| Injection | Generation (any) | Available | 19.2 MW | Firm, ≤ 0 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Injection | Generation (any) | Available | 0 MW | Firm, ≤ 0 % curtailment a year | 2029 (2029)variant: 70kv | 17 Nov 2026 |
| Injection | Generation (any) | Available | 56.2 MW | Flexible, ≤ 5 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Injection | Generation (any) | Available | 0 MW | Flexible, ≤ 5 % curtailment a year | 2029 (2029)variant: 70kv | 17 Nov 2026 |
| Injection | Generation (any) | Available | 175 MW | Flexible, ≤ 10 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Injection | Generation (any) | Available | 0 MW | Flexible, ≤ 10 % curtailment a year | 2029 (2029)variant: 70kv | 17 Nov 2026 |
| Injection | Generation (any) | Available | 175 MW | Flexible, ≤ 20 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Injection | Generation (any) | Available | 0 MW | Flexible, ≤ 20 % curtailment a year | 2029 (2029)variant: 70kv | 17 Nov 2026 |
| Injection | Generation (any) | Available | 175 MW | Firm, ≤ 0 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |
| Injection | Generation (any) | Available | 175 MW | Flexible, ≤ 5 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |
| Injection | Generation (any) | Available | 175 MW | Flexible, ≤ 10 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |
| Injection | Generation (any) | Available | 175 MW | Flexible, ≤ 20 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |
| Injection | Solar PV | Available | 175 MW | Firm, ≤ 0 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Injection | Solar PV | Available | 0 MW | Firm, ≤ 0 % curtailment a year | 2029 (2029)variant: 70kv | 17 Nov 2026 |
| Injection | Solar PV | Available | 175 MW | Flexible, ≤ 5 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Injection | Solar PV | Available | 0 MW | Flexible, ≤ 5 % curtailment a year | 2029 (2029)variant: 70kv | 17 Nov 2026 |
| Injection | Solar PV | Available | 175 MW | Flexible, ≤ 10 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Injection | Solar PV | Available | 0 MW | Flexible, ≤ 10 % curtailment a year | 2029 (2029)variant: 70kv | 17 Nov 2026 |
| Injection | Solar PV | Available | 175 MW | Flexible, ≤ 20 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Injection | Solar PV | Available | 0 MW | Flexible, ≤ 20 % curtailment a year | 2029 (2029)variant: 70kv | 17 Nov 2026 |
| Injection | Solar PV | Available | 175 MW | Firm, ≤ 0 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |
| Injection | Solar PV | Available | 175 MW | Flexible, ≤ 5 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |
| Injection | Solar PV | Available | 175 MW | Flexible, ≤ 10 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |
| Injection | Solar PV | Available | 175 MW | Flexible, ≤ 20 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |
| Injection | Onshore wind | Available | 22.2 MW | Firm, ≤ 0 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Injection | Onshore wind | Available | 0 MW | Firm, ≤ 0 % curtailment a year | 2029 (2029)variant: 70kv | 17 Nov 2026 |
| Injection | Onshore wind | Available | 67.6 MW | Flexible, ≤ 5 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Injection | Onshore wind | Available | 0 MW | Flexible, ≤ 5 % curtailment a year | 2029 (2029)variant: 70kv | 17 Nov 2026 |
| Injection | Onshore wind | Available | 175 MW | Flexible, ≤ 10 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Injection | Onshore wind | Available | 0 MW | Flexible, ≤ 10 % curtailment a year | 2029 (2029)variant: 70kv | 17 Nov 2026 |
| Injection | Onshore wind | Available | 175 MW | Flexible, ≤ 20 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Injection | Onshore wind | Available | 0 MW | Flexible, ≤ 20 % curtailment a year | 2029 (2029)variant: 70kv | 17 Nov 2026 |
| Injection | Onshore wind | Available | 175 MW | Firm, ≤ 0 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |
| Injection | Onshore wind | Available | 175 MW | Flexible, ≤ 5 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |
| Injection | Onshore wind | Available | 175 MW | Flexible, ≤ 10 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |
| Injection | Onshore wind | Available | 175 MW | Flexible, ≤ 20 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |
| Offtake | Load (any) | Available | 5 MW | Firm, ≤ 0 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Offtake | Load (any) | Available | 0 MW | Firm, ≤ 0 % curtailment a year | 2029 (2029)variant: 70kv | 17 Nov 2026 |
| Offtake | Load (any) | Available | 16.6 MW | Flexible, ≤ 5 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Offtake | Load (any) | Available | 0 MW | Flexible, ≤ 5 % curtailment a year | 2029 (2029)variant: 70kv | 17 Nov 2026 |
| Offtake | Load (any) | Available | 49.5 MW | Flexible, ≤ 10 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Offtake | Load (any) | Available | 0 MW | Flexible, ≤ 10 % curtailment a year | 2029 (2029)variant: 70kv | 17 Nov 2026 |
| Offtake | Load (any) | Available | 104.3 MW | Flexible, ≤ 20 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Offtake | Load (any) | Available | 0 MW | Flexible, ≤ 20 % curtailment a year | 2029 (2029)variant: 70kv | 17 Nov 2026 |
| Offtake | Load (any) | Available | 5 MW | Firm, ≤ 0 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |
| Offtake | Load (any) | Available | 22.3 MW | Flexible, ≤ 5 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |
| Offtake | Load (any) | Available | 49.5 MW | Flexible, ≤ 10 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |
| Offtake | Load (any) | Available | 104.3 MW | Flexible, ≤ 20 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |
| Bidirectional | Battery | Available | 5 MW | Firm, ≤ 0 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Bidirectional | Battery | Available | 0 MW | Firm, ≤ 0 % curtailment a year | 2029 (2029)variant: 70kv | 17 Nov 2026 |
| Bidirectional | Battery | Available | 15.6 MW | Flexible, ≤ 5 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Bidirectional | Battery | Available | 0 MW | Flexible, ≤ 5 % curtailment a year | 2029 (2029)variant: 70kv | 17 Nov 2026 |
| Bidirectional | Battery | Available | 37.9 MW | Flexible, ≤ 10 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Bidirectional | Battery | Available | 0 MW | Flexible, ≤ 10 % curtailment a year | 2029 (2029)variant: 70kv | 17 Nov 2026 |
| Bidirectional | Battery | Available | 91.9 MW | Flexible, ≤ 20 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Bidirectional | Battery | Available | 0 MW | Flexible, ≤ 20 % curtailment a year | 2029 (2029)variant: 70kv | 17 Nov 2026 |
| Bidirectional | Battery | Available | 5 MW | Firm, ≤ 0 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |
| Bidirectional | Battery | Available | 17.6 MW | Flexible, ≤ 5 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |
| Bidirectional | Battery | Available | 37.9 MW | Flexible, ≤ 10 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |
| Bidirectional | Battery | Available | 91.9 MW | Flexible, ≤ 20 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |