78.2 MW | Flexible, ≤ 10 % curtailment a year | 2029 (2029)variant: 220kv | 17 Nov 2026 |
| Bidirectional | Battery | Available | 175 MW | Flexible, ≤ 20 % curtailment a year | 2029 (2029)variant: 220kv | 17 Nov 2026 |
| Bidirectional | Battery | Available | 19.5 MW | Firm, ≤ 0 % curtailment a year | 2033 (2033)variant: 220kv | 17 Nov 2026 |
| Bidirectional | Battery | Available | 52.6 MW | Flexible, ≤ 5 % curtailment a year | 2033 (2033)variant: 220kv | 17 Nov 2026 |
| Bidirectional | Battery | Available | 159.8 MW | Flexible, ≤ 10 % curtailment a year | 2033 (2033)variant: 220kv | 17 Nov 2026 |
| Bidirectional | Battery | Available | 175 MW | Flexible, ≤ 20 % curtailment a year | 2033 (2033)variant: 220kv | 17 Nov 2026 |