Skip to content

Substation / 36 kV

EEKLO

Elia Transmission Belgium / Belgium

Latest published values

40 served · 0 withheld

Each row is what the operator’s latest published dataset reports for one combination of direction, technology, measure, firmness and horizon. Hosting-capacity figures are indicative and reflect what operators publish. They are not a connection offer; only the operator can confirm capacity for a specific request.

Latest published capacity values, one row per series
DirectionTechnologyMeasureValueFirmnessHorizonSource date
InjectionGeneration (any)Available60 MWFirm, ≤ 0 % curtailment a year2029 (2029)variant: 36kv17 Nov 2026
InjectionGeneration (any)Available60 MWFlexible, ≤ 5 % curtailment a year2029 (2029)variant: 36kv17 Nov 2026
InjectionGeneration (any)Available60 MWFlexible, ≤ 10 % curtailment a year2029 (2029)variant: 36kv17 Nov 2026
InjectionGeneration (any)Available60 MWFlexible, ≤ 20 % curtailment a year2029 (2029)variant: 36kv17 Nov 2026
InjectionGeneration (any)Available60 MWFirm, ≤ 0 % curtailment a year2033 (2033)variant: 36kv17 Nov 2026
InjectionGeneration (any)Available60 MWFlexible, ≤ 5 % curtailment a year2033 (2033)variant: 36kv17 Nov 2026
InjectionGeneration (any)Available60 MWFlexible, ≤ 10 % curtailment a year2033 (2033)variant: 36kv17 Nov 2026
InjectionGeneration (any)Available60 MWFlexible, ≤ 20 % curtailment a year2033 (2033)variant: 36kv17 Nov 2026
InjectionSolar PVAvailable60 MWFirm, ≤ 0 % curtailment a year2029 (2029)variant: 36kv17 Nov 2026
InjectionSolar PVAvailable60 MWFlexible, ≤ 5 % curtailment a year2029 (2029)variant: 36kv17 Nov 2026
InjectionSolar PVAvailable60 MWFlexible, ≤ 10 % curtailment a year2029 (2029)variant: 36kv17 Nov 2026
InjectionSolar PVAvailable60 MWFlexible, ≤ 20 % curtailment a year2029 (2029)variant: 36kv17 Nov 2026
InjectionSolar PVAvailable60 MWFirm, ≤ 0 % curtailment a year2033 (2033)variant: 36kv17 Nov 2026
InjectionSolar PVAvailable60 MWFlexible, ≤ 5 % curtailment a year2033 (2033)variant: 36kv17 Nov 2026
InjectionSolar PVAvailable60 MWFlexible, ≤ 10 % curtailment a year2033 (2033)variant: 36kv17 Nov 2026
InjectionSolar PVAvailable60 MWFlexible, ≤ 20 % curtailment a year2033 (2033)variant: 36kv17 Nov 2026
InjectionOnshore windAvailable60 MWFirm, ≤ 0 % curtailment a year2029 (2029)variant: 36kv17 Nov 2026
InjectionOnshore windAvailable60 MWFlexible, ≤ 5 % curtailment a year2029 (2029)variant: 36kv17 Nov 2026
InjectionOnshore windAvailable60 MWFlexible, ≤ 10 % curtailment a year2029 (2029)variant: 36kv17 Nov 2026
InjectionOnshore windAvailable60 MWFlexible, ≤ 20 % curtailment a year2029 (2029)variant: 36kv17 Nov 2026
InjectionOnshore windAvailable60 MWFirm, ≤ 0 % curtailment a year2033 (2033)variant: 36kv17 Nov 2026
InjectionOnshore windAvailable60 MWFlexible, ≤ 5 % curtailment a year2033 (2033)variant: 36kv17 Nov 2026
InjectionOnshore windAvailable60 MWFlexible, ≤ 10 % curtailment a year2033 (2033)variant: 36kv17 Nov 2026
InjectionOnshore windAvailable60 MWFlexible, ≤ 20 % curtailment a year2033 (2033)variant: 36kv17 Nov 2026
OfftakeLoad (any)Available13.3 MWFirm, ≤ 0 % curtailment a year2029 (2029)variant: 36kv17 Nov 2026
OfftakeLoad (any)Available32.4 MWFlexible, ≤ 5 % curtailment a year2029 (2029)variant: 36kv17 Nov 2026
OfftakeLoad (any)Available39 MWFlexible, ≤ 10 % curtailment a year2029 (2029)variant: 36kv17 Nov 2026
OfftakeLoad (any)Available48.2 MWFlexible, ≤ 20 % curtailment a year2029 (2029)variant: 36kv17 Nov 2026
OfftakeLoad (any)Available60 MWFirm, ≤ 0 % curtailment a year2033 (2033)variant: 36kv17 Nov 2026
OfftakeLoad (any)Available60 MWFlexible, ≤ 5 % curtailment a year2033 (2033)variant: 36kv17 Nov 2026
OfftakeLoad (any)Available60 MWFlexible, ≤ 10 % curtailment a year2033 (2033)variant: 36kv17 Nov 2026
OfftakeLoad (any)Available60 MWFlexible, ≤ 20 % curtailment a year2033 (2033)variant: 36kv17 Nov 2026
BidirectionalBatteryAvailable0.6 MWFirm, ≤ 0 % curtailment a year2029 (2029)variant: 36kv17 Nov 2026
BidirectionalBatteryAvailable9.4 MWFlexible, ≤ 5 % curtailment a year2029 (2029)variant: 36kv17 Nov 2026
BidirectionalBatteryAvailable12.1 MWFlexible, ≤ 10 % curtailment a year2029 (2029)variant: 36kv17 Nov 2026
BidirectionalBatteryAvailable28 MWFlexible, ≤ 20 % curtailment a year2029 (2029)variant: 36kv17 Nov 2026
BidirectionalBatteryAvailable6.9 MWFirm, ≤ 0 % curtailment a year2033 (2033)variant: 36kv17 Nov 2026
BidirectionalBatteryAvailable9.4 MWFlexible, ≤ 5 % curtailment a year2033 (2033)variant: 36kv17 Nov 2026
BidirectionalBatteryAvailable12.1 MWFlexible, ≤ 10 % curtailment a year2033 (2033)variant: 36kv17 Nov 2026
BidirectionalBatteryAvailable28 MWFlexible, ≤ 20 % curtailment a year2033 (2033)variant: 36kv17 Nov 2026

Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map

What each value means

Methodology, both clocks, provenance and rights

Injection · Generation (any) · Available

60 MW

Granted

The operator's latest published dataset reports 60 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2029 (2029) · variant: 36kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/EEKLO 36 · payload sha256 e1542d6343ff…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
EEKLO 36
Operator note: flexibilityLevel
0%_flex
Operator note: variant
36kv
Operator note: voltage kv
36

Injection · Generation (any) · Available

60 MW

Granted

The operator's latest published dataset reports 60 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2029 (2029) · variant: 36kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/EEKLO 36 · payload sha256 e1542d6343ff…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
EEKLO 36
Operator note: flexibilityLevel
5%_flex
Operator note: variant
36kv
Operator note: voltage kv
36

Injection · Generation (any) · Available

60 MW

Granted

The operator's latest published dataset reports 60 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2029 (2029) · variant: 36kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/EEKLO 36 · payload sha256 e1542d6343ff…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
EEKLO 36
Operator note: flexibilityLevel
10%_flex
Operator note: variant
36kv
Operator note: voltage kv
36

Injection · Generation (any) · Available

60 MW

Granted

The operator's latest published dataset reports 60 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2029 (2029) · variant: 36kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/EEKLO 36 · payload sha256 e1542d6343ff…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
EEKLO 36
Operator note: flexibilityLevel
20%_flex
Operator note: variant
36kv
Operator note: voltage kv
36

Injection · Generation (any) · Available

60 MW

Granted

The operator's latest published dataset reports 60 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2033 (2033) · variant: 36kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/EEKLO 36 · payload sha256 cbbf0dde93e7…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
EEKLO 36
Operator note: flexibilityLevel
0%_flex
Operator note: variant
36kv
Operator note: voltage kv
36

Injection · Generation (any) · Available

60 MW

Granted

The operator's latest published dataset reports 60 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2033 (2033) · variant: 36kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/EEKLO 36 · payload sha256 cbbf0dde93e7…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
EEKLO 36
Operator note: flexibilityLevel
5%_flex
Operator note: variant
36kv
Operator note: voltage kv
36

Injection · Generation (any) · Available

60 MW

Granted

The operator's latest published dataset reports 60 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2033 (2033) · variant: 36kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/EEKLO 36 · payload sha256 cbbf0dde93e7…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
EEKLO 36
Operator note: flexibilityLevel
10%_flex
Operator note: variant
36kv
Operator note: voltage kv
36

Injection · Generation (any) · Available

60 MW

Granted

The operator's latest published dataset reports 60 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2033 (2033) · variant: 36kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/EEKLO 36 · payload sha256 cbbf0dde93e7…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
EEKLO 36
Operator note: flexibilityLevel
20%_flex
Operator note: variant
36kv
Operator note: voltage kv
36

Injection · Solar PV · Available

60 MW

Granted

The operator's latest published dataset reports 60 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2029 (2029) · variant: 36kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/EEKLO 36 · payload sha256 e1542d6343ff…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
EEKLO 36
Operator note: flexibilityLevel
0%_flex
Operator note: variant
36kv
Operator note: voltage kv
36

Injection · Solar PV · Available

60 MW

Granted

The operator's latest published dataset reports 60 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2029 (2029) · variant: 36kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/EEKLO 36 · payload sha256 e1542d6343ff…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
EEKLO 36
Operator note: flexibilityLevel
5%_flex
Operator note: variant
36kv
Operator note: voltage kv
36

Injection · Solar PV · Available

60 MW

Granted

The operator's latest published dataset reports 60 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2029 (2029) · variant: 36kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/EEKLO 36 · payload sha256 e1542d6343ff…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
EEKLO 36
Operator note: flexibilityLevel
10%_flex
Operator note: variant
36kv
Operator note: voltage kv
36

Injection · Solar PV · Available

60 MW

Granted

The operator's latest published dataset reports 60 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2029 (2029) · variant: 36kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/EEKLO 36 · payload sha256 e1542d6343ff…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
EEKLO 36
Operator note: flexibilityLevel
20%_flex
Operator note: variant
36kv
Operator note: voltage kv
36

Injection · Solar PV · Available

60 MW

Granted

The operator's latest published dataset reports 60 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2033 (2033) · variant: 36kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/EEKLO 36 · payload sha256 cbbf0dde93e7…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
EEKLO 36
Operator note: flexibilityLevel
0%_flex
Operator note: variant
36kv
Operator note: voltage kv
36

Injection · Solar PV · Available

60 MW

Granted

The operator's latest published dataset reports 60 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2033 (2033) · variant: 36kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/EEKLO 36 · payload sha256 cbbf0dde93e7…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
EEKLO 36
Operator note: flexibilityLevel
5%_flex
Operator note: variant
36kv
Operator note: voltage kv
36

Injection · Solar PV · Available

60 MW

Granted

The operator's latest published dataset reports 60 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2033 (2033) · variant: 36kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/EEKLO 36 · payload sha256 cbbf0dde93e7…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
EEKLO 36
Operator note: flexibilityLevel
10%_flex
Operator note: variant
36kv
Operator note: voltage kv
36

Injection · Solar PV · Available

60 MW

Granted

The operator's latest published dataset reports 60 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2033 (2033) · variant: 36kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/EEKLO 36 · payload sha256 cbbf0dde93e7…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
EEKLO 36
Operator note: flexibilityLevel
20%_flex
Operator note: variant
36kv
Operator note: voltage kv
36

Injection · Onshore wind · Available

60 MW

Granted

The operator's latest published dataset reports 60 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2029 (2029) · variant: 36kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/EEKLO 36 · payload sha256 e1542d6343ff…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
EEKLO 36
Operator note: flexibilityLevel
0%_flex
Operator note: variant
36kv
Operator note: voltage kv
36

Injection · Onshore wind · Available

60 MW

Granted

The operator's latest published dataset reports 60 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2029 (2029) · variant: 36kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/EEKLO 36 · payload sha256 e1542d6343ff…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
EEKLO 36
Operator note: flexibilityLevel
5%_flex
Operator note: variant
36kv
Operator note: voltage kv
36

Injection · Onshore wind · Available

60 MW

Granted

The operator's latest published dataset reports 60 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2029 (2029) · variant: 36kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/EEKLO 36 · payload sha256 e1542d6343ff…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
EEKLO 36
Operator note: flexibilityLevel
10%_flex
Operator note: variant
36kv
Operator note: voltage kv
36

Injection · Onshore wind · Available

60 MW

Granted

The operator's latest published dataset reports 60 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2029 (2029) · variant: 36kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/EEKLO 36 · payload sha256 e1542d6343ff…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
EEKLO 36
Operator note: flexibilityLevel
20%_flex
Operator note: variant
36kv
Operator note: voltage kv
36

Injection · Onshore wind · Available

60 MW

Granted

The operator's latest published dataset reports 60 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2033 (2033) · variant: 36kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/EEKLO 36 · payload sha256 cbbf0dde93e7…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
EEKLO 36
Operator note: flexibilityLevel
0%_flex
Operator note: variant
36kv
Operator note: voltage kv
36

Injection · Onshore wind · Available

60 MW

Granted

The operator's latest published dataset reports 60 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2033 (2033) · variant: 36kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/EEKLO 36 · payload sha256 cbbf0dde93e7…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
EEKLO 36
Operator note: flexibilityLevel
5%_flex
Operator note: variant
36kv
Operator note: voltage kv
36

Injection · Onshore wind · Available

60 MW

Granted

The operator's latest published dataset reports 60 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2033 (2033) · variant: 36kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/EEKLO 36 · payload sha256 cbbf0dde93e7…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
EEKLO 36
Operator note: flexibilityLevel
10%_flex
Operator note: variant
36kv
Operator note: voltage kv
36

Injection · Onshore wind · Available

60 MW

Granted

The operator's latest published dataset reports 60 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2033 (2033) · variant: 36kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/EEKLO 36 · payload sha256 cbbf0dde93e7…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
EEKLO 36
Operator note: flexibilityLevel
20%_flex
Operator note: variant
36kv
Operator note: voltage kv
36

Offtake · Load (any) · Available

13.3 MW

Granted

The operator's latest published dataset reports 13.3 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2029 (2029) · variant: 36kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/EEKLO 36 · payload sha256 e1542d6343ff…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
EEKLO 36
Operator note: flexibilityLevel
0%_flex
Operator note: variant
36kv
Operator note: voltage kv
36

Offtake · Load (any) · Available

32.4 MW

Granted

The operator's latest published dataset reports 32.4 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2029 (2029) · variant: 36kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/EEKLO 36 · payload sha256 e1542d6343ff…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
EEKLO 36
Operator note: flexibilityLevel
5%_flex
Operator note: variant
36kv
Operator note: voltage kv
36

Offtake · Load (any) · Available

39 MW

Granted

The operator's latest published dataset reports 39 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2029 (2029) · variant: 36kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/EEKLO 36 · payload sha256 e1542d6343ff…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
EEKLO 36
Operator note: flexibilityLevel
10%_flex
Operator note: variant
36kv
Operator note: voltage kv
36

Offtake · Load (any) · Available

48.2 MW

Granted

The operator's latest published dataset reports 48.2 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2029 (2029) · variant: 36kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/EEKLO 36 · payload sha256 e1542d6343ff…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
EEKLO 36
Operator note: flexibilityLevel
20%_flex
Operator note: variant
36kv
Operator note: voltage kv
36

Offtake · Load (any) · Available

60 MW

Granted

The operator's latest published dataset reports 60 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2033 (2033) · variant: 36kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/EEKLO 36 · payload sha256 cbbf0dde93e7…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
EEKLO 36
Operator note: flexibilityLevel
0%_flex
Operator note: variant
36kv
Operator note: voltage kv
36

Offtake · Load (any) · Available

60 MW

Granted

The operator's latest published dataset reports 60 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2033 (2033) · variant: 36kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/EEKLO 36 · payload sha256 cbbf0dde93e7…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
EEKLO 36
Operator note: flexibilityLevel
5%_flex
Operator note: variant
36kv
Operator note: voltage kv
36

Offtake · Load (any) · Available

60 MW

Granted

The operator's latest published dataset reports 60 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2033 (2033) · variant: 36kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/EEKLO 36 · payload sha256 cbbf0dde93e7…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
EEKLO 36
Operator note: flexibilityLevel
10%_flex
Operator note: variant
36kv
Operator note: voltage kv
36

Offtake · Load (any) · Available

60 MW

Granted

The operator's latest published dataset reports 60 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2033 (2033) · variant: 36kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/EEKLO 36 · payload sha256 cbbf0dde93e7…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
EEKLO 36
Operator note: flexibilityLevel
20%_flex
Operator note: variant
36kv
Operator note: voltage kv
36

Bidirectional · Battery · Available

0.6 MW

Granted

The operator's latest published dataset reports 0.6 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2029 (2029) · variant: 36kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/EEKLO 36 · payload sha256 e1542d6343ff…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
EEKLO 36
Operator note: flexibilityLevel
0%_flex
Operator note: variant
36kv
Operator note: voltage kv
36

Bidirectional · Battery · Available

9.4 MW

Granted

The operator's latest published dataset reports 9.4 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2029 (2029) · variant: 36kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/EEKLO 36 · payload sha256 e1542d6343ff…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
EEKLO 36
Operator note: flexibilityLevel
5%_flex
Operator note: variant
36kv
Operator note: voltage kv
36

Bidirectional · Battery · Available

12.1 MW

Granted

The operator's latest published dataset reports 12.1 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2029 (2029) · variant: 36kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/EEKLO 36 · payload sha256 e1542d6343ff…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
EEKLO 36
Operator note: flexibilityLevel
10%_flex
Operator note: variant
36kv
Operator note: voltage kv
36

Bidirectional · Battery · Available

28 MW

Granted

The operator's latest published dataset reports 28 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2029 (2029) · variant: 36kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/EEKLO 36 · payload sha256 e1542d6343ff…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
EEKLO 36
Operator note: flexibilityLevel
20%_flex
Operator note: variant
36kv
Operator note: voltage kv
36

Bidirectional · Battery · Available

6.9 MW

Granted

The operator's latest published dataset reports 6.9 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2033 (2033) · variant: 36kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/EEKLO 36 · payload sha256 cbbf0dde93e7…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
EEKLO 36
Operator note: flexibilityLevel
0%_flex
Operator note: variant
36kv
Operator note: voltage kv
36

Bidirectional · Battery · Available

9.4 MW

Granted

The operator's latest published dataset reports 9.4 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2033 (2033) · variant: 36kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/EEKLO 36 · payload sha256 cbbf0dde93e7…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
EEKLO 36
Operator note: flexibilityLevel
5%_flex
Operator note: variant
36kv
Operator note: voltage kv
36

Bidirectional · Battery · Available

12.1 MW

Granted

The operator's latest published dataset reports 12.1 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2033 (2033) · variant: 36kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/EEKLO 36 · payload sha256 cbbf0dde93e7…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
EEKLO 36
Operator note: flexibilityLevel
10%_flex
Operator note: variant
36kv
Operator note: voltage kv
36

Bidirectional · Battery · Available

28 MW

Granted

The operator's latest published dataset reports 28 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2033 (2033) · variant: 36kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-22 00:09 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/EEKLO 36 · payload sha256 cbbf0dde93e7…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
EEKLO 36
Operator note: flexibilityLevel
20%_flex
Operator note: variant
36kv
Operator note: voltage kv
36

History

Served series only

Bidirectional · Battery · Available · 2027

last, until 17 Nov 2026: 0 MW

26 Sep 2026: 0 MW
26 Sep 2026range 0 to 0 MW24 Nov 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 202617 Nov 20260 MW

Time axis: when we observed each value, not the operator’s effective date.

Bidirectional · Battery · Available · 2027

last, until 17 Nov 2026: 0 MW

26 Sep 2026: 0 MW
26 Sep 2026range 0 to 0 MW24 Nov 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 202617 Nov 20260 MW

Time axis: when we observed each value, not the operator’s effective date.

Bidirectional · Battery · Available · 2027

last, until 17 Nov 2026: 11.1 MW

26 Sep 2026: 11 MW17 Oct 2026: 11.1 MW
26 Sep 2026range 11 to 11.1 MW24 Nov 2026
2 published values, as a table
Observed fromUntilValue
26 Sep 202617 Oct 202611 MW
17 Oct 202617 Nov 202611.1 MW

Time axis: when we observed each value, not the operator’s effective date.

Bidirectional · Battery · Available · 2027

last, until 17 Nov 2026: 20.6 MW

26 Sep 2026: 19.3 MW17 Oct 2026: 20.6 MW
26 Sep 2026range 19.3 to 20.6 MW24 Nov 2026
2 published values, as a table
Observed fromUntilValue
26 Sep 202617 Oct 202619.3 MW
17 Oct 202617 Nov 202620.6 MW

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Load (any) · Available · 2027

last, until 17 Nov 2026: 0.7 MW

26 Sep 2026: 0.7 MW
26 Sep 2026range 0.7 to 0.7 MW24 Nov 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 202617 Nov 20260.7 MW

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Load (any) · Available · 2027

last, until 17 Nov 2026: 20.7 MW

26 Sep 2026: 20.6 MW17 Oct 2026: 20.7 MW
26 Sep 2026range 20.6 to 20.7 MW24 Nov 2026
2 published values, as a table
Observed fromUntilValue
26 Sep 202617 Oct 202620.6 MW
17 Oct 202617 Nov 202620.7 MW

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Load (any) · Available · 2027

last, until 17 Nov 2026: 30.3 MW

26 Sep 2026: 30.3 MW
26 Sep 2026range 30.3 to 30.3 MW24 Nov 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 202617 Nov 202630.3 MW

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Load (any) · Available · 2027

last, until 17 Nov 2026: 41.4 MW

26 Sep 2026: 41.4 MW
26 Sep 2026range 41.4 to 41.4 MW24 Nov 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 202617 Nov 202641.4 MW

Time axis: when we observed each value, not the operator’s effective date.

Injection · Generation (any) · Available · 2027

last, until 17 Nov 2026: 0 MW

26 Sep 2026: 0 MW
26 Sep 2026range 0 to 0 MW24 Nov 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 202617 Nov 20260 MW

Time axis: when we observed each value, not the operator’s effective date.

Injection · Generation (any) · Available · 2027

last, until 17 Nov 2026: 0 MW

26 Sep 2026: 0 MW
26 Sep 2026range 0 to 0 MW24 Nov 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 202617 Nov 20260 MW

Time axis: when we observed each value, not the operator’s effective date.

Injection · Generation (any) · Available · 2027

last, until 17 Nov 2026: 58 MW

26 Sep 2026: 59.4 MW17 Oct 2026: 58 MW
26 Sep 2026range 58 to 59.4 MW24 Nov 2026
2 published values, as a table
Observed fromUntilValue
26 Sep 202617 Oct 202659.4 MW
17 Oct 202617 Nov 202658 MW

Time axis: when we observed each value, not the operator’s effective date.

Injection · Generation (any) · Available · 2027

last, until 17 Nov 2026: 60 MW

26 Sep 2026: 60 MW
26 Sep 2026range 60 to 60 MW24 Nov 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 202617 Nov 202660 MW

Time axis: when we observed each value, not the operator’s effective date.

The first 12 of 80 served series with a history. The history route returns every one of them.

Through the API

curl "https://api.gridcapacityapi.com/v1/substations/sub_06gdrm9m45rtd4s8x5fcg4cn74/capacity" \  -H "Authorization: Bearer gc_live_..."