| Injection | Generation (any) | Available | 63.1 MW | Firm, ≤ 0 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Injection | Generation (any) | Available | 175 MW | Flexible, ≤ 5 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Injection | Generation (any) | Available | 175 MW | Flexible, ≤ 10 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Injection | Generation (any) | Available | 175 MW | Flexible, ≤ 20 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Injection | Generation (any) | Available | 63.1 MW | Firm, ≤ 0 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |
| Injection | Generation (any) | Available | 175 MW | Flexible, ≤ 5 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |
| Injection | Generation (any) | Available | 175 MW | Flexible, ≤ 10 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |
| Injection | Generation (any) | Available | 175 MW | Flexible, ≤ 20 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |
| Injection | Solar PV | Available | 160.2 MW | Firm, ≤ 0 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Injection | Solar PV | Available | 175 MW | Flexible, ≤ 5 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Injection | Solar PV | Available | 175 MW | Flexible, ≤ 10 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Injection | Solar PV | Available | 175 MW | Flexible, ≤ 20 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Injection | Solar PV | Available | 175 MW | Firm, ≤ 0 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |
| Injection | Solar PV | Available | 175 MW | Flexible, ≤ 5 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |
| Injection | Solar PV | Available | 175 MW | Flexible, ≤ 10 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |
| Injection | Solar PV | Available | 175 MW | Flexible, ≤ 20 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |
| Injection | Onshore wind | Available | 70.5 MW | Firm, ≤ 0 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Injection | Onshore wind | Available | 175 MW | Flexible, ≤ 5 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Injection | Onshore wind | Available | 175 MW | Flexible, ≤ 10 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Injection | Onshore wind | Available | 175 MW | Flexible, ≤ 20 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Injection | Onshore wind | Available | 70.5 MW | Firm, ≤ 0 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |
| Injection | Onshore wind | Available | 175 MW | Flexible, ≤ 5 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |
| Injection | Onshore wind | Available | 175 MW | Flexible, ≤ 10 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |
| Injection | Onshore wind | Available | 175 MW | Flexible, ≤ 20 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |
| Offtake | Load (any) | Available | 3.4 MW | Firm, ≤ 0 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Offtake | Load (any) | Available | 51.7 MW | Flexible, ≤ 5 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Offtake | Load (any) | Available | 82.1 MW | Flexible, ≤ 10 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Offtake | Load (any) | Available | 106.8 MW | Flexible, ≤ 20 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Offtake | Load (any) | Available | 3.4 MW | Firm, ≤ 0 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |
| Offtake | Load (any) | Available | 51.7 MW | Flexible, ≤ 5 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |
| Offtake | Load (any) | Available | 82.1 MW | Flexible, ≤ 10 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |
| Offtake | Load (any) | Available | 110.3 MW | Flexible, ≤ 20 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |
| Bidirectional | Battery | Available | 3 MW | Firm, ≤ 0 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Bidirectional | Battery | Available | 5.2 MW | Flexible, ≤ 5 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Bidirectional | Battery | Available | 11.7 MW | Flexible, ≤ 10 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Bidirectional | Battery | Available | 52.6 MW | Flexible, ≤ 20 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Bidirectional | Battery | Available | 3 MW | Firm, ≤ 0 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |
| Bidirectional | Battery | Available | 5.2 MW | Flexible, ≤ 5 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |
| Bidirectional | Battery | Available | 11.7 MW | Flexible, ≤ 10 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |
| Bidirectional | Battery | Available | 52.6 MW | Flexible, ≤ 20 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |