Substation / 150 kV

CROIX

Elia Transmission Belgium / Belgium

Latest published values

40 served · 0 withheld

Each row is what the operator’s latest published dataset reports for one combination of direction, technology, measure, firmness and horizon. Hosting-capacity figures are indicative and reflect what operators publish. They are not a connection offer; only the operator can confirm capacity for a specific request.

Latest published capacity values, one row per series
DirectionTechnologyMeasureValueFirmnessHorizonSource date
InjectionGeneration (any)Available4.4 MWFirm, ≤ 0 % curtailment a year2029 (2029)variant: 150kv17 Nov 2026
InjectionGeneration (any)Available51.8 MWFlexible, ≤ 5 % curtailment a year2029 (2029)variant: 150kv17 Nov 2026
InjectionGeneration (any)Available175 MWFlexible, ≤ 10 % curtailment a year2029 (2029)variant: 150kv17 Nov 2026
InjectionGeneration (any)Available175 MWFlexible, ≤ 20 % curtailment a year2029 (2029)variant: 150kv17 Nov 2026
InjectionGeneration (any)Available4.4 MWFirm, ≤ 0 % curtailment a year2033 (2033)variant: 150kv17 Nov 2026
InjectionGeneration (any)Available51.8 MWFlexible, ≤ 5 % curtailment a year2033 (2033)variant: 150kv17 Nov 2026
InjectionGeneration (any)Available175 MWFlexible, ≤ 10 % curtailment a year2033 (2033)variant: 150kv17 Nov 2026
InjectionGeneration (any)Available175 MWFlexible, ≤ 20 % curtailment a year2033 (2033)variant: 150kv17 Nov 2026
InjectionSolar PVAvailable12.5 MWFirm, ≤ 0 % curtailment a year2029 (2029)variant: 150kv17 Nov 2026
InjectionSolar PVAvailable175 MWFlexible, ≤ 5 % curtailment a year2029 (2029)variant: 150kv17 Nov 2026
InjectionSolar PVAvailable175 MWFlexible, ≤ 10 % curtailment a year2029 (2029)variant: 150kv17 Nov 2026
InjectionSolar PVAvailable175 MWFlexible, ≤ 20 % curtailment a year2029 (2029)variant: 150kv17 Nov 2026
InjectionSolar PVAvailable12.5 MWFirm, ≤ 0 % curtailment a year2033 (2033)variant: 150kv17 Nov 2026
InjectionSolar PVAvailable175 MWFlexible, ≤ 5 % curtailment a year2033 (2033)variant: 150kv17 Nov 2026
InjectionSolar PVAvailable175 MWFlexible, ≤ 10 % curtailment a year2033 (2033)variant: 150kv17 Nov 2026
InjectionSolar PVAvailable175 MWFlexible, ≤ 20 % curtailment a year2033 (2033)variant: 150kv17 Nov 2026
InjectionOnshore windAvailable5.2 MWFirm, ≤ 0 % curtailment a year2029 (2029)variant: 150kv17 Nov 2026
InjectionOnshore windAvailable10 MWFlexible, ≤ 5 % curtailment a year2029 (2029)variant: 150kv17 Nov 2026
InjectionOnshore windAvailable14.9 MWFlexible, ≤ 10 % curtailment a year2029 (2029)variant: 150kv17 Nov 2026
InjectionOnshore windAvailable167.4 MWFlexible, ≤ 20 % curtailment a year2029 (2029)variant: 150kv17 Nov 2026
InjectionOnshore windAvailable5.2 MWFirm, ≤ 0 % curtailment a year2033 (2033)variant: 150kv17 Nov 2026
InjectionOnshore windAvailable10 MWFlexible, ≤ 5 % curtailment a year2033 (2033)variant: 150kv17 Nov 2026
InjectionOnshore windAvailable14.9 MWFlexible, ≤ 10 % curtailment a year2033 (2033)variant: 150kv17 Nov 2026
InjectionOnshore windAvailable167.4 MWFlexible, ≤ 20 % curtailment a year2033 (2033)variant: 150kv17 Nov 2026
OfftakeLoad (any)Available4.3 MWFirm, ≤ 0 % curtailment a year2029 (2029)variant: 150kv17 Nov 2026
OfftakeLoad (any)Available15 MWFlexible, ≤ 5 % curtailment a year2029 (2029)variant: 150kv17 Nov 2026
OfftakeLoad (any)Available88.3 MWFlexible, ≤ 10 % curtailment a year2029 (2029)variant: 150kv17 Nov 2026
OfftakeLoad (any)Available166.4 MWFlexible, ≤ 20 % curtailment a year2029 (2029)variant: 150kv17 Nov 2026
OfftakeLoad (any)Available4.3 MWFirm, ≤ 0 % curtailment a year2033 (2033)variant: 150kv17 Nov 2026
OfftakeLoad (any)Available15 MWFlexible, ≤ 5 % curtailment a year2033 (2033)variant: 150kv17 Nov 2026
OfftakeLoad (any)Available88.3 MWFlexible, ≤ 10 % curtailment a year2033 (2033)variant: 150kv17 Nov 2026
OfftakeLoad (any)Available166.4 MWFlexible, ≤ 20 % curtailment a year2033 (2033)variant: 150kv17 Nov 2026
BidirectionalBatteryAvailable4.3 MWFirm, ≤ 0 % curtailment a year2029 (2029)variant: 150kv17 Nov 2026
BidirectionalBatteryAvailable14.2 MWFlexible, ≤ 5 % curtailment a year2029 (2029)variant: 150kv17 Nov 2026
BidirectionalBatteryAvailable71.6 MWFlexible, ≤ 10 % curtailment a year2029 (2029)variant: 150kv17 Nov 2026
BidirectionalBatteryAvailable157.3 MWFlexible, ≤ 20 % curtailment a year2029 (2029)variant: 150kv17 Nov 2026
BidirectionalBatteryAvailable4.3 MWFirm, ≤ 0 % curtailment a year2033 (2033)variant: 150kv17 Nov 2026
BidirectionalBatteryAvailable14.2 MWFlexible, ≤ 5 % curtailment a year2033 (2033)variant: 150kv17 Nov 2026
BidirectionalBatteryAvailable79.5 MWFlexible, ≤ 10 % curtailment a year2033 (2033)variant: 150kv17 Nov 2026
BidirectionalBatteryAvailable157.3 MWFlexible, ≤ 20 % curtailment a year2033 (2033)variant: 150kv17 Nov 2026

Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map

What each value means

Methodology, both clocks, provenance and rights

Injection · Generation (any) · Available

4.4 MW

Granted

The operator's latest published dataset reports 4.4 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2029 (2029) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/CROIX150 · payload sha256 4598361d5630…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
CROIX150
Operator note: flexibilityLevel
0%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Injection · Generation (any) · Available

51.8 MW

Granted

The operator's latest published dataset reports 51.8 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2029 (2029) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/CROIX150 · payload sha256 4598361d5630…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
CROIX150
Operator note: flexibilityLevel
5%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Injection · Generation (any) · Available

175 MW

Granted

The operator's latest published dataset reports 175 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2029 (2029) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/CROIX150 · payload sha256 4598361d5630…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
CROIX150
Operator note: flexibilityLevel
10%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Injection · Generation (any) · Available

175 MW

Granted

The operator's latest published dataset reports 175 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2029 (2029) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/CROIX150 · payload sha256 4598361d5630…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
CROIX150
Operator note: flexibilityLevel
20%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Injection · Generation (any) · Available

4.4 MW

Granted

The operator's latest published dataset reports 4.4 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2033 (2033) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/CROIX150 · payload sha256 a1980acc6b69…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
CROIX150
Operator note: flexibilityLevel
0%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Injection · Generation (any) · Available

51.8 MW

Granted

The operator's latest published dataset reports 51.8 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2033 (2033) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/CROIX150 · payload sha256 a1980acc6b69…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
CROIX150
Operator note: flexibilityLevel
5%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Injection · Generation (any) · Available

175 MW

Granted

The operator's latest published dataset reports 175 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2033 (2033) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/CROIX150 · payload sha256 a1980acc6b69…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
CROIX150
Operator note: flexibilityLevel
10%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Injection · Generation (any) · Available

175 MW

Granted

The operator's latest published dataset reports 175 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2033 (2033) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/CROIX150 · payload sha256 a1980acc6b69…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
CROIX150
Operator note: flexibilityLevel
20%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Injection · Solar PV · Available

12.5 MW

Granted

The operator's latest published dataset reports 12.5 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2029 (2029) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/CROIX150 · payload sha256 4598361d5630…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
CROIX150
Operator note: flexibilityLevel
0%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Injection · Solar PV · Available

175 MW

Granted

The operator's latest published dataset reports 175 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2029 (2029) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/CROIX150 · payload sha256 4598361d5630…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
CROIX150
Operator note: flexibilityLevel
5%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Injection · Solar PV · Available

175 MW

Granted

The operator's latest published dataset reports 175 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2029 (2029) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/CROIX150 · payload sha256 4598361d5630…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
CROIX150
Operator note: flexibilityLevel
10%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Injection · Solar PV · Available

175 MW

Granted

The operator's latest published dataset reports 175 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2029 (2029) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/CROIX150 · payload sha256 4598361d5630…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
CROIX150
Operator note: flexibilityLevel
20%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Injection · Solar PV · Available

12.5 MW

Granted

The operator's latest published dataset reports 12.5 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2033 (2033) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/CROIX150 · payload sha256 a1980acc6b69…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
CROIX150
Operator note: flexibilityLevel
0%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Injection · Solar PV · Available

175 MW

Granted

The operator's latest published dataset reports 175 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2033 (2033) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/CROIX150 · payload sha256 a1980acc6b69…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
CROIX150
Operator note: flexibilityLevel
5%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Injection · Solar PV · Available

175 MW

Granted

The operator's latest published dataset reports 175 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2033 (2033) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/CROIX150 · payload sha256 a1980acc6b69…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
CROIX150
Operator note: flexibilityLevel
10%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Injection · Solar PV · Available

175 MW

Granted

The operator's latest published dataset reports 175 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2033 (2033) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/CROIX150 · payload sha256 a1980acc6b69…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
CROIX150
Operator note: flexibilityLevel
20%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Injection · Onshore wind · Available

5.2 MW

Granted

The operator's latest published dataset reports 5.2 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2029 (2029) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/CROIX150 · payload sha256 4598361d5630…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
CROIX150
Operator note: flexibilityLevel
0%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Injection · Onshore wind · Available

10 MW

Granted

The operator's latest published dataset reports 10 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2029 (2029) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/CROIX150 · payload sha256 4598361d5630…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
CROIX150
Operator note: flexibilityLevel
5%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Injection · Onshore wind · Available

14.9 MW

Granted

The operator's latest published dataset reports 14.9 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2029 (2029) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/CROIX150 · payload sha256 4598361d5630…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
CROIX150
Operator note: flexibilityLevel
10%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Injection · Onshore wind · Available

167.4 MW

Granted

The operator's latest published dataset reports 167.4 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2029 (2029) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/CROIX150 · payload sha256 4598361d5630…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
CROIX150
Operator note: flexibilityLevel
20%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Injection · Onshore wind · Available

5.2 MW

Granted

The operator's latest published dataset reports 5.2 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2033 (2033) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/CROIX150 · payload sha256 a1980acc6b69…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
CROIX150
Operator note: flexibilityLevel
0%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Injection · Onshore wind · Available

10 MW

Granted

The operator's latest published dataset reports 10 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2033 (2033) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/CROIX150 · payload sha256 a1980acc6b69…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
CROIX150
Operator note: flexibilityLevel
5%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Injection · Onshore wind · Available

14.9 MW

Granted

The operator's latest published dataset reports 14.9 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2033 (2033) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/CROIX150 · payload sha256 a1980acc6b69…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
CROIX150
Operator note: flexibilityLevel
10%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Injection · Onshore wind · Available

167.4 MW

Granted

The operator's latest published dataset reports 167.4 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2033 (2033) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/CROIX150 · payload sha256 a1980acc6b69…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
CROIX150
Operator note: flexibilityLevel
20%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Offtake · Load (any) · Available

4.3 MW

Granted

The operator's latest published dataset reports 4.3 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2029 (2029) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/CROIX150 · payload sha256 4598361d5630…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
CROIX150
Operator note: flexibilityLevel
0%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Offtake · Load (any) · Available

15 MW

Granted

The operator's latest published dataset reports 15 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2029 (2029) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/CROIX150 · payload sha256 4598361d5630…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
CROIX150
Operator note: flexibilityLevel
5%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Offtake · Load (any) · Available

88.3 MW

Granted

The operator's latest published dataset reports 88.3 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2029 (2029) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/CROIX150 · payload sha256 4598361d5630…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
CROIX150
Operator note: flexibilityLevel
10%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Offtake · Load (any) · Available

166.4 MW

Granted

The operator's latest published dataset reports 166.4 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2029 (2029) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/CROIX150 · payload sha256 4598361d5630…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
CROIX150
Operator note: flexibilityLevel
20%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Offtake · Load (any) · Available

4.3 MW

Granted

The operator's latest published dataset reports 4.3 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2033 (2033) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/CROIX150 · payload sha256 a1980acc6b69…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
CROIX150
Operator note: flexibilityLevel
0%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Offtake · Load (any) · Available

15 MW

Granted

The operator's latest published dataset reports 15 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2033 (2033) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/CROIX150 · payload sha256 a1980acc6b69…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
CROIX150
Operator note: flexibilityLevel
5%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Offtake · Load (any) · Available

88.3 MW

Granted

The operator's latest published dataset reports 88.3 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2033 (2033) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/CROIX150 · payload sha256 a1980acc6b69…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
CROIX150
Operator note: flexibilityLevel
10%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Offtake · Load (any) · Available

166.4 MW

Granted

The operator's latest published dataset reports 166.4 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2033 (2033) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/CROIX150 · payload sha256 a1980acc6b69…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
CROIX150
Operator note: flexibilityLevel
20%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Bidirectional · Battery · Available

4.3 MW

Granted

The operator's latest published dataset reports 4.3 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2029 (2029) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/CROIX150 · payload sha256 4598361d5630…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
CROIX150
Operator note: flexibilityLevel
0%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Bidirectional · Battery · Available

14.2 MW

Granted

The operator's latest published dataset reports 14.2 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2029 (2029) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/CROIX150 · payload sha256 4598361d5630…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
CROIX150
Operator note: flexibilityLevel
5%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Bidirectional · Battery · Available

71.6 MW

Granted

The operator's latest published dataset reports 71.6 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2029 (2029) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/CROIX150 · payload sha256 4598361d5630…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
CROIX150
Operator note: flexibilityLevel
10%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Bidirectional · Battery · Available

157.3 MW

Granted

The operator's latest published dataset reports 157.3 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2029 (2029) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2029/CROIX150 · payload sha256 4598361d5630…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
CROIX150
Operator note: flexibilityLevel
20%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Bidirectional · Battery · Available

4.3 MW

Granted

The operator's latest published dataset reports 4.3 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2033 (2033) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/CROIX150 · payload sha256 a1980acc6b69…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
CROIX150
Operator note: flexibilityLevel
0%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Bidirectional · Battery · Available

14.2 MW

Granted

The operator's latest published dataset reports 14.2 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2033 (2033) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/CROIX150 · payload sha256 a1980acc6b69…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
CROIX150
Operator note: flexibilityLevel
5%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Bidirectional · Battery · Available

79.5 MW

Granted

The operator's latest published dataset reports 79.5 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2033 (2033) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/CROIX150 · payload sha256 a1980acc6b69…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
CROIX150
Operator note: flexibilityLevel
10%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Bidirectional · Battery · Available

157.3 MW

Granted

The operator's latest published dataset reports 157.3 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2033 (2033) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-11-17 03:51 UTClast confirmed unchanged 2026-11-23 21:38 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2033/CROIX150 · payload sha256 a1980acc6b69…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
CROIX150
Operator note: flexibilityLevel
20%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

History

Served series only

Bidirectional · Battery · Available · 2027

last, until 17 Nov 2026: 0 MW

26 Sep 2026: 0 MW
26 Sep 2026range 0 to 0 MW24 Nov 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 202617 Nov 20260 MW

Time axis: when we observed each value, not the operator’s effective date.

Bidirectional · Battery · Available · 2027

last, until 17 Nov 2026: 0 MW

26 Sep 2026: 0 MW
26 Sep 2026range 0 to 0 MW24 Nov 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 202617 Nov 20260 MW

Time axis: when we observed each value, not the operator’s effective date.

Bidirectional · Battery · Available · 2027

last, until 17 Nov 2026: 0 MW

26 Sep 2026: 0 MW
26 Sep 2026range 0 to 0 MW24 Nov 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 202617 Nov 20260 MW

Time axis: when we observed each value, not the operator’s effective date.

Bidirectional · Battery · Available · 2027

last, until 17 Nov 2026: 0 MW

26 Sep 2026: 0 MW
26 Sep 2026range 0 to 0 MW24 Nov 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 202617 Nov 20260 MW

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Load (any) · Available · 2027

last, until 17 Nov 2026: 0 MW

26 Sep 2026: 0 MW
26 Sep 2026range 0 to 0 MW24 Nov 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 202617 Nov 20260 MW

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Load (any) · Available · 2027

last, until 17 Nov 2026: 0 MW

26 Sep 2026: 0 MW
26 Sep 2026range 0 to 0 MW24 Nov 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 202617 Nov 20260 MW

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Load (any) · Available · 2027

last, until 17 Nov 2026: 0 MW

26 Sep 2026: 0 MW
26 Sep 2026range 0 to 0 MW24 Nov 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 202617 Nov 20260 MW

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Load (any) · Available · 2027

last, until 17 Nov 2026: 0 MW

26 Sep 2026: 0 MW
26 Sep 2026range 0 to 0 MW24 Nov 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 202617 Nov 20260 MW

Time axis: when we observed each value, not the operator’s effective date.

Injection · Generation (any) · Available · 2027

last, until 17 Nov 2026: 0 MW

26 Sep 2026: 0 MW
26 Sep 2026range 0 to 0 MW24 Nov 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 202617 Nov 20260 MW

Time axis: when we observed each value, not the operator’s effective date.

Injection · Generation (any) · Available · 2027

last, until 17 Nov 2026: 0 MW

26 Sep 2026: 0 MW
26 Sep 2026range 0 to 0 MW24 Nov 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 202617 Nov 20260 MW

Time axis: when we observed each value, not the operator’s effective date.

Injection · Generation (any) · Available · 2027

last, until 17 Nov 2026: 0 MW

26 Sep 2026: 0 MW
26 Sep 2026range 0 to 0 MW24 Nov 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 202617 Nov 20260 MW

Time axis: when we observed each value, not the operator’s effective date.

Injection · Generation (any) · Available · 2027

last, until 17 Nov 2026: 0 MW

26 Sep 2026: 0 MW
26 Sep 2026range 0 to 0 MW24 Nov 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 202617 Nov 20260 MW

Time axis: when we observed each value, not the operator’s effective date.

The first 12 of 80 served series with a history. The history route returns every one of them.

Through the API

curl "https://api.gridcapacityapi.com/v1/substations/sub_06gdrm9m39tsbbk4tfg35qbtmw/capacity" \  -H "Authorization: Bearer gc_live_..."